This document is a Justification for Other Than Full and Open Competition related to a federal contract opportunity for the Department of Veterans Affairs (VA) in Northern California.

The key details are:

  • The contract opportunity is for a dental expansion and relocation project at the VA Northern California Health Care System (NCHCS) located on Travis Air Force Base in California. The solicitation number is 36C77624R0085.
  • The procurement will be set aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSBs). Brand name equipment from HID and Software House is required as it is compatible with the existing VA security and access control system. Market research showed no other vendors whose products fully integrate with the existing system.
  • The government estimate for the brand name equipment is approximately $XXX. The overall procurement will be competed, and the Contracting Officer will determine fair and reasonable pricing prior to award.
  • The Justification concludes that the brand name equipment is critical for the efficiency and security of the overall project and the VA medical center.

View the file

Other files

File Type Posted
Dental Expansion and Relocation RFI-Questions 9.27.2024.pdf PDF
36C77624R0085 0005.docx DOCX document
3 Dental Final Spec 2 of 3.pdf PDF
4 Dental Final Spec 3 of 3.pdf PDF
5 Prelim Contractor Construct Fence Area.pdf PDF
2 Dental Final Spec 1 of 3.pdf PDF
6 Prelim Contractor Laydown Area.pdf PDF
1 Dental Expansion and Relocation_Responses to Questions.pdf PDF
36C77624R0085 Amd 04.docx DOCX document
36C77624R0085 Amd 03.docx DOCX document
S04 - Site Visit Agenda.doc DOC document
Dental Pre-Bid Site Walk Attendence 20240829.pdf PDF
Amd 02 Dental Expansion and Relocation RFI-Questions.pdf PDF
36C77624R0085 Amd 02.docx DOCX document
36C77624R0085 Amd 01.docx DOCX document
Amd 01 Dental Expansion and Relocation-Questions.xlsx XLSX spreadsheet
Att 15-Dental Final Support Doc 7 of 8.pdf PDF
Att 02 - Dental Final Drawing 2 of 6.pdf PDF
Att 09-Dental Final Support Doc 1 of 8.pdf PDF
Att 04 - Dental Final Drawing 4 of 6.pdf PDF
Att 05 - Dental Final Drawing 5 of 6.pdf PDF
Att 16-Dental Final Support Doc 8 of 8.pdf PDF
Att 01 - Dental Final Drawing 1 of 6.pdf PDF
Att 19-Limitations on Subcontracting.docx DOCX document
Att 21-Division Cost Breakdown.xlsx XLSX spreadsheet
Att 03 - Dental Final Drawing 3 of 6.pdf PDF
Att 08 - Dental Final Spec 2 of 2.pdf PDF
Att 06 - Dental Final Drawing 6 of 6.pdf PDF
Att 07 - Dental Final Spec 1 of 2.pdf PDF
36C77624R0085_1 FINAL.docx DOCX document
Att 17b-DBIDS Enrollment QR.pdf PDF
Att 14-Dental Final Support Doc 6 of 8.pdf PDF
Att 18-DBA WD CA20240007 0726.pdf PDF
Att 17c-DVES - Slide Deck.pptx PPTX presentation
Att 13-Dental Final Support Doc 5 of 8.pdf PDF
Att 20-PPQ form.docx DOCX document
Att 17a-Site Visit Information.docx DOCX document
Att 11-Dental Final Support Doc 3 of 8.pdf PDF
Att 10-Dental Final Support Doc 2 of 8.pdf PDF
Att 12-Dental Final Support Doc 4 of 8.pdf PDF
Att 22-JA_Brand Name_redacted.pdf PDF
Show all 41

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

i. Software House

ii. Impact: HID pivCLASS card readers are compatible with existing PIV cards and software system (from Software House). CCure 9000 is installed in in Northern

California Health Care System (NCHSC). This will aid in standardizing the PIV lock system of all buildings at VA Northern California Health Care System (NCHSC). It was reported that VA Police have had numerous problems with the different brands of card readers and maintaining multiple systems that couldn’t be accessed remotely as CCure 9000 is able to. Installation of HID card readers compatible with CCure

9000 system and VA’s PIV cards will aid in security and standardize all buildings throughout VA Northern California Health Care System (NCHSC).

6. Description of Efforts Made to ensure that offers are solicited from as many potential sources as deemed practicable:

In accordance with the Competition in Contracting Act (CICA), the components listed above are identified as brand name; however, the overall procurement will be completed as a Service-Disabled

Veteran Owned Small Business (SDVOSB) set-aside. This Justification for Other Than Full and Open

Competition will be posted to SAM.gov with the solicitation.

7. Determination by the Contracting Officer (CO) that the Anticipated Cost to the Government will be Fair and Reasonable:

Government estimate was prepared and provided by the Contracting Officer’s Representative

(COR). The anticipated price to the Government for the items required to be brand name is approximately

The items for which brand name approval is being requested are subsequent components to the overall construction project. This procurement will be competed and based on competition; the CO will make a determination of fair and reasonable pricing prior to award.

8. Description of the Market Research Conducted and the Results, or a Statement of the Reasons

Market Research Was Not Conducted:

The market research for the equipment was conducted and prepared by the COR and shared with the CO for further review. The CO was in concurrence with information provided in the estimate that supported the brand name items. Approval of the items as brand name only is critical for the overall efficiency of the completed project and the Mather VAMC, as a whole.

9. Any Other Facts Supporting the Use of Other than Full and Open Competition:

New components must be able to tie into an existing and operational system including the use of software. At this time, there are no competing vendors whose products are fully compatible with the existing system being used at the Mather VAMC. Converting to another manufacturer’s system would be extremely disruptive to medical center operations and prohibitively expensive.

10. Listing of Sources that Expressed, in Writing, an Interest in the Acquisition:

Not applicable. It is the responsibility of the offerors and the general contractor awarded the project to locate suppliers and obtain pricing for all materials and components, including the items listed in this justification.

11. A Statement of the Actions, if any, the Agency May Take to Remove or Overcome any Barriers to

Competition before Making subsequent acquisitions for the supplies or services required:

There will be competition for the overall procurement. It will be the responsibility of the offerors to obtain pricing from the suppliers of the items and to submit a competitive proposal for the project.