This solicitation is for an infrastructure upgrade construction project at the Omaha VA Medical Center. The solicitation seeks a contractor to provide all labor, materials, and supervision necessary to complete the project, which includes a near-complete recabling of the main hospital building and associated campus buildings. The project involves replacing all telecommunications cable, outlets, and associated equipment across multiple campus buildings as delineated in the project plans. The period of performance is 1,095 calendar days. Interested offerors should review the detailed project plans and specifications included in the solicitation documentation.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Romanyk Consulting Corp. Copyright © 2016
PRIVILEGED AND CONFIDENTIAL PROPRIETARY INFORMATION
OMAHA EHRM
INFRASTRUCTURE UPGRADE
DESIGN
OMAHA VA MEDICAL CENTER
Omaha, NE
100% CONSTRUCTION DOCUMENTS
SPECIFICATIONS VOLUME I
May 15, 2023
Project Number: 636‐21‐704
100% Construction Documents Omaha EHRM Infrastructure Upgrade Design
Project Number 636‐21‐704 May 15, 2023
00 00 01 ‐ 1
SECTION 00 00 01
SEAL CERTIFICATIONS
ROMANYK CONSULTING CORP.
Architecture:
00 01 15 List of Drawing Sheets
00 01 10 Table of Contents
01 00 00 General Requirements
01 32 16.15 Project Schedules
01 33 23 Shop Drawings, Product Data, and Samples
01 35 26 Safety Requirements
01 42 19 Reference Standards
01 45 00 Quality Control
01 57 19 Temporary Environmental Controls
01 74 19 Construction Waste Management
01 81 13 Sustainable Construction Requirements
01 91 00 General Commissioning Requirements
02 41 00 Demolition
04 05 13 Masonry Mortaring
04 05 16 Masonry Grouting
04 20 00 Unit Masonry
05 12 00 Structural Steel Framing
05 51 00 Metal Stairs
06 10 00 Rough Carpentry
07 22 00 Roof and Deck Insulation
07 40 00 Roofing and Siding Panels
07 54 23 Thermoplastic Polyolefin (TPO) Roofing
07 60 00 Flashing and Sheet Metal
07 61 16 Batten Seam Sheet Metal Roofing
07 71 00 Roof Specialties
07 72 00 Roof Accessories
07 84 00 Firestopping
Replace with Seal at 100% Final/
Construction set
Project Number 636‐21‐704 May 15, 2023
00 00 01 ‐ 2
07 92 00 Joint Sealants
08 11 13 Hollow Metal Doors and Frames
08 14 00 Interior Wood Doors
08 71 00 Door Hardware
08 90 00 Louvers and Vents
09 05 16 Subsurface Preparation for Floor Finishes
09 06 00 Schedule for Finishes
09 22 16 Non‐Structural Metal Framing
09 29 00 Gypsum Board
09 51 00 Acoustical Ceilings
09 65 13 Resilient Base and Accessories
09 65 16 Resilient Sheet Flooring
09 69 00 Access Flooring
09 91 00 Painting
10 14 00 Signage
13 05 41 Seismic Restraint Requirements for Non‐Structural Components
32 31 40 High Security Fences and Gates
Mechanical, Plumbing and Fire Protection:
21 13 13 Wet‐Pipe Sprinkler Systems
22 05 11 Common Work Results for Plumbing
22 05 12 General Motor Requirements for Plumbing Equipment
22 05 23 General‐Duty Valves for Plumbing Piping
22 07 11 Plumbing Insulation
22 11 00 Facility Water Distribution
22 13 00 Facility Sanitary and Vent Piping
22 15 00 General Service Compressed‐Air Systems
22 40 00 Plumbing Fixtures
23 05 11 Common Work Results for HVAC
23 05 12 General Motor Requirements for HVAC and Steam Generation Equipment
23 05 93 Testing, Adjusting, and Balancing for HVAC
23 07 11 HVAC and Boiler Plant Insulation
Replace with Seal at 100% Final/
Construction set
STATE OF NEBRASKA
PR
O
FE
SS
IO
NAL MECHANICAL ENGIN
EER
ARLO G.
WIECZOREK
E-17213
05/15/23
Project Number 636‐21‐704 May 15, 2023
00 00 01 ‐ 3
23 09 23 Direct‐Digital Control System for HVAC
23 10 00 Facility Fuel Systems
23 23 00 Refrigerant Piping
23 31 00 HVAC Ducts and Casings
23 37 00 Air Outlets and Inlets
23 81 23 Computer‐Room Air‐Conditioners
23 82 00 Convection Heating and Cooling Units
Electrical and Fire Alarm:
26 05 11 Requirements for Electrical Installations
26 05 13 Medium‐Voltage Cables
26 05 19 Low‐Voltage Electrical Power Conductors and Cables
26 05 26 Grounding and Bonding for Electrical Systems
26 05 33 Raceway and Boxes for Electrical Systems
26 05 41 Underground Electrical Construction
26 05 73 Overcurrent Protective Coordination Study
26 09 23 Lighting Controls
26 11 16 Secondary Unit Substations
26 24 16 Panelboards
26 25 11 Busways
26 26 00 Power Distribution Units for Static Uninterruptible Power Systems
26 27 26 Wiring Devices
26 29 21 Enclosed Switches and Circuit Breakers
26 33 53 Static Uninterruptible Power Supply
26 36 23 Automatic Transfer Switches
26 43 13 Surge Protective Devices
26 51 00 Interior Lighting
IMEG GROUP
Technology:
27 05 11 Requirements for Communications Installations
Replace with Seal at 100% Final/
Construction set
Replace with Seal at
Project Number 636‐21‐704 May 15, 2023
00 00 01 ‐ 4
27 05 26 Grounding and Bonding for Communication Systems
27 05 33 Conduits and Backboxes for Communication Systems
27 05 36 Cable Trays for Communications Systems
27 05 53 Identification for Communications Systems
27 10 00 Structured Cabling
27 11 16 Communication Cabinets, Racks, Frames and Enclosures
27 11 19 Communications Termination Blocks and Patch Panels
27 11 26 Communications Rack Mounted Power Protection and Power Strips
27 13 13 Communications Copper Backbone Cabling
27 13 13.13 Communications Copper Cable Splicing and Terminations
27 13 23 Communications Optical Fiber Backbone Cabling
27 15 13 Communications Copper Horizontal Cabling
27 15 13.13 Communications Optical Fiber Cable Splicing and Terminations
27 16 19 Communications Patch Cords, Station Cords, and Cross Connect Wire
28 05 00 Common Work Results for Electronic Safety and Security
28 05 13 Conductors and Cables for Electronic Safety and Security
28 05 26 Grounding and Bonding for Electronic Safety and Security
28 05 28.33 Conduits and Backboxes for Electronic Safety and Security
28 08 00 Commissioning of Electronic Safety and Security Systems
28 13 00 Physical Access Control System
28 23 00 Video Surveillance
28 31 00 Fire Detection and Alarm
Project Number 636‐21‐704 May 15, 2023
00 00 01 ‐ 5
LEO A. DALY
Structural and Civil Specifications:
03 30 00 Cast‐in‐Place Concrete
05 12 00 Structural Steel Framing
05 31 00 Steel Decking
05 36 00 Composite Metal Decking
05 50 00 Metal Fabrications
31 20 00 Earthwork
SPECIFICATION DIVISIONS NOT USED:
11 Equipment
12 Furnishings
14 Conveying Equipment
25 Integrated Automation
33 Utilities
34 Transportation
48 Electrical Power Generation
Replace with Seal at
100% Construc on Documents
Omaha EHRM Infrastructure Upgrade Design
Project Number 636-21-704
May 15, 2023
VA 09-01-21
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS VHA
MASTER SPECIFICATIONS
TABLE OF CONTENTS
Sec�on 00 01 10
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 00 01 Seal Cer fica ons
00 01 15 List of Drawing Sheets 05-20
00 01 10 Table of Contents 09-21
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 05-21
01 32 16.01 Architectural and Engineering CPM Schedules 03-20
01 32 16.15 Project Schedules 11-21
01 33 23 Shop Drawings, Product Data, and Samples 06-21
01 35 26 Safety Requirements 07-20
01 42 19 Reference Standards 11-20
01 45 00 Quality Control 02-21
01 57 19 Temporary Environmental Controls 01-21
01 74 19 Construc on Waste Management 01-21
01 81 13 Sustainable Construc on Requirements 10-17
01 91 00 General Commissioning Requirements 10-15
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demoli on 08-17
Omaha EHRM Infrastructure Upgrade Design
Project Number 636-21-704
May 15, 2023
VA 09-01-21
00 01 10-2
DIVISION 03 – CONCRETE
03 30 00 Cast-in-Place Concrete 01-21
DIVISION 04 – MASONRY
04 05 13 Masonry Mortaring 10-17
04 05 16 Masonry Grou ng 01-21
04 20 00 Unit Masonry 08-17
DIVISION 05 – METALS
05 12 00 Structural Steel Framing 11-18
05 31 00 Steel Decking 01-21
05 36 00 Composite Metal Decking 01-21
05 50 00 Metal Fabrica ons 08-18
05 51 00 Metal Stairs 01-21
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry 10-17
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
Omaha EHRM Infrastructure Upgrade Design
Project Number 636-21-704
May 15, 2023
VA 09-01-21
00 01 10-3
07 22 00 Roof and Deck Insula on 01-21
07 54 23 Thermoplas c Polyolefin (TPO) Roofing 01-21
07 60 00 Flashing and Sheet Metal 01-21
07 61 16 BaAen Seam Sheet Metal Roofing 01-21
07 71 00 Roof Special es 01-21
07 72 00 Roof Accessories 01-21
07 84 00 Firestopping 01-21
07 92 00 Joint Sealants 04-22
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 01-21
08 14 00 Interior Wood Doors 01-21
08 71 00 Door Hardware 05-22
08 90 00 Louvers and Vents 01-21
DIVISION 09 – FINISHES
09 05 16 Subsurface Prepara on for Floor Finishes 01-21
09 06 00 Schedule for Finishes 01-21
09 22 16 Non-Structural Metal Framing 06-18
09 29 00 Gypsum Board 04-20
09 51 00 Acous cal Ceilings 12-18
09 65 13 Resilient Base and Accessories 01-21
09 65 16 Resilient Sheet Flooring 06-22
09 69 00 Access Flooring 01-21
09 91 00 Pain ng 01-21
DIVISION 10 – SPECIALTIES
Omaha EHRM Infrastructure Upgrade Design
Project Number 636-21-704
May 15, 2023
VA 09-01-21
00 01 10-4
10 14 00 Signage 01-21
DIVISION 11 – EQUIPMENT – NOT USED
DIVISION 12 – FURNISHINGS – NOT USED
DIVISION 13 - SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint Requirements for Non-Structural Components 01-21
DIVISION 14– CONVEYING EQUIPEMENT – NOT USED
DIVISION 21- FIRE SUPPRESSION
21 13 13 Wet-Pipe Sprinkler Systems 06-15
Project Number 636‐21‐704 May 15, 2023
VA 05‐20
00 01 15 ‐ 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
GENERAL
GI100 GENERAL INFORMATION
GI101 SHEET INDEX
GI102 SHEET INDEX
GI103 ABBREVIATIONS & SYMBOLS
GI103.1 ICRA DETAILS FOR OR ROOMS
GI103.2 ICRA DETAILS FOR TELECOM
GI103.3 ICRA DETAILS CLASS 1 & 2
GI103.4 ICRA DETAILS CLASS 3
GI103.5 CLASS IV ICRA DETAILS
GI103.6 CLASS IV ALT ICRA DETAILS
GI104 SITE & STAGING PLAN
GI104B ENLARGED SITE PLAN
GI105 CODE SUMMARY
GENERAL
01‐GI106 LEVEL 00 LIFE SAFETY/ PHASING PLAN
01‐GI107 LEVEL 01 LIFE SAFETY/ PHASING PLAN
01‐GI108 LEVEL 02 LIFE SAFETY/ PHASING PLAN
01‐GI109 LEVEL 03 LIFE SAFETY/ PHASING PLAN
01‐GI110 LEVEL 04 LIFE SAFETY/ PHASING PLAN
01‐GI111 LEVEL 05 LIFE SAFETY/ PHASING PLAN
01‐GI112 LEVEL 06 LIFE SAFETY/ PHASING PLAN
01‐GI113 LEVEL 07 LIFE SAFETY/ PHASING PLAN
01‐GI114 LEVEL 08 LIFE SAFETY/ PHASING PLAN
01‐GI115 LEVEL 09 LIFE SAFETY/ PHASING PLAN
01‐GI116 LEVEL 10 LIFE SAFETY/ PHASING PLAN
01‐GI117 LEVEL 11 LIFE SAFETY/ PHASING PLAN
01‐GI118 LEVEL 12 LIFE SAFETY/PHASING PLAN
01‐GI119 LEVEL 14 LIFE SAFETY/PHASING PLAN
02‐GI118 BLDG. 02 ‐ LIFE SAFETY/ PHASING PLAN
06‐GI119 BLDG. 06 LIFE SAFETY/ PHASING PLAN
08‐GI120 BLDG. 08 ‐ LIFE SAFETY/ PHASING PLAN
09‐GI121 BLDG. 09 ‐ LIFE SAFETY/ PHASING PLAN
15‐GI122 BLDG. 15 ‐ LIFE SAFETY/ PHASING PLAN
ACC‐GI123 BLDG. ACC ‐ LEVEL 00 LIFE SAFETY/ PHASING PLAN
ACC‐GI124 BLDG. ACC ‐ LEVEL 01 LIFE SAFETY/ PHASING PLAN
Project Number 636‐21‐704 May 15, 2023
VA 05‐20
00 01 15 ‐ 2
ACC‐GI125 BLDG. ACC ‐ LEVEL 02 LIFE SAFETY/ PHASING PLAN
D‐GI126 BLDG. D ‐ LEVEL 01 LIFE SAFETY/ PHASING PLAN
G‐ GI101 GENERATOR BUILDING ‐ LIFE SAFETY PLAN/CODE REVIEW
CIVIL
CD201 SITE DEMOLITION
CD202 DEMOLITION ‐ PARKING STALL REMIDIATION
CG201 SITE GRADING
CG202 SITE GRADING ‐ PARKING STALL REMEDIATION
CS101 OVERALL SITE
CS102 SITE LAYOUT A1
CS103 SITE LAYOUT A2
CS104 SITE LAYOUT A3
CS105 SITE LAYOUT A4
CS201 SITE LAYOUT
CS202 SITE LAYOUT ‐ PARKING STALL REMEDIATION
CS501 SITE DETAILS
CS901 SITE PHOTOS
CU201 SITE UTILITIES
CIVIL
C510 DETAILS
C511 DETAILS
STRUCTURAL
01‐S001 STRUCTURAL GENERAL NOTES & DETAILS
01‐SB101 PLANS & DETAILS
01‐SF501 FRAMING PLAN
G‐SB201 PLANS AND DETAILS
G‐SB202 FOUNDATION AND FRAMING DETAILS
G‐SB203 FRAMING DETAILS
ARCHITECTURAL
01‐AD101 BLDG. 01 ‐ LEVEL 00 OVERALL DEMO REFLECTED CEILING PLAN
01‐AD102 BLDG. 01 ‐ LEVEL 00 ENLARGED DEMOLITION PLANS & REFLECTED CEILING PLANS ‐
DEMO
01‐AD103 BLDG. 01 ‐ LEVEL 00 ENLARGED DEMOLITION PLANS & REFLECTED CEILING PLANS ‐
DEMO
Project Number 636‐21‐704 May 15, 2023
VA 05‐20
00 01 15 ‐ 3
01‐AD104 BLDG. 01 ‐ LEVEL 00 ENLARGED DEMOLITION PLANS & REFLECTED CEILING PLANS ‐
DEMO
01‐AD105 BLDG. 01 ‐ LEVEL 01 OVERALL DEMO REFLECTED CEILING PLAN
01‐AD106 BLDG. 01 ‐ LEVEL 01 ENLARGED DEMOLITION PLANS & REFLECTED CEILING PLANS ‐
DEMO
01‐AD107 BLDG. 01 ‐ LEVEL 01 ENLARGED DEMOLITION PLANS & REFLECTED CEILING PLANS ‐
DEMO
01‐AD108 BLDG. 01 ‐ LEVEL 01 RM. 1205B ENLARGED FLOOR PLANS, REFLECTED CEILING PLANS, & BUILDING SECTION ‐ DEMO
01‐AD109 BLDG. 01 ‐ LEVEL 01 RM. 1205B ENLARGED ROOF PLAN & BUILDING SECTION ‐ DEMO
01‐AD110 BLDG. 01 ‐ LEVEL 02 OVERALL DEMO REFLECTED CEILING PLAN
01‐AD111 BLDG. 01 ‐ LEVEL 03 OVERALL DEMO REFLECTED CEILING PLAN
01‐AD112 BLDG. 01 ‐ LEVEL 02 & 03 ENLARGED DEMOLITION PLANS & REFLECTED CEILING PLANS
‐ DEMO
01‐AD113 BLDG. 01 ‐ LEVEL 02 & 03 ENLARGED DEMOLITION PLANS & REFLECTED CEILING PLANS
‐ DEMO
01‐AD114 BLDG. 01 ‐ LEVEL 04 OVERALL DEMO REFLECTED CEILING PLAN
01‐AD115 BLDG. 01 ‐ LEVEL 05 OVERALL DEMO REFLECTED CEILING PLAN
01‐AD116 BLDG. 01 ‐ LEVEL 04 & 05 ENLARGED DEMOLITION PLANS & REFLECTED CEILING PLANS
‐ DEMO
01‐AD117 BLDG. 01 ‐ LEVEL 06 OVERALL DEMO REFLECTED CEILING PLAN
01‐AD118 BLDG. 01 ‐ LEVEL 07 OVERALL DEMO REFLECTED CEILING PLAN
01‐AD119 BLDG. 01 ‐ LEVEL 06 & 07 ENLARGED DEMOLITION PLANS & REFLECTED CEILING PLANS
‐ DEMO
01‐AD120 BLDG. 01 ‐ LEVEL 08 OVERALL DEMO REFLECTED CEILING PLAN
01‐AD121 BLDG. 01 ‐ LEVEL 09 OVERALL DEMO REFLECTED CEILING PLAN
01‐AD122 BLDG. 01 ‐ LEVEL 08 & 09 ENLARGED DEMOLITION PLANS & REFLECTED CEILING PLANS
‐ DEMO
01‐AD123 BLDG. 01 ‐ LEVEL 10 OVERALL DEMO REFLECTED CEILING PLAN
01‐AD124 BLDG. 01 ‐ LEVEL 11 OVERALL DEMO REFLECTED CEILING PLAN
01‐AD125 BLDG. 01 ‐ LEVEL 10 & 11 ENLARGED DEMOLITION PLANS & REFLECTED CEILING PLANS
‐ DEMO
01‐AD126 BLDG. 01 ‐ LEVEL 12 OVERALL DEMO REFLECTED CEILING PLAN
01‐AD127 BLDG. 01 ‐ LEVEL 13 OVERALL DEMO REFLECTED CEILING PLAN
01‐AD128 BLDG. 01 ‐ LEVEL 14 OVERALL DEMO REFLECTED CEILING PLAN
01‐AD129 BLDG. 01 ‐ LEVEL 12 & 14 ENLARGED DEMOLITION PLANS & REFLECTED CEILING PLANS
‐ DEMO
01‐AD130 BLDG. 01 ‐ LEVEL 13 OVERALL DEMO FLOOR PLAN
01‐AD131 BLDG. 01 ‐ LEVEL 14 OVERALL DEMO FLOOR PLAN
01‐AE101 BLDG. 01 ‐ LEVEL 00 OVERALL REFLECTED CEILING PLAN
01‐AE102 BLDG. 01 ‐ LEVEL 00 FLOOR PLAN ‐ QUADRANT A
01‐AE103 BLDG. 01 ‐ LEVEL 00 FLOOR PLAN ‐ QUADRANT B
01‐AE104 BLDG. 01 ‐ LEVEL 00 FLOOR PLAN ‐ QUADRANT C
01‐AE105 BLDG. 01 ‐ LEVEL 00 FLOOR PLAN ‐ QUADRANT D
01‐AE106 BLDG. 01 ‐ LEVEL 00 FLOOR PLAN ‐ QUADRANT E
Project Number 636‐21‐704 May 15, 2023
VA 05‐20
00 01 15 ‐ 4
01‐AE107 BLDG. 01 ‐ LEVEL 00 ENLARGED FLOOR PLANS & REFLECTED CEILING PLANS
01‐AE108 BLDG. 01 ‐ LEVEL 00 ENLARGED FLOOR PLANS & REFLECTED CEILING PLANS
01‐AE109 BLDG. 01 ‐ LEVEL 00 ENLARGED FLOOR PLANS & REFLECTED CEILING PLANS
01‐AE110 BLDG. 01 ‐ LEVEL 01 OVERALL REFLECTED CEILING PLAN
01‐AE111 BLDG. 01 ‐ LEVEL 01 FLOOR PLAN ‐ QUADRANT A
01‐AE112 BLDG. 01 ‐ LEVEL 01 FLOOR PLAN ‐ QUADRANT B
01‐AE113 BLDG. 01 ‐ LEVEL 01 FLOOR PLAN ‐ QUADRANT C
01‐AE114 BLDG. 01 ‐ LEVEL 01 FLOOR PLAN ‐ QUADRANT D
01‐AE115 BLDG. 01 ‐ LEVEL 01 FLOOR PLAN ‐ QUADRANT E
01‐AE116 BLDG. 01 ‐ LEVEL 01 ENLARGED FLOOR PLANS & REFLECTED CEILING PLANS
01‐AE117 BLDG. 01 ‐ LEVEL 01 ENLARGED FLOOR PLANS & REFLECTED CEILING PLANS
01‐AE118 BLDG. 01 ‐ LEVEL 01 RM. 1205B ENLARGED FLOOR PLAN & REFLECTED CEILING PLAN
01‐AE119 BLDG. 01 ‐ LEVEL 01 RM. 1205B ENLARGED ROOF PLAN
01‐AE120 BLDG. 01 ‐ LEVEL 01 RM. 1205B BUILDING SECTIONS
01‐AE121 BLDG. 01 ‐ LEVEL 01 RM. 1205B WALL DETAILS
01‐AE122 BLDG. 01 ‐ LEVEL 02 OVERALL REFLECTED CEILING PLAN
01‐AE123 BLDG. 01 ‐ LEVEL 02 FLOOR PLAN ‐ QUADRANT B
01‐AE124 BLDG. 01 ‐ LEVEL 02 FLOOR PLAN ‐ QUADRANT C
01‐AE125 BLDG. 01 ‐ LEVEL 02 FLOOR PLAN ‐ QUADRANT D
01‐AE126 BLDG. 01 ‐ LEVEL 02 FLOOR PLAN ‐ QUADRANT E
01‐AE127 BLDG. 01 ‐ LEVEL 03 OVERALL REFLECTED CEILING PLAN
01‐AE128 BLDG. 01 ‐ LEVEL 03 FLOOR PLAN ‐ QUADRANT B
01‐AE129 BLDG. 01 ‐ LEVEL 03 FLOOR PLAN ‐ QUADRANT C
01‐AE130 BLDG. 01 ‐ LEVEL 03 FLOOR PLAN ‐ QUADRANT D
01‐AE131 BLDG. 01 ‐ LEVEL 03 FLOOR PLAN ‐ QUADRANT E
01‐AE132 BLDG. 01 ‐ LEVEL 02 & 03 ENLARGED FLOOR PLANS & REFLECTED CEILING PLANS
01‐AE133 BLDG. 01 ‐ LEVEL 03 ENLARGED FLOOR PLANS & REFLECTED CEILING PLANS
01‐AE134 BLDG. 01 ‐ LEVEL 04 OVERALL REFLECTED CEILING PLAN
01‐AE135 BLDG. 01 ‐ LEVEL 04 FLOOR PLAN ‐ QUADRANT B
01‐AE136 BLDG. 01 ‐ LEVEL 04 FLOOR PLAN ‐ QUADRANT C
01‐AE137 BLDG. 01 ‐ LEVEL 04 FLOOR PLAN ‐ QUADRANT D
01‐AE138 BLDG. 01 ‐ LEVEL 04 FLOOR PLAN ‐ QUADRANT E
01‐AE139 BLDG. 01 ‐ LEVEL 05 OVERALL REFLECTED CEILING PLAN
01‐AE140 BLDG. 01 ‐ LEVEL 05 FLOOR PLAN ‐ QUADRANT B
01‐AE141 BLDG. 01 ‐ LEVEL 05 FLOOR PLAN ‐ QUADRANT C
01‐AE142 BLDG. 01 ‐ LEVEL 05 FLOOR PLAN ‐ QUADRANT D
01‐AE143 BLDG. 01 ‐ LEVEL 05 FLOOR PLAN ‐ QUADRANT E
01‐AE144 BLDG. 01 ‐ LEVEL 04 & 05 ENLARGED FLOOR PLANS & REFLECTED CEILING PLANS
01‐AE145 BLDG. 01 ‐ LEVEL 06 OVERALL REFLECTED CEILING PLAN
01‐AE146 BLDG. 01 ‐ LEVEL 06 FLOOR PLAN ‐ QUADRANT B
01‐AE147 BLDG. 01 ‐ LEVEL 06 FLOOR PLAN ‐ QUADRANT C
01‐AE148 BLDG. 01 ‐ LEVEL 06 FLOOR PLAN ‐ QUADRANT D
01‐AE149 BLDG. 01 ‐ LEVEL 06 FLOOR PLAN ‐ QUADRANT E
01‐AE150 BLDG. 01 ‐ LEVEL 07 OVERALL REFLECTED CEILING PLAN
01‐AE151 BLDG. 01 ‐ LEVEL 07 FLOOR PLAN ‐ QUADRANT B
Project Number 636‐21‐704 May 15, 2023
VA 05‐20
00 01 15 ‐ 5
01‐AE152 BLDG. 01 ‐ LEVEL 07 FLOOR PLAN ‐ QUADRANT C
01‐AE153 BLDG. 01 ‐ LEVEL 07 FLOOR PLAN ‐ QUADRANT D
01‐AE154 BLDG. 01 ‐ LEVEL 07 FLOOR PLAN ‐ QUADRANT E
01‐AE155 BLDG. 01 ‐ LEVEL 06 & 07 ENLARGED FLOOR PLANS & REFLECTED CEILING PLANS
01‐AE156 BLDG. 01 ‐ LEVEL 08 OVERALL REFLECTED CEILING PLAN
01‐AE157 BLDG. 01 ‐ LEVEL 08 FLOOR PLAN ‐ QUADRANT B
01‐AE158 BLDG. 01 ‐ LEVEL 08 FLOOR PLAN ‐ QUADRANT C
01‐AE159 BLDG. 01 ‐ LEVEL 08 FLOOR PLAN ‐ QUADRANT D
01‐AE160 BLDG. 01 ‐ LEVEL 08 FLOOR PLAN ‐ QUADRANT E
01‐AE161 BLDG. 01 ‐ LEVEL 09 OVERALL REFLECTED CEILING PLAN
01‐AE162 BLDG. 01 ‐ LEVEL 09 FLOOR PLAN ‐ QUADRANT B
01‐AE163 BLDG. 01 ‐ LEVEL 09 FLOOR PLAN ‐ QUADRANT C
01‐AE164 BLDG. 01 ‐ LEVEL 09 FLOOR PLAN ‐ QUADRANT D
01‐AE165 BLDG. 01 ‐ LEVEL 09 FLOOR PLAN ‐ QUADRANT E
01‐AE166 BLDG. 01 ‐ LEVEL 08 & 09 ENLARGED FLOOR PLANS & REFLECTED CEILING PLANS
01‐AE167 BLDG. 01 ‐ LEVEL 10 OVERALL REFLECTED CEILING PLAN
01‐AE168 BLDG. 01 ‐ LEVEL 10 FLOOR PLAN ‐ QUADRANT B
01‐AE169 BLDG. 01 ‐ LEVEL 10 FLOOR PLAN ‐ QUADRANT C
01‐AE170 BLDG. 01 ‐ LEVEL 10 FLOOR PLAN ‐ QUADRANT D
01‐AE171 BLDG. 01 ‐ LEVEL 10 FLOOR PLAN ‐ QUADRANT E
01‐AE172 BLDG. 01 ‐ LEVEL 11 OVERALL REFLECTED CEILING PLAN
01‐AE173 BLDG. 01 ‐ LEVEL 11 FLOOR PLAN ‐ QUADRANT B
01‐AE174 BLDG. 01 ‐ LEVEL 11 FLOOR PLAN ‐ QUADRANT C
01‐AE175 BLDG. 01 ‐ LEVEL 11 FLOOR PLAN ‐ QUADRANT D
01‐AE176 BLDG. 01 ‐ LEVEL 11 FLOOR PLAN ‐ QUADRANT E
01‐AE177 BLDG. 01 ‐ LEVEL 10 & 11 ENLARGED FLOOR PLANS & REFLECTED CEILING PLANS
01‐AE178 BLDG. 01 ‐ LEVEL 12 OVERALL REFLECTED CEILING PLAN
01‐AE179 BLDG. 01 ‐ LEVEL 12 FLOOR PLAN ‐ QUADRANT B
01‐AE180 BLDG. 01 ‐ LEVEL 12 FLOOR PLAN ‐ QUADRANT D
01‐AE181 BLDG. 01 ‐ LEVEL 12 FLOOR PLAN ‐ QUADRANT E
01‐AE182 BLDG. 01 ‐ LEVEL 13 OVERALL FLOOR PLAN
01‐AE183 BLDG. 01 ‐ LEVEL 14 OVERALL REFLECTED CEILING PLAN
01‐AE184 BLDG. 01 ‐ LEVEL 12 & 14 ENLARGED FLOOR PLANS & REFLECTED CEILING PLANS
02‐AD101 BLDG. 02 ‐ LEVEL 02 DEMOLITION PLAN & REFLECTED CEILING PLAN ‐ DEMO
02‐AE101 BLDG. 02 ‐ LEVEL 02 FLOOR PLAN & REFLECTED CEILING PLAN
06‐AD101 BLDG. 06 ‐ LEVEL 01 DEMOLITION PLAN & REFLECTED CEILING PLAN ‐ DEMO
06‐AE101 BLDG. 06 ‐ LEVEL 01 FLOOR PLAN & REFLECTED CEILING PLAN
08‐AD101 BLDG. 08 ‐ LEVEL 01 DEMOLITION PLAN & REFLECTED CEILING PLAN ‐ DEMO
08‐AE101 BLDG. 08 ‐ LEVEL 01 FLOOR PLAN & REFLECTED CEILING PLAN
09‐AD101 BLDG. 09 ‐ LEVEL 00 DEMOLITION PLAN & REFLECTED CEILING PLAN ‐ DEMO
09‐AE101 BLDG. 09 ‐ LEVEL 00 FLOOR PLAN & REFLECTED CEILING PLAN
15‐AD101 BLDG. 15 ‐ LEVEL 02 DEMOLITION PLAN & REFLECTED CEILING PLAN ‐ DEMO
15‐AE101 BLDG. 15 ‐ LEVEL 02 FLOOR PLAN & REFLECTED CEILING PLAN
ACC‐AD101 BLDG. ACC ‐ LEVEL 00 DEMOLITION PLAN & REFLECTED CEILING PLAN ‐ DEMO
ACC‐AD102 BLDG. ACC ‐ LEVEL 01 DEMOLITION PLAN & REFLECTED CEILING PLAN ‐ DEMO
Project Number 636‐21‐704 May 15, 2023
VA 05‐20
00 01 15 ‐ 6
ACC‐AD103 BLDG. ACC ‐ LEVEL 02 DEMOLITION PLAN & REFLECTED CEILING PLAN ‐ DEMO
ACC‐AE101 BLDG. ACC ‐ LEVEL 00 QUADRANT A
ACC‐AE102 BLDG. ACC ‐ LEVEL 00 QUADRANT B
ACC‐AE103 BLDG. ACC ‐ LEVEL 00 QUADRANT C
ACC‐AE104 BLDG. ACC ‐ LEVEL 00 FLOOR PLAN & REFLECTED CEILING PLAN
ACC‐AE105 BLDG. ACC ‐ LEVEL 01 QUADRANT A
ACC‐AE106 BLDG. ACC ‐ LEVEL 01 QUADRANT B
ACC‐AE107 BLDG. ACC ‐ LEVEL 01 QUADRANT C
ACC‐AE108 BLDG. ACC ‐ LEVEL 01 QUADRANT D
ACC‐AE109 BLDG. ACC ‐ LEVEL 01 FLOOR PLAN & REFLECTED CEILING PLAN
ACC‐AE110 BLDG. ACC ‐ LEVEL 02 QUADRANT A
ACC‐AE111 BLDG. ACC ‐ LEVEL 02 QUADRANT B
ACC‐AE112 BLDG. ACC ‐ LEVEL 02 QUADRANT C
ACC‐AE113 BLDG. ACC ‐ LEVEL 02 FLOOR PLAN & REFLECTED CEILING PLAN
D‐AD101 BLDG. D ‐ LEVEL 01 DEMOLITION PLAN & REFLECTED CEILING PLAN ‐ DEMO
D‐AE101 BLDG. D ‐ LEVEL 01 FLOOR PLAN & REFLECTED CEILING PLAN
G‐ AE101 GENERATOR BUILDING ‐ LEVEL 01 FLOOR PLAN & REFLECTED CEILING PLAN
G‐ AE104 GENERATOR BUILDING ‐ ROOF PLAN
G‐ AE201 GENERATOR BUILDING ‐ ELEVATIONS
G‐ AE202 GENERATOR BUILDING ‐ BUILDING SECTIONS
G‐ AI101 GENERATOR BUILDING ‐ WALL SECTIONS
G‐AI102 GENERATOR BUILDING ‐ WALL DETAILS
ARCHITECTURAL
AE500 WALL TYPES
AE501 TYPICAL PARTITION DETAILS
AE502 CEILING DETAILS
AE503 ROOF DETAILS
AE504 MISCELLANEOUS DETAILS
AE601 DOOR SCHEDULE/DETAILS
AF101 ROOM/SIGNAGE SCHEDULE
FIRE PROTECTION
F‐100 FIRE PROTECTION LEGEND, NOTES, AND ABBREVIATIONS
FIRE PROTECTION
01‐FA101 BLDG. 01 ‐ LEVEL 00 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT A
01‐FA102 BLDG. 01 ‐ LEVEL 00 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT B
01‐FA103 BLDG. 01 ‐ LEVEL 00 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT C
01‐FA104 BLDG. 01 ‐ LEVEL 00 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT D
01‐FA105 BLDG. 01 ‐ LEVEL 00 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT E
01‐FA111 BLDG. 01 ‐ LEVEL 01 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT A
Project Number 636‐21‐704 May 15, 2023
VA 05‐20
00 01 15 ‐ 7
01‐FA112 BLDG. 01 ‐ LEVEL 01 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT B
01‐FA113 BLDG. 01 ‐ LEVEL 01 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT C
01‐FA114 BLDG. 01 ‐ LEVEL 01 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT D
01‐FA115 BLDG. 01 ‐ LEVEL 01 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT E
01‐FA122 BLDG. 01 ‐ LEVEL 02 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT B
01‐FA123 BLDG. 01 ‐ LEVEL 02 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT C
01‐FA124 BLDG. 01 ‐ LEVEL 02 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT D
01‐FA125 BLDG. 01 ‐ LEVEL 02 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT E
01‐FA132 BLDG. 01 ‐ LEVEL 03 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT B
01‐FA133 BLDG. 01 ‐ LEVEL 03 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT C
01‐FA134 BLDG. 01 ‐ LEVEL 03 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT D
01‐FA135 BLDG. 01 ‐ LEVEL 03 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT E
01‐FA142 BLDG. 01 ‐ LEVEL 04 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT B
01‐FA143 BLDG. 01 ‐ LEVEL 04 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT C
01‐FA144 BLDG. 01 ‐ LEVEL 04 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT D
01‐FA145 BLDG. 01 ‐ LEVEL 04 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT E
01‐FA152 BLDG. 01 ‐ LEVEL 05 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT B
01‐FA153 BLDG. 01 ‐ LEVEL 05 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT C
01‐FA154 BLDG. 01 ‐ LEVEL 05 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT D
01‐FA155 BLDG. 01 ‐ LEVEL 05 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT E
01‐FA162 BLDG. 01 ‐ LEVEL 06 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT B
01‐FA163 BLDG. 01 ‐ LEVEL 06 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT C
01‐FA164 BLDG. 01 ‐ LEVEL 06 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT D
01‐FA165 BLDG. 01 ‐ LEVEL 06 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT E
01‐FA172 BLDG. 01 ‐ LEVEL 07 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT B
01‐FA173 BLDG. 01 ‐ LEVEL 07 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT C
01‐FA174 BLDG. 01 ‐ LEVEL 07 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT D
01‐FA175 BLDG. 01 ‐ LEVEL 07 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT E
01‐FA182 BLDG. 01 ‐ LEVEL 08 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT B
01‐FA183 BLDG. 01 ‐ LEVEL 08 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT C
01‐FA184 BLDG. 01 ‐ LEVEL 08 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT D
01‐FA185 BLDG. 01 ‐ LEVEL 08 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT E
01‐FA192 BLDG. 01 ‐ LEVEL 09 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT B
01‐FA193 BLDG. 01 ‐ LEVEL 09 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT C
01‐FA194 BLDG. 01 ‐ LEVEL 09 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT D
01‐FA195 BLDG. 01 ‐ LEVEL 09 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT E
01‐FA202 BLDG. 01 ‐ LEVEL 10 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT B
01‐FA203 BLDG. 01 ‐ LEVEL 10 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT C
01‐FA204 BLDG. 01 ‐ LEVEL 10 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT D
01‐FA205 BLDG. 01 ‐ LEVEL 10 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT E
01‐FA212 BLDG. 01 ‐ LEVEL 11 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT B
01‐FA213 BLDG. 01 ‐ LEVEL 11 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT C
01‐FA214 BLDG. 01 ‐ LEVEL 11 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT D
01‐FA215 BLDG. 01 ‐ LEVEL 11 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT E
01‐FA222 BLDG. 01 ‐ LEVEL 12 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT B
Project Number 636‐21‐704 May 15, 2023
VA 05‐20
00 01 15 ‐ 8
01‐FA225 BLDG. 01 ‐ LEVEL 12 FIRE PROTECTION FLOOR PLAN ‐ QUADRANT E
01‐FA231 BLDG. 01 ‐ LEVELS 13 & 14 FIRE PROTECTION FLOOR PLAN ‐ QUADRANTS B & E
01‐FE101 BLDG. 01 ‐ LEVEL 00 FIRE PROTECTION ENLARGED PLANS
01‐FE102 BLDG. 01 ‐ LEVELS 00 & 01 FIRE PROTECTION ENLARGED PLANS
01‐FE103 BLDG. 01 ‐ LEVEL 01 FIRE PROTECTION ENLARGED PLANS
01‐FE104 BLDG. 01 ‐ LEVELS 02‐04 FIRE PROTECTION ENLARGED PLANS
01‐FE105 BLDG. 01 ‐ LEVELS 05‐08 FIRE PROTECTION ENLARGED PLANS
01‐FE106 BLDG. 01 ‐ LEVELS 09‐12 & 14 FIRE PROTECTION ENLARGED PLANS
06‐FE101 BLDG. 06 ‐ LEVEL 01 FIRE PROTECTION FLOOR PLAN
09‐FE101 BLDG. 09 ‐ LEVEL 00 FIRE PROTECTION FLOOR PLAN
15‐FE101 BLDG. 15 ‐ LEVEL 02 FIRE PROTECTION FLOOR PLAN
G‐FE101 BLDG. G ‐ LEVEL 01 FIRE PROTECTION FLOOR PLAN
MECHANICAL
M‐100 MECHANICAL LEGEND, NOTES, AND ABBREVIATIONS
M‐101 MECHANICAL DETAILS
M‐102 MECHANICAL DETAILS
M‐103 MECHANICAL SCHEDULES
M‐104 MECHANICAL CONTROLS
MECHANICAL
01‐MA101 BLDG. 01 ‐ LEVEL 00 MECHANICAL FLOOR PLAN ‐ QUADRANT A
01‐MA102 BLDG. 01 ‐ LEVEL 00 MECHANICAL FLOOR PLAN ‐ QUADRANT B
01‐MA103 BLDG. 01 ‐ LEVEL 00 MECHANICAL FLOOR PLAN ‐ QUADRANT C
01‐MA104 BLDG. 01 ‐ LEVEL 00 MECHANICAL FLOOR PLAN ‐ QUADRANT D
01‐MA105 BLDG. 01 ‐ LEVEL 00 MECHANICAL FLOOR PLAN ‐ QUADRANT E
01‐MA111 BLDG. 01 ‐ LEVEL 01 MECHANICAL FLOOR PLAN ‐ QUADRANT A
01‐MA112 BLDG. 01 ‐ LEVEL 01 MECHANICAL FLOOR PLAN ‐ QUADRANT B
01‐MA113 BLDG. 01 ‐ LEVEL 01 MECHANICAL FLOOR PLAN ‐ QUADRANT C
01‐MA114 BLDG. 01 ‐ LEVEL 01 MECHANICAL FLOOR PLAN ‐ QUADRANT D
01‐MA115 BLDG. 01 ‐ LEVEL 01 MECHANICAL FLOOR PLAN ‐ QUADRANT E
01‐MA121 BLDG. 01 ‐ LEVEL 02 MECHANICAL ROOF PLAN ‐ QUADRANT A
01‐MA122 BLDG. 01 ‐ LEVEL 02 MECHANICAL FLOOR PLAN ‐ QUADRANT B
01‐MA123 BLDG. 01 ‐ LEVEL 02 MECHANICAL FLOOR PLAN ‐ QUADRANT C
01‐MA124 BLDG. 01 ‐ LEVEL 02 MECHANICAL FLOOR PLAN ‐ QUADRANT D
01‐MA125 BLDG. 01 ‐ LEVEL 02 MECHANICAL FLOOR PLAN ‐ QUADRANT E
01‐MA132 BLDG. 01 ‐ LEVEL 03 MECHANICAL FLOOR PLAN ‐ QUADRANT B
01‐MA133 BLDG. 01 ‐ LEVEL 03 MECHANICAL FLOOR PLAN ‐ QUADRANT C
01‐MA134 BLDG. 01 ‐ LEVEL 03 MECHANICAL FLOOR PLAN ‐ QUADRANT D
01‐MA135 BLDG. 01 ‐ LEVEL 03 MECHANICAL FLOOR PLAN ‐ QUADRANT E
01‐MA142 BLDG. 01 ‐ LEVEL 04 MECHANICAL FLOOR PLAN ‐ QUADRANT B
01‐MA143 BLDG. 01 ‐ LEVEL 04 MECHANICAL FLOOR PLAN ‐ QUADRANT C
Project Number 636‐21‐704 May 15, 2023
VA 05‐20
00 01 15 ‐ 9
01‐MA144 BLDG. 01 ‐ LEVEL 04 MECHANICAL FLOOR PLAN ‐ QUADRANT D
01‐MA145 BLDG. 01 ‐ LEVEL 04 MECHANICAL FLOOR PLAN ‐ QUADRANT E
01‐MA152 BLDG. 01 ‐ LEVEL 05 MECHANICAL FLOOR PLAN ‐ QUADRANT B
01‐MA153 BLDG. 01 ‐ LEVEL 05 MECHANICAL FLOOR PLAN ‐ QUADRANT C
01‐MA154 BLDG. 01 ‐ LEVEL 05 MECHANICAL FLOOR PLAN ‐ QUADRANT D
01‐MA155 BLDG. 01 ‐ LEVEL 05 MECHANICAL FLOOR PLAN ‐ QUADRANT E
01‐MA162 BLDG. 01 ‐ LEVEL 06 MECHANICAL FLOOR PLAN ‐ QUADRANT B
01‐MA163 BLDG. 01 ‐ LEVEL 06 MECHANICAL FLOOR PLAN ‐ QUADRANT C
01‐MA164 BLDG. 01 ‐ LEVEL 06 MECHANICAL FLOOR PLAN ‐ QUADRANT D
01‐MA165 BLDG. 01 ‐ LEVEL 06 MECHANICAL FLOOR PLAN ‐ QUADRANT E
01‐MA172 BLDG. 01 ‐ LEVEL 07 MECHANICAL FLOOR PLAN ‐ QUADRANT B
01‐MA173 BLDG. 01 ‐ LEVEL 07 MECHANICAL FLOOR PLAN ‐ QUADRANT C
01‐MA174 BLDG. 01 ‐ LEVEL 07 MECHANICAL FLOOR PLAN ‐ QUADRANT D
01‐MA175 BLDG. 01 ‐ LEVEL 07 MECHANICAL FLOOR PLAN ‐ QUADRANT E
01‐MA182 BLDG. 01 ‐ LEVEL 08 MECHANICAL FLOOR PLAN ‐ QUADRANT B
01‐MA183 BLDG. 01 ‐ LEVEL 08 MECHANICAL FLOOR PLAN ‐ QUADRANT C
01‐MA184 BLDG. 01 ‐ LEVEL 08 MECHANICAL FLOOR PLAN ‐ QUADRANT D
01‐MA185 BLDG. 01 ‐ LEVEL 08 MECHANICAL FLOOR PLAN ‐ QUADRANT E
01‐MA192 BLDG. 01 ‐ LEVEL 09 MECHANICAL FLOOR PLAN ‐ QUADRANT B
01‐MA193 BLDG. 01 ‐ LEVEL 09 MECHANICAL FLOOR PLAN ‐ QUADRANT C
01‐MA194 BLDG. 01 ‐ LEVEL 09 MECHANICAL FLOOR PLAN ‐ QUADRANT D
01‐MA195 BLDG. 01 ‐ LEVEL 09 MECHANICAL FLOOR PLAN ‐ QUADRANT E
01‐MA202 BLDG. 01 ‐ LEVEL 10 MECHANICAL FLOOR PLAN ‐ QUADRANT B
01‐MA203 BLDG. 01 ‐ LEVEL 10 MECHANICAL FLOOR PLAN ‐ QUADRANT C
01‐MA204 BLDG. 01 ‐ LEVEL 10 MECHANICAL FLOOR PLAN ‐ QUADRANT D
01‐MA205 BLDG. 01 ‐ LEVEL 10 MECHANICAL FLOOR PLAN ‐ QUADRANT E
01‐MA212 BLDG. 01 ‐ LEVEL 11 MECHANICAL FLOOR PLAN ‐ QUADRANT B
01‐MA213 BLDG. 01 ‐ LEVEL 11 MECHANICAL FLOOR PLAN ‐ QUADRANT C
01‐MA214 BLDG. 01 ‐ LEVEL 11 MECHANICAL FLOOR PLAN ‐ QUADRANT D
01‐MA215 BLDG. 01 ‐ LEVEL 11 MECHANICAL FLOOR PLAN ‐ QUADRANT E
01‐MA222 BLDG. 01 ‐ LEVEL 12 MECHANICAL FLOOR PLAN ‐ QUADRANT B
01‐MA224 BLDG. 01 ‐ LEVEL 12 MECHANICAL FLOOR PLAN ‐ QUADRANT D
01‐MA225 BLDG. 01 ‐ LEVEL 12 MECHANICAL FLOOR PLAN ‐ QUADRANT E
01‐MA231 BLDG. 01 ‐ LEVELS 13 & 14 MECHANICAL FLOOR PLAN ‐ QUADRANTS B & E
01‐ME101 BLDG. 01 ‐ LEVEL 00 MECHANICAL ENLARGED PLANS
01‐ME102 BLDG. 01 ‐ LEVELS 00 & 01 MECHANICAL ENLARGED PLANS
01‐ME103 BLDG. 01 ‐ LEVEL 01 MECHANICAL ENLARGED PLANS
01‐ME104 BLDG. 01 ‐ LEVELS 02‐04 MECHANICAL ENLARGED PLANS
01‐ME105 BLDG. 01 ‐ LEVELS 05‐07 MECHANICAL ENLARGED PLANS
01‐ME106 BLDG. 01 ‐ LEVELS 08‐11 MECHANICAL ENLARGED PLANS
01‐ME107 BLDG. 01 ‐ LEVELS 12‐14 MECHANICAL ENLARGED PLANS
02‐ME101 BLDG. 02 ‐ LEVEL 02 MECHANICAL FLOOR PLAN
06‐ME101 BLDG. 06 ‐ LEVEL 01 MECHANICAL FLOOR PLAN
08‐ME101 BLDG. 08 ‐ LEVEL 01 MECHANICAL FLOOR PLAN
09‐ME101 BLDG. 09 ‐ LEVEL 00 MECHANICAL FLOOR PLAN
Project Number 636‐21‐704 May 15, 2023
VA 05‐20
00 01 15 ‐ 10
15‐ME101 BLDG. 15 ‐ LEVEL 02 MECHANICAL FLOOR PLAN
ACC‐MA101 BLDG. ACC ‐ LEVEL 00 MECHANICAL FLOOR PLAN ‐ QUADRANT A
ACC‐MA102 BLDG. ACC ‐ LEVEL 00 MECHANICAL FLOOR PLAN ‐ QUADRANT B
ACC‐MA103 BLDG. ACC ‐ LEVEL 00 MECHANICAL FLOOR PLAN ‐ QUADRANT C
ACC‐MA111 BLDG. ACC ‐ LEVEL 01 MECHANICAL FLOOR PLAN ‐ QUADRANT A
ACC‐MA112 BLDG. ACC ‐ LEVEL 01 MECHANICAL FLOOR PLAN ‐ QUADRANT B
ACC‐MA113 BLDG. ACC ‐ LEVEL 01 MECHANICAL FLOOR PLAN ‐ QUADRANT C
ACC‐MA114 BLDG. ACC ‐ LEVEL 01 MECHANICAL FLOOR PLAN ‐ QUADRANT D
ACC‐MA121 BLDG. ACC ‐ LEVEL 02 MECHANICAL FLOOR PLAN ‐ QUADRANT A
ACC‐MA122 BLDG. ACC ‐ LEVEL 02 MECHANICAL FLOOR PLAN ‐ QUADRANT B
ACC‐MA123 BLDG. ACC ‐ LEVEL 02 MECHANICAL FLOOR PLAN ‐ QUADRANT C
ACC‐MA124 BLDG. ACC ‐ LEVEL 02 MECHANICAL FLOOR PLAN ‐ QUADRANT D
ACC‐ME101 BLDG. ACC ‐ LEVEL 00 MECHANICAL ENLARGED PLANS
ACC‐ME102 BLDG. ACC ‐ LEVEL 01 MECHANICAL ENLARGED PLANS
ACC‐ME103 BLDG. ACC ‐ LEVEL 02 MECHANICAL ENLARGED PLANS
D‐ME101 BLDG. D ‐ LEVEL 01 MECHANICAL FLOOR PLAN
G‐ME101 BLDG. G ‐ LEVEL 01 MECHANICAL FLOOR PLAN
PLUMBING
P‐100 PLUMBING LEGEND, NOTES, SCHEDULES, AND ABBREVIATIONS
P‐101 DRY FOG HUMIDIFICATION SCHEMATIC AND COMPRESSED AIR RISER
P‐102 PLUMBING DETAILS
PLUMBING
01‐PA101 BLDG. 01 ‐ LEVEL 00 PLUMBING FLOOR PLAN ‐ QUADRANT A
01‐PA102 BLDG. 01 ‐ LEVEL 00 PLUMBING FLOOR PLAN ‐ QUADRANT B
01‐PA103 BLDG. 01 ‐ LEVEL 00 PLUMBING FLOOR PLAN ‐ QUADRANT C
01‐PA104 BLDG. 01 ‐ LEVEL 00 PLUMBING FLOOR PLAN ‐ QUADRANT D
01‐PA105 BLDG. 01 ‐ LEVEL 00 PLUMBING FLOOR PLAN ‐ QUADRANT E
01‐PA111 BLDG. 01 ‐ LEVEL 01 PLUMBING FLOOR PLAN ‐ QUADRANT A
01‐PA112 BLDG. 01 ‐ LEVEL 01 PLUMBING FLOOR PLAN ‐ QUADRANT B
01‐PA113 BLDG. 01 ‐ LEVEL 01 PLUMBING FLOOR PLAN ‐ QUADRANT C
01‐PA114 BLDG. 01 ‐ LEVEL 01 PLUMBING FLOOR PLAN ‐ QUADRANT D
01‐PA115 BLDG. 01 ‐ LEVEL 01 PLUMBING FLOOR PLAN ‐ QUADRANT E
01‐PA122 BLDG. 01 ‐ LEVEL 02 PLUMBING FLOOR PLAN ‐ QUADRANT B
01‐PA123 BLDG. 01 ‐ LEVEL 02 PLUMBING FLOOR PLAN ‐ QUADRANT C
01‐PA124 BLDG. 01 ‐ LEVEL 02 PLUMBING FLOOR PLAN ‐ QUADRANT D
01‐PA125 BLDG. 01 ‐ LEVEL 02 PLUMBING FLOOR PLAN ‐ QUADRANT E
01‐PA132 BLDG. 01 ‐ LEVEL 03 PLUMBING FLOOR PLAN ‐ QUADRANT B
01‐PA133 BLDG. 01 ‐ LEVEL 03 PLUMBING FLOOR PLAN ‐ QUADRANT C
01‐PA134 BLDG. 01 ‐ LEVEL 03 PLUMBING FLOOR PLAN ‐ QUADRANT D
01‐PA135 BLDG. 01 ‐ LEVEL 03 PLUMBING FLOOR PLAN ‐ QUADRANT E
01‐PA142 BLDG. 01 ‐ LEVEL 04 PLUMBING FLOOR PLAN ‐ QUADRANT B
Project Number 636‐21‐704 May 15, 2023
VA 05‐20
00 01 15 ‐ 11
01‐PA143 BLDG. 01 ‐ LEVEL 04 PLUMBING FLOOR PLAN ‐ QUADRANT C
01‐PA144 BLDG. 01 ‐ LEVEL 04 PLUMBING FLOOR PLAN ‐ QUADRANT D
01‐PA145 BLDG. 01 ‐ LEVEL 04 PLUMBING FLOOR PLAN ‐ QUADRANT E
01‐PA152 BLDG. 01 ‐ LEVEL 05 PLUMBING FLOOR PLAN ‐ QUADRANT B
01‐PA153 BLDG. 01 ‐ LEVEL 05 PLUMBING FLOOR PLAN ‐ QUADRANT C
01‐PA154 BLDG. 01 ‐ LEVEL 05 PLUMBING FLOOR PLAN ‐ QUADRANT D
01‐PA155 BLDG. 01 ‐ LEVEL 05 PLUMBING FLOOR PLAN ‐ QUADRANT E
01‐PA162 BLDG. 01 ‐ LEVEL 06 PLUMBING FLOOR PLAN ‐ QUADRANT B
01‐PA163 BLDG. 01 ‐ LEVEL 06 PLUMBING FLOOR PLAN ‐ QUADRANT C
01‐PA164 BLDG. 01 ‐ LEVEL 06 PLUMBING FLOOR PLAN ‐ QUADRANT D
01‐PA165 BLDG. 01 ‐ LEVEL 06 PLUMBING FLOOR PLAN ‐ QUADRANT E
01‐PA172 BLDG. 01 ‐ LEVEL 07 PLUMBING FLOOR PLAN ‐ QUADRANT B
01‐PA173 BLDG. 01 ‐ LEVEL 07 PLUMBING FLOOR PLAN ‐ QUADRANT C
01‐PA174 BLDG. 01 ‐ LEVEL 07 PLUMBING FLOOR PLAN ‐ QUADRANT D
01‐PA175 BLDG. 01 ‐ LEVEL 07 PLUMBING FLOOR PLAN ‐ QUADRANT E
01‐PA182 BLDG. 01 ‐ LEVEL 08 PLUMBING FLOOR PLAN ‐ QUADRANT B
01‐PA183 BLDG. 01 ‐ LEVEL 08 PLUMBING FLOOR PLAN ‐ QUADRANT C
01‐PA184 BLDG. 01 ‐ LEVEL 08 PLUMBING FLOOR PLAN ‐ QUADRANT D
01‐PA185 BLDG. 01 ‐ LEVEL 08 PLUMBING FLOOR PLAN ‐ QUADRANT E
01‐PA192 BLDG. 01 ‐ LEVEL 09 PLUMBING FLOOR PLAN ‐ QUADRANT B
01‐PA193 BLDG. 01 ‐ LEVEL 09 PLUMBING FLOOR PLAN ‐ QUADRANT C
01‐PA194 BLDG. 01 ‐ LEVEL 09 PLUMBING FLOOR PLAN ‐ QUADRANT D
01‐PA195 BLDG. 01 ‐ LEVEL 09 PLUMBING FLOOR PLAN ‐ QUADRANT E
01‐PA202 BLDG. 01 ‐ LEVEL 10 PLUMBING FLOOR PLAN ‐ QUADRANT B
01‐PA203 BLDG. 01 ‐ LEVEL 10 PLUMBING FLOOR PLAN ‐ QUADRANT C
01‐PA204 BLDG. 01 ‐ LEVEL 10 PLUMBING FLOOR PLAN ‐ QUADRANT D
01‐PA205 BLDG. 01 ‐ LEVEL 10 PLUMBING FLOOR PLAN ‐ QUADRANT E
01‐PA212 BLDG. 01 ‐ LEVEL 11 PLUMBING FLOOR PLAN ‐ QUADRANT B
01‐PA213 BLDG. 01 ‐ LEVEL 11 PLUMBING FLOOR PLAN ‐ QUADRANT C
01‐PA214 BLDG. 01 ‐ LEVEL 11 PLUMBING FLOOR PLAN ‐ QUADRANT D
01‐PA215 BLDG. 01 ‐ LEVEL 11 PLUMBING FLOOR PLAN ‐ QUADRANT E
01‐PA222 BLDG. 01 ‐ LEVEL 12 PLUMBING FLOOR PLAN ‐ QUADRANT B
01‐PA225 BLDG. 01 ‐ LEVEL 12 PLUMBING FLOOR PLAN ‐ QUADRANT E
01‐PA231 BLDG. 01 ‐ LEVELS 13 & 14 PLUMBING FLOOR PLAN ‐ QUADRANTS B & E
01‐PE101 BLDG. 01 ‐ LEVEL 00 PLUMBING ENLARGED PLANS
01‐PE102 BLDG. 01 ‐ LEVEL 00 PLUMBING ENLARGED PLANS
01‐PE103 BLDG. 01 ‐ LEVELS 00 & 01 PLUMBING ENLARGED PLANS
01‐PE104 BLDG. 01 ‐ LEVEL 01 PLUMBING ENLARGED PLANS
01‐PE105 BLDG. 01 ‐ LEVELS 02‐04 PLUMBING ENLARGED PLANS
01‐PE106 BLDG. 01 ‐ LEVELS 05‐08 PLUMBING ENLARGED PLANS
01‐PE107 BLDG. 01 ‐ LEVELS 09‐12 & 14 PLUMBING ENLARGED PLANS
02‐PE101 BLDG. 02 ‐ LEVEL 02 PLUMBING FLOOR PLAN
06‐PE101 BLDG. 06 ‐ LEVEL 01 PLUMBING FLOOR PLAN
08‐PE101 BLDG. 08 ‐ LEVEL 01 PLUMBING FLOOR PLAN
09‐PE101 BLDG. 09 ‐ LEVEL 00 PLUMBING FLOOR PLAN
Project Number 636‐21‐704 May 15, 2023
VA 05‐20
00 01 15 ‐ 12
15‐PE101 BLDG. 15 ‐ LEVEL 02 PLUMBING FLOOR PLAN
D‐PE101 BLDG. D ‐ LEVEL 01 PLUMBING FLOOR PLAN
G‐PE101 BLDG. G ‐ LEVEL 01 PLUMBING FLOOR PLAN
ELECTRICAL
E‐001 ELECTRICAL LEGEND, NOTES, AND ABBREVIATIONS
ES‐100 ELECTRICAL SITE PLAN
ES‐101 ELECTRICAL SITE PLAN
ELECTRICAL
01‐ED100 BUILDING 01 ‐ LEVEL 00 ELECTRICAL DEMOLITION PLAN
01‐ED101 BUILDING 01 ‐ LEVEL 01 ELECTRICAL DEMOLITION PLAN
01‐ED102 BUILDING 01 ‐ LEVEL 02 ELECTRICAL DEMOLITION PLAN
01‐ED103 BUILDING 01 ‐ LEVEL 03 & 04 ELECTRICAL DEMOLITION PLAN
01‐ED104 BUILDING 01 ‐ LEVEL 05 & 06 ELECTRICAL DEMOLITION PLAN
01‐ED105 BUILDING 01 ‐ LEVEL 07 & 08 ELECTRICAL DEMOLITION PLAN
01‐ED106 BUILDING 01 ‐ LEVEL 09 & 10 ELECTRICAL DEMOLITION PLAN
01‐ED107 BUILDING 01 ‐ LEVEL 11, 12, & 14 ELECTRICAL DEMOLITION PLAN
01‐EP100 BUILDING 01 ‐ LEVEL 00 ELECTRICAL FLOOR PLAN
01‐EP101 BUILDING 01 ‐ LEVEL 00 ELECTRICAL FLOOR PLAN
01‐EP102 BUILDING 01 ‐ LEVEL 01 ELECTRICAL FLOOR PLAN
01‐EP103 BUILDING 01 ‐ LEVEL 02 ELECTRICAL FLOOR PLAN
01‐EP104 BUILDING 01 ‐ LEVEL 03 & 04 ELECTRICAL FLOOR PLAN
01‐EP105 BUILDING 01 ‐ LEVEL 05 & 06 ELECTRICAL FLOOR PLAN
01‐EP106 BUILDING 01 ‐ LEVEL 07 & 08 ELECTRICAL FLOOR PLAN
01‐EP107 BUILDING 01 ‐ LEVEL 09 & 10 ELECTRICAL FLOOR PLAN
01‐EP108 BUILDING 01 ‐ LEVEL 11 & 12 ELECTRICAL FLOOR PLAN
01‐EP109 BUILDING 01 ‐ LEVEL 13 & 14 ELECTRICAL ROOF PLAN
01‐EP110 BUILDING 01 ‐ ELECTRICAL RISER DIAGRAM
02‐ED100 BUILDING 02 ‐ LEVEL 02 ELECTRICAL DEMOLITION PLAN
02‐EP100 BUILDING 02 ‐ LEVEL 02 ELECTRICAL FLOOR PLAN
06‐ED100 BUILDING 06 ‐ LEVEL 01 ELECTRICAL DEMOLITION PLAN
06‐EP100 BUILDING 06 ‐ LEVEL 01 ELECTRICAL FLOOR PLAN
08‐ED100 BUILDING 08 ‐ LEVEL 01 ELECTRICAL DEMOLITION PLAN
08‐EP100 BUILDING 08 ‐ LEVEL 01 ELECTRICAL FLOOR PLAN
09‐ED100 BUILDING 09 ‐ LEVEL 00 ELECTRICAL DEMOLITION PLAN
09‐EP100 BUILDING 09 ‐ LEVEL 00 ELECTRICAL FLOOR PLAN
15‐ED100 BUILDING 15 ‐ LEVEL 01 ELECTRICAL DEMOLITION PLAN
15‐ED101 BUILDING 15 ‐ LEVEL 02 ELECTRICAL DEMOLITION PLAN
15‐EP100 BUILDING 15 ‐ LEVEL 01 ELECTRICAL FLOOR PLAN
15‐EP101 BUILDING 15 ‐ LEVEL 02 ELECTRICAL FLOOR PLAN
ACC‐ED100 BUILDING ACC ‐ LEVEL 00 ELECTRICAL DEMOLITION PLAN
ACC‐ED101 BUILDING ACC ‐ LEVEL 01 ELECTRICAL DEMOLITION PLAN
Project Number 636‐21‐704 May 15, 2023
VA 05‐20
00 01 15 ‐ 13
ACC‐ED102 BUILDING ACC ‐ LEVEL 02 ELECTRICAL DEMOLITION PLAN
ACC‐EP100 BUILDING ACC ‐ LEVEL 00 ELECTRICAL FLOOR PLAN
ACC‐EP101 BUILDING ACC ‐ LEVEL 01 ELECTRICAL FLOOR PLAN
ACC‐EP102 BUILDING ACC ‐ LEVEL 02 ELECTRICAL FLOOR PLAN
D‐ED100 BUILDING D ‐ LEVEL 01 ELECTRICAL DEMOLITION PLAN
D‐EP100 BUILDING D ‐ LEVEL 01 ELECTRICAL FLOOR PLAN
G‐EP100 BUILDING G ‐ LEVEL 01 ELECTRICAL FLOOR PLAN
ELECTRICAL
E‐400 ELECTRICAL DETAILS
E‐401 ELECTRICAL DETAILS
E‐500 ELECTRICAL SCHEDULES
E‐501 ELECTRICAL SCHEDULES
E‐502 ELECTRICAL SCHEDULES
E‐503 ELECTRICAL SCHEDULES
E‐504 ELECTRICAL SCHEDULES
E‐505 ELECTRICAL SCHEDULES
E‐506 ELECTRICAL SCHEDULES
E‐507 ELECTRICAL SCHEDULES
E‐508 ELECTRICAL SCHEDULES
TECHNOLOGY
00‐TN000 TECHNOLOGY COVERSHEET
00‐TN001 TECHNOLOGY NOTES AND SHEET INDEX
00‐TN002 SITE PLAN ‐ TECHNOLOGY
01‐TD100 LEVEL 00 FLOOR DEMOLITION PLAN ‐TECHNOLOGY
01‐TD100A LEVEL 00 FLOOR DEMOLITION PLAN ‐TECHNOLOGY
01‐TD100B LEVEL 00 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT B
01‐TD100C LEVEL 00 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT C
01‐TD100D LEVEL 00 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT D
01‐TD100E LEVEL 00 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT E
01‐TD101 LEVEL 01 FLOOR DEMOLITION PLAN ‐TECHNOLOGY
01‐TD101A LEVEL 01 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT A
01‐TD101B LEVEL 01 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT B
01‐TD101C LEVEL 01 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT C
01‐TD101D LEVEL 01 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT D
01‐TD101E LEVEL 01 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT E
01‐TD102 LEVEL 02 FLOOR DEMOLITION PLAN ‐TECHNOLOGY
01‐TD102B LEVEL 02 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT B
Project Number 636‐21‐704 May 15, 2023
VA 05‐20
00 01 15 ‐ 14
01‐TD102C LEVEL 02 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT C
01‐TD102D LEVEL 02 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT D
01‐TD102E LEVEL 02 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT E
01‐TD103 LEVEL 03 FLOOR DEMOLITION PLAN ‐TECHNOLOGY
01‐TD103B LEVEL 03 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT B
01‐TD103C LEVEL 03 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT C
01‐TD103D LEVEL 03 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT D
01‐TD103E LEVEL 03 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT E
01‐TD104 LEVEL 04 FLOOR DEMOLITION PLAN ‐TECHNOLOGY
01‐TD104B LEVEL 04 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT B
01‐TD104C LEVEL 04 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT C
01‐TD104D LEVEL 04 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT D
01‐TD104E LEVEL 04 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT E
01‐TD105 LEVEL 05 FLOOR DEMOLITION PLAN ‐TECHNOLOGY
01‐TD105B LEVEL 05 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT B
01‐TD105C LEVEL 05 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT C
01‐TD105D LEVEL 05 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT D
01‐TD105E LEVEL 05 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT E
01‐TD106 LEVEL 06 FLOOR DEMOLITION PLAN ‐TECHNOLOGY
01‐TD‐106B LEVEL 06 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT B
01‐TD‐106C LEVEL 06 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT C
01‐TD‐106D LEVEL 06 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT D
01‐TD‐106E LEVEL 06 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT E
01‐TD‐107 LEVEL 07 FLOOR DEMOLITION PLAN ‐TECHNOLOGY
01‐TD‐107B LEVEL 07 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT B
01‐TD‐107C LEVEL 07 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT C
01‐TD‐107D LEVEL 07 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT D
01‐TD‐107E LEVEL 07 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT E
01‐TD‐108 LEVEL 08 FLOOR DEMOLITION PLAN ‐TECHNOLOGY
01‐TD‐108B LEVEL 08 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT B
01‐TD‐108C LEVEL 08 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT C
01‐TD‐108D LEVEL 08 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT D
01‐TD‐108E LEVEL 08 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT E
01‐TD‐109 LEVEL 09 FLOOR DEMOLITION PLAN ‐TECHNOLOGY
01‐TD‐109B LEVEL 09 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT B
01‐TD‐109C LEVEL 09 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT C
01‐TD‐109D LEVEL 09 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT D
01‐TD‐109E LEVEL 09 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT E
01‐TD‐110 LEVEL 10 FLOOR DEMOLITION PLAN ‐TECHNOLOGY
01‐TD‐110B LEVEL 10 FLOOR DEMOLITION PLAN‐ TECHNOLOGY ‐ QUADRANT B
Project Number 636‐21‐704 May 15, 2023
VA 05‐20
00 01 15 ‐ 15
01‐TD‐110C LEVEL 10 FLOOR DEMOLITION PLAN‐ TECHNOLOGY ‐ QUADRANT C
01‐TD‐110D LEVEL 10 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT D
01‐TD‐110E LEVEL 10 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT E
01‐TD‐111 LEVEL 11 FLOOR DEMOLITION PLAN ‐TECHNOLOGY
01‐TD‐111B LEVEL 11 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT B
01‐TD‐111C LEVEL 11 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT C
01‐TD‐111D LEVEL 11 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT D
01‐TD‐111E LEVEL 11 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT E
01‐TD‐112 LEVEL 12 FLOOR DEMOLITION PLAN ‐TECHNOLOGY
01‐TD‐112B LEVEL 12 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT B
01‐TD‐112D LEVEL 12 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT D
01‐TD‐112E LEVEL 12 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT E
01‐TD‐113 LEVEL 13 FLOOR DEMOLITION PLAN ‐TECHNOLOGY
01‐TD‐113B LEVEL 13 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT B
01‐TD‐113E LEVEL 13 FLOOR DEMOLITION PLAN ‐ TECHNOLOGY ‐ QUADRANT E
01‐TD‐114 LEVEL 14 FLOOR DEMOLITION PLAN ‐TECHNOLOGY
01‐TD‐114E LEVEL 14 FLOOR DEMOLITION ‐ TECHNOLOGY ‐ QUADRANT E
01‐TN100 LEVEL 00 FLOOR PLAN ‐ TECHNOLOGY
01‐TN100A LEVEL 00 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT A
01‐TN100B LEVEL 00 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT B
01‐TN100C LEVEL 00 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT C
01‐TN100D LEVEL 00 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT D
01‐TN100E LEVEL 00 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT E
01TN100TR LEVEL 00 ‐ TECHNOLOGY ROOM ENLARGEMENTS
01TN100TR LEVEL 00 ‐ TECHNOLOGY ROOM ENLARGEMENTS
01TN100TR LEVEL 00 ‐ TECHNOLOGY ROOM ENLARGEMENTS
01TN100TR BLDG. 01 ‐ LEVEL 00 ‐ TECHNOLOGY ROOM ENLARGEMENTS
01‐TN101 LEVEL 01 FLOOR PLAN ‐ TECHNOLOGY
01‐TN101A LEVEL 01 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT A
01‐TN101B LEVEL 01 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT B
01‐TN101C LEVEL 01 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT C
01‐TN101D LEVEL 01 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT D
01‐TN101E LEVEL 01 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT E
01TN101TR LEVEL 01 ‐ TECHNOLOGY ROOM ENLARGEMENTS
01TN101TR LEVEL 01 ‐ TECHNOLOGY ROOM ENLARGEMENTS
01‐TN102 LEVEL 02 FLOOR PLAN ‐ TECHNOLOGY
01‐TN102B LEVEL 02 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT B
01‐TN102C LEVEL 02 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT C
01‐TN102D LEVEL 02 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT D
01‐TN102E LEVEL 02 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT E
Project Number 636‐21‐704 May 15, 2023
VA 05‐20
00 01 15 ‐ 16
01‐TN102TR LEVEL 02 ‐ TECHNOLOGY ROOM ENLARGEMENTS
01‐TN103 LEVEL 03 FLOOR PLAN ‐ TECHNOLOGY
01‐TN103B LEVEL 03 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT B
01‐TN103C LEVEL 03 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT C
01‐TN103D LEVEL 03 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT D
01‐TN103E LEVEL 03 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT E
01‐TN103TR LEVEL 03 ‐ TECHNOLOGY ROOM ENLARGEMENTS
01‐TN104 LEVEL 04 FLOOR PLAN ‐ TECHNOLOGY
01‐TN104B LEVEL 04 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT B
01‐TN104C LEVEL 04 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT C
01‐TN104D LEVEL 04 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT D
01‐TN104E LEVEL 04 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT E
01‐TN104TR LEVEL 04 ‐ TECHNOLOGY ROOM ENLARGEMENTS
01‐TN105 LEVEL 05 FLOOR PLAN ‐ TECHNOLOGY
01‐TN105B LEVEL 05 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT B
01‐TN105C LEVEL 05 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT C
01‐TN105D LEVEL 05 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT D
01‐TN105E LEVEL 05 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT E
01‐TN105TR LEVEL 05 ‐ TECHNOLOGY ROOM ENLARGEMENTS
01‐TN106 LEVEL 06 FLOOR PLAN ‐ TECHNOLOGY
01‐TN106B LEVEL 06 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT B
01‐TN106C LEVEL 06 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT C
01‐TN106D LEVEL 06 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT D
01‐TN106E LEVEL 06 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT E
01‐TN106TR LEVEL 06 ‐ TECHNOLOGY ROOM ENLARGEMENTS
01‐TN107 LEVEL 07 FLOOR PLAN ‐ TECHNOLOGY
01‐TN107B LEVEL 07 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT B
01‐TN107C LEVEL 07 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT C
01‐TN107D LEVEL 07 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT D
01‐TN107E LEVEL 07 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT E
01‐TN107TR LEVEL 07 ‐ TECHNOLOGY ROOM ENLARGEMENTS
01‐TN108 LEVEL 08 FLOOR PLAN ‐ TECHNOLOGY
01‐TN108B LEVEL 08 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT B
01‐TN108C LEVEL 08 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT C
01‐TN108D LEVEL 08 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT D
01‐TN108E LEVEL 08 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT E
01‐TN108TR LEVEL 08 ‐ TECHNOLOGY ROOM ENLARGEMENTS
01‐TN109 LEVEL 09 FLOOR PLAN ‐ TECHNOLOGY
01‐TN109B LEVEL 09 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT B
01‐TN109C LEVEL 09 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT C
Project Number 636‐21‐704 May 15, 2023
VA 05‐20
00 01 15 ‐ 17
01‐TN109D LEVEL 09 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT D
01‐TN109E LEVEL 09 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT E
01‐TN109TR LEVEL 09 ‐ TECHNOLOGY ROOM ENLARGEMENTS
01‐TN110 LEVEL 10 FLOOR PLAN ‐ TECHNOLOGY
01‐TN110B LEVEL 10 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT B
01‐TN110C LEVEL 10 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT C
01‐TN110D LEVEL 10 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT D
01‐TN110E LEVEL 10 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT E
01‐TN110TR LEVEL 10 ‐ TECHNOLOGY ROOM ENLARGEMENTS
01‐TN111 LEVEL 11 FLOOR PLAN ‐ TECHNOLOGY
01‐TN111B LEVEL 11 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT B
01‐TN111C LEVEL 11 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT C
01‐TN111D LEVEL 11 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT D
01‐TN111E LEVEL 11 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT E
01‐TN111TR LEVEL 11 ‐ TECHNOLOGY ROOM ENLARGEMENTS
01‐TN112 LEVEL 12 FLOOR PLAN ‐ TECHNOLOGY
01‐TN112B LEVEL 12 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT B
01‐TN112E LEVEL 12 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT E
01‐TN112TR LEVEL 12 ‐ TECHNOLOGY ROOM ENLARGEMENTS
01‐TN113 LEVEL 13 FLOOR PLAN ‐ TECHNOLOGY
01‐TN113E LEVEL 13 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT E
01‐TN114 LEVEL 14 FLOOR PLAN ‐ TECHNOLOGY
01‐TN114E LEVEL 14 FLOOR PLAN ‐ TECHNOLOGY ‐ QUADRANT E
01‐TN114TR LEVEL 14 ‐ TECHNOLOGY ROOM ENLARGEMENTS
02‐TN200 LEVEL 00 FLOOR PLAN ‐ TECHNOLOGY
02‐TN201 LEVEL 01 FLOOR PLAN ‐ TECHNOLOGY
02‐TN202 LEVEL 02 FLOOR PLAN ‐ TECHNOLOGY
06‐TD101 LEVEL 01 FLOOR DEMOLITION PLAN ‐TECHNOLOGY
06‐TN101 LEVEL 01 FLOOR PLAN ‐ TECHNOLOGY
06‐TN101TR LEVEL 01 TECHNOLOGY ROOM ENLARGEMENTS
08‐TN201 LEVEL 01 FLOOR PLAN ‐ TECHNOLOGY
09‐T‐201TR LEVEL 00 ‐ TECHNOLOGY ROOM ENLARGEMENTS
09‐TD100 LEVEL 00 FLOOR DEMOLITION PLAN ‐TECHNOLOGY
09‐TD101 LEVEL 01 FLOOR DEMOLITION PLAN ‐TECHNOLOGY
09‐TN100 LEVEL 00 FLOOR PLAN ‐ TECHNOLOGY
09‐TN101 LEVEL 01 FLOOR PLAN ‐ TECHNOLOGY
09‐TN101TR LEVEL 00 ‐ TECHNOLOGY ROOM ENLARGEMENTS
15‐TD100 LEVEL 00 FLOOR DEMOLITION PLAN ‐TECHNOLOGY
15‐TD101 LEVEL 01 FLOOR DEMOLITION PLAN ‐TECHNOLOGY
15‐TD102 LEVEL 02 FLOOR DEMOLITION PLAN ‐TECHNOLOGY
Project Number 636‐21‐704 May 15, 2023
VA 05‐20
00 01 15 ‐ 18
15‐TD103 LEVEL 03 FLOOR DEMOLITION PLAN ‐TECHNOLOGY
15‐TN100 LEVEL 00 FLOOR PLAN ‐ TECHNOLOGY
15‐TN101 LEVEL 01 FLOOR PLAN ‐ TECHNOLOGY
15‐TN102 LEVEL 02 FLOOR PLAN ‐ TECHNOLOGY
15‐TN103 LEVEL 03 FLOOR PLAN ‐ TECHNOLOGY
ACC‐TN100 LEVEL 00 ‐ TECHNOLOGY
ACC‐TN101 LEVEL 01 ‐ TECHNOLOGY
ACC‐TN102 LEVEL 02 ‐ TECHNOLOGY
D‐TN101 LEVEL 01 FLOOR PLANS ‐ TECHNOLOGY
G‐TN101 LEVEL 01 FLOOR PLANS ‐ TECHNOLOGY
TN400 TECHNOLOGY DETAILS
TN401 TECHNOLOGY DETAILS
TN500 TECHNOLOGY DIAGRAMS
TN501 TECHNOLOGY DIAGRAMS
TN502 TECHNOLOGY DIAGRAMS
TN503 TECHNOLOGY DIAGRAMS
TN504 TECHNOLOGY DIAGRAMS
TN505 TECHNOLOGY DIAGRAMS
TN506 TECHNOLOGY DIAGRAMS
TN507 TECHNOLOGY DIAGRAMS
TN508 TECHNOLOGY DIAGRAMS
TN600 TECHNOLOGY SCHEDULES
100% Construc on Documents
Project Number 636‐21‐704
May 15, 2023
VA 05‐01‐21
01 00 00 ‐1
SECTION 01 00 00
GENERAL REQUIREMENTS
GENERAL
1.1 SAFETY REQUIREMENTS
a. Refer to sec on 01 35 26, SAFETY REQUIREMENTS for safety and infec on control requirements.
1.2 GENERAL INTENTION
a. Contractor shall completely prepare site for building opera ons, including demoli on and removal of exis ng structures, and furnish labor and materials and perform work for Project
Number 636‐21‐704 Project tle Omaha EHRM Infrastructure Upgrade Design as required by drawings and specifica ons.
b. Visits to the site by Bidders may be made in accordance with what is listed in the solicita on and at the discre on of the Contrac ng Officer. Only one site visit will be scheduled prior to the bid date. A endance is recommended.
c. Offices of Romanyk Consul ng Corpora on , as Architect Engineers, will render certain technical services during construc on. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirma ons by Contrac ng Officer or his duly authorized representa ve. A/E informa on as follows:
Company Romanyk Consul ng Corpora on
Address 3308 Preston Road, Suite 350‐164
Plano, Texas 75093
Phone 1‐855‐424‐3838 ext 315
Email jim.booher@romanykconsul ng.com
Email Yumei Wang <Yumei.Wang@romanykconsul ng.com>
d. Before placement and installa on of work subject to tests by tes ng laboratory retained by
Department of Veterans Affairs, the Contractor shall no fy the COR in sufficient me to enable
Project Number 636‐21‐704
May 15, 2023
VA 05‐01‐21
01 00 00 ‐2 tes ng laboratory personnel to be present at the site in me for proper taking and tes ng of specimens and field inspec on. Such prior no ce shall be not less than three workdays unless otherwise designated by the COR.
e. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be iden fied by project and employer, and restricted from unauthorized access.
1.3 STATEMENT OF BID ITEM(S)
f. ITEM I, GENERAL CONSTRUCTION: BASE BID: Contractor to provide all labor, equipment, materials and supervision…