ADD 1 - 02 Project Manual - 00 01 10 - TABLE OF CONTENTS - Addendum 1.pdf

PDF 304 KB Posted

Attached to
EHRM Infrastructure Construction Grand Island Project #636-21-701
Solicitation number
36C77623B0002
Issued by

About this file

This document contains a table of contents for the project manual for construction of the EHRM Infrastructure Upgrades at the Grand Island Veterans Affairs Medical Center in Grand Island, Nebraska under solicitation number 36C77623B0002. The project manual outlines specifications for various construction divisions involving demolition, hazardous material abatement, concrete, masonry, metals, wood, thermal and moisture protection, openings, finishes, specialties, equipment, furnishings, conveyances, fire suppression, plumbing, HVAC, electrical, communications, electronic safety and security, earthwork, exterior improvements, utilities, and transportation. The Department of Veterans Affairs Technology Acquisition Center in Austin is the contracting agency for this infrastructure construction opportunity.

View the file

Other files

File Type Posted
36C77623B0002 0004 Amendment - Bid Opening and Wage Rates.pdf PDF
Attachment 15 - Construction Wage Rates - Hall 01-13-2022.pdf PDF
ADD 1 - 01 Reports - 1947 Original Construction A2.pdf PDF
Alesia Addendum 1.pdf PDF
ADD 1 - 02 Project Manual - 07 40 00 - ROOFING AND SIDING PANELS - Addendum 1.pdf PDF
ADD 1 - 03 Architectural - A-701.pdf PDF
ADD 1 - 01 Reports - Geotechnical Report 20220114 TD2.pdf PDF
ADD 1 - 02 Project Manual - 09 06 00 - SCHEDULE FOR FINISHES - Addendum 1.pdf PDF
ADD 1 - 03 Architectural - 19-A-102.pdf PDF
ADD 1 - 02 Project Manual - 26 32 13 - ENGINE GENERATORS - Addendum 1.pdf PDF
36C77623B0002 Amendment 0003 - Addendum 1.pdf PDF
ADD 1 - 03 Architectural - A-601.pdf PDF
ADD 1 - 01 Reports - HAZMAT Report GI VA EHRM 01-10-22.pdf PDF
SES Addendum 1.pdf PDF
ADD 1 - 03 General - GI002.pdf PDF
ADD 1 - 05 ME - ME Drawings Add 01.pdf PDF
ADD 1 - 03 Architectural - 19-A-201.pdf PDF
ADD 1 - 04 Civil - C3.0.pdf PDF
ADD 1 - 04 Civil - C2.0.pdf PDF
ADD 1 - 01 Reports - 1947 Original Construction S3.pdf PDF
36C77623B0002 Grand Island EHRM - Technical Questions and Answers.pdf PDF
36C77623B0002 0001 IFB Amendment - Grand Island.pdf PDF
Site Visit Sign-in Sheet - Grand Island.pdf PDF
Questions - 36C77623B0002 Grand Island.pdf PDF
Attachment 9 - Mechanical - Drawings.pdf PDF
Attachment 5 - Hazardous Materials - Drawings.pdf PDF
Attachment 16 - Site Visit Instructions.pdf PDF
Attachment 4 - Life Safety - Drawings.pdf PDF
Attachment 1 - Specifications 1.pdf PDF
Attachment 6 - Civil - Drawings.pdf PDF
Attachment 12 - COVID-19 Safety Protocols 12-14-21.pdf PDF
Attachment 13 - Limitations on Subcontracting - Construction.pdf PDF
Attachment 15 - Construction Wage Rates - Hall 09-02-2022.pdf PDF
Attachment 11 - Technology - Drawings.pdf PDF
Attachment 2 - Specifications 2.pdf PDF
Attachment 14 - Contractor Safety - Environmental Form.pdf PDF
36C77623B0002_1.pdf PDF
Attachment 10 - Electrical - Drawings.pdf PDF
Attachment 7 - Structural - Drawings.pdf PDF
Attachment 8 - Architectural - Drawings.pdf PDF
Attachment 3 - Drawings Sheet Index.pdf PDF
Show all 41

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

636a-21-701, EHRM Infrastructure Upgrades VAMC Grand Island, NE

03-01-22

00 01 10-1 Addendum 1

TABLE OF CONTENTS

Section 00 01 10

SECTION NO. DIVISION AND SECTION TITLES DATE

DIVISION 00 - SPECIAL SECTIONS

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 11-21 01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 11-21 01 33 23 Shop Drawings, Product Data, and Samples 06-21 01 35 26 Safety Requirements 11-21 01 42 19 Reference Standards 11-20 01 45 00 Quality Control 02-21 01 45 29 Testing Laboratory Services 11-18 01 45 35 Special Inspections 06-21 01 57 19 Temporary Environmental Controls 01-21 01 58 16 Temporary Interior Signage 07-15 01 74 19 Construction Waste Management 11-21 01 81 13 Sustainable Construction Requirements 10-17 01 91 00 General Commissioning Requirements 03-22

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition 08-17 02 82 13.13 Glovebag Asbestos Abatement 01-22 02 82 13.19 Asbestos Floor Tile and Mastic Abatement 01-22 02 83 33.13 Lead-Based Paint Removal and Disposal 01-22

DIVISION 03 – CONCRETE

03 30 00 Cast-in-Place Concrete 01-21

DIVISION 04 – MASONRY

04 05 13 Masonry Mortaring 10-17 04 05 16 Masonry Grouting 01-21 04 20 00 Unit Masonry 08-17 04 72 00 Cast Stone Masonry 01-21

DIVISION 05 – METALS

05 12 00 Structural Steel Framing 11-18 05 31 00 Steel Decking 01-21 05 36 00 Composite Metal Decking 01-21 05 40 00 Cold-Formed Metal Framing 01-21 05 50 00 Metal Fabrications 08-18

03-01-22

00 01 10-2 Addendum 1

SECTION NO. DIVISION AND SECTION TITLES DATE

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

06 10 00 Rough Carpentry 10-17

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 21 13 Thermal Insulation 01-21 07 22 00 Roof and Deck Insulation 01-21 07 27 27 Fluid-Applied Membrane Air Barrier, Vapor Retarding 01-21 07 40 00 Roofing and Siding Panels 01-21 07 53 23 Ethylene-Propylene-Diene-Monomer Roofing 01-21 07 60 00 Flashing and Sheet Metal 01-21 07 72 00 Roof Accessories 01-21 07 81 00 Applied Fireproofing 10-17 07 84 00 Firestopping 01-21 07 92 00 Joint Sealants 10-17

DIVISION 08 - OPENINGS

08 11 13 Hollow Metal Doors and Frames 01-21 08 14 00 Interior Wood Doors 01-21 08 34 53 Security Doors and Frames 01-21 08 56 59 Service and Teller Window Units 01-21 08 71 00 Door Hardware 01-21 08 80 00 Glazing 01-21 08 90 00 Louvers and Vents 01-21

DIVISION 09 – FINISHES

09 05 16 Subsurface Preparation for Floor Finishes 01-21 09 06 00 Schedule for Finishes 01-21 09 22 16 Non-Structural Metal Framing 06-18 09 29 00 Gypsum Board 04-20 09 51 00 Acoustical Ceilings 12-18 09 65 13 Resilient Base and Accessories 01-21 09 65 16 Resilient Sheet Flooring 05-18 09 65 19 Resilient Tile Flooring 05-18 09 68 00 Carpeting 01-21 09 72 16 Vinyl-Coated Fabric Wall Covering 01-21 09 91 00 Painting 01-21

DIVISION 10 – SPECIALTIES

10 14 00 Signage 01-21 10 26 00 Wall and Door Protection 01-21

DIVISION 11 – EQUIPMENT (Not Used)

03-01-22

00 01 10-3 Addendum 1

SECTION NO. DIVISION AND SECTION TITLES DATE

DIVISION 12 – FURNISHINGS

12 36 00 Countertops 12-18

DIVISION 13 - SPECIAL CONSTRUCTION (Not Used)

DIVISION 14– CONVEYING EQUIPEMENT (Not Used)

VOLUME 2

DIVISION 21- FIRE SUPPRESSION

21 08 00 Commissioning of Fire Suppression System 03-22 21 13 13 Wet-Pipe Sprinkler Systems 06-15 21 13 16 Dry-Pipe Sprinkler Systems 01-15 21-22-00 Clean Agent Fire Suppression Systems 05-15

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 09-20 22 05 23 General-Duty Valves for Plumbing Piping 09-20 22 07 11 Plumbing Insulation 09-19 22 08 00 Commissioning of Plumbing Systems 03-22 22 11 00 Facility Water Distribution 05-21 22 13 00 Facility Sanitary and Vent Piping 09-20 22 40 00 Plumbing Fixtures 09-15 22 62 00 Vacuum Systems for Laboratory and Healthcare Facilities 09-15 22 63 00 Gas Systems for Laboratory and Healthcare Facilities 09-15

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 02-20 23 05 12 General Motor Requirements for HVAC and Steam

Generation Equipment 02-20

23 05 41 Noise and Vibration Control for HVAC Piping and Equipment

02-20

23 05 93 Testing, Adjusting, and Balancing for HVAC 02-20 23 07 11 HVAC and Boiler Plant Insulation 02-20 23 08 00 Commissioning of HVAC Systems 03-22 23 09 23 Direct-Digital Control System for HVAC 09-11 23 10 00 Facility Fuel Oil Systems 04-20 23 21 13 Hydronic Piping 02-20 23 22 13 Steam and Condensate Heating Piping 02-20 23 23 00 Refrigerant Piping 02-20 23 31 00 HVAC Ducts and Casings 02-20 23 34 00 HVAC Fans 02-20 23 37 00 Air Outlets and Inlets 02-20 23 81 00 Decentralized Unitary HVAC Equipment 03-20 23 81 23 Computer-Room Air-Conditioners 03-20

03-01-22

00 01 10-4 Addendum 1

SECTION NO. DIVISION AND SECTION TITLES DATE

DIVISION 25 – INTEGRATED AUTOMATION (Not Used)

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 01-16 26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17 26 05 26 Grounding and Bonding for Electrical Systems 01-17 26 05 33 Raceway and Boxes for Electrical Systems 01-18 26 05 41 Underground Electrical Construction 01-17 26 05 73 Overcurrent Protective Device Coordination Study 01-18 26 08 00 Commissioning of Electrical Systems 03-22 26 22 00 Low-Voltage Transformers 01-18 26 23 13 Generator Paralleling Controls 01-17 26 24 13 Distribution Switchboards 01-18 26 24 16 Panelboards 01-18 26 25 11 Busways 01-17 26 27 26 Wiring Devices 01-18 26 29 21 Enclosed Switches and Circuit Breakers 01-17 26 32 13 Engine Generators 01-18 26 33 53 Static Uninterruptible Power Supply 01-17 26 36 23 Automatic Transfer Switches 01-17 26 43 13 Surge Protective Devices 01-17 26 51 00 Interior Lighting 01-18 26 56 00 Exterior Lighting 01-18

DIVISION 27 – COMMUNICATIONS

27 05 11 Requirements for Communications Installations 09-19 27 05 26 Grounding and Bonding for Communications Systems 06-15 27 05 33 Conduits and Boxes for Communications Systems 10-18 27 05 36 Cable Trays for Communications Systems 11-21 27 05 53 Identification for Communications Systems 07-21 27 08 00 Commissioning of Communications Systems 11-16 27 10 00 Structured Cabling 11-21 27 11 16 Communications Cabinets, Racks, Frames, and Enclosures 11-21 27 11 19 Communications Termination Block and Patch Panels 11-21 27 11 26 Communications Rack Mounted Power Protection and Power

Strips 11-21

27 13 13 Communications Copper Backbone Cabling 11-21 27 13 13.13 Communications Copper Cable Splicing and Terminations 11-21 27 13 23 Communications Optical Fiber Backbone Cabling 11-21 27 15 13 Communications Copper Horizontal Cabling 11-21 27 15 13.13 Communications Optical Fiber Splicing and Terminations 11-21 27 16 19 Communications Patch Cords, Station Cords, and Cross

Connect Wire 11-21

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 05 00 Common Work Results for Electronic Safety and Security 01-22

03-01-22

00 01 10-5 Addendum 1

SECTION NO. DIVISION AND SECTION TITLES DATE

28 05 13 Conductors and Cables for Electronic Safety and Security

01-22

28 05 26 Grounding and Bonding for Electronic Safety and Security

01-22

28 05 28.33 Conduits and Backboxes for Electronic Safety and Security

01-22

28 08 00 Commissioning of Electronic Safety and Security Systems 01-22 28 13 00 Physical Access Control System 01-22 28 23 00 Video Surveillance 01-22

DIVISION 31 – EARTHWORK

31 20 11 Earthwork (Short Form) 10-12 31 23 19 Dewatering 10-12

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 05 23 Cement and Concrete for Exterior Improvements 08-16 32 17 23 Pavement Markings 08-16

DIVISION 33 – UTILITIES

33 10 00 Water Utilities 03-17

DIVISION 34 – TRANSPORTATION Not Used

DIVISION 48 – Electrical Power Generation (Not Used)

03-01-22

00 01 10-6 Addendum 1

(This page is left blank intentionally)

File details come from the government source that posted it. Updated .