This federal contract opportunity notice is for construction services for the EHRM Infrastructure Upgrades at the Grand Island VAMC in Nebraska. The solicitation number is 36C77623B0002 and seeks offers for Project #636-21-701. The Department of Veterans Affairs Technology Acquisition Center Austin is the contracting agency. Construction services required include upgrades to the EHRM infrastructure at the Grand Island VAMC. The response due date is not specified in the notice. The award date is also not included. No pricing terms, set asides or incumbent information is provided in the opportunity description.
View the file
Other files
Show all 41
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HAZARDOUS BUILDING MATERIALS
INSPECTION REPORT
EHRM Infrastructure Upgrades VA Grand Island Healthcare System U.S. Department of Veterans Affairs
2201 North Broadwell Avenue Grand Island, NE 68803-2153
VA Project No: 636a-21-701
July 08, 2021 Revised January 10, 2022
Prepared for:
Veterans Affairs Medical Center c/o Alesia Architects, PC 3705 North 200th Street
Elkhorn, NE 68022
Prepared by:
AMI Environmental 8802 South 135th Street, Suite 100
Omaha, Nebraska 68138
AMI Project No. 21-185
TABLE OF CONTENTS
1. SURVEY OVERVIEW
1.1. Purpose and Scope
1.1.1. Inspection Area
1.1.2. Limitations
1.2. Regulatory Reference
2. BUILDING INFORMATION
2.1. General Construction
2.2. Pre-Existing Information
3. INSPECTION METHODOLOGIES
3.1. Asbestos Inspection
3.1.1. Key Definitions
3.1.2. Homogenous Material Numbering Convention
3.1.3. Bulk Sampling
3.2. Lead-Based Paint Inspection
3.2.1. Key Definitions
3.2.2. Homogenous Paint Applications Numbering Convention
3.2.3. Paint Chip Sampling
4. SUMMARY OF INSPECTION FINDINGS
4.1. Asbestos Inspection Findings
4.2. Lead Paint Inspection Findings
5. RISKS AND HAZARDS
5.1. Asbestos
5.2. Lead-Based Paint
6. RECOMMENDATIONS
6.1. General Recommendations
6.1.1. Asbestos
6.1.2. Lead-Based Paint
6.2. Hazardous Conditions Recommendations
6.3. Point Count Analysis / TEM Chatfield Analysis Recommendations
7. REGULATORY REQUIREMENTS
7.1. Asbestos-Containing Materials
7.1.1. Notification Requirements
7.1.2. Asbestos Removal Requirements
7.1.3. OSHA Regulation of <1 Percent Asbestos
7.1.4. Asbestos Removal Regulations
7.2. Lead-Based Paint
7.2.1. Disposal Requirements
7.2.2. Construction Requirements
APPENDIX A: Tables
APPENDIX B: Photo Logs
APPENDIX C: Analytical Results
APPENDIX D: Inspector’s Credentials
APPENDIX E: Schematics
HAZARDOUS BUILDING MATERIALS INSPECTION REPORT
EHRM Infrastructure Upgrades VA Grand Island Healthcare System U.S. Department of Veterans Affairs
2201 North Broadwell Avenue Grand Island, NE 68803-2153
7/08/21 REVISED 01/10/22
VA Project No: 636a-21-701
1. SURVEY OVERVIEW
The Hazardous Materials Survey was conducted with three site visits: On June 28, 2021, selected areas of Buildings: 01, 03, 04, 05, 06, 07, 08, and 17 at the Grand Island Veterans Affairs Health Care System, Grand Island, NE, were inspected for asbestos-containing material (ACM) and lead-based paint (LBP) by a representative of AMI Environmental (AMIE). On October 28, 2021, a second site visit was conducted due to scope of work increase. On December 17, 2021 rooms where displaced personnel will be moved to were sampled as well. The hazardous building materials inspection was conducted in preparation for renovation of the structure in accordance with the above referenced project. The renovation project is hereinafter referred to as The Project. The inspection was initiated at the request of Mr. Jim Hageman, NCARB, ACHA of Alesia Architects on behalf of the VA Medical Center.
The inspection was performed by Mr. Colin Lauenroth in accordance with regulatory requirements and generally accepted industry methods. Copies of applicable requisite training certificate for Mr.
Lauenroth is provided in Appendix D.
1.1. Purpose and Scope
The purpose and scope of the inspection was to identify and sample suspect Asbestos Containing Materials (ACMs) and Lead-based Paints (LBPs) in the project area that may be impacted by The Project.
1.1.1. Inspection Area
The hazardous building materials inspection included limited project specific interior and exterior areas of the subject structures which include the following: Building 01, 1st floor laundry room, C305 janitor closet & oxygen room, C404B, and N513B as well as the exterior windows of these rooms. Building 03 basement IT room. Building 04 basement IT room.
Building 05 basement storage room. Building 06 IT room. Building 07 IT room. Building 08 IT room. Building 17 South exterior wall. Following the scope of work change, the following rooms in Building 01 were added to the inspection area: Existing server room (C01), office (N02), Canteen office (C6), S111, S110, S202, S203, S302, S302A, S402, S502, S517, C404, C404, S208, N117/Vending area, NE2, NE3, N03, and N07. The above described areas are hereinafter referred to collectively as the Inspection Area.: See Appendix E for Schematics.
1.1.2. Limitations
Nondestructive sampling protocols were employed, where needed, to determine underlying materials. Limited quantities of suspect materials may possibly be present concealed inside wall or floor interstitial spaces of the building. Ceramic tiles were not sampled in occupied areas.
Rooms S302 and S302A were not sampled due to an outbreak of COVID-19.
Hazardous Building Materials Inspection Report AMI Project No. 21-185 VA Project 636a-21-701 Grand Island VA Medical Center 7/08/21 REVISED 01/10/22 Grand Island, NE Page of 9
It is recommended that prior to or during construction that any new materials discovered in the demolition process be tested or abated.
Sampling of these materials may not be necessary if, in the case of suspect ACM, the materials are assumed to be ACM or if they are determined by a licensed asbestos inspector to be homogenous to other materials that were sampled.
1.2. Regulatory Reference
The asbestos inspection was conducted in accordance with USEPA National Emission Standard for Hazardous Air Pollutants (NESHAP) regulations (ref.: 40 CFR, Part 61), following criteria established for identifying asbestos-containing building materials that may be impacted by planned renovation activities; applicable protocols established by the Asbestos Hazard Emergency Response Act (AHERA) (ref.: 40 CFR 763).
The State of Nebraska licenses asbestos inspectors to perform asbestos inspections in the State of Nebraska.
There is also no licensing requirement for lead-based paint sampling in non-HUD facilities.
2. BUILDING INFORMATION
2.1. General Construction
This project involves renovation of selected rooms within Buildings 01, 03, 04, 05, 06, 07, 08, and 17.
2.2. Pre-Existing Information
Information on previous surveys or sampling for lead-based paint or asbestos, was not provided.
3. INSPECTION METHODOLOGIES
3.1. Asbestos Inspection
The inspection and sampling were conducted in accordance with the USEPA National Emission Standard for Hazardous Air Pollutants (NESHAP) regulations (ref.: 40 CFR, Part 61), following criteria established for identifying asbestos-containing. building materials that may be impacted by planned renovation. Additional aspects of the inspection methodology are discussed below.
3.1.1. Key Definitions
3.1.1.1. Homogenous Material
Homogenous materials are unique applications of building materials uniform in color and texture. The homogeneity of a material can be further defined by area(s) of application. Bulk sampling is conducted to determine the asbestos content of a homogenous material.
Grand Island VA Medical Center 7/08/21 REVISED 01/10/22
3.1.1.2. Asbestos-Containing Material (ACM)
The Environmental Protection Agency (EPA) and the Occupational Safety and Health Administration (OSHA) define ACMs as any material that contains greater than one percent asbestos, as determined by visual area estimation (microscopic analysis). The State of Missouri follows the EPA standard. Some materials contain one percent or less asbestos. While these materials are not ACMs, by definition, they are still regulated by OSHA, for worker exposure.
3.1.1.3. Friable/Non-Friable ACM
Friable ACMs are materials that contain more than one percent asbestos and, when dry, can be crumbled, pulverized, or reduced to powder by hand pressure, thereby releasing fibers into the air more readily. In contrast, non-friable ACMs are ACMs that, when dry, cannot be crumbled, pulverized, or reduced to powder by hand pressure. Non-friable ACMs are grouped into two categories: Category I and Category
II.
3.1.1.4. Regulated Asbestos-Containing Materials (RACM)
Regulated Asbestos-Containing Materials (RACM) include friable ACMs and non-friable ACMs that, depending on their category, have become friable, have been subjected to specific forms of impact damage, have a high probability of becoming friable, and/or may become friable during removal.
3.1.2. Homogenous Material Numbering Convention
All suspect asbestos materials are assigned a unique homogeneous material number. AHERA identifies three basic material types: Surfacing Materials (SM), which include spray and trowel applied materials, such as fireproofing, ceiling texture, plaster, etc.; Thermal System Insulation (TSI), which includes insulating materials applied to mechanical and plumbing components for temperature preservation and condensation prevention purposes; and Miscellaneous Materials (MM), which includes all other materials, such as floor coverings and mastics, roofing materials, asbestos cement products, and many others. When a homogenous material has multiple layers, individual layers are identified and analyzed separately by laboratory analysis.
3.1.3. Bulk Sampling
Bulk sampling must be performed to determine whether suspect building material contains asbestos. Asbestos bulk sampling for the inspection was conducted in accordance with protocols established by the Asbestos Hazard Emergency Response Act (AHERA) (ref.: 40 CFR 763). Friability of the suspect asbestos-containing materials was determined by touching and/or sampling of the material.
3.1.3.1. Bulk Sample Numbering Convention
Bulk samples are given a sequence number when collected.
Grand Island VA Medical Center 7/08/21 REVISED 01/10/22
3.1.3.2. Polarized Light Microscopy Analysis (PLM)
Bulk samples collected during the inspection were submitted to an EPA accredited laboratory, EMSL Analytical, Inc. (EMSL), located at 200 Route 130 North, Cinnaminson, New Jersey. EMSL was instructed to perform Polarized Light Microscopy (PLM) analysis, utilizing dispersion staining techniques (ref: EPA Method 600/M4-82-020). PLM analysis is the most commonly used visual estimate method. While PLM analysis is acceptable to EPA, OSHA, and most states for determining asbestos content, some states now require more sophisticated methods when analyzing certain types of materials.
A total of 45 asbestos bulk samples were collected and submitted for laboratory analysis. PLM Analysis was performed on the 45 samples collected, including additional distinct layers (i.e. mastic). Heterogeneous applications are individual layers of different materials contained within a single bulk sampled, each of which must be analyzed individually to determine its asbestos content (e.g. vinyl floor tiles and mastic; cove base and mastic; etc.). Table 1 lists all samples collected and analyzed in the current survey.
Some samples and/or heterogeneous applications may not have been analyzed by the lab if a positive result was obtained from a sample that is among a group of samples representing a suspect material. This process, known as stop on first positive, is followed because if a single sample is found to be positive, that material is determined to be ACM, thus making it unnecessary to analyze any additional samples in the sampling group.
Please refer to the Table 1– Asbestos Material Sampling Table in Appendix A for a complete listing of all materials sampled. The laboratory analytical reports may be found in Appendix C for the current inspection.
3.1.3.3. Quantification Method Analysis
EPA regulations allow materials determined to contain less than 10 percent asbestos utilizing a visual estimate quantification method, such as PLM analysis, to be treated as non-asbestos containing if the material is re-analyzed using one of two quantification methods and determined to contain one percent or less of asbestos. The two acceptable quantification methods are point count analysis and TEM Chatfield analysis.
Quantification methods are more time-consuming and more expensive analytical procedures that are occasionally used to more accurately determine the amount of asbestos in certain samples. Because of their higher cost and the acceptable accuracy of the less expensive visual estimation method, laboratories do not typically perform quantification analyses unless specifically requested.
The quantification method known as point count analysis is used for most ACM types, except floor tile. The organic matrix composition of floor tile precludes the use of point count analysis to more accurately determine asbestos amounts within a sample.
Therefore, TEM Chatfield analysis—which effectively removes all organic materials, Grand Island VA Medical Center 7/08/21 REVISED 01/10/22 leaving only asbestos behind—is necessary to provide a more precise percentage of asbestos content in floor tile.
Please refer to section 6.0 Recommendations, for recommendations concerning supplemental analysis.
3.2. Lead-Based Paint Inspection
The LBP inspection included visual identification of homogenous paint applications and bulk sampling of the paint(s) for laboratory analysis. While the U. S. Department of Housing and Urban Development (HUD) promulgates guidelines for LBP inspections in child occupied facilities, there are no formal guidelines for non-HUD regulated inspections. Thus, the LBP inspection was conducted in accordance with generally accepted industry standards and practices. Additional aspects of the inspection methodology are discussed below.
3.2.1. Key Definitions
3.2.1.1. Homogenous Paint Applications
Homogenous paint applications are significant paint applications that are visually distinct by their color and uniformity. Significant paint applications do not include incidental occurrences of paint such as isolated occurrences of accent trim, artistic paints, etc. While visual inspection alone cannot generally identify sub-layers of paint, these applications are often identified in the XRF analysis.
3.2.1.2. Lead-Based Paint (LBP)
Pursuant to Federal Register, Vol. 61, No. 169, LBP is defined as paint or other surface coatings equal to or greater than 0.5 percent lead by weight or equal to or greater than 1 mg/cm2.
3.2.2. Homogenous Paint Applications Numbering Convention
Homogenous paints and coatings are assigned a unique homogeneous material number (HM#).
The HM# is referenced throughout the report to uniquely identify each paint application.
3.2.3. Lead-based Paint and Lead Containing Materials Sampling Sampling of suspected lead-based paint or other suspected lead containing materials was conducted using bulk sampling of the paint applications and materials identified. A total of 27 samples were collected and analyzed by Atomic Absorption to determine the lead content of materials or painted surfaces.
Grand Island VA Medical Center 7/08/21 REVISED 01/10/22
4. SUMMARY OF INSPECTION FINDINGS
Key findings of the hazardous building materials inspection are summarized below. Please refer to the Appendices for complete details of the inspection findings and supporting documentation.
4.1. Asbestos Inspection Findings
Below is a summary of the findings of the asbestos inspection:
Asbestos Containing Materials identified as follows:
• Laminate Flooring / Tan Bldg 1 20 % Chrysotile 150 SF
• Duct Mastic / Light Red Bldg 1 60 % Chrysotile 600 LF
• 12in x 12in Floor Tile / Beige Bldg 1 2 % Chrysotile 150 SF
• 9in x 9in Floor Tile / Black Bldg 1 4 % Chrysotile 16 SF
• 12in x 12in Floor Tile / Black Bldg. 1 3 % Chrysotile 150 SF
• 12in x 12in Floor Tile / Beige Bldg. 1 2 % Chrysotile 10 SF
Please refer to Table 1 – Asbestos Sampling Table in Appendix A for a complete listing of all asbestos sampling.
4.2. Lead Paint Inspection Findings
Below is a summary of the findings of the lead-based paint inspection:
Lead-based Paint identified as follows:
• White Radiator Pipe Bldg. 6 IT Room 11% Lead 24 SF/20 LF
• Gray Door Frame Bldg. 6 IT Room 2.1% Lead 9 SF
• Yellow Door Frame Bldg. 1 NE3 & NE1 0.59% Lead 2 EA
Paint containing lead below 0.5% and Suspect Lead Containing Ceramic Tile was found. (See Section 7.2.2 29 CFR 1926.62 Lead in Construction)
Please refer to Table 2 – Lead Paint Sampling Table in Appendix A for a complete listing of all lead-based paint and lead containing materials sampling.
5. RISKS AND HAZARDS
5.1. Asbestos
To be a significant health concern, asbestos fibers must be inhaled. When asbestos fibers are inhaled, they become lodged in the lung tissue or alveoli. Here they clog and scar the tissues, causing the walls of the alveoli to lose their elasticity and useful function in respiration. Asbestosis (scarring of the lung), lung
Grand Island VA Medical Center 7/08/21 REVISED 01/10/22 cancer, and Mesothelioma (cancer of the lining of the chest or lining of the abdominal wall) are diseases associated with asbestos exposure. Risks and hazards increase with increased exposure. ACM condition, proximity to building occupants, building use, and other factors can influence the potential for asbestos fibers to become airborne, and therefore increase exposure risks.
5.2. Lead-Based Paint
Inhalation and ingestion are the major routes of lead exposure. Once in the body, lead is distributed via the bloodstream to red blood cells, soft-tissue and bone. The kidneys and gastrointestinal (GI) tract eliminate lead in the body very slowly, while minute amounts are lost through perspiration.
Lead in the body can cause serious damage to the central and peripheral nervous system, the cardiovascular system, and the kidneys. Exposure to high concentrations of lead can cause retardation, convulsions, coma, and sometimes death. Children are especially vulnerable and susceptible to lead poisoning. Even low levels of exposure persisting during childhood are known to slow a child’s normal development and cause learning and behavioral problems. Exposure to lead can result from deteriorating surfaces and activities mechanically impacting lead surfaces. Preventing exposure requires proper work practices, monitoring, disposal and personal protective equipment during demolition, alteration and friction producing activities.
6. RECOMMENDATIONS
The purpose of this section is to interpret survey findings and provide preliminary recommendations that may be relevant and appropriate at this time. Because this document is a presentation of investigative findings, recommendations related to future construction activities are inherently general in nature. More specific determinations concerning hazardous building materials to be impacted by construction should be made during the abatement project design process.
6.1. General Recommendations
6.1.1. Asbestos
State and/or federal regulations require that ACMs be removed prior to demolition or renovation activities that will impact the ACMs. Depending on the specific renovation work to be performed, certain ACMs may not require removal if they will not be disturbed and do not pose a risk to building occupants or construction trade workers. However, to ensure worker safety and to eliminate future asbestos-related maintenance and management costs and risks, AMIE recommends removal of all identified ACMs in the areas to be renovated. While partial abatement may be technically possible, it is often impractical and not cost-effective.
ACMs not impacted by renovation or demolition activities should be inspected annually and maintained in good condition. ACMs deemed to be in less than good condition (damaged or significantly damaged) should be repaired or removed and replaced. Such repairs should be performed by qualified persons and in accordance with regulatory guidelines.
6.1.2. Lead-Based Paint and Lead Containing Materials
Facility owners are ultimately liable for their lead-containing hazardous waste from cradle to grave. EPA regulations provide two ways to determine whether a waste stream, such as
Grand Island VA Medical Center 7/08/21 REVISED 01/10/22 demolition debris containing LBP, must be classified as hazardous waste. Waste generators can either test the waste using an approved testing method (Toxicity Characteristic Leaching Procedure [TCLP]), or they can apply knowledge of the hazardous characteristic of the waste.
Based on the initial lead paint testing results, AMIE recommends TCLP testing be conducted on the existing building materials, painted and unpainted, prior to the start of renovation or demolition activity. In addition, trade contractors who work in the facility should also be notified of the presence of lead so that they can appropriately monitor and protect their workers against lead exposure.
Any lead-based painted building components not removed during renovation should be considered for inclusion in a facility management plan that maintains potential exposure below OSHA action levels and ensures the material will be handled properly and in accordance with applicable regulations.
6.2. Hazardous Conditions Recommendations
No hazardous conditions, from hazardous materials, were observed in the building during the inspection.
6.3. Point Count Analysis / TEM Chatfield Analysis Recommendations AMIE does not recommend Point Count or TEM Chatfield analysis of any of the ACMs identified.
7. REGULATORY REQUIREMENTS
7.1. Asbestos-Containing Materials
The removal and disposal of ACMs is regulated at the federal, state, and, sometimes, local level. While some states have developed their own regulatory standards for the various asbestos disciplines, many states have adopted the federal standards but have established licensing requirements and enforcement authority at the state level.
7.1.1. Notification Requirements
EPA’s NESHAP regulation, 40 CFR, Subpart M, 61.145, Standard for Demolition and Renovation, stipulates that an owner of a facility submit proper notification with either the EPA’s regional office and/or the state and local regulatory agency of intention to demolish or renovate. Notifications must be received by the appropriate regulatory agencies 10 working days prior to commencement of asbestos stripping or removal, or other site work. If the demolition or renovation date changes, or the scope of work is increased, another notification is required.
7.1.2. Asbestos Removal Requirements
Asbestos removal must be performed by a licensed abatement contractor. The contractor should follow all work practices, worker protection, and disposal requirements set forth in the contract specifications and by the Occupational Safety and Health Administration (OSHA)
Grand Island VA Medical Center 7/08/21 REVISED 01/10/22 and the EPA. Key federal regulations concerning asbestos include 29 CFR 1910.1001, 29 CFR 1926.1101, 40 CFR Part 61, Subpart M, and 40 CFR 763.
7.1.3. OSHA Regulation of ≤ 1 Percent Asbestos
While EPA and many states do not regulate materials containing one percent or less asbestos, OSHA regulates materials containing any amount of asbestos. (Ref. OSHA Construction Industry Standard, 29 CFR 1926.1101(a)(3))
7.1.4. State of Nebraska Asbestos Removal Regulations
The State of Nebraska has adopted the EPA NESHAP regulations for asbestos removal and requires asbestos removal contractors to be licensed with the state. Asbestos Containing Building Material (ACBM) should only be removed by licensed and accredited contractors in the State of Nebraska.
7.2. Lead Waste
7.2.1. Disposal Requirements
The Resource Conservation and Recovery Act (RCRA) classifies lead-containing waste streams as hazardous materials if TCLP levels exceed five parts per million. If TCLP leachable lead levels exceed that threshold, EPA regulations (40 CFR 261) require the waste stream to be handled and disposed of as a hazardous waste. Waste streams containing less the five parts per million of leachable lead are classified as non-hazardous waste and can be disposed of in a construction and demolition landfill.
7.2.2. Construction Requirements
OSHA’s 29 CFR 1926.62 regulates worker exposure to lead during construction activities that include demolition or salvage of structures where lead or materials containing lead are present, as well as removal or encapsulation of lead-containing materials. The standard establishes maximum limits of exposure to lead, including a permissible exposure limit and action level, and should be adhered to during construction and demolition activities.
APPENDIX A
Tables
Table 1 – Asbestos Materials Sampling Table
Table 2 – Lead Paint Sampling Table
Table 1 – Asbestos Material Sampling Table
Table I
Table 1: Asbestos-Containing Material Sampling Table & Test Results AMI Project No.: 21-185 Grand Island VA, Omaha, NE January 10, 2022
HA #/
Description
Sample
ID
Layers ID # Color Location Sample
Result Condition Friable (Y/N)
Estimated Quantity Photo No.
001:
Caulking/Putties
/ Gray 01 01 White Bldg 8 IT Room None
Detected
002:
Caulking/Putties
/ Red 02 02 Red Bldg 8, IT Room None
Detected
002:
Caulking/Putties
/ Red 29 29 Red Bldg 3
Basement None
Detected
002:
Caulking/Putties
/ Red 34 34 Red
Bldg 5, Basement Storage
None Detected
003: Pipe Insulation, Wrap, Mudded End Cap / White
03 03-Wrap Tan/ Silver
Room 6, IT Room
None Detected
003: Pipe Insulation, Wrap, Mudded End Cap / White
03 03- Insulation Yellow Room 6, IT
Room None
Detected
003: Pipe Insulation, Wrap, Mudded End Cap / White
03 03-End Cap White Room 6, IT
Room None
Detected
004: Fire Caulk / Red
04 04 Red Bldg 7, IT Room None
Detected
AMI Project No.: 21-185 Grand Island VA, Omaha, NE January 10, 2022
HA #/
Description
Sample
ID
Layers ID # Color Location Sample
Result Condition Friable (Y/N)
Estimated Quantity Photo No.
005:
Caulking/Putties
/ Light Gray 05 05 White
Building 1, Exterior
Windows None
Detected
005:
Caulking/Putties
/ Light Gray 06 06 White
Building 1, Exterior
Windows None
Detected
006: Interior Window Caulk /
Light Gray 07 07 White Bldg 1, All
Floors None
Detected
006: Interior Window Caulk /
Light Gray 08 08 White
Bldg 1, All Floors None
Detected
007: Pipe Wrap, Insulation, And Mastic / White
09 09-Wrap Tan/ Silver
Bldg 1, All Floors None
Detected
007: Pipe Wrap, Insulation, And Mastic / White
09 09- Insulation Yellow
Bldg 1, All Floors None
Detected
007: Pipe Wrap, Insulation, And Mastic / White
09 09- Mastic White
Bldg 1, All Floors None
Detected
007: Pipe Wrap, Insulation, And Mastic / White
10 10- Mastic White
Bldg 1, All Floors None
Detected
007: Pipe Wrap, Insulation, And Mastic / White
10 10-Wrap Tan/ Silver
Bldg 1, All Floors None
Detected
007: Pipe Wrap, Insulation, And Mastic / White
10 10- Insulation Yellow
Bldg 1, All Floors None
AMI Project No.: 21-185 Grand Island VA, Omaha, NE January 10, 2022
HA #/
Description
Sample
ID
Layers ID # Color Location Sample
Result Condition Friable (Y/N)
Estimated Quantity Photo No.
007: Pipe Wrap, Insulation, And Mastic / White
35 35- Mastic White
Bldg 5 Basement Storage
None Detected
007: Pipe Wrap, Insulation, And Mastic / White
35 35-Wrap White/ Silver
Bldg 5 Basement Storage
None Detected
007: Pipe Wrap, Insulation, And Mastic / White
35 35- Insulation Yellow
Bldg 5 Basement Storage
None Detected
008: 12in X 12in Ceiling Tile /
White / Rough 11 11 Gray/
White Bldg 1, C305 Janitor Closet
None Detected
008: 12in X 12in Ceiling Tile /
White / Rough 12 12 Gray/
White Bldg 1, C305 Janitor Closet
None Detected
009:
Drywall/Joint Compound Composite /
White
13 13 Brown/ White
Bldg 1, 1st Floor Laundry Room and Bldg 1, 3rd
Floor Oxygen Room, Throughout Bldg
None Detected
009:
Drywall/Joint Compound Composite /
White
14 14 Brown/ White
Bldg 1, 3rd Floor Laundry Room and 3rd Floor
Oxygen Room, Throughout Bldg
None Detected
009:
Drywall/Joint Compound Composite /
White
30 30 Brown/ White
Bldg 3 Basement
None
AMI Project No.: 21-185 Grand Island VA, Omaha, NE January 10, 2022
HA #/
Description
Sample
ID
Layers ID # Color Location Sample
Result Condition Friable (Y/N)
Estimated Quantity Photo No.
009:
Drywall/Joint Compound Composite /
White
31 31 Brown/ White
Bldg 3 Basement
None Detected
009:
Drywall/Joint Compound Composite /
White
36 36 Brown/ White
Bldg 5, Basement Storage
None Detected
009:
Drywall/Joint Compound Composite /
White
37 37 Brown/ White
Bldg 5, Basement Storage
None Detected
010: Plaster (Skim Coat) /
White 15 15 White Bldg 1, C305
Janitor Closet None
Detected
010: Plaster (Skim Coat) /
White 16 16 White Bldg 1, C305
Janitor Closet None
Detected
010: Plaster (Skim Coat) /
White 17 17 White Bldg 1, C305
Janitor Closet None
Detected
010: Plaster (Skim Coat) /
White 21 21 White Bldg 1, C404B None
Detected
010: Plaster (Skim Coat) /
White 22 22 White Bldg 1, C404B None
AMI Project No.: 21-185 Grand Island VA, Omaha, NE January 10, 2022
HA #/
Description
Sample
ID
Layers ID # Color Location Sample
Result Condition Friable (Y/N)
Estimated Quantity Photo No.
011: 12in X 12in Floor Tile /
Beige 18 18-
Mastic Black Bldg 1, C305 Janitor Closet
None Detected
011: 12in X 12in Floor Tile /
Beige 18 18-Floor
Tile Beige Bldg 1, C305 Janitor Closet
None Detected
011: 12in X 12in Floor Tile /
Beige 19 19-Floor
Tile Beige Bldg 1, C305 Janitor Closet
None Detected
011: 12in X 12in Floor Tile /
Beige 19 19-
Mastic Black Bldg 1, C305 Janitor Closet
None Detected
012: Cove Base / Gray 20 20-
Mastic Tan
Bldg 1, C305 Janitor Closet and Bldg 1, 3rd Floor Oxygen
Room
None Detected
012: Cove Base / Gray 20 20-Cove
Base Gray
Bldg 1, C305 Janitor Closet and Bldg 1, 3rd Floor Oxygen
Room
None Detected
013: 2ft X 4ft Ceiling Tile /
White / Wormhole
23 23 Gray/ White
Bldg 1, C404B, S502, S402, S302 & S30A (Assumed), S111, S110, Server Room, TR C6
None Detected
013: 2ft X 4ft Ceiling Tile /
White / Wormhole
24 24 Gray/ White
Bldg 1, C404B, S502, S402, S302 & S30A (Assumed), S111, S110, None
AMI Project No.: 21-185 Grand Island VA, Omaha, NE January 10, 2022
HA #/
Description
Sample
ID
Layers ID # Color Location Sample
Result Condition Friable (Y/N)
Estimated Quantity Photo No.
Server Room, TR C6
014: Laminate Flooring / Tan 25 25-
Mastic Tan/ Black Bldg 1, N513B <1 %
Chrysotile
014: Laminate Flooring / Tan 25 25-
Flooring Gray/ White Bldg 1, N513B 20 %
Chrysotile Fair N 150 SF 14
014: Laminate Flooring / Tan 25 25-
Mastic Blue/Gr een Bldg 1, N513B None Detected
014: Laminate Flooring / Tan 26 26-
Mastic Blue/ Green Bldg 1, N513B None
Detected
014: Laminate Flooring / Tan 26 26-
Mastic Black/ Yellow Bldg 1, N513B <1 %
Chrysotile
014: Laminate Flooring / Tan 26 26-
Flooring Gray/ White Bldg 1, N513B 20 %
Chrysotile Fair N Included Above 14
015: 12in X 12in Floor Tile / White With Speckles
27 27-Floor Tile White Bldg 3
Basement None
Detected
015: 12in X 12in Floor Tile / White With Speckles
27 27- Mastic Yellow Bldg 3
Basement None
Detected
015: 12in X 12in Floor Tile / White With Speckles
28 28- Mastic Yellow Bldg 3
Basement None
AMI Project No.: 21-185 Grand Island VA, Omaha, NE January 10, 2022
HA #/
Description
Sample
ID
Layers ID # Color Location Sample
Result Condition Friable (Y/N)
Estimated Quantity Photo No.
015: 12in X 12in Floor Tile / White With Speckles
28 28-Floor Tile White Bldg 3
Basement None
Detected
017: 12in X 12in Floor Tile / Blue
With Specks 32 32-Floor
Tile Gray/ Blue
Bldg 4 Basement
None Detected
017: 12in X 12in Floor Tile / Blue
With Specks 32 32-
Mastic Yellow Bldg 4 Basement
None Detected
017: 12in X 12in Floor Tile / Blue
With Specks 33 33-Floor
Tile Gray/Bl ue Bldg 4
Basement None
Detected
017: 12in X 12in Floor Tile / Blue
With Specks 33 33-
Mastic Yellow Bldg 4 Basement
None Detected
018: Exterior Building Caulk /
Light Gray 38 38 Gray
Bldg 17, Exterior South
Wall
None Detected
2nd Site Visit
001: Duct Mastic / Light
Red 39 39-
Mastic Light Red
Bldg 1, Above Drop Ceiling on
Duct Work, S502, S402, S302 & S30A (Assumed) S203, S202, S111, S110, Server Room, TR C6 , S517, C404A, N3, NE1, and N7
60 % Chrysotile Good N
~40 LF Per Room
(Total: 600 LF)
AMI Project No.: 21-185 Grand Island VA, Omaha, NE January 10, 2022
HA #/
Description
Sample
ID
Layers ID # Color Location Sample
Result Condition Friable (Y/N)
Estimated Quantity Photo No.
001: Duct Mastic / Peach 39 39-
Mastic Red Bldg 1, Above
Drop Ceiling, All Floors
<1 % Chrysotile
002: 12in x 12in Floor Tile /
Beige 40 40-Floor
Tile Beige Bldg 1, S402, Under Carpet
2 % Chrysotile Good N 150 SF 19
002: 12in x 12in Floor Tile /
Beige 40 40-
Mastic Yellow Bldg 1, S402, Under Carpet
None Detected
003: 12in x 12in Floor Tile / Beige with
Brown Streaks 41 41-
Mastic Black Bldg 1, Canteen
Office, Under Carpet
None Detected
003: 12in x 12in Floor Tile / Beige with
Brown Streaks 41 41-
Mastic Yellow/ Green
Bldg 1, Canteen Office, Under
Carpet
None Detected
003: 12in x 12in Floor Tile / Beige with
Brown Streaks 41 41-Floor
Tile Tan Bldg 1, Canteen
Office, Under Carpet
None Detected
004: 9in x 9in Floor Tile /
Black 42 42-Floor
Tile Black Bldg 1, Closet in Canteen Office (1st
Floor)
4 % Chrysotile Good N 16 SF 21
004: 9in x 9in Floor Tile / Black 42 42-
Mastic Black Bldg 1, Closet in Canteen Office
(1st Floor)
<1 % Chrysotile
AMI Project No.: 21-185 Grand Island VA, Omaha, NE January 10, 2022
HA #/
Description
Sample
ID
Layers ID # Color Location Sample
Result Condition Friable (Y/N)
Estimated Quantity Photo No.
005:
Fireproofing /
Gray 43 43 Gray
Bldg 1, Sub- Basement, Under Server Room
None Detected
005:
Fireproofing /
Gray 44 44 Gray
Bldg 1, Sub- Basement, Under Server Room
None Detected
005:
Fireproofing /
Gray 45 45 Gray
Bldg 1, Sub- Basement, Under Server Room
None Detected
3rd Site Visit
001: Gray Interior Window
Caulking 46 46 Gray
S517 None Detected 23
001: Gray Interior Window
Caulking 47 47 Gray
S517 None Detected 23
002: Gray 12” x 12” VFT with yellow mastic and green carpet mastic
48 48- Mastic Yellow
S517 None Detected
002: Gray 12” x 12” VFT with yellow mastic and green carpet mastic
48 48 - Floor Tile Gray
S517 None Detected
002: Gray 12” x 12” VFT with yellow mastic and green carpet mastic
48 48- Mastic Green
S517 None
AMI Project No.: 21-185 Grand Island VA, Omaha, NE January 10, 2022
HA #/
Description
Sample
ID
Layers ID # Color Location Sample
Result Condition Friable (Y/N)
Estimated Quantity Photo No.
002: Gray 12” x 12” VFT with yellow mastic and green carpet mastic
49 49- Mastic Yellow
S517
<1 % Chrysotile 24
002: Gray 12” x 12” VFT with yellow mastic and green carpet mastic
49 49-Floor Tile Gray S517 None
Detected 24
002: Gray 12” x 12” VFT with yellow mastic and green carpet mastic
49 49- Mastic Green S517 None
Detected 24
003: Gray with speckles12” x 12” Vinyl Floor Tile with Black
Mastic
50 50-Vinyl Floor Tile Gray C404A None
Detected 25
003: Gray with speckles12” x 12” Vinyl Floor Tile with Black
Mastic
50 50- Mastic Black C404A None
Detected 25
003: Gray with speckles12” x 12” Vinyl Floor Tile with Black
Mastic
51 51- Vinyl Floor Tile Gray C404A None
Detected 25
003: Gray with speckles12” x 12” Vinyl Floor
51 51- Mastic Black C404A None
Detected 25
AMI Project No.: 21-185 Grand Island VA, Omaha, NE January 10, 2022
HA #/
Description
Sample
ID
Layers ID # Color Location Sample
Result Condition Friable (Y/N)
Estimated Quantity Photo No.
Tile with Black Mastic
004: White Floor Leveler 52 52-
Leveler White S208 None
Detected 26
004: White Floor Leveler 52 52-
Mastic Yellow S208 None
Detected 26
004: White Floor Leveler 53 53-
Leveler White S208 None
Detected 26
004: White Floor Leveler 53 53-
Mastic Yellow S208 None
Detected 26
005: Plaster (Gray) w/Skim Coat (White)
54 54-Skim Coat White N117 Vending
Area
None Detected 27
005: Plaster (Gray) w/Skim Coat (White)
54 54- Plaster Gray N117 Vending
Area
None Detected 27
005: Plaster (Gray) w/Skim Coat (White)
55 55-Skim Coat White N117 Vending
Area
None Detected 27
005: Plaster (Gray) w/Skim Coat (White)
55 55- Plaster Gray N117 Vending
Area
None Detected 27
005: Plaster (Gray) w/Skim Coat (White)
56 56-Skim Coat White N117 Vending
Area
None Detected 27
005: Plaster (Gray) w/Skim Coat (White)
56 56- Plaster Gray N117 Vending
Area
None Detected 27
006: Gray Brick Mortar 57 57 Gray
N117 Vending Area
None Detected 28
006: Gray Brick Mortar 58 58 Gray
N117 Vending Area
None Detected 28
AMI Project No.: 21-185 Grand Island VA, Omaha, NE January 10, 2022
HA #/
Description
Sample
ID
Layers ID # Color Location Sample
Result Condition Friable (Y/N)
Estimated Quantity Photo No.
006: Gray Brick Mortar 59 59 Gray
N117 Vending Area
None Detected 28
007: 12"x12” Black VFT with Black Mastic
60 60- Mastic Yellow Room N3
None Detected 29
007: 12"x12” Black VFT with Black Mastic
60 60-Floor Tile Black Room N3 3%
Chrysotile Good N 150 SF 29
007: 12"x12” Black VFT with Black Mastic
60-
Mastic Black Room N3 None
Detected 29
007: 12"x12” Black VFT with Black Mastic
61-
Mastic Yellow Room N3 None
Detected 29
007: 12"x12” Black VFT with Black Mastic
61 61-Floor Tile Black Room N3 Positive
Stop Good N See above 29
007: 12"x12” Black VFT with Black Mastic
61-
Mastic Black Room N3 Insufficient Material 29
008: Brick Mortar, Gray/Tan 62 62 Tan Room N3 None
Detected 30
009: Brick (Tan) 63 63 Tan Room N3 None Detected 31
010: 12"x12" VFT, Beige with
Tan Specks with Black
Mastic
64 64- Floor Tile Beige NE3 + NE1
Hallway 2%
Chrysotile Good N 10 SF 32
010: 12"x12" VFT, Beige with Tan Specks with
Black Mastic
64 64- Mastic Black NE3 + NE1
Hallway
Detected 32
AMI Project No.: 21-185 Grand Island VA, Omaha, NE January 10, 2022
HA #/
Description
Sample
ID
Layers ID # Color Location Sample
Result Condition Friable (Y/N)
Estimated Quantity Photo No.
011: Ceramic Brick Mortar
(Brown) 65 65 Tan N7
None Detected 33
011: Ceramic Brick Mortar
(Brown) 66 66 Brown N7
Detected 33
Table 2
Table 2: Lead Based Paint Sampling Table & Test Results AMI Project No.: 21-185 Grand Island VA, Omaha, NE January 10, 2022
Sample Location Description Substrate Color Paint Condition Lab Result Photo No. Quantity
L1 Bldg 8, IT Room Wall Board Paint Wood Gray Good 0.045 % wt
L2 Bldg 8, IT Room Ceramic Wall Paint Ceramic Tan Good <0.0080 % wt
L3 Bldg 8, IT Room Door/Door Frame Paint Metal Tan Good <0.010 % wt
L4 Bldg 6, IT Room Ceiling/Wall Paint Concrete White Fair <0.0080 % wt
L5 Bldg 6, IT Room Radiator & Pipe Paint Metal White Fair 11 % wt
Radiator
(24 SF),
Pipe
(20 LF)
L6 Bldg 6, IT Room Door Frame Paint Metal Gray Good 2.1 % wt
6 1 EA
(9 SF)
L7 Bldg 7, IT Room Wall/Door/Door Frame Paint Wood Cream Good <0.0080 % wt
L8 Exterior of Building 1 Railing Paint Metal Black Good 0.15 % wt
L9 Bldg 1, 1st Floor Laundry Room
Wall/Ceiling/Door Frame Paint Plaster
White, Blue, Tan
Good 0.051 % wt
L10 Bldg 1, 1st Floor Laundry Room Floor Paint Concrete Black Fair 0.11 % wt
AMI Project No.: 21-185 Grand Island VA, Omaha, NE January 10, 2022
Sample Location Description Substrate Color Paint Condition Lab Result Photo No. Quantity
L11 Bldg 1, 1st Floor Laundry Room
Radiator And Pipe Paint Metal White Poor 0.30 % wt
L12
Bldg 1, C305, Janitor Closet and
Oxygen Room, N513B, S502, S402
Wall Paint Sheetrock/Wallboard Beige Good <0.0080 % wt
L13 Bldg 1, C305
Janitor Closet and Oxygen Room
Door Frame Paint Metal Gray Good <0.0080 % wt
L14
Bldg 1, C305 Janitor Closet, South Wall and
513B
Ceramic Wall Tile Ceramic Gray Good <0.0080 % wt
L15 Bldg 1, C404B, TR C6
Rectangular Wall Tile Ceramic Tan Good
Not Sampled, Only
Documented
L16 Bldg 1, C404B Base Tile Ceramic Brown Good Not Sampled
Only Documented
L17 Bldg 1, C404B, S110, S111 Wall Paint Plaster White Good 0.087 % wt
L18
Bldg 1, C404B, 513B, S502, S402, S202, S 203, S110, S111, Server Room, TR-C6
Door Frame Paint Metal White, Green Good <0.016 % wt
AMI Project No.: 21-185 Grand Island VA, Omaha, NE January 10, 2022
Sample Location Description Substrate Color Paint Condition Lab Result Photo No. Quantity
L19 Bldg 3 and 4 Basement Wall Paint Plaster White Good <0.0080 % wt
L20 Bldg 3 and 4 Basement, IT
Room Floor Paint Concrete Gray Good 0.015 % wt
L21 Bldg 3, 4, and 5 Basement, IT
Room Door Frame Paint Metal White Good 0.015 % wt
L22 Bldg 4, Basement Wall Paint Sheetrock/Wallboard Tan Good <0.015 % wt
L23 Bldg 5, Basement Storage Wall Paint Concrete White Good 0.015 % wt
2nd Site Visit
L24 Bldg 1,5th Floor, Room S502 Perimeter Walls
Wall Paint Plaster Light Green Flaking 0.30 % wt 24
L25 Bldg 1, 4th Floor, Room S402, Perimeter Walls
Wall Paint Plaster Peach Flaking 0.18 % wt 25
L26
Bldg 1, Ground Floor, Server
Room Doors and Door Frames
Door/ Door Frame Paint Metal Bluish
Green Cracking/ Flaking 0.088 % wt 26
AMI Project No.: 21-185 Grand Island VA, Omaha, NE January 10, 2022
Sample Location Description Substrate Color Paint Condition Lab Result Photo No. Quantity
L27 Bldg 1, Ground Floor, Server Room Walls
Wall Paint Plaster Light Blue Cracking 0.17 % wt 27
3rd Site Visit
L28 N117 Vending Area Blue Plaster Wall Paint Plaster Blue Cracking .015 % wt 28
L29 N117 Vending Area Green Plaster Wall Paint Plaster Green Cracking .10% % wt 29
L30 Room N3 Radiator Paint Metal White Cracking .19 % wt 30
L31 Above Ceiling Rm N3 Brick Paint Brick Yellow Good <.0083 % wt 31
L32 NE 3 & NE 1 Door Frame Paint Metal Yellow Cracking 0.59 % wt 32 2 Each
APPENDIX B
Photo Logs
Asbestos Photo Log
Lead-Based Paint Photo Log
Asbestos-Containing Material Photo Log AMI Project No.: 21-185
PHOTO 1
PHOTO 2
PHOTO 3
PHOTO 4
PHOTO 5
PHOTO 6
PHOTO 7
PHOTO 8
PHOTO 9
PHOTO 10
PHOTO 11 PHOTO 12
PHOTO 13
PHOTO 14
Laminate Flooring, 20% Chrysotile. Located in Building 1, Room: N513 B, Under Carpet
PHOTO 15 PHOTO 16
PHOTO 17
PHOTO 18 Duct Mastic / Peach (60% Chrysotile)
Located on Ductwork Above Ceiling Tiles in All Rooms in Building 1
PHOTO 19
12” x 12” Floor Tile / Beige (2% Chrysotile). Located in Building 1, Room S402, Under Carpet
PHOTO 20 PHOTO 21 9” x 9” Floor Tile / Black (4%
Chrysotile) Located in Building 1, Canteen Office Closet on 1st Floor
PHOTO 22
PHOTO 23 001: Gray Interior Window Caulking PHOTO 24
002: Gray 12” x 12” VFT with yellow mastic and green carpet mastic
PHOTO 25 003: Gray with speckles12” x 12” Vinyl
Floor Tile with Black Mastic PHOTO 26 004: White Floor Leveler
PHOTO 27 005: Plaster (Gray) w/Skim Coat (White) PHOTO 28 006: Gray Brick Mortar
PHOTO 29 007: 12"x12” Black VFT PHOTO 30
008: Brick Mortar, Gray/Tan
PHOTO 31 009: Brick (Tan) PHOTO 32 010: 12"x12" VFT, Beige with Tan
Specks with Black Mastic
PHOTO 33 011: Ceramic Brick Mortar (Brown)
Lead Based Paint Photo Log
PHOTO 1
Wall Board Paint, Gray PHOTO 2
Ceramic Wall Paint, Tan
PHOTO 3
Door/Door Frame Paint, Tan PHOTO 4
Ceiling/Wall Paint, White
PHOTO 5
Radiator/Pipe Paint, White (11% wt) PHOTO 6
Door Frame Paint, Gray (2.1% wt)
PHOTO 7
Wall/Door/Door Frame Paint, Cream PHOTO 8
Railing Paint, Black
PHOTO 9
Wall/Ceiling/Door Frame Paint, White, Blue, Tan
PHOTO 10
Floor Paint, Black
PHOTO 11 Radiator And Pipe Paint, White PHOTO 12
Wall Paint, Beige
PHOTO 13
Door Frame Paint, Gray PHOTO 14
Ceramic Wall Tile, Gray
PHOTO 15 Rectangular Wall Tile, Tan, Not Sampled PHOTO 16
Base Tile, Tan, Not Sampled
PHOTO 17
Wall Paint, White PHOTO 18
Door Frame Paint, White, Green
PHOTO 19 Wall Paint, White PHOTO 20
Floor Paint, Gray
PHOTO 21
Door Frame Paint, White PHOTO 22
Wall Paint, Tan
PHOTO 23 Wall Paint, White
PHOTO 24
Light Green Plaster Wall Paint PHOTO 25
Peach Plaster Wall Paint
PHOTO 26
Bluish Green Door/ Door Frame Paint PHOTO 27
Light Blue Plaster Wall Paint
PHOTO 28
Blue Plaster Wall Paint PHOTO 29
Green Plaster Wall Paint
PHOTO 30
Radiator Paint, White PHOTO 31
Brick Paint, Yellow
PHOTO 32
Door Frame Paint, Yellow. Rms NE3 and NE1
APPENDIX C
Analytical Reports
Asbestos Results
Lead-Based Paint Results
EMSL Analytical, Inc.
6340 CastlePlace Dr. Indianapolis, IN 46250
Tel/Fax: (317) 803-2997 / (317) 803-3047 http://www.EMSL.com / indianapolislab@emsl.com
162114042EMSL Order:
Customer ID: AMI50
Customer PO: 21-185
Project ID:
Attention: Phone:Colin Lauenroth (402) 397-5001
Fax:AMI Group, Inc. (402) 397-3313
Received Date:8802 South 135th Street 06/30/2021 10:15 AM
Analysis Date:Suite 100 07/01/2021
Collected Date:Omaha, NE 68138-6511 06/29/2021
Project: 21-185/Grand Island VA EHRM ACM
Test Report: Asbestos Analysis of Bulk Materials via EPA 600/R-93/116 Method using Polarized
Light Microscopy
Sample Description Appearance % Fibrous % Non-Fibrous
Non-Asbestos Asbestos
% Type
162114042-0001
None DetectedNon-fibrous (Other)100%White
Non-Fibrous
Homogeneous
Bldg 8 IT Room -
HA-001 -
Caulking/Putties /
Gray /Gray
HA: 001
162114042-0002
None DetectedNon-fibrous (Other)95%Glass5%Red
Non-Fibrous
Homogeneous
Bldg 8, IT Room -
HA-002 -
Caulking/Putties /
Red /Red
HA: 002
03-Insulation
162114042-0003
None DetectedNon-fibrous (Other)2%Glass98%Yellow
Fibrous
Homogeneous
Room 6, IT Room -
HA-003 - Pipe
Insulation, Wrap, Mudded End Cap /
White /White
HA: 003
03-Wrap
162114042-0003A
None DetectedNon-fibrous (Other)30%Cellulose
Glass
40%
30%
Tan/Silver
Fibrous
Homogeneous
Room 6, IT Room -
HA-003 - Pipe
Insulation, Wrap, Mudded End Cap /
White /White
HA: 003
03-End Cap
162114042-0003B
None DetectedNon-fibrous (Other)100%White
Non-Fibrous
Homogeneous
Room 6, IT Room -
HA-003 - Pipe
Insulation, Wrap, Mudded End Cap /
White /White
HA: 003
162114042-0004
None DetectedNon-fibrous (Other)98%Glass2%Red
Non-Fibrous
Homogeneous
Bldg 7, IT Room -
HA-004 - Fire Caulk /
Red /Red
HA: 004
162114042-0005
None DetectedNon-fibrous (Other)100%White
Non-Fibrous
Homogeneous
Building 1, Exterior
Windows - HA-005 -
Caulking/Putties /
Light Gray /Light Gray
HA: 005
162114042-0006
None DetectedNon-fibrous (Other)100%White
Non-Fibrous
Homogeneous
Building 1, Exterior
Windows - HA-005 -
Caulking/Putties /
Light Gray /Light Gray
HA: 005
162114042-0007
None DetectedNon-fibrous (Other)100%White
Non-Fibrous
Homogeneous
Bldg 1, Laundry
Room - HA-006 -
Interior Window Caulk
/ Light Gray /Light
Gray
HA: 006
Initial report from: 07/01/2021 11:55:48
Page 1 of 6ASB_PLM_0008_0001 - 1.78 Printed: 7/1/2021 11:55 AM
Tel/Fax: (317) 803-2997 / (317) 803-3047 http://www.EMSL.com / indianapolislab@emsl.com
162114042EMSL Order:
Customer ID: AMI50
Customer PO: 21-185
Project ID:
Test Report: Asbestos Analysis of Bulk Materials via EPA 600/R-93/116 Method using Polarized
Light Microscopy
Sample Description Appearance % Fibrous % Non-Fibrous
Non-Asbestos Asbestos
% Type
162114042-0008
None DetectedNon-fibrous (Other)100%White
Non-Fibrous
Homogeneous
Bldg 1, Laundry
Room - HA-006 -
Interior Window Caulk
/ Light Gray /Light
Gray
HA: 006
09-Insulation
162114042-0009
None DetectedNon-fibrous (Other)2%Glass98%Yellow
Fibrous
Homogeneous
Bldg 1, Laundry
Room - HA-007 - Pipe
Wrap, Insulation, and
Mastic / White /White
HA: 007
09-Wrap
162114042-0009A
None DetectedNon-fibrous (Other)30%Cellulose
Glass
50%
20%
Tan/Silver
Fibrous
Homogeneous
Bldg 1, Laundry
Room - HA-007 - Pipe
Wrap, Insulation, and
Mastic / White /White
HA: 007
09-Mastic
162114042-0009B
None DetectedNon-fibrous (Other)100%White
Non-Fibrous
Homogeneous
Bldg 1, Laundry
Room - HA-007 - Pipe
Wrap, Insulation, and
Mastic / White /White
HA: 007
10-Insulation
162114042-0010
None DetectedNon-fibrous (Other)2%Glass98%Yellow
Fibrous
Homogeneous
Bldg 1, Laundry
Room - HA-007 - Pipe
Wrap, Insulation, and
Mastic / White /White
HA: 007
10-Wrap
162114042-0010A
None DetectedNon-fibrous (Other)30%Cellulose
Glass
50%
20%
Tan/Silver
Fibrous
Homogeneous
Bldg 1, Laundry
Room - HA-007 - Pipe
Wrap, Insulation, and
Mastic / White /White
HA: 007
10-Mastic
162114042-0010B
None DetectedNon-fibrous (Other)100%White
Non-Fibrous
Homogeneous
Bldg 1, Laundry
Room - HA-007 - Pipe
Wrap, Insulation, and
Mastic / White /White
HA: 007
162114042-0011
None DetectedPerlite
Non-fibrous (Other)
15%
5%
Cellulose
Min. Wool
50%
30%
Gray/White
Fibrous
Homogeneous
Bldg 1, C305 Janitor
Closet - HA-008 - 12 x
12 Ceiling Tile / White
/ Rough /White /
Rough
HA: 008
162114042-0012
None DetectedPerlite
Non-fibrous (Other)
15%
5%
Cellulose
Min. Wool
60%
20%
Gray/White
Fibrous
Homogeneous
Bldg 1, C305 Janitor
Closet - HA-008 - 12 x
12 Ceiling Tile / White
/ Rough /White /
Rough
HA: 008
162114042-0013
None DetectedGypsum
Non-fibrous (Other)
20%
15%
Cellulose
Glass
60%
5%
Brown/White
Fibrous
Heterogeneous
Bldg 1, Laundry
Room and Oxygen
Room, Throughout -
HA-009 -
Drywall/Joint
Compound
Composite / White
/White
This is a composite result of wallboard, jt. compound, and tape
HA: 009
Page 2 of 6ASB_PLM_0008_0001 - 1.78 Printed: 7/1/2021 11:55 AM
Tel/Fax: (317) 803-2997 / (317) 803-3047 http://www.EMSL.com / indianapolislab@emsl.com
162114042EMSL Order:
Customer ID: AMI50
Customer PO: 21-185
Project ID:
Test Report: Asbestos Analysis of Bulk Materials via EPA 600/R-93/116 Method using Polarized
Light Microscopy
Sample Description Appearance % Fibrous % Non-Fibrous
Non-Asbestos Asbestos
% Type
162114042-0014
None DetectedGypsum
Non-fibrous (Other)
30%
15%
Cellulose
Glass
50%
5%
Brown/White
Fibrous
Heterogeneous
Bldg 1, Laundry
Room and Oxygen
Room, Throughout -
HA-009 -
Drywall/Joint
Compound
Composite / White
/White
This is a composite result of wallboard, jt. compound, and tape
HA: 009
162114042-0015
None DetectedNon-fibrous (Other)100%White
Non-Fibrous
Homogeneous
Bldg 1, C305 Laundry
Room - HA-010 -
Plaster (skim coat) /
White /White
HA: 010
162114042-0016
None DetectedNon-fibrous (Other)100%White
Non-Fibrous
Homogeneous
Bldg 1, C305 Laundry
Room - HA-010 -
Plaster (skim coat) /
White /White
HA: 010
162114042-0017
None DetectedNon-fibrous (Other)100%White
Non-Fibrous
Homogeneous
Bldg 1, C305 Laundry
Room - HA-010 -
Plaster (skim coat) /
White /White
HA: 010
18-Floor Tile
162114042-0018
None DetectedNon-fibrous (Other)100%Beige
Non-Fibrous
Homogeneous
C305 Janitor Closet -
HA-011 - 12 x 12
Floor Tile / Beige
/Beige
HA: 011
18-Mastic
162114042-0018A
None DetectedNon-fibrous (Other)100%Black
Non-Fibrous
Homogeneous
C305 Janitor Closet -
HA-011 - 12 x 12
Floor Tile / Beige
/Beige
HA: 011
19-Floor Tile
162114042-0019
None DetectedNon-fibrous (Other)100%Beige
Non-Fibrous
Homogeneous
C305 Janitor Closet -
HA-011 - 12 x 12
Floor Tile / Beige
/Beige
HA: 011
19-Mastic
162114042-0019A
None DetectedNon-fibrous (Other)100%Black
Non-Fibrous
Homogeneous
C305 Janitor Closet -
HA-011 - 12 x 12
Floor Tile / Beige
/Beige
HA: 011
20-Cove Base
162114042-0020
None DetectedNon-fibrous (Other)100%Gray
Non-Fibrous
Homogeneous
C305 Janitor Closet and Oxygen Room -
HA-012 - Cove Base /
Gray /Gray
HA: 012
20-Mastic
162114042-0020A
None DetectedNon-fibrous (Other)100%Tan
Non-Fibrous
Homogeneous
C305 Janitor Closet and Oxygen Room -
HA-012 - Cove Base /
Gray /Gray
HA: 012
162114042-0021
None DetectedNon-fibrous (Other)100%White
Non-Fibrous
Homogeneous
C404B - HA-010 -
Plaster (skim coat) /
White /White
HA: 010
Page 3 of 6ASB_PLM_0008_0001 - 1.78 Printed: 7/1/2021 11:55 AM
Tel/Fax: (317) 803-2997 / (317) 803-3047 http://www.EMSL.com / indianapolislab@emsl.com
162114042EMSL Order:
Customer ID: AMI50
Customer PO: 21-185
Project ID:
Test Report: Asbestos Analysis of Bulk Materials via EPA 600/R-93/116 Method using Polarized
Light Microscopy
Sample Description Appearance % Fibrous % Non-Fibrous
Non-Asbestos Asbestos
% Type
162114042-0022
None DetectedNon-fibrous (Other)100%White
Non-Fibrous
Homogeneous
C404B - HA-010 -
Plaster (skim coat) /
White /White
HA: 010
162114042-0023
None DetectedPerlite
Non-fibrous (Other)
15%
5%
Cellulose
Min. Wool
60%
20%
Gray/White
Fibrous
Homogeneous
C404B - HA-013 - 2 x
4 Ceiling Tile / White /
Wormhole /White /
Wormhole
HA: 013
162114042-0024
None DetectedPerlite
Non-fibrous (Other)
15%
5%
Cellulose
Min. Wool
60%
20%
Gray/White
Fibrous
Homogeneous
C404B - HA-013 - 2 x
4 Ceiling Tile / White /
Wormhole /White /
Wormhole
HA: 013
25-Mastic
16211…