Technical Questions - FINAL - Tomah 8-2-21.pdf
PDF 364 KB Posted
- Solicitation number
- 36C77621B0009
About this file
This document contains a technical questions and answers log pertaining to a solicitation for expanding and renovating space B400 at the Tomah VA Medical Center for urgent and primary care services.
The solicitation involves demolishing existing structures and constructing an addition to provide approximately 15,000 square feet of renovated and new clinical space. Key requirements include structural steel, masonry, windows, doors, finishes, plumbing, HVAC and controls work. The performance period is 660 calendar days. The solicitation includes deductive alternates and requires adherence to sustainable acquisition, AISC quality certification, and third party inspections.
The Department of Veterans Affairs Technology Acquisition Center in Austin is the contracting agency. The document provides responses to contractor questions on drawings, specifications, permitting, site conditions like groundwater management, and clarifies that no elevator or spray painting access will be permitted. It also addresses requirements for things like infection control barriers, safety plans, and operations and maintenance documentation.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation #36C77621B0009 Expand and Renovate B400 for Urgent and Primary Care – Tomah Technical Questions and VA Response Tracking Sheet
ITEM
NO.
DATE
QUESTION
RECEIVED
DATE
QUESTION
ANSWERED
QUESTION GOVERNMENT RESPONSE
1. 6-30-21 7-22-21 After a review of the drawing index, we’ve determined that two Civil drawings are missing. They are VF100 and VF101. Please advise or provide missing drawings.
Missing drawings VF100 and VF101 have been provided as an attachment to this Amendment 0003.
2. 7-13-21 7-13-21 Is this project tax-exempt? If yes, please issue the Tax Exemption number for bidding purposes. If not, what is the percentage of tax?
No, this is not exempt of sales tax. Contractors are required to pay sales and excise tax. Offerors shall include all applicable taxes in accordance with FAR by Reference Clause 52.229-3 “Federal, State and Local Taxes.” Percentage of tax information is the responsibility of the bidder.
3. 7-16-21 7-16-21 On page 18 of the solicitation, VAAR Provision 852.223-70 Instructions to Offerors – Sustainable Acquisition Plan (SEP 2019) is included. Does the VA require this as part of the bid submission?
After review, the VA has concluded that this provision was inadvertently included in this solicitation. This provision has now been removed in its entirety and replaced by VAAR 852.233-70.
Reference Amendment 0002 for provision information.
4. 7-16-21 7-27-21 I looked at the bid documents for this project & was unable to find the elevations for the Patient Bed Service Walls. In addition, please provide a list of the approved contractors.
Please refer to detail D4/AE401 equipment number A1110/ The following manufacturers supply comparable products to existing equipment Modular Services Company https://www.modularservices.com/product-type/vertical-headwalls/ or Amico https://www.amico.com/products/headwalls
5. 7-16-21 7-27-21 Could you please tell me the height of the soffit above the Team Area Nurse Station for B400?
Refer to enlarged detail F5/AC101. Nurses station 1086A & 1101A has 2 materials. The gypsum wallboard soffit elevation is 7’-8” the wood accent panel elevation is 7’-9”.
https://www.modularservices.com/product-type/vertical-headwalls/ https://www.modularservices.com/product-type/vertical-headwalls/ https://www.amico.com/products/headwalls
DATE
QUESTION
RECEIVED
DATE
QUESTION
ANSWERED
QUESTION GOVERNMENT RESPONSE
6. 7-21-21 7-27-21 Ref drawingGC102- Phase 1 which is the new addition, phase 2 which is space 2 and phase 3 which is space 1 are scheduled for 300 days each based on the statement of work under part 1.3 of general requirement specification. The performance period on the SF1442 is shown as 660 calendar days. Based on phasing notes on GC102 Phase 2 will not be available until 21 days after phase 1 is complete and phase 3 will not be available until 21 days after phase 2 is complete. Phase 1 interior work (space 4 &5 is scheduled for 150 days. Phase 2 (space 2 is scheduled for 300 days and phase 3 (space 1) is scheduled for 300 days which total 750days. The statement of bid items on drawing GI000 allows 730 days. 60 to 90 days administrative time will be needed to generate product submittals and progress schedule. Will administrative NTP be issued prior to construction NTP?
Can allowable days from NTP be increased to 840 or so?
Work in Phases 1, 2, & 3 may over lap as some of the spaces complete early and may be ready for beneficial occupancy early. See diagram on GC101. The longest amount of work is 642 days, allowing for 18 days to start to generate preconstruction items. The renovated and new rooms are important to this VAMC and the VA has determined that it needs this project sooner then the A/E and the VA discussed in the design phase. The awarded contractor shall prosecute the worked quickly and diligently in accordance with SF1442.
7. 7-21-21 7-27-21 Ref drawing AD101 keynote 9- How are the existing windows mounted in the wall? Are the existing window frames grouted in place? Are the existing walls made up of 8” CMU and single wythe brick veneer?
The exterior walls are made up of hollow clay structural tiles, triple wythe of brick, and true row locks. The A/E was informed that the original frames may still be in place and some of those frames were grouted in place.
8. 7-21-21 7-27-21 Ref drawing Ad103-407 – Does the partition wall in room 3775 require demolition?
Yes, the partition wall depicted in a dashed line does require demolition.
9. 7-21-21 7-27-21 Ref drawing AD103-407 -Will the elevator be available to move materials and equipment to and from the spaces?
No elevator use per COR.
10. 7-21-21 7-27-21 Ref drawing Gl201 detail C5- Will a temporary wall be required in the NW corner of the ambulance garage?
No temporary wall will be required for the ambulance garage, there was a late change in design and this wall is no longer needed.
DATE
QUESTION
RECEIVED
DATE
QUESTION
ANSWERED
QUESTION GOVERNMENT RESPONSE
11. 7-26-21 7-27-21 Per section 01 00 00-4 General Requirements, a Certified Industrial Hygienist is required to be a third party contractor. The Certified Industrial Hygienist is also referenced in attachment CC Section 02 82 11. This section indicates that the Certified Industrial Hygienist needs to be hired by the asbestos abatement Contractor.
Can this person be employed by the Demo/Abatement contractor, or does this need to be an independent person hired by the General Contractor?
**SEE ATTACHMENT-A** (following this spreadsheet)
12. 7-26-21 7-27-21 Per spec section 05 12 00 Structural Steel, paragraph 1.5 AISC Quality Certification is required for the structural steel fabricator. These qualifications severely limit the number of available steel fabricators in the geographic area suitable for this project. These requirements could force contractors to utilize nonlocal or regional vendors introducing additional cost into this scope of work.
Please consider removing the AISC Quality Certification for the structural steel fabricators.
AISC Quality Certification will be required
If AISC Quality Certification is removed a fabricator full time shop inspection must be provided. Refer to the following Specification section.
Per 01 45 35 (Special Inspections) Part 2 – 2.1 A “Special Inspections of fabricator's work performed in the fabricator's shop is required to be inspected in accordance with the Statement of Special Inspections and the Schedule of Special Inspections unless the fabricator is certified by the approved agency to perform such work without Special Inspections.”
DATE
QUESTION
RECEIVED
DATE
QUESTION
ANSWERED
QUESTION GOVERNMENT RESPONSE
13. 7-26-21 7-28-21 Per spec section 05 12 00 Structural Steel, paragraph 1.5 AISC Quality Certification is required for the structural steel erector. These qualifications severely limit the number of available steel erectors in the geographic area suitable for this project. These requirements could force contractors to utilize nonlocal or regional vendors introducing additional cost into this scope of work.
Please consider removing the AISC Quality Certification for the structural steel erectors.
AISC/CSE Quality Certification of installers/erectors will be required.
14. 7-26-21 7-27-21 Per spec section 28 05 00 Paragraph 1.4 an RCDD is required to provide consistent oversight of the project cabling throughout design, layout, installation, termination and testing. Please confirm that this does not need to be a third party.
The RCDD needs to be on staff of the low voltage sub-contractor who is bidding the project.
15. 7-26-21 7-27-21 The Price Schedule is unclear as to how the Deduct Alternates should be listed. Are CLIN's 0002-0006 to be the overall base bid less each deduct alternate item, or the overall value of the deduct alternate. E.g. If 0001 Base bid is $10,000,000 and 0002 Deduct Alternate No 1 is $200,000 less than the Base Bid should we list $9,800,000 or $(200,000) for the price on item number 0002?
You should list $9,800,000.00 for Line Item 0002, if your pricing was $200,000.00 less than your Base Bid Line Item 0001 pricing of $10,000,000.00.
16. 7-26-21 7-27-21 The Construction Cost Estimate Breakdown Form on Page 92 of Attachment 1 is not listed in 2.8: Bid Submission of the IFB. Please confirm that this document is not required to be submitted with the bid.
The answer to your question is contained on Specifications page 91 - APPENDIX A – BID FORM TEMPLATE (ATTACHED). Template is for an EXAMPLE only. Bidders are not required to submit with their proposal. Pricing should be cited on Line Items only.
17. 7-26-21 Per the pre-bid walkthrough, it was mentioned that the elevator in B407 will not be able to be used by the contractor. Please confirm that this is correct.
Correct, no elevator use for construction services.
DATE
QUESTION
RECEIVED
DATE
QUESTION
ANSWERED
QUESTION GOVERNMENT RESPONSE
18. 7-26-21 7-28-21 Specification section 01 00 00 – N requires a third party Industrial Hygienist. Would an Industrial Technician be sufficient for IH requirements?
**SEE ATTACHMENT-A** (following this spreadsheet)
19. 7-26-21 7-28-21 Can the prime contractors superintendent be the same person as the contractors quality control manager?
See Section 01 45 00 3.2 B. 1. ... Include a CQC System Manager that reports to the project Superintendent.
20. 7-26-21 7-28-21 Can the prime contractors superintendent be the same person as the contractors SSHO?
See Section 01 35 26 1.7 C.
21. 7-26-21 7-27-21 HEPA filtration units will be used at multiple locations to maintain negative air pressure throughout construction. Can these units vent into hallways, ceiling plenums, or existing exhaust ducting? Or do these units need to vent to the outside?
Venting into adjacent spaces or existing ductwork is prohibited. Please see ICRA note J on sheet
GI201.
22. 7-26-21 7-28-21 Specification section 04 20 00 3.14 requires water penetration testing via “direct water on masonry unit”.
Can you please clarify how water is to be directed or ASTM standard for this test?
ASTM C1601 which is the Standard Test Method for Field Determination of Water Penetration of Masonry Wall Surfaces.
23. 7-26-21 7-28-21 Specification section 07 01 50 3.9 requires a roofing inspection of the existing roof to verify compliance with existing warranty conditions. Can you please specify what area/size of the existing is to be inspected? Can you please provide the existing roofing installer and warranty conditions that are to be verified?
The existing roof on the Ambulance Garage and existing flat roof addition to west of the Garage ~1,300 sq ft of roofing. Warranty and installer information is not available.
24. 7-26-21 7-28-21 Specification section 07 27 27 3.3 requires inspections based on surface area. Are these inspections referencing total project area or project area phases (reference paragraph D)? Are these audits by ABAA (paragraph F) based on each project phase?
See Section 07 27 27 3.3 D. ... Determined by installed air barrier surface area. Per 3.3 A. 1.
Perform inspections and tests before concealing air barrier with subsequent work.
DATE
QUESTION
RECEIVED
DATE
QUESTION
ANSWERED
QUESTION GOVERNMENT RESPONSE
25. 7-26-21 7-27-21 Specification section 13 05 41 1.3 requires seismic force restraint shop drawings and calculations prepared by a professional structural engineer. Is this engineering cost/calculations provided by the government or is this design cost to be incorporated within the contractors proposal pricing?
Per 13 05 41 1.3 A. Shop-Drawing Preparation: 1.
seismic-force-restraint shop drawings and calculations prepared by a professional structural engineer experienced in the area of seismic force restraints. Per Section 01 33 23 1.2 B. Shop Drawings... Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be integrated and coordinated.
26. 7-26-21 7-27-21 Are there utility testing requirements that will require testing against any existing utilities including sewer lines, curb stops, shut off valves, meters etc.?
All utilities are connecting to existing utilities.
Sewer and storm will not need to be tested. You will be required to perform flow tests and leak tests per spec 32 08 00,33 30 00, 33 40 00.
27. 7-26-21 7-27-21 Do the window frames have a CRF requirement? See Section 08 41 13 2.1; Section 08 51 13 2.1; & Section 08 56 53 1.4.
28. 7-26-21 7-27-21 Does the window frame and the glazing have to be factory tested as an assembly or does individual tests qualify?
Contractor shall submit Test reports that each product complies with the specifications per each section in Division 08.
29. 7-26-21 7-27-21 Is this facility designated a mission critical facility? Can you please clarify what version of the Physical Security Design Manual is to be followed for this project?
Correct, the addition at Urgent Care is classified as Mission Critical, the Design Manual followed for this construction package is PSDM Jan 2015 version.
30. 7-26-21 7-27-21 Are there any brick or mortar repairs necessary on existing structures? Including weep holes, flashing, WRB, sealants?
See wall sections on AE320, AE321, & AE322 for scope.
31. 7-26-21 7-27-21 Will the VA provide utility locates? Contractor is required to locate utilities per Civil drawing sheet CU101 “Utility Notes #9”
DATE
QUESTION
RECEIVED
DATE
QUESTION
ANSWERED
QUESTION GOVERNMENT RESPONSE
32. 7-26-21 7-27-21 Are there any historic locations/buildings/rooms etc. that need to be considered on the VA campus that my impact the cost or schedule of this project?
Historic Preservation considerations were evaluated with the COR during design. The building addition follows the approved aesthetic of the campus and will not require further evaluation from the governing board. SHPO will be furnished to the contractor after bid award, upon request.
33. 7-26-21 7-27-21 Does this project require a 24 hour fall protection competent person?
Follow the requirements in Section 01 35 26.
34. 7-26-21 7-27-21 Per attachment 10, drawing # AW001, It appears that the VA is procuring them themselves, can you please confirm this?
Owner has requested that signage be included in the BASE BID design and shall be procured by the general contractor. This revision will be included in the addendum #1. Updated drawings will be furnished to the contractor after bid award.
35. 7-26-21 7-27-21 Ref spec 10 91 00 & drawing AG900- Can dimensions with make & model be provided for the bubble wall fountain?
Fountain basis of design is Bluworld BluGuard bubble system. 96”Hx48”W http://www.bluworldusa.com/
36. 7-26-21 7-27-21 Reference spec section 10 50 20 Canopies: please specify manufacturer.
Basis of design is located in drawing package, AE Did not design around one specific manufacturer.
https://www.archlouvers.com/Metal_Awnings.ht m or http://www.victoryawning.net/awningsdallasfortw orth-commercialmetal/ would be appropriate sources.
37. 7-26-21 7-27-21 Reference spec section 10 91 00 Water Features: please specify manufacturer.
Fountain basis of design is Bluworld BluGuard bubble system. 96”Hx48”W http://www.bluworldusa.com/
38. 7-26-21 7-27-21 Reference 01 35 26 1.13 Tuberculosis Screening:
confirm TB testing for all construction workers is necessary for this project.
This is correct, all personnel shall be TB screened prior to working on site.
http://www.bluworldusa.com/ https://www.archlouvers.com/Metal_Awnings.htm https://www.archlouvers.com/Metal_Awnings.htm http://www.victoryawning.net/awningsdallasfortworth-commercialmetal/ http://www.victoryawning.net/awningsdallasfortworth-commercialmetal/ http://www.bluworldusa.com/
DATE
QUESTION
RECEIVED
DATE
QUESTION
ANSWERED
QUESTION GOVERNMENT RESPONSE
39. 7-26-21 7-27-21 Reference spec section 01 00 00 1.2.I, confirm ALL third-party inspections are by contractor. If so, reference 01 45 38 Special Instructions, are all inspections listed required?
Confirmed, yes all 3rd party inspections are the responsibility of the contractor and all inspections are required.
40. 7-26-21 7-27-21 Please confirm that non-destructive examination of the piping welds as described in specification section 23 22 13, section 3.2, item “H” is a requirement for this project for the steam and condensate piping.
Yes, Section 23 22 13, Section 3.2, item “H” is required. – Contractor to submit inspection method prior to start of construction for approval by COR.
41. 7-26-21 7-27-21 Reference 01 00 00 1.9.D, confirm an NPDES (National Pollutant Discharge Elimination System) is required for this project.
Confirmed, it is required.
42. 7-26-21 7-28-21 Has the VA tested the ductwork and mechanical systems scheduled for demolition or relocation for bio-hazards. If the ductwork or equipment are contaminated, remediation will be required by a subcontractor.
No active biohazards have been identified in this Scope of work.
43. 7-26-21 7-27-21 Specification Section 23 31 00: Clarify ductwork pressure classes.
Duct pressure classes based on duct size and system. Refer to sheet M0.00 for duct pressure classifications.
44. 7-26-21 7-27-21 Clarify who is responsible for motor controllers for HVAC equipment.
Awardee’s Electrical contractor to provide.
45. 7-26-21 7-28-21 Is a third-party scheduling consultant required on this project?
See Section 01 32 16.15 1.2.
46. 7-26-21 7-27-21 Please clarify the scope of work associated with duct testing as there is minimal supply air ductwork. Please be specific what the VA needs tested.
Provide pre- and post-construction TAB readings as indicated on drawings. Refer to specification section 23 05 93 for TAB procedures and reporting. All ductwork within project scope shall be duct pressure tested.
47. 7-26-21 7-27-21 Reference specification section 01 91 00 1.4.C, is this project’s goal to be LEED certified? If so what level is desired for this project? Also, please provide specifications for LEED.
This project is not required to be LEED certified.
Energy/sustainable design components were factored into the project as a basis of design.
DATE
QUESTION
RECEIVED
DATE
QUESTION
ANSWERED
QUESTION GOVERNMENT RESPONSE
48. 7-26-21 7-28-21 If after uncovering existing conditions there is a need for subgrade soil repairs, will the work have to stop until an approved Supplemental Agreement is in place or will there be pre-determined unit rates/costs established so the work can proceed accordingly?
See Section 01 00 00 1.11.
49. 7-26-21 7-27-21 Is over excavation for the footings anticipated? If so please advise what quantities of over excavation should be covered, and what should the over excavation be filled with to planned footing elevation?
**SEE ATTACHMENT-A** (following this spreadsheet)
DATE
QUESTION
RECEIVED
DATE
QUESTION
ANSWERED
QUESTION GOVERNMENT RESPONSE
50. 7-26-21 7-27-21 Is ground water anticipated? If so at what depth and is the contractor responsible to control groundwater?
Should an allowance for groundwater control be included? IF so please advise the allowance amount to be included.
1. Ground water shall be anticipated - From Geotechnical Report: “Groundwater was encountered at depths of about 4 to 9 feet (944 to 948 feet) below existing grades while drilling and after completion of drilling. Thus, shallow excavations to construct the building foundations will likely intercept the local groundwater table and the Contractor should be prepared to dewater the excavations as necessary.”
Per sheet SJ001 “FOUNDATION - GENERAL” Structural Notes section refer to the following Geotechnical Report for additional information.
“FOUNDATION DESIGN IS BASED ON
RECOMMENDATIONS INCLUDED IN
GEOTECHNICAL ENGINEERING REPORT
NO. 58205106-R1 BY TERRACON
CONSULTANTS DATED AUGUST 4, 2020.”
2. Yes, refer to 31 23 19 Specification provided with this Amendment 0003. Section 1.2 B for summary of contractor's responsibilities.
3. There will be no allowance provided, contractor to assess volume during excavation.
DATE
QUESTION
RECEIVED
DATE
QUESTION
ANSWERED
QUESTION GOVERNMENT RESPONSE
51. 7-26-21 7-27-21 Per Section 31 20 11 Part 3.5-D, contaminated soils need to be segregated from all other excavated soils, stockpiled on 6 mil polyethylene sheets with a polyethylene cover at a designated area. Will the designated area for stockpiling contaminated soils be located with the project boundaries? Are contaminated soils expected? Is all the soil considered contaminated or is there only isolated areas?
It is not anticipated that contaminated soils exist outside of the pipe basement, but experience tells us there may be. If there are contaminated soils then they will be handle under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and
"CHANGES" (FAR 52.243-4).
52. 7-26-21 7-27-21 Can any of the contaminated soils designated by the Resident Engineer be used as backfill?
It is not anticipated that contaminated soils exist outside of the pipe basement, but experience tells us there may be. If there are contaminated soils then they will be handle under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4). Contaminated soil shall not be used as backfill and shall be removed from site, soils that are acceptable per Geotech report soils report can be reused for backfill.
53. 7-26-21 7-27-21 Will the VA provide direction as to when the stockpiled contaminated soil is to be removed and where it is to be taken to?
It is not anticipated that contaminated soils exist outside of the pipe basement, but experience tells us there may be. If there are contaminated soils then they will be handle under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4). Contaminated and Unsuitable soil shall be removed from site, removal costs will be the contractors responsibility.
DATE
QUESTION
RECEIVED
DATE
QUESTION
ANSWERED
QUESTION GOVERNMENT RESPONSE
54. 7-26-21 7-27-21 Is there a Soil Profile showing the levels of contaminates for this project and will it be provided? If not, where should we figure the contaminated soils need to be hauled to and will the VA be providing that paperwork showing compliance with all State and Local requirements?
It is not anticipated that contaminated soils exist outside of the pipe basement, but experience tells us there may be. If there are contaminated soils then they will be handle under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4). Refer to Geotech report for soil that was tested. Contaminates were not found for this scope of work.
55. 7-26-21 7-27-21 Will the contractor be responsible to carry in their bid and pay for the tipping fees associated with the disposal of the contaminated soils?
It is not anticipated that contaminated soils exist outside of the pipe basement, but experience tells us there may be. If there are contaminated soils then they will be handle under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4). Yes GC is responsible for all fees.
56. 7-26-21 7-27-21 Can all work be done during normal daytime work shifts?
See Section 01 00 00 1.6 L.
57. 7-26-21 7-27-21 Is the contractor required to clean all ducts including existing ductwork?
See Section 23 05 11 1.6 & Section 23 31 00 3.1 K.
58. 7-26-21 7-27-21 Is an offer guarantee (Bid Bond) required? Yes, reference Solicitation page 16 - 52.228-1 BID GUARANTEE (SEP 1996) for requirements.
59. 7-26-21 7-27-21 What percent of SDVOSB labor is required? Reference ATTACHMENT 18 - Limitations on Subcontracting – Construction, which was posted with the solicitation, for requirements.
60. 7-26-21 7-27-21 Is AISC Steel Certification required for both the fabricator and the installer?
Yes, Refer to Specification 05 12 00 Section 1.5 (Quality Assurance) for Fabricator and installer AISC Steel Certification requirements
61. 7-26-21 7-27-21 Is a third-party Fire penetration inspector required for this project, if so, is that inspector hired by contractor?
See Section 07 84 00 1.5 C.
DATE
QUESTION
RECEIVED
DATE
QUESTION
ANSWERED
QUESTION GOVERNMENT RESPONSE
62. 7-26-21 7-27-21 How many copies of the O&M do you require? One Paper copy in a three ring binder, and electrotonic copy on CD/DVD.
63. 7-26-21 7-27-21 Specs say all OSHA cards and AHAs need to be submitted with APP. This is not feasible. Is it acceptable to submit OSHA cards and AHAs during the project, but prior to related work starting?
See Section 01 35 26 1.5 C. See Section 01 00 00 1.5 B. 1. a.
64. 7-26-21 7-27-21 Are the infection control walls to be built to the deck?
Please provide floor to deck height of all floors. How do we know there is room to build walls to deck?
Per Section 01 35 26 1.12 D. 3. & GI201.
See AE201 & AE201-407 for elevations.
65. 7-26-21 7-27-21 Is full time SSHO required? See Section 01 35 26 1.7 D.
66. 7-26-21
7-27-21
Can paint be sprayed on? Spec says spray with approval of COR.
If the contractor proposes to spray application then a room mock-up shall be provided so the COR can evaluate the quality of application and make an acceptance or rejection.
67. 7-26-21 7-27-21 Reference spec section 08 11 13 HM Doors and Frames:
Sound doors must have the frame filled with insulation.
Frames in masonry walls are to be filled with grout. Are all HM Door Frames to be filled with grout?
Being the installation is taking place in new openings in existing masonry walls it will be impossible to install the grout. Provide thermal and acoustical insulation.
68. 7-26-21 7-27-21 Does the SSHO need to be a separate individual from the prime contractor’s superintendent?
See #20 above.
69. 7-26-21 7-27-21 Can we use flexible conduit in casework? Normal branch power wiring is allowed to be routed in flexible metal conduit. Critical branch power is NOT permitted to be routed in flexible conduit per NEC 517.31.C.3.3.
70. 7-26-21 7-27-21 For alternate #4, please provide a detailed description of the work required and sizing information of all new components associated with the rebuilding of the existing air handling unit including any components that can be reused.
Refer to enlarged plans for sizing. Refer to sheet M-402 for layout.
DATE
QUESTION
RECEIVED
DATE
QUESTION
ANSWERED
QUESTION GOVERNMENT RESPONSE
71. 7-26-21 7-27-21 Provide a drawing detail and a detailed description of the work required including sizing information for the temporary roof top unit shown on plan sheet M 100. Also provide the temperature control requirements, sequence of operation, ductwork sizing, temporary piping (if required) and insulation requirements,.
Provide skid mounted temporary HVAC unit.
Unit shall have heating and cooling capabilities and sized the same RTU-10. This unit shall be able to condition, temper, and ventilate the entire urgent care area including the existing and addition in case the new unit or the existing unit is temporarily not functioning or usable. This unit should function the same as RTU-10.
72. 7-26-21 7-27-21 Please provide the refrigeration piping sizes for the new air cooling condensing unit.
Refrigerant piping to be sized based on manufacturers manual.
73. 7-26-21 7-27-21 Reference Specification Section 01 91 00, please confirm the commissioning agent is a subcontractor provided by the general contractor.
Confirmed.
74. 7-26-21 7-27-21 Reference Specification Section 23 02 11, page 6, item ”J”. Please confirm that BIM drawings are not required for coordination drawings for the project.
Per Section 23 05 11 1.7 C. As-built 3D BIM models shall be provided, it would be beneficial for contractor to draft work in 3D BIM models to coordinate. Contractor shall have access to the AE BIM model, highly preferred to be in a BIM format. This requirement is a contractor cost, not a separate reimbursable cost.
75. 7-26-21 7-27-21 Reference Specification Section 23 02 11, page 9, item ”C” indicates as built drawings are to be provided in BIM. If this is truly a requirement of the project, is the A/E of record providing the modeling of the existing building structure and existing mechanical work shown to remain or is this work the responsibility of the mechanical contractor?
All design, drawings, specifications, notes, and other work developed in the performance of this contract shall be and remain the sole property of the government. And the Government can provide the contractor with the CAD, BIM, and other files as required.
76. 7-26-21 7-27-21 Reference Specification Section 23 05 11, page 13. Are VFD’s to be provided and mounted by the mechanical contract or the electrical contractor per the requirements of specification section 26 29 11?
Electrical contractor to provide per Specification Section 26 29 11.
DATE
QUESTION
RECEIVED
DATE
QUESTION
ANSWERED
QUESTION GOVERNMENT RESPONSE
77. 7-26-21 7-27-21 Reference Specification Section 23 07 11, page 12, the insulation schedule calls rigid cellular phenolic foam or flexible elastomeric cellular thermal for various piping systems depending on fluid temperature. Can fiberglass insulation be used for any of these piping systems? If so, please provide a list of systems where fiberglass is acceptable.
Provide insulation required per Specification Section 23 07 11.
78. 7-26-21 7-27-21 Reference Specification Section 23 09 23, page 8, item 1.4, please confirm the general contractor is responsible to hire the control system installation subcontractor and control system integration subcontractor as a 1st tier subcontractor.
Confirmed.
79. 7-26-21 7-27-21 Reference Specification Section 23 21 13, page 5, item 2.4, please advise if the use pro-press fittings are acceptable for copper piping systems.
Refer to Specification Section 23 21 13, paragraph 2.4. Pro-press fittings are not allowed.
80. 7-26-21 7-27-21 Reference Specification Section 23 21 13, page 5, item 2.3, please advise if the use of grooved fittings and grooved end valves are acceptable for steel piping systems.
Refer to Specification Section 23 21 13, paragraph 2.3. Grooved fittings are not allowed.
81. 7-26-21 7-27-21 Reference Specification Section 23 31 00, page 3, item 2.2, please clarify and provide a schedule of the ductwork pressure construction requirements for all ductwork systems.
Refer to line item #43 response.
82. 7-26-21 7-27-21 Reference Specification Section 23 31 00, page 8, item 3.1.K, please clarify the ductwork cleaning requirements.
Is cleaning of existing ductwork only required at the point of connection of new to existing ductwork systems or is addition cleaning required on existing ductwork.
Refer to line item #57 response.
ATTACHMENT-A
RESPONSE TO ITEM #18
Per Specifications 02 82 11 Part 1.11, 02 82 13.133 Part 1.4.B and 02 82 13.19 Part 1.5.B, two (2) Professional Industrial Hygienists (PIH)/Certified Industrial Hygienists (CIH) are required for this project:
1. Contractor's Professional Industrial Hygienist (CPIH/CIH) - The asbestos abatement contractor's industrial hygienist. The industrial hygienist must meet the qualification requirements of a PIH and may be a certified industrial hygienist (CIH).
a. Professional Industrial Hygienist (PIH) – A professional qualified by education, training, and experience to anticipate, recognize, evaluate and develop controls for occupational health hazards and meets definition requirements of the American Industrial Hygiene Association (AIHA). In addition to the requirements of AIHA; An IH who meets the definition requirements of AIHA; meets the definition requirements of OSHA as a "Competent Person" at 29 CFR 1926.1101 (b); has completed two specialized EPA approved courses on management and supervision of asbestos abatement projects; has formal training in respiratory protection and waste disposal; and has a minimum of four projects of similar complexity with this project of which at least three projects serving as the supervisory IH.”
b. Certified Industrial Hygienist (CIH) - A person certified in the comprehensive practice of industrial hygiene by the American Board of Industrial Hygiene.
c. Scope of services for the CPIH/CIH are defined in Specifications 02 82 11 Part 2.6, Specification 02 82 13.13 Part 2.3.C and 02 82 13.19 Part 2.3.C.
2. Third-Party Professional Industrial Hygienist (TPPIH/CIH) – The Third-Party Professional Industrial Hygienist must meet the qualifications of a PIH, and may be a Certified Industrial Hygienist (CIH).
a. Professional Industrial Hygienist (PIH) – A professional qualified by education, training, and experience to anticipate, recognize, evaluate and develop controls for occupational health hazards and meets definition requirements of the American Industrial Hygiene Association (AIHA). In addition to the requirements of AIHA; An IH who meets the definition requirements of AIHA; meets the definition requirements of OSHA as a "Competent Person" at 29 CFR 1926.1101 (b); has completed two specialized EPA approved courses on management and supervision of asbestos abatement projects; has formal training in respiratory protection and waste disposal; and has a minimum of four projects of similar complexity with this project of which at least three projects serving as the supervisory IH.”
b. Certified Industrial Hygienist (CIH) - A person certified in the comprehensive practice of industrial hygiene by the American Board of Industrial Hygiene.
c. Scope of services for the TPPIH/CIH are defined in Specifications 02 82 11 Part 2.5, Specification 02 82 13.13 Part 2.3.B and 02 82 13.19 Part 2.3.B.
The cost of the CPIH/CIH and TPPIH/CIH and their services will be borne by the General Contractor including any repeat of final inspection and testing that may be required due to unsatisfactory initial results. Any repeated final inspections and/or testing, if required, will also be paid for by the Contractor.
ATTACHMENT-A
RESPONSE TO ITEM #49
1. Some over excavation shall be anticipated
2. Quantities of over excavation will be determined by the Geotechnical engineer during inspections and unearthed conditions.
3. Over excavations shall be filled as stated in Geotechnical Report. See References provided below and Geotechnical report for additional information.
Refer to Sheet SJ001 “SHALLOW FOUNDATIONS” Structural Notes section for foundation bearing requirements.
Additional information can also be found in the Geotechnical Report Referenced in “FOUNDATION - GENERAL” Structural Notes section refer to the following Geotechnical Report for additional information.
“FOUNDATION DESIGN IS BASED ON RECOMMENDATIONS INCLUDED IN GEOTECHNICAL
ENGINEERING REPORT NO. 58205106-R1 BY TERRACON CONSULTANTS DATED AUGUST 4,
2020.”
From Geotechnical Report Per Design Parameters Table: “Suitable native very stiff to hard clay soils with hand penetrometer value ≥2.0 tsf, native very loose to medium granular soils that have been redensified as recommended below, or engineered fill or lean concrete extending to suitable native soils” Per footer 3 “Unsuitable or soft soils should be over-excavated and replaced per the recommendations presented in the Earthwork and Foundation Construction Considerations.”
“As noted in Earthwork, the footing excavations should be evaluated under the direction of the Geotechnical Engineer... If unsuitable bearing soils, such as the existing fill and possible fill soils observed at B-1, B-2, B-4, and B-5 to depths of about 3 to 8 feet (944 to 949 feet), are encountered at the base of the planned footing excavation, the excavation should be extended deeper to suitable soils, and the footings could bear directly on these soils at the lower level, or on lean concrete backfill placed in the excavations.” Refer to the geotechnical report for additional illustrated sketches.
| ITEM |
| ASTM C1601 which is the Standard Test Method for Field Determination of Water Penetration of Masonry Wall Surfaces. |