Updated SOW Replace Flooring in McCellan_20261105_.pdf

PDF 252 KB Posted

Attached to
FY27 NRM Replace Flooring in McClellan VA Northern California Health Care System McClellan CA Project 612A4 27 020
Solicitation number
36C26127Q0047
Issued by

About this file

Statement of Work Summary

This Statement of Work (SOW) outlines a Department of Veterans Affairs Northern California Healthcare System (VANCHCS) project to replace flooring, stair treads, and wall bases at three McClellan Park, California VA facilities (Buildings 98, 209, and 949). The scope encompasses approximately 43,008 square feet of flooring, 750 square feet of stair treads, and 9,610 linear feet of wall base replacement, including demolition, asbestos-contaminated material (ACM) surveying, testing, abatement, removal, disposal, and installation. The contractor must provide all labor, equipment, supervision, materials, tools, transportation, and incidentals necessary for complete project execution. Work must be performed during normal business hours (7:30 AM to 4:00 PM PT, Monday through Friday, excluding OPM federal holidays), though after-hours work is permissible with written approval from both the Contracting Officer (CO) and Contracting Officer's Representative (COR) submitted at least three working days in advance. The Period of Performance is 300 calendar days from Notice to Proceed issuance.

Key requirements include contractor responsibility for asbestos management services with subcontractors meeting specific EPA and Cal/OSHA certifications; provision of up to ten Conex units for furniture storage at Building 911's parking lot; coordination with VA Safety officials for hazardous materials work; site cleanliness and debris management compliant with federal, state, and local disposal regulations; submission of all submittals and Requests for Information through a VA-approved electronic project management platform (such as Procore or Autodesk); preparation of complete and accurate meeting minutes submitted to the COR within seven calendar days; maintenance of VA access throughout construction; and scheduling final inspection at least 48 hours in advance with resolution of all punch-list items before final payment. The contractor is fully responsible for verifying actual site conditions and quantities, and all premium-time labor and overtime costs must be included in the original bid. Records management requirements mandate compliance with federal records laws, NARA regulations, the Privacy Act, and FOIA, with all contractor employees required to complete VHA-provided records management training.

View the file

Other files

File Type Posted
98_209_949 FLOORING SF.xlsx XLSX spreadsheet
06 10 00 Rough Carpentry.pdf PDF
36C26127Q0047 Amendment 0003.pdf PDF
Updated SOW ATTACHMENT_Reference Drawings 20261106.pdf PDF
20261117_RFI Responses Replace Flooring MCC.pdf PDF
36C26127Q0047 Amendment 0002.pdf PDF
36C26127Q0047 Amendment 0001.pdf PDF
Site Visit Sign-in 612A4 27 020 _ 10 23 2026.pdf PDF
36C26127Q0047_Sol.pdf PDF
18. Site Visit Flyer 36C26127Q0047.pdf PDF
2. SOW ATTACHMENT_Reference Drawings.pdf PDF
16._VHA ICRA PROJECT.pdf PDF
13. RB-2_WALL BASE.pdf PDF
9. LVT-2_LUXURY VINYL TILE.pdf PDF
14. RST_RESILIENT STAIR TREADS.pdf PDF
6. CPT-1_CARPET.pdf PDF
1. SOW ATTACHMENT_Specifications_.pdf PDF
8. LVT-1_LUXURY VINYL TILE.pdf PDF
3. SOW ATTACHMENT_Bldg 209 McClellan Lead-Asbestos REP 2017.pdf PDF
12. RB-1_MILLWORK_WALL_FINISHING_SYSTEMS.pdf PDF
19. Price Breakdown Worksheet.docx DOCX document
20. Requests for Information RFI_ Form.docx DOCX document
5. Schluter_vinpro-data-sheet.pdf PDF
11. PCRA 612A4-27-020 Replace Flooring in McCellan.pdf PDF
4. SOW ATTACHMENT_1996 BW Asbestos Survey Bldgs 209.pdf PDF
7. ILSM 612A4-27-020 Replace Flooring in McCellan.pdf PDF
17. WD CA20260007 dtd 9 3 2026.pdf PDF
15. Tarkett Wall Base Made in USA.pdf PDF
10. MANN-0263 Made in the USA Supply Chain PDF v7_Digital.pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

* Updated November 5, 2026: All revisions made in this update are highlighted below.

Statement of Work Title: Replace Flooring at McClellan

Project #612A4-27-020

1. GENERAL INTENTION

A. The purpose of this project is to replace flooring throughout VA Northern California

Healthcare System (VANCHCS). This project involves replacing flooring, stair treads, and wall bases at three VA buildings in McClellan Park, California. The work will improve the VANCHCS facilities by updating approximately 43,000 square feet of flooring and related materials. The contractor will handle all demolition, asbestos testing and abatement, installation, and site coordination.

B. Contractor will provide all labor, equipment, supervision, materials, tools, transportation, and incidentals necessary to perform complete demolition, asbestos‑contaminated material (ACM) surveying, testing, abatement, removal, disposal, replacement, and installation of all components identified in this statement of work and the attached specifications.

C. Location(s) of work; the geographic location for service(s) are the following areas:

• McClellan VA Clinic, Building 98 5342 Dudley Boulevard McClellan Park, CA 95652

• McClellan VA, Administrative Building 209 3230 Peacekeeper Way

• McClellan VA, Administrative Building 949 3401 Beech Street

E. The Contractor must assume that no staging areas are available anywhere on the facility grounds. Any staging area will only be allowed if the Contracting Officer’s Representative (COR) approves one and only if space is available. The Contractor must not park in any Patient Parking areas, without exception or authorization from the COR. NCHCS will not void, dismiss, or reimburse any parking citations or towing fees incurred by Contractor personnel under any circumstances.

F. The Contractor must remove and legally dispose of all materials, debris, and components demolished or replaced under this project. Disposal must follow all applicable Federal, State, local, and VA requirements. The Contractor will keep the site clean, prevent debris from accumulating, and transport all waste in a safe manner to approved disposal or recycling facilities. No debris may be stored in unauthorized areas or left on site once removal work is complete.

G. Schedule of work; the Contractor will perform work during normal working hours except as noted on drawing sheet VA110 provided in amendment 0003. Normal working hours are: 7:30 AM(PT) to 4:00 PM(PT), Monday through Friday, excluding OPM official Federal holidays(OPM. GOV,web link:https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=Overview ).

H. If the Contractor needs to work outside normal hours, the Contractor must submit a written request to the VA Contracting Officer’s Representative (COR) and CO at least three (3) working days in advance. Approval depends on whether the VA can support the work and provide a VA representative to grant access at that time. All after‑hours requests must include the proposed dates and times, the location, the type of work, justification, and any noise‑control or safety measures. Written authorization from both the COR and CO is required before any after‑hours work may begin.

I. VA Approval to work outside normal working hours does not give the Contractor the right to request extra payment for premium time. The Contractor is responsible and must plan all work in accordance with the scheduling limits in this Statement of Work (SOW) and must include all premium‑time labor, overtime costs, and any related expenses in its original bid or quote.

J. The Contractor will provide up to (10) Conex’s for storing VA furniture. Contractor’s Conex’s will be used for storing VA furnishings and will be placed by the Contractor at Building 911’s parking lot, this space is as shown on sheet VA100 attached and provided in amendment 0003. Contractor may submit a formal request for approval to the VA COR a minimum of three (3) working days in advance of the Contractor’s need for relocating VA furniture. The Contractor is responsible for providing a professional furniture moving company for the disassembly and reassembly, relocation, storage and security of VA owned furniture and equipment throughout this project.

K. ACM has been reported to exist in Building 209. Past asbestos reports from 1996 and 2017 are attached to this SOW for reference. The General Contractor is responsible for obtaining and managing services for hazardous building materials surveying, testing, and abatement. Subcontracted personnel must be Asbestos Hazard Emergency Response Act Building Inspector trained under EPA requirements. Cal/OSHA Certified Asbestos Consultants and Certified Site Surveillance Technicians must be certified through the Division of Occupational Safety and Health. The testing laboratory must be recognized by the National Voluntary Laboratory Accreditation Program. Abatement subcontractors must be C-22 Asbestos Abatement Licensed from the Contractor’s State License Board and be officially registered with Cal/OSHA’s Asbestos Contractors Registration Unit.

L. The General Contractor is also responsible for coordinating with VA COR to have a VA Safety official(s) present for all phases of hazardous building materials surveying, testing, and abatement tasks should the VA Safety official desire to be https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=Overview https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=Overview present. Contractor must provide VA COR at least three (3) working days’ notice to schedule a VA Safety official(s) to be present.

M. The Contractor will prepare any necessary construction documents and provide all necessary/required professional services to include, but not limited to tools, equipment, materials, labor, travel, expertise, supervision, asbestos testing and analysis, asbestos abatement, and specialty services to accomplish all items and requirements outlined in this SOW. All work will comply with all applicable federal, state, local and VA regulations and requirements.

N. SUBMITTALS, RFIs, AND MEETING MINUTES REQUIREMENTS

1. Electronic Platform for Submittals and RFIs

1.1 General Requirement

The Contractor must provide, maintain, and utilize a secure, VA‑approved electronic project management platform for the submission, coordination, and tracking of all project submittals and Requests for Information (RFIs).

Use of Microsoft Teams, emails, SharePoint, or similar collaboration tools for official submittal or RFI processing is not permitted. The software must be accessible through the VAs secure firewall network.

1.2 Platform Approval

Before use, the Contractor will submit the proposed electronic platform to the Contracting Officer’s Representative (COR) for review and approval via email. Approved platforms may include industry systems such as Procore or Autodesk. The platform must remain fully accessible to both the COR and Contracting Officer (CO) throughout the period of performance and per records requirements after completion as well as cited in the SOW and specifications.

1.3 Compliance and Accessibility

The Contractor must ensure that all submittals and RFIs are transmitted exclusively through the approved platform and that all related documentation, logs, and tracking remain accurate and up to date. All RFIs must adhere to contract requirements, including numbering, supporting documentation, and identification of critical‑path RFIs when applicable. Any deviation from approved procedures may result in rejection of the submittal or RFI.

2. Meeting Minutes Requirements

2.1 Contractor Responsibility

The Contractor will draft complete and accurate meeting minutes for every project meeting conducted during the contract, including progress meetings, coordination meetings, and any meeting where project status, decisions, or direction are discussed.

2.2 Submission Timeline

Draft meeting minutes must be submitted to the COR for review and final approval no later than seven (7) calendar days after each meeting. Meeting minutes are not considered official until the COR provides written concurrence.

2.3 Accuracy Standards and Review

The Contractor must ensure that all meeting minutes are factually accurate and fully reflect discussions, decisions, and action items from each meeting.

While AI‑assisted drafting tools may be used, all AI‑generated content must be thoroughly reviewed and corrected by both the Contractor and COR approval received before submission and acceptance to avoid inaccuracies or misinterpretations. Official recording of meetings is not recommended and if done, must be approved by the VA ahead of time in writing and be in compliance with all federal and local VA policies and regulations, including permission received from all attendees in the meeting.

2. SCOPE OF WORK

A. The contractor will replace flooring, stair treads, and wall bases throughout three VANCHCS sites at their McClellan campus. There is approximately 43,008 SF of flooring, 750 SF of stair treads, and 9,610 LF of wall base to be replaced throughout McClellan buildings 98, 209 and 949, as shown in the attached Reference Drawings. These are a brief description of quantities and are estimates only and are provided for information and planning purposes. They do not represent guaranteed amounts, and the Contractor is fully responsible for verifying actual conditions and quantities before and during performance of the work.

B. Before any construction begins, the Contractor must have a certified asbestos inspector examine, sample, and test work areas in building 209 that they suspect to contain asbestos. The inspector will send all collected samples to an accredited laboratory for analysis. After testing is completed, the inspector will provide both the Contractor and the VA with a written report that identifies the location, type, and condition of all asbestos‑containing materials and includes a risk assessment describing the likelihood of disturbance during demolition or construction. The Contractor must use this report to develop a complete and safe asbestos‑abatement work plan.

C. The contractor will remove and install new accessories associated with the flooring including, but not limited to, subfloors, carpet tack strips, carpet padding, and vinyl/rubber adhesive.

D. The contractor must meet with the COR to discuss and outline phasing requirements for the project. These phasing requirements will describe the general sequence of the project work, estimated project duration, and what Government constraints will exist that will influence the Contractor’s approach to the construction project.

E. If the Contractor’s planned work alters existing egress routes, Contractor must submit a formal request to the COR for Interim Life Safety Measure (ILSM) approval at least three (3) working days in advance. Contractor’s ILSM request will detail the egress route affected, the start and completion dates, and the duration of the work hours affecting egress. ILSM approval is at the discretion of VA Safety officials.

F. VANCHCS administrative staff will be actively working throughout construction;

therefore, the Contractor must plan all work to maintain VA access to all areas of Buildings 98, 209, and 949. The Contractor will account for staff movement, ongoing operations, and any access needs while developing and executing the project schedule.

G. The Contractor will be responsible for the administration and management of all aspects of this SOW. This includes responsibility for all Contractor employees, Subcontractors, Agents, and anyone acting for or on behalf of the Contractor.

H. The Period of Performance(PoP) of this project is 300 calendar days from the date the Government issues the Notice to Proceed (NTP).

I. Only the Contracting Officer (CO) is authorized to modify the contract. All change orders initiated by the contractor require the contractor to formally submit a request to the CO for their consideration. Performing work in addition to the contract without the CO agreeing to scope, price and schedule is not authorized.

J. Final Inspection, Punch List, and Acceptance; the Contractor must schedule the Final Inspection and acceptance of all contract deliverables and completed work at least forty‑eight (48) hours in advance of the requested inspection date.

During the Final Inspection, any outstanding deficiencies will be documented on a punch list by the COR and provided electronically to the Contractor. The Contractor must correct all punch‑list items and provide verification to the COR that corrective actions have been completed. For project acceptance, the Contractor must use the official Final Inspection and Acceptance Form provided by the COR, or, if proposing an alternate form, must obtain written approval from the COR prior to its use. Final acceptance will not occur, and no final payment will be processed, until the COR confirms that all punch‑list items have been resolved and all work, reports, documentation, warranty letters, and deliverables fully comply with contract requirements.

3. DRAWINGS AND SPECIFICATIONS FOR CONTRACTOR

A. The following documents are attachments to this SOW:

• Reference Drawings

• Specifications

• 1996 BW Asbestos Survey, Bldgs 209

• Bldg. 209 McClellan Lead-Asbestos REP 2017

4. RECORDS MANAGEMENT REQUIREMENTS:

A. Applicability

This clause applies to all Contractors whose employees create, work with, or otherwise handle Federal records, as defined in Section B, regardless of the medium in which the record exists.

B. Definitions

“Federal record” as defined in 44 U.S.C. § 3301, includes all recorded information, regardless of form or characteristics, made or received by a Federal agency under Federal law or in connection with the transaction of public business and preserved or appropriate for preservation by that agency or its legitimate successor as evidence of the organization, functions, policies, decisions, procedures, operations, or other activities of the United States Government or because of the informational value of data in them.

The term Federal record:

1. includes VHA records.

2. does not include personal materials.

3. applies to records created, received, or maintained by Contractors pursuant to their VHA contract.

4. may include deliverables and documentation associated with deliverables.

C. Requirements

1. Contractor shall comply with all applicable records management laws and regulations, as well as National Archives and Records Administration (NARA) records policies, including but not limited to the Federal Records Act (44 U.S.C.

chs. 21, 29, 31, 33), NARA regulations at 36 CFR Chapter XII Subchapter B, and those policies associated with the safeguarding of records covered by the Privacy Act of 1974 (5 U.S.C. 552a). These policies include the preservation of all records, regardless of form or characteristics, mode of transmission, or state of completion.

2. In accordance with 36 CFR 1222.32, all data created for Government use and delivered to, or falling under the legal control of, the Government are Federal records subject to the provisions of 44 U.S.C. chapters 21, 29, 31, and 33, the Freedom of Information Act (FOIA) (5 U.S.C. 552), as amended, and the Privacy Act of 1974 (5 U.S.C. 552a), as amended and must be managed and scheduled for disposition only as permitted by statute or regulation.

3. In accordance with 36 CFR 1222.32, the Contractor shall maintain all records created for Government use or created in the course of performing the contract and/or delivered to, or under the legal control of the Government and must be managed in accordance with Federal law. Electronic records and associated metadata must be accompanied by sufficient technical documentation to permit understanding and use of the records and data.

4. VHA and its contractors are responsible for preventing the alienation or unauthorized destruction of records, including all forms of mutilation. Records may not be removed from the legal custody of VHA or destroyed except in accordance with the provisions of the agency records schedules and with the written concurrence of the Head of the Contracting Activity. Willful and unlawful destruction, damage, or alienation of Federal records is subject to the fines and penalties imposed by 18 U.S.C. 2701. In the event of any unlawful or accidental removal, defacing, alteration, or destruction of records, the Contractor must report to VHA. The agency must report promptly to NARA in accordance with 36 CFR 1230.

5. The Contractor shall immediately notify the appropriate Contracting Officer upon discovery of any inadvertent or unauthorized disclosures of information, data, documentary materials, records, or equipment. Disclosure of non-public information is limited to authorized personnel with a need-to-know as described in the [contract vehicle]. The Contractor shall ensure that the appropriate personnel, administrative, technical, and physical safeguards are established to ensure the security and confidentiality of this information, data, documentary material, records, and/or equipment is properly protected. The Contractor shall not remove material from Government facilities or systems, or facilities or systems operated or maintained on the Government’s behalf, without the express written permission of the Head of the Contracting Activity. When information, data, documentary material, records, and/or equipment is no longer required, it shall be returned to VHA control or the Contractor must hold it until otherwise directed. Items returned to the Government shall be hand-carried, mailed, emailed, or securely electronically transmitted to the Contracting Officer or address prescribed in the [contract vehicle]. Destruction of records is EXPRESSLY PROHIBITED unless in accordance with Paragraph (4).

6. The Contractor is required to obtain the Contracting Officer's approval prior to engaging in any contractual relationship (sub-contractor) in support of this contract requiring the disclosure of information, documentary material, and/or records generated under, or relating to, contracts. The Contractor (and any sub-contractor) is required to abide by Government and VHA guidance for protecting sensitive, proprietary information, classified, and controlled unclassified information.

7. The Contractor shall only use Government IT equipment for purposes specifically tied to or authorized by the contract and in accordance with VHA policy.

8. The Contractor shall not create or maintain any records containing any non-public VHA information that is not specifically tied to or authorized by the contract.

9. The Contractor shall not retain, use, sell, or disseminate copies of any deliverable that contains information covered by the Privacy Act of 1974 or that which is generally protected from public disclosure by an exemption to the Freedom of Information Act.

10. The VHA owns the rights to all data and records produced as part of this contract.

All deliverables under the contract are the property of the U.S. Government for which VHA shall have unlimited rights to use, dispose of, or disclose such data contained therein as it determines to be in the public interest. Any Contractor rights in the data or deliverables must be identified as required by FAR 52.227-11 through FAR 52.227-20.

11. Training. All Contractor employees assigned to this contract who create, work with or otherwise handle records are required to take VHA-provided records management training. The Contractor is responsible for confirming training has been completed according to agency policies, including initial training and any annual or refresher training.

[Note: To the extent an agency requires contractors to complete records management training, the agency must provide the training to the contractor.]

D. Flow down of requirements to subcontractors

1. The Contractor shall incorporate the substance of this clause, its terms, and requirements including this paragraph, in all subcontracts under this [contract vehicle], and require written subcontractor acknowledgment of same.

2. Violation by a subcontractor of any provision set forth in this clause will be attributed to the Contractor.

END OF STATEMENT OF WORK