20261117_RFI Responses Replace Flooring MCC.pdf
PDF 670 KB Posted
- Solicitation number
- 36C26127Q0047
About this file
This document is a comprehensive compilation of Requests for Information (RFIs) and official responses for a federal construction solicitation to replace flooring at Veterans Affairs facilities in Sacramento, California.
The project involves replacing approximately 43,008 square feet of flooring, 750 square feet of stair treads, and 9,610 linear feet of wall base across three VA buildings (Buildings 98, 209, and 949). The scope includes installation of modular carpet tile (Shaw Respond, 9x36-inch, CPT-1), luxury vinyl tile in two variants (Mannington LVT-1 at 6x36 inches and LVT-2 at 7.25x48 inches), and rubber base in two profiles (RB-1 at 6 inches for general areas and RB-2 at 4 inches for specific rooms). The contract also requires asbestos abatement, pre-construction hazardous materials surveying, and testing. The period of performance has been extended from 160 calendar days to 300 calendar days from Notice to Proceed. Building 98 work is restricted to weekends with completion required by Monday morning before patient care operations resume. Buildings 209 and 949 work occurs during normal business hours with phased execution shown on drawing VA110. The contractor is fully responsible for all asbestos surveying, testing, notifications, abatement, and regulatory compliance with the Sacramento Metropolitan Air Quality Management District (SMAQMD), including obtaining approvals and paying associated fees. No hazardous materials survey data is available for Buildings 98 and 949; materials encountered during construction must be reported to the Contracting Officer for determination of additional scope. The contractor must provide furniture removal and storage services using up to ten Conex containers, hire a third-party Certified Asbestos Consultant independent of the abatement subcontractor, perform moisture and pH testing per ASTM standards, and coordinate all staging, dumpster, and laydown areas through the Contracting Officer Representative. No attic stock, temporary power restrictions, dedicated office space, or guaranteed parking are provided by the VA.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VA Responses to Requests for Information (RFI’s)
Solicitation# 36C26127Q0047
Project Title: Replace Flooring VA McClellan
Project Number: 612A4-27-020
RFI #1. Section 09 65 19 §2.3 calls for LVT 30 mil thick, 6"x48" and 12"x24", with at least 30% recycled content. Section 09 06 00
§2.1.B schedules Mannington Spacia LVT-1 (6"x36") and LVT-2 (7.25"x48"). Please confirm whether the Section 09 06 00 schedule governs.
RFI #1 Response: Section 09 06 00 governs for flooring type, manufacturer, product, and pattern selection. Offerors are to base their
Quotes on the flooring schedule identified in Section 09 06 00 and the contract drawings. Where conflicts exist between Section 09 65
19 and Section 09 06 00, the requirements of Section 09 06 00 apply.
RFI #2. The drawings identify LVT areas but do not distinguish LVT-1 from LVT-2. Please identify where each is located.
RFI #2 Response: VA106B, Lactation Room 211 is now called out as LVT-2. All other rooms not called out to be LVT-2 are default as LVT-1.
RFI #3. Section 09 65 13 §2.2 specifies 4" resilient base of one type throughout. The drawing notes designate RB-1 (6" Millwork
Reveal) as the default and RB-2 for exam rooms. Please confirm which governs.
RFI #3 Response: RB-1 6” Millwork Reveal is the default wall base and is requested for installation in all areas other than offices and building 209 Lactation Room 211. RB-2 4” Resilient Base will be used for offices and building 209 Lactation Room 211.
RFI #4. Please confirm that the building 209 basement scope is limited to the stair tread replacement shown on VA104B. Please also confirm that the asbestos survey and abatement scope is limited to Building 209, per SOW ¶2.B.
RFI #4 Response: VA confirms that only the stair treads leading to/from 209’s basement are in the scope of this project for flooring replacement and nothing else in the basement. EPA Asbestos NESHAP makes pre-work surveys mandatory. The Contractor is required to perform the pre-work survey for all areas shown to be removing existing flooring and receiving new flooring. The
Contractor is also responsible for requesting and obtaining approval to perform the work with the Sacramento Metropolitan Air
Quality Management District (SMAQMD). The Contractor is solely responsible for securing SMAQMD approval and paying all fees, costs, and charges associated with obtaining that approval.
RFI #5. Section 01 35 26 §1.9.A requires a full-time SSHO at each project site, for each shift. Please confirm whether one SSHO may cover Buildings 98, 209 and 949, and whether afterhours shifts require a separate SSHO.
RFI #5 Response: One qualified SSHO may provide safety oversight for Buildings 98, 209, and 949. The VA does not require a separate SSHO for after-hours shifts. Accordingly, a single SSHO may cover all work performed under this contract, including after-hours work, provided the SSHO satisfies all requirements of Section 01 35 26 and maintains effective oversight of the work and project safety program at all times.
RFI #6. SOW ¶1.E–1.G requires after-hours work where staff or furnishings are relocated. Please confirm whether furniture lifted in place under SOW ¶1.H may be worked during normal hours when the room is temporarily unoccupied.
RFI #6 Response: The Statement of Work has been revised to allow the Contractor to provide up to ten (10) conex containers at the building 911 parking lot location identified on Sheet VA100 for temporary storage of VA furnishings. This SOW revision enables the
Contractor to relocate furnishings and take control of entire work areas so that occupants and furnishings are removed from the work zone.
Except where Sheet VA110 specifically identifies after-hours work, work should be performed during normal working hours. The
Contractor is fully responsible for providing all costs for professional movers to disassemble, relocate, store, and reassemble VA property to its original condition and configuration as necessary to support the work. Once occupants and furnishings have been removed from the work area, work may proceed during normal working hours.
RFI #7. Please confirm whether the 6-ft chain link construction fence in Section 01 00 00 §1.6.J applies to this interior project.
RFI #7 Response: Yes, but only for Contractor-designated exterior laydown and storage areas. Any exterior laydown area approved for Contractor use by VA, including areas used for Conex containers and temporary storage of VA furnishings, requires a 6-foot chain-link fence around the perimeter.
The Contractor may request exterior laydown or storage space by submitting the proposed location and dimensions to the VA COR via email. Approval of any requested space is subject to review by VA Facility Management and may be granted, denied, modified, suspended, or revoked at the VA's discretion. No exterior laydown or storage area may be used until written approval has been provided by the VA.
The Contractor is solely responsible for furnishing, installing, securing, maintaining, repairing, relocating, and removing all required fencing. All costs associated with the fencing, including installation, maintenance, access control, and restoration of the area upon completion of the work, are the responsibility of the Contractor and are included in the contract price.
Approval of a laydown or storage area does not relieve the Contractor of responsibility for the security, protection, and safe operation of the area, nor does it create any Government liability for loss of or damage to the Contractor's equipment, materials, or property stored within the area.
RFI #8. Section 09 68 00 §1.7.B reads “ten (25) years.” Please confirm the required manufacturer warranty term.
RFI #8 Response: VA is confirming the warranty is for ten (10) years.
RFI #9. The PCRA lists phases for Buildings 209 and 949 only. Please confirm the phasing and sequencing requirements for Building
98, and whether phases may run concurrently.
RFI #9 Response: 98 was added to the project later in the process after PCRA approval. Bldg. 98 work will be during the weekend, per new drawings sheet VA110. 949 will need to be the last building as staff will be relocated to 209 during 949 flooring renovation.
Bldg. 209 must be completed before 949 work begins. Expected phasing is now shown on new drawing sheet VA110 attached to amendment 0003.
RFI #10. Please confirm whether systems furniture is present in the work areas, and whether the Government will remove personal items, files and IT equipment before work in each room.
RFI #10 Response: Modular systems are present in buildings 209 and 949. Per RFI #6 response, above, the Contractor is responsible for disassembly, move, and reassembly of all VA furnishings. Personal items of VA employees will be removed by VA staff prior to
VA handover of space to the Contractor to perform work.
RFI #11. Please confirm whether a container or dumpster location will be made available at each building (SOW ¶1.E).
RFI #11 Response: The VA does not guarantee the availability of container or dumpster locations at each building. The Contractor may request the use of exterior space for dumpsters, containers, or other temporary storage by submitting the proposed location and dimensions to the COR. Requests are subject to review by VA COR and Facility Management and may be approved, denied, modified, suspended, or revoked at the VA’s discretion.
No dumpster, container, or storage area may be placed or used until written approval has been provided by the VA COR. The
Contractor is responsible for furnishing, placing, maintaining, securing, relocating, and removing all dumpsters and containers, and for all costs associated with their use. Approval of a location does not relieve the Contractor of responsibility for maintaining safe access, protecting adjacent facilities and operations, and complying with all contract requirements.
RFI #12. Please confirm that clearance air sampling following abatement will be performed by the VA’s industrial hygiene consultant, per the definitions in Section 02 82 11 §1.3.
RFI #12 Response: VA does not have their own Industrial Hygienist. Contractor will coordinate with the COR three (3) days prior to the Contractor performing clearance air sampling so that the COR may notify the VA Safety Officer. VA Safety Officer presence is not required, just that they be given the option to attend.
RFI #13. Please provide any available slab moisture test data for the three buildings.
RFI #13 Response: The VA does not possess or have available slab moisture test data for Buildings 98, 209, or 949. Contractors are responsible for relying on their own judgment in preparing their Quotes and should account for the potential need to perform moisture testing and address field conditions as necessary to comply with the contract requirements.
RFI #14: Baseline Environmental Survey Data for Buildings 98 and 949. The solicitation package provides detailed hazardous building materials reports for Building 209 (1996 Lee & Ro and 2018 Ninyo & Moore). To ensure consistent bidding across the full
43,000 SF envelope, please clarify whether prior survey data exists for Building 98 (5342 Dudley Blvd) and Building 949 (3401
Beech St), or if bidders should incorporate a pre-demolition AHERA baseline survey and bulk PLM sampling allowance for these two facilities.
RFI #14 Response: The VA is not aware of, and is not providing, any hazardous building materials survey data for Buildings 98 and
949. Contractors should assume that no environmental survey data is available for these buildings and must include all costs necessary to perform any required pre-demolition hazardous materials surveys, sampling, testing, analysis, notifications, and permitting needed to complete the work in accordance with applicable federal, state, local, and contract requirements. This includes all costs associated with obtaining Sacramento Metropolitan Air Quality Management District (SMAQMD) approvals, permits, and related fees.
RFI #15: Clarification on Non-Mechanical Manual Scraping (Manual Tile Popping) vs. SMAQMD Rule 902 RACM
Notification. In legacy facilities, resilient floor tile removal can sometimes be performed intact using manual, non-mechanical hand methods (e.g., manual scraping or dry ice). However, under Sacramento Metropolitan Air Quality Management District (SMAQMD)
Rule 902, if cutback mastic or broken tiles become crumbled, pulverized, or reduced to powder, or if mechanical blades or scrapers are utilized, the material is categorized as Regulated Asbestos-Containing Material (RACM). Clarification Request: Please confirm whether the VA and SMAQMD will require full Rule 902 RACM procedures—including the mandatory 10-working-day air district notification, district fee schedules, and negative-pressure containment—for all 43,000 SF, or if manual razor scraping without district notification is contemplated for any sound, intact floor zones.
RFI #15 Response: The Contractor must comply with all applicable asbestos, environmental, and air-quality regulations, including any required Sacramento Metropolitan Air Quality Management District (SMAQMD) notifications, approvals, permits, and waiting periods. For purposes of proposal preparation, offerors must assume that the SMAQMD 10-working-day notification requirement applies to the work. The Contractor is solely responsible for obtaining all required SMAQMD approvals and for payment of all associated fees, costs, and charges.
The VA does not prescribe the specific asbestos-abatement methods to be used. The determination of whether negative-pressure containment, RACM controls, manual removal methods, or other abatement procedures are required is the responsibility of the
Contractor's qualified asbestos professional based on field conditions, applicable regulations, VA Policies, and the Contractor's VA
COR approved abatement plan. The Contractor remains responsible for performing the work in full compliance with all regulatory requirements.
RFI # 16: Historical 'Maintenance-In-Place' (MIP) vs. 100% Substrate Abatement Mandate. The 1996 Basewide Survey designated confirmed vinyl asbestos tile in Building 209 as 'MIP' (Maintenance In Place / O&M Program). The current Statement of
Work calls for complete replacement. Clarification Request: Please confirm for all bidding contractors that the project requirement is
100% removal down to the concrete substrate (superseding the historical MIP designation), or identify if encapsulating / skim-coat leveling over sound, intact non-friable tile is approved in any designated clinical or administrative suites.
RFI #16 Response: Confirmed, VA requires 100% removal down to the concrete substrate.
RFI #17: Third-Party CAC Independence and California B&P Code § 7187 Demarcation. Under California Business and
Professions Code § 7187 and Cal/OSHA standards, environmental consultants performing asbestos assessments, containment oversight, and clearance testing must maintain independent professional judgment free from the beneficial or financial control of the abatement removal contractor. Clarification Request: Please confirm that the Certified Asbestos Consultant (CAC) providing third-party industrial hygiene oversight and clearances may subcontract directly to the Prime General Contractor (or directly to the VA) rather than reporting through the C-22 abatement subcontractor, ensuring statutory compliance while preserving the turnkey procurement structure.
RFI #17 Response: VA confirms the third-party industrial hygienist providing oversight and clearances will be subcontracted with the Prime General Contractor (not with the abatement subcontractor).
RFI #18: Demarcation of Contractor Cal/OSHA Worker Exposure Monitoring. Under Cal/OSHA Title 8 CCR § 1529(f) and 29
CFR 1926.1101, the employer performing abatement is required to conduct personal breathing-zone monitoring (8-hour TWA and 30-minute excursion sampling) for its workforce.
Clarification Request: To maintain clear quality control boundaries, please confirm that the abatement contractor's internal OSHA worker compliance monitoring remains the independent responsibility of the C-22 contractor's Competent Person and is separate from the third-party CAC's area air monitoring and facility clearance testing.
RFI #18 Response: The Contractor performing the asbestos work remains solely responsible for complying with applicable worker-protection requirements, including employee exposure assessments and personal breathing-zone monitoring required by 29 CFR
1926.1101(f). This responsibility includes determining the type, frequency, and extent of worker exposure monitoring required for the employer's workforce.
The Contractor's employee exposure monitoring is separate and distinct from the third-party asbestos oversight required by the contract, including area air monitoring, visual inspections, and final clearance testing performed by the Certified Asbestos Consultant
(CAC). The CAC's activities do not satisfy the Contractor's worker exposure monitoring obligations, nor do the Contractor's worker exposure monitoring activities satisfy the contract requirements for independent third-party monitoring and clearance. The Contractor remains responsible for all costs, personnel, equipment, and regulatory compliance associated with employee exposure monitoring.
RFI #19: Mandatory Analytical Clearance Protocol (AHERA TEM vs. NIOSH PCM). Building 209 contains over 27,000 SF of confirmed asbestos-containing tile and mastic in an active healthcare environment. VA Master Specifications Section 02 82 11 and 02
82 13.19 typically specify Transmission Electron Microscopy (TEM) for regulated containment areas exceeding 160 SF / 260 LF.
Clarification Request: Please confirm that final air clearance for containment areas exceeding 160 SF will strictly utilize AHERA
TEM protocol (Z-test sampling set: 5 inside, 5 outside, 3 blanks), or identify if Phase Contrast Microscopy (NIOSH 7400 PCM) is authorized for any specific containment phases.
RFI #19 Response: Section 02 82 11, 3.6.C-D, and Section 02 82 13.19, 3.6.C-D, govern project clearance. For a regulated area at or above 160 SF / 260 LF / 35 CF, the specifications require AHERA TEM clearance; below those thresholds, five PCM samples plus at least two field blanks are specified. For TEM, the project specification requires the AHERA protocol and five inside samples, five outside samples, two field blanks, and one sealed blank as applicable under AHERA Appendix A. All five inside TEM samples must be at or below 70 asbestos structures/mm²; no averaging is permitted. The specification also requires visual clearance and the stated
PCM/TEM release criteria.
RFI #20: Mandatory Analytical Clearance Protocol (AHERA TEM vs. NIOSH PCM). Building 209 contains over 27,000 SF of confirmed asbestos-containing tile and mastic in an active healthcare environment. VA Master Specifications Section 02 82 11 and 02
82 13.19 typically specify Transmission Electron Microscopy (TEM) for regulated containment areas exceeding 160 SF / 260 LF.
Clarification Request: Please confirm that final air clearance for containment areas exceeding 160 SF will strictly utilize AHERA
TEM protocol (Z-test sampling set: 5 inside, 5 outside, 3 blanks), or identify if Phase Contrast Microscopy (NIOSH 7400 PCM) is authorized for any specific containment phases.
RFI #20 Response: Per VA’s response to RFI #19, above, the VA project specifications require TEM for regulated areas at or above
160 SF / 260 LF / 35 CF and PCM for smaller areas, with the sample counts, AHERA procedures, visual inspection, and individual
TEM sample limit stated in Sections 02 82 11 and 02 82 13.19, 3.6.
RFI #21: Multi-Layer Flooring Delamination & Containment Protocols. The 2018 Ninyo & Moore report (e.g., Sample A-71 in
South Stairwell) and 1996 logs document multi-layer assemblies where modern tile or carpet is installed directly over legacy chrysotile tile and black mastic.
Clarification Request: In the event that peeling carpet or modern tile causes mechanical delamination or damage to underlying ACM tile, please confirm that the affected areas must immediately transition to full Cal/OSHA Class II negative-pressure containment and
SMAQMD Rule 902 RACM handling.
RFI #21 Response: If concealed ACM is exposed, delaminated, broken, or otherwise disturbed, stop the affected work, restrict access, notify the asbestos Competent Person and COR, and implement the applicable regulated-area controls and approved abatement plan before resuming. Whether the condition is RACM and whether negative-pressure containment/Rule 902 procedures apply depends on the Contractor’s asbestos professional’s abatement plan.
RFI #22: Project Phasing, Work Envelope Sizing, and Clinic Coordination. Executing 43,000 SF of flooring, 9,610 LF of wall base, and 750 SF of stair treads in operational VANCHCS buildings requires careful scheduling around patient care and administration.
Clarification Request: To assist contractors in establishing consistent labor and mobilization assumptions, does the VA have a preferred baseline phasing breakdown (e.g., maximum SF per containment phase), or will the phasing sequence be finalized collaboratively during the post-award Infection Control Risk Assessment (ICRA) and pre-construction meeting?
RFI #22 Response: A preferred phasing plan is now included; please see new drawing sheet VA110 attached with amendment 0003.
RFI #23: Off-Hours Re-Occupancy Schedules and Laboratory Turnaround Times. The solicitation notes that work may require off-hours scheduling. Clarification Request: For phases completed during night or weekend shifts, what is the required re-occupancy milestone for clinic staff, and should laboratory pricing account for rapid rush TEM turnaround times (e.g., 6-hour or 12-hour analysis) to ensure certified clearances prior to weekday clinic reopening?
RFI #23 Response: Buildings 209 and 949 are administrative facilities where work may be performed during normal VA working hours. Building 98 is an outpatient clinical facility and requires phased work to be completed during weekends, with affected areas returned to an occupiable and fully operational condition before the start of patient care activities on Monday. Work areas in Building
98 will not remain incomplete or unavailable for use during the normal work week unless specifically authorized by the VA COR.
Work is permitted during the hours identified in the Statement of Work. Any deviation from those hours or any schedule exception requires prior approval from the VA COR. Approval of a schedule exception is at the sole discretion of the VA and may be granted, denied, modified, or revoked based on operational needs.
Contractors are responsible for including all labor, testing, monitoring, and laboratory resources necessary to support the required construction schedule and re-occupancy requirements. If accelerated laboratory analysis, including rapid-turnaround TEM testing, is necessary to achieve contract-required clearance and re-occupancy milestones, the associated costs and scheduling considerations are the responsibility of the Contractor. Based on the anticipated phasing, the Audiology Corridor identified as CORRIDOR 2M20 on
Sheet VA103B is the only area currently expected to require rapid-turnaround clearance results to support timely re-occupancy.
However, the Contractor remains responsible for providing any testing, monitoring, and laboratory turnaround times necessary to meet the contract schedule and re-occupancy requirements.
RFI #24: Affirmative Safety Intervention Authority for Licensed Professionals & Authorized OSHA Trainers.
Consultants on site hold active California CAC licensing and OSHA General Industry Outreach Trainer authorizations, carrying professional and statutory obligations to safeguard personnel and occupants. Clarification Request: Please confirm that the third-party
CAC maintains the professional authority to temporarily halt work or require containment adjustment in the event of an imminent safety risk (such as negative pressure loss below -0.02" w.g. or containment breach adjacent to occupied clinics) without the consultant incurring delay liabilities.
RFI #24 Response: The asbestos Competent Person has authority to take prompt corrective measures under 29 CFR 1926.1101 and the VA specification. The Contractor's Asbestos Competent Person is responsible for directing asbestos work and implementing corrective actions when required. If the Certified Asbestos Consultant (CAC) identifies an imminent hazard, containment breach, loss of required negative pressure, or other unsafe condition, the CAC may recommend to the VA COR that the affected work stop until the condition is corrected.
Any person observing an imminent hazard should stop the affected operation, secure the area, and immediately notify the Competent
Person and VA COR. A CAC acting in good faith within its professional responsibilities to identify and report unsafe conditions will not be held responsible for resulting delays. However, the CO, and VA COR must be informed in writing of any delays. The CO will determine any contract impacts resulting from a work stoppage.
RFI # 25: Wall Base Removal Drywall Damage & Concealed Joint Compound
The project includes 9,610 LF of wall base. In legacy buildings, cove base mastic removal can pull drywall paper or expose underlying joint compound.
Clarification Request: If baseboard removal reveals previously uncharacterized mastic or impacts older joint compound in Buildings
98 and 949, what unit rate mechanism or change protocol will govern localized wall patching, secondary sampling, and containment adjustments?
RFI #25 Response: No unit-rate allowance is established for this work. If wall base removal exposes suspect materials, the Contractor must immediately notify the VA COR and Contracting Officer (CO), and evaluate and, as necessary, sample the materials before disturbing them in accordance with the contract requirements.
The Contractor is responsible for all costs associated with sampling, testing, and repairing damage resulting from its work. If the
Contractor encounters a materially differing concealed condition that it believes constitutes additional scope, it must promptly notify the CO and obtain written direction before proceeding with any work associated with the condition. Only the CO has authority to determine whether additional work is outside the contract scope and to modify the contract. Absent a contract modification executed by the CO, all work required to complete the contract remains the Contractor's responsibility.
RFI #26: Lead-Containing Paint (LCP) Disturbance on Stairwell Concrete Substrates.
The 2018 Ninyo & Moore report identified lead-containing paint on the 1st Floor South Stairwell concrete wall (Sample L-02) at
1,300 mg/kg (0.13% lead by weight), which exceeds California Title 22 hazardous waste and Cal/OSHA compliance thresholds.
Clarification Request: Does replacing the 750 SF of stair treads require surface grinding, mechanical scraping, or prep on adjacent concrete risers/stringers that would trigger Cal/OSHA Title 8 CCR § 1532.1 lead engineering controls, HEPA ventilation, and lead waste profiling as part of the base scope?
RFI #26 Response: VA projects do not fall under Cal OSHA. Base scope must include all necessary controls required by 29 CFR
1926.62.
RFI #27: Room-by-room flooring assignments, Reference: New flooring plans VA102B–VA109B; Section 09 06 00.
The plans identify a general LVT hatch, while the finish schedule specifies both LVT-1 and LVT-2. Please provide a room-by-room finish schedule identifying the required LVT type and confirm that unhatched areas are excluded from flooring replacement.
RFI #27 Response: LVT-1 is the default LVT flooring required. Per response to RFI #2, building 209 Lactation Room 211 on
VA106B is to be LVT-2. An Excel sheet is now provided for reference, but the Contractor must determine their own amounts. The drawings are scalable. VA is confirming that all unhatched areas are excluded from this flooring replacement project. Drawings have been updated to be colorized to assist Contractors in distinguishing what areas are hatched and what areas are not.
RFI #28: LVT dimensions, thickness, and wear layer, Reference: Section 09 65 19, paragraph 2.3; Section 09 06 00; Attachments
8 and 9.
Section 09 65 19 specifies “30 mil (3/32 inch)” thickness and sizes of 6 × 48 inches and 12 × 24 inches. The finish schedule specifies
6 × 36-inch LVT-1 and 7.25 × 48-inch LVT-2, while the product sheets offer 2.5 mm and 4 mm products with a 20-mil wear layer.
Please confirm the governing dimensions, total thickness, and wear-layer requirement.
RFI #28 Response: Section 09 06 00 is the coordinated finish schedule and controls scheduled product sizes. Per response to RFI #1, when 09 65 19 specifications conflict with 09 06 00, 09 06 00 will govern.
RFI #29: Carpet tile size, Reference: Section 09 68 00, paragraph 2.1; Section 09 06 00; Attachment 6.
Section 09 68 00 specifies 24 × 24-inch carpet modules, while the finish schedule and Shaw Respond product information identify 9 ×
36-inch modules. Please confirm that the scheduled 9 × 36-inch product governs and identify the required brick or ashlar installation pattern.
RFI #29 Response: Per response to RFI #1 and RFI #29, 09 06 00 governs when there is conflicting information.
RFI #30: Wall base height and profile, Reference: Section 09 65 13, paragraph 2.2; Section 09 06 00; new flooring plan notes.
Section 09 65 13 specifies 4-inch cove base throughout, while the finish schedule identifies 6-inch profiled RB-1 and 4-inch cove RB-
2. Please confirm that RB-1 applies to all flooring replacement areas except exam rooms, which receive RB-2, and identify any additional exceptions.
RFI #30 Response: Per response to RFI #1, RFI #29 and RFI #30, 09 06 00 governs when there is conflicting information.
RFI #31: Building 209 asbestos removal limits, Reference: Building 209 hazardous materials report, PDF page 9, Table 1; Sections
02 82 11 and 02 82 13.19. The report identifies approximately 17,000 SF of green floor tile and associated mastic, 10,000 SF of tan floor tile and associated mastic, and 380 SF of brown mastic associated with ceiling tile. Please provide an overlay correlating these locations with the current flooring replacement areas and clarify whether the ceiling-tile mastic is included in this contract.
RFI #31 Response:
The quantities identified in the hazardous materials report are approximate building-wide quantities and do not represent a verified overlay of the flooring replacement areas included in this contract. Contractors are responsible for reviewing the contract drawings and specifications to determine the anticipated work areas.
The ceiling-tile mastic, HVAC duct insulation/materials, and lead-based paint identified in the report are not included in the scope of this flooring replacement project. The asbestos-related work under this contract is limited to the materials required to perform the flooring replacement work shown in the contract documents.
The Contractor is responsible for assessing and, as necessary, sampling suspect materials encountered within the work area to support its means and methods, regulatory compliance, and execution of the work. All costs associated with such sampling, testing, analysis, notifications, permits, and related compliance activities are the responsibility of the Contractor and are included in the contract price.
If the Contractor encounters suspect materials outside the identified scope and believes the condition constitutes additional work, the
Contractor must promptly notify the VA COR and Contracting Officer (CO) before disturbing the material. Only the CO may authorize a change to the contract scope.
RFI #32: Updated asbestos information and concealed flooring. Reference: Building 209 hazardous materials report, PDF page 6, “Physical Limitations”; SOW Section 2.B. The report excludes certain areas and notes that some existing flooring is beneath carpet.
Please provide records of subsequent abatement or renovations and clarify the bid basis for concealed flooring layers or additional
ACM identified during the required preconstruction survey. Please confirm whether separate unit prices or an allowance should be submitted for quantities that cannot be verified before bidding.
RFI #32 Response: There have been no abatement or renovation in the areas included in this project. Per response to RFI #25, for materially differing concealed conditions or added scope, notify the CO and obtain written direction/modification before proceeding;
only the CO may modify the contract. Separate unit prices are not allowed as changes to the contract must be as directed from the CO.
RFI #33: Hazardous-material survey coverage in Buildings 98 and 949. Reference: SOW hazardous-material provisions; attached surveys for Building 209. Please provide available hazardous-material surveys for Buildings 98 and 949 and confirm whether additional testing is required before disturbing their flooring, adhesive, wall base, or associated materials.
RFI #33 Response: No hazardous material surveys are available for buildings 98 and 949. Per response to RFI #4, the Contractor is required to perform the pre-work survey for all areas shown to be removing existing flooring and receiving new flooring. The
Contractor is also responsible for requesting and obtaining approval to perform the work with the Sacramento Metropolitan Air
Quality Management District (SMAQMD). The Contractor is responsible for paying all related fees for obtaining SMAQMD approval.
RFI # 34: Lead-containing materials affected by the work. Reference: Building 209 hazardous materials report, PDF page 9, Section 6.2. The report identifies lead-containing painted materials, including basement HVAC ductwork. Please identify any lead-containing surfaces expected to be disturbed by flooring or wall-base removal and clarify the required testing, controls, and restoration scope.
RFI #34 Response: The hazardous materials report does not identify specific lead-containing surfaces that will be affected by the flooring or wall-base removal work, and the VA does not anticipate disturbing lead-containing materials or lead containing abatement costs as part of this project.
If Lead is discovered the Contractor is responsible for complying with all applicable lead-related regulatory requirements, including any necessary testing, monitoring, and protective measures. If lead-containing materials are encountered that may constitute additional scope or costs to the contract, the Contractor must notify the VA COR and Contracting Officer (CO) promptly and obtain written direction before proceeding. Only the CO may modify the contract.
RFI #35: Asbestos inspection and clearance responsibilities. Reference: Sections 02 82 11 and 02 82 13.19; monitoring and final-clearance provisions. The specifications assign monitoring duties to the contractor’s industrial hygienist and final inspection/clearance duties to the VA’s industrial hygienist. Please confirm who retains and pays for the independent final-clearance consultant and laboratory, including after-hours attendance, and provide the anticipated clearance turnaround for each phase.
RFI #35 Response: Per response to RFI #12, the VA has no in-house Industrial Hygienist and requires three days' notice to the COR before clearance sampling so the VA Safety Officer can be offered attendance. Per response to RFI #17 the third-party Industrial
Hygienist providing oversight/clearance is subcontracted to the Prime General Contractor (GC), not the abatement subcontractor. The
Industrial Hygienist providing oversight and clearance must be independent of the asbestos abatement subcontractor.
The Contractor must budget any costs in quote for retaining and paying the Industrial Hygienist for any laboratory services, sampling, analysis, retests, and after-hours support required by Sections 02 82 11 and 02 82 13.19 The final visual inspection and clearance sampling will be performed by the Contractor's Industrial Hygienist.
RFI #36: PCRA and ILSM scope discrepancies. Reference: Attachments 7 and 11; SOW Section 2.
The PCRA and ILSM describe carpet and wall-base replacement in Buildings 209 and 949. The current scope also includes Building
98, Building 209 basement work, LVT, stair treads, and asbestos abatement. Please issue updated assessments covering the complete contract scope and reconcile the PCRA’s “No” response for disturbance of hazardous building materials with the required asbestos work.
RFI #36 Response: Building 98 scope was added after PCRA and ILSM approvals were obtained. An updated PCRA will be provided to the awarded Contractor. There is no scope that includes 209 basement, only the interior stairs leading down to the basement. ILSMs will be coordinated with the Contractor based on how the project will be phased.
RFI #37: Required infection-control precautions. Reference: Attachment 16, VHA ICRA; Section 01 35 26.
The ICRA highlights Level II measures, but the activity category, patient-risk category, precaution-level fields, and permit are not completed. Please confirm the required precaution level for each building and phase, including barrier construction, negative air, exhaust routing, HVAC isolation, monitoring, and clearance requirements.
RFI #37 Response: Except areas being abated, ICRA level II applies at all other locations. Specific to building 98 work, because building 98 work will be performed on the weekend and cleaned up entirely prior to Monday patient care hours, then ICRA level II applies.
RFI #38: Phasing and available work areas. Reference: SOW Sections 2.D and 2.F; PCRA and ILSM phase schedules.
Please provide the required construction sequence and identify the maximum rooms or area available per phase, permitted simultaneous work in separate buildings, and required daily turnover conditions. Please reconcile the five phases in the safety attachments with the additional Building 98 and Building 209 basement scope and the 160-calendar-day contract duration.
RFI #38 Response: Drawing VA110 in amendment 0003 identifies the anticipated construction phasing, sequence of work, and areas included in each phase. Contractors are responsible for reviewing Drawing VA110, the contract drawings, and specifications when developing their construction approach and schedule.
For Building 98, work must be phased so that only areas that can be fully completed, 100% cleaned, cleared for occupancy, and returned to service by Monday morning are taken out of service during weekend work. Daily turnover conditions require work areas to be left safe, clean, and ready for normal operations in accordance with the contract requirements.
The Building 209 basement scope is limited to the stairway leading to the basement and does not include replacement of basement flooring. Work may be performed concurrently in multiple buildings to the extent it is consistent with the approved schedule, phasing requirements, and facility operations.
To accommodate the required phasing and operational constraints, the Statement of Work has been revised to extend the period of performance from 160 calendar days to 300 calendar days. Any deviation from the approved phasing or work-hour requirements requires prior approval from the VA COR.
RFI #39: After-hours work and uninterrupted access. Reference: SOW work-hours provisions; Section 09 68 00, paragraph 3.2.
The SOW requires certain activities after hours and continued VA access, while the carpet specification prohibits traffic and furniture movement for 24 hours after installation. Please identify the permitted night/weekend work windows and confirm whether completed areas may remain closed through the required adhesive cure period.
RFI #39 Response: Drawing VA110, issued with Amendment 0003, identifies the areas authorized for weekend work in Building 98.
Work hours are limited to those identified in the Statement of Work and approved by the VA COR. Weekend work in Building 98 is subject to VA operational availability and is limited to no more than eight (8) hours per day unless otherwise approved by the VA
COR.
Completed areas may remain closed as necessary to allow the manufacturer's required adhesive curing period. The Contractor is responsible for planning and sequencing the work to accommodate curing times while meeting all occupancy, phasing, and operational requirements. Building 98 Office 1C21 may remain unavailable for one Monday during the curing period, provided the area is returned to service before the next morning patient service hours on Tuesday.
RFI #40: Furniture, equipment, and workstation systems. Reference: SOW furniture-lifting and relocation provisions.
Please provide an inventory or representative plans identifying modular workstations, anchored furniture, heavy equipment, and items unsuitable for hydraulic lifting. Please clarify responsibility for disconnecting and reconnecting power, data, and specialty equipment, and identify any items that VA personnel will handle.
RFI #40 Response: No inventory or furniture plans are provided. Per the response to RFI #6, the SOW has been revised to require the
Contractor to provide up to ten (10) Conex containers for temporary storage of VA furnishings. The Contractor is responsible for all labor, equipment, materials, supervision, and costs required to disassemble, disconnect, relocate, store, reconnect, reassemble, and return furniture, workstations, power, data, and other associated components necessary to complete the work and restore the area to its pre-construction configuration.
VA employees/personnel will remove personal belongings before turning over a work area to the Contractor. The VA will not perform furniture disassembly, relocation, storage, reconnection, or reassembly activities.
For quote pricing purposes, offerors must assume the following minimum furniture quantity for each 96 square feet (12' × 8') of office space: 3.5 walls of 8-foot-wide partitions, one (1) 2' × 4' desk, one (1) 3' × 4' hutch, one (1) wheeled armchair, and one (1) 18" ×
36" wardrobe/shelf. The Contractor is responsible for surveying existing furniture and documenting its configuration before relocation. A copy of the survey must be provided to the VA COR for record purposes.
The Contractor must include all costs associated with furniture, workstation, power, data, and equipment relocation in its proposal. If the Contractor encounters conditions that it believes constitute materially different site conditions or additional scope beyond the assumptions identified above, it must notify the Contracting Officer (CO) and VA COR and obtain written direction before proceeding. Only the CO has authority to determine whether additional work is outside the contract scope and to modify the contract.
RFI #41: Moisture mitigation and floor leveling. Reference: Section 09 05 16, paragraphs 3.2–3.4.
The specifications require testing, moisture remediation where necessary, and underlayment to meet substrate tolerances. Please provide available moisture-test results and existing slab-condition information. Where conditions cannot be assessed before flooring removal, please establish a common bidding allowance or unit-price basis for mitigation and leveling, including assumed treatment area and underlayment depth.
RFI #41 Response:
No moisture-test results or existing slab-condition data are available. Offerors are responsible for including all costs necessary to perform the testing required by Section 09 05 16 and to assess slab conditions after flooring removal.
No bidding allowance or unit-price mechanism is being established for moisture mitigation, floor leveling, underlayment installation, or related corrective work. The Contractor must include in its Quote all work and costs reasonably necessary to comply with the substrate preparation, moisture, and floor-flatness requirements of the contract.
If the Contractor encounters a condition that it believes constitutes a materially differing site condition or work outside the contract scope, it must immediately notify the Contracting Officer (CO) and obtain written direction before proceeding with the affected work.
Only the CO has authority to determine whether additional work is outside the contract scope and to modify the contract.
RFI #42: Extent of subfloor replacement. Reference: SOW Section 2.C; Section 09 05 16.
The SOW includes removal and installation of flooring accessories “including…subfloors.” Please clarify whether this requires replacement of existing subfloor assemblies or only localized repairs and preparation. Identify any required replacement locations, materials, and thicknesses.
RFI #42 Response: For Building 209, contractor is to remove flooring and associated materials down to the existing substrate. For quote pricing purposes, assume an APA-rated sheathing subfloor of 19/32-inch thickness with 1/4-inch underlayment. The
Contractor is responsible for all floor preparation necessary to install the new flooring system in accordance with the contract requirements.
For Buildings 98 and 949, assume there is no subfloor or underlayment beneath the existing flooring.
No allowance or unit-price mechanism is being established for subfloor replacement. If the Contractor encounters concealed conditions that materially differ from these assumptions and believes they constitute additional scope, the Contractor must immediately notify the Contracting Officer (CO) and obtain written direction before proceeding with the affected work.
RFI #43: Stair tread assemblies and quantity basis. Reference: Section 09 65 13; Section 09 06 00; Attachment 14; SOW estimated quantities. Please identify the stair flights and landings included and confirm whether the estimated 750 SF includes tread surfaces only or also risers and landings, and whether it is additional to the estimated 43,008 SF of flooring. Please confirm the required integrated riser, contrasting nosing strip, stringer finish, and landing material.
RFI #43 Response: The 750 square feet of stair treads is from the plan view and did not account for vertical surfaces at the stairs, but it does include the landings. This is in addition to the 43,008 SF estimated for flooring. The landing material will be LVT-1, and the treads are per 09 06 00 “RST” Resilient Stair Tread; hammered integrated riser with black contrasting nosing strip.
RFI #44: Static-dissipative flooring requirements. Reference: Section 09 65 19, paragraphs 2.4–2.5 and 3.4.
The specification includes static-dissipative tile, conductive adhesive, copper grounding tape, and electrical testing, but the finish schedule identifies ordinary LVT products. Please confirm whether these requirements apply. If applicable, identify the rooms, flooring product, grounding details, and electrical connection responsibilities.
RFI #44 Response: Static dissipating tile flooring does not apply. VA had completed the specifications prior to establishing the exact rooms to include on the project; 09 65 19 paragraphs 2.4-2.5 and 3.4 do not apply to any of the spaces chosen for renovation.
RFI #45: Wall restoration following base removal. Reference: Wall-base replacement scope; Section 09 65 13.
Please clarify the required wall repairs and painting following removal of existing base, particularly where new 4-inch base may expose surfaces previously covered by taller base. Confirm whether painting is limited to repaired areas or extends across the affected wall.
RFI #45 Response: Painting is limited to only repair areas to match existing wall finishes.
RFI #46: Staging, acclimation, and material deliveries. Reference: SOW staging restrictions; Sections 01 00 00 and 09 65 19.
The SOW directs bidders to assume no available staging area, while the specifications require material acclimation and limit deliveries to immediate work areas. Please identify approved indoor acclimation locations, loading routes, elevator availability and capacity, and permitted locations for debris containers and abatement support facilities.
RFI #46 Response: Staging areas refers to exterior areas used by Contractors for parking equipment; these spaces are assumed to be not available. Interior staging for flooring materials for acclimation can be coordinated with the COR, as needed, through formal request of plausible areas, how much space is requested, and for how long. Loading routes should also be included in the Contractors request for interior staging space. Exterior staging areas can also be requested formally through the COR, with requests showing where and how large a space is requested. VA Facility Management has full discretion on approving the Contractor’s request for exterior space. Elevators are typically rated for 2,500 pounds at the minimum.
RFI #47: Is there a place to store the office furniture within the building. Please share the location on the floor plan.
RFI #47 Response: Per response to RFI #6, SOW has been updated to allow the Contractor to stage up to (10) Conex’s to store VA furnishings. Please also see sheet VA100 attached in amendment 0003 for where those Conex’s are to be located.
RFI #48: Are we moving any heavy equipment from the work area.
RFI #48 Response: The heaviest equipment known for movement is the Xerox 6TB059632 AltaLink C8070 Printers, each approximately 321 pounds.
RFI #49: Will the building remain operational during demolition.
RFI #49 Response: The majority of each building will remain operational during demolition.
RFI #50: How many phases & mobilizations per building and/or floor?
RFI #50 Response: Drawing VA110, issued with Amendment 0003, identifies the anticipated phasing and sequencing of the work.
The number of mobilizations, work areas, and phases within each building are dependent on the Contractor's means and methods and proposed construction schedule.
For Building 98, work is limited to approved weekend work windows and must be phased so that each work area is fully completed, cleaned, and returned to service before the start of patient care operations on Monday. Contractors are responsible for determining the number of weekends, mobilizations, and work phases required to complete the work within the contract period of performance while complying with all phasing, occupancy, and operational constraints shown in the contract documents.
RFI #51: Will we be able to get machine equipment up or will floor & glue removal need to be done by hand?
RFI #51 Response: Elevators may be available for Contractor use upon request and approval by the VA COR. Any approved use of elevators for moving equipment, materials, or debris requires the Contractor to protect the elevator cab walls, doors, and flooring from damage.
The VA does not restrict the Contractor to hand removal methods. The Contractor is responsible for determining and providing the equipment, tools, and removal methods necessary to perform the work in compliance with the contract requirements, facility constraints, and all applicable safety and environmental regulations. Any required approvals for equipment access or elevator use must be obtained through the VA COR before use.
RFI #52: Will we have a designated elevator/loadout path for each building?
RFI #52 Response: See response to RFI #51. Submit delivery and debris routes to the COR for approval.
RFI #53: Who is responsible for all the furniture/office partition/misc. removal? Confirm if the intent is for cubicles and furniture to remain in place.
RFI # 53 Response: per response to RFI #6, SOW has been revised to have the Contractor provide professional service to disassemble, move, store, and reassemble all VA furnishings. Contractor may bring up to (10) Conex’s to the parking lot of building
911 for furniture storage.
RFI #54: Do I assume buildings 98 & 949 will be clean or abatement demo until Haz report is performed & released because I noticed there was only a Haz report for building 209?
RFI #54…