This is a Request for Information (RFI) form template for Solicitation 36C26127Q0047, a flooring replacement project at three VA McClellan locations in California. The form provides standardized procedures and requirements for offerors to submit preproposal inquiries regarding the solicitation, evaluation factors, statement of work, and technical data.
All RFIs must be submitted in writing via email to Mr. Rosario Chaidez (Rosario.chaidez1@va.gov) by November 3, 2026, at 12:00 PM PT. Offerors are instructed to consolidate multiple inquiries into a single document to reduce administrative burden and submit all RFIs by the deadline to the maximum extent possible. Late submissions will be reviewed at the Government's discretion without guarantee of incorporation into amendments or solicitation adjustments, and the Government will not extend deadlines or provide additional consideration for delays resulting from late submissions. The Government reserves the right to return unclear, incomplete, or ambiguous RFIs to offerors for revision and resubmission, and may revise or clarify any RFI question to ensure consistency across all offerors. RFI responses will be issued through formal amendments sent via email to the Contracting Officer.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOR OFFICIAL USE ONLY
REQUEST FOR INFORMATION (RFI) FORM
SOLICITATION: 36C26127Q0047
All pre‑proposal inquiries shall be submitted via email using an editable version of this form. Telephone or oral requests for information will not be accepted or answered. RFI responses will be issued, as necessary, through formal amendments. Amendments will be sent via email to the Contracting Officer, Mr. Rosario Chaidez, at Rosario.chaidez1@va.gov.
CONSOLIDATION OF RFIs: Offerors will submit all RFIs by the due date stated in the solicitation (Instructions to Offerors) to the maximum extent possible. It’s not recommended that RFIs be submitted in separate emails; doing so is at the Offeror’s own risk. When practicable and to the maximum possible, RFIs should be consolidated into a single document to reduce administrative burden and prevent duplicate or lost submissions.
LATE RFIs: Offerors submitting RFIs after the stated deadline or RFI due date in the solicitation (Instruction to Offerors) do so at their own risk. The Government may be unable to review or respond to late submitted RFIs, incorporate clarifications into an amendment, or adjust solicitation requirements. Any delays, misunderstandings, or proposal impacts resulting from late submitted RFIs are solely the responsibility of the Offeror, and the Government will not extend deadlines or provide additional consideration due to late submissions.
UNCLEAR RFIs: RFIs that are written unclear, incomplete, or ambiguous may be returned to the Offeror for revision and resubmission. The Government also reserves the right to revise or clarify any RFI question to ensure all offerors receive clear, consistent, and understandable information.
Please identify, in numerical sequence, each set of inquiries that you send.
Question(s) is/are regarding the solicitation, evaluation factors [ ]
Question(s) is/are regarding the statement of work, technical data [ ]
Company Name and Offeror:
From (person submitting question):________________________________
Date of Inquiry:
Phone Number:
Proposal Inquiry: (Type inquiry below) RFI #1 –
RFI #2 –
RFI #3 –
RFI #4 –