This is a Semi Annual Inspection Report for water-based fire protection systems at VA Grand Junction Building 6, completed on December 16, 2025, by James Trudeau of Platinum Fire Protection. The inspection was conducted in accordance with NFPA 25 2011 - Standard for the Inspection, Testing, and Maintenance of Water Based Fire Protection Systems and included a Joint Commission inspection.
The report identifies six deficiencies requiring corrective action. Deficiency #1 notes that two control valve signs are missing on control valves with locks or electrical supervision per section 13.3.2.2. Deficiency #2 indicates two gauges are due for replacement as they are not in good condition and not showing normal water supply pressure per section 5.2.4.1. Deficiency #3 documents that electrical waterflow alarm devices failed testing due to bad inspector's test valves that will open but do not want to shut after testing, allowing only manual trip operation per section 5.3.3.3. Deficiency #4 involves the basement inspector's test connection, which can only be manually tripped as the inspector's test valve is extremely difficult to close once opened. Deficiencies #5 and #6 identify missing signage on two basement backflow preventers (Backflow #1 and #2), both 3-inch butterfly valves. No deficiencies were found in the general wet system questions category. The inspector certified that all equipment tested was left in operational condition upon completion of the inspection except as noted.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Semi Annual Inspection Report
Completed on: 12-16-2025 for
VA Grand Junction Building 6 2121 North Ave
Grand Junction, CO
Conducted By:
James Trudeau
Platinum Fire Protection PO Box 607
Mead, CO 80542
This Joint Commission inspection was performed in accordance with the following codes and regulations:
• NFPA 25 2011 - Standard for the Inspection, Testing, and Maintenance of Water Based Fire Protection Systems
Deficiencies - General Questions
Deficiency #1
Are the control valves (including valves on backflow preventers) with locks or electrical supervision properly identified? - 13.3.2.2: No
Notes: 2 control valve signs missing
Deficiency #2
Are the gauges on system in good condition and showing normal water supply pressure? - 5.2.4.1: No
Notes: 2 gauges due for replacement
Deficiency #3
The electrical waterflow alarm devices passed test by opening inspector's test connection/bypass connection with alarms actuating and flow observed? - 5.3.3.3:
No
Notes: Manual trip only due to bad inspectors test valves it will open but does not want to shut after testing.
Deficiency #3 - Photo #1
Date Taken: December 16, 2025
Deficiencies - General Wet System Questions
None
Deficiencies - Wet
Report of Inspection / Test Semi-Annual NFPA 25
12-16-2025 Property VA Grand Junction Building 6 2121 North Ave Grand Junction CO
Print Date: 12-22-2025
Conducted by: James Trudeau
Platinum Fire Protection PO Box 607 Mead CO 80542 3036880177 rachel@platfire.com
Copyright 2025 Inspect Point
None
Deficiencies - Inspectors Test Connection
Deficiency #4
Location: Basement Description: Inspectors test Pass?: No
Notes: Manual trip only. Inspectors test valve so bad it is almost impossible to close once it's open.
Deficiencies - Valves
Deficiency #5
Location: Basement Valve Type: Butterfly Size: 3 Description: Backflow #2 Signs: No
Notes: No sign
Deficiency #6
Location: Basement Valve Type: Butterfly Size: 3 Description: Backflow #1 Signs: No
Notes: No sign
Report of Inspection / Test Semi-Annual NFPA 25
12-16-2025 Property VA Grand Junction Building 6 2121 North Ave Grand Junction CO
Print Date: 12-22-2025
Conducted by: James Trudeau
Platinum Fire Protection PO Box 607 Mead CO 80542 3036880177 rachel@platfire.com
Inspector Signature
I state that the information on this form is correct at the time and place of my inspection, and all equipment tested at this time was left in operational condition upon completion of this inspection except as noted.
Inspector Name Signature Date Completed
James Trudeau 2025-12-16
Report of Inspection / Test Semi-Annual NFPA 25
12-16-2025 Property VA Grand Junction Building 6 2121 North Ave Grand Junction CO
Print Date: 12-22-2025
Conducted by: James Trudeau
Platinum Fire Protection PO Box 607 Mead CO 80542 3036880177 rachel@platfire.com