This is a Statement of Work (SOW) Amendment for the procurement and installation of antimicrobial shelving units at the Overton Brooks VA Medical Center in Shreveport, Louisiana. The Department of Veterans Affairs requires the replacement of existing end-of-life shelving in walk-in freezers and refrigerators with 41 new shelving units consisting of eight antimicrobial aluminum units (24" D x 48" W x 74" H), ten antimicrobial aluminum units (24" D x 48" W x 69" H), twelve stainless steel slotted units (48" W x 24" D x 74" H), and eleven stainless steel slotted units (48" W x 24" D x 69" H). All units must include louvered/embossed shelf design, donut bumpers, fall arresting bars, wire shelving, label holder clips, adjustable shelf heights and feet, four 5-inch casters per unit (two swivel, two with brakes), and clear label covers, with factory assembly required unless site access prevents it. The contractor must remove all existing shelving, dispose of it per federal, state, local, and VA requirements, and deliver and install all new units fully assembled, leveled, and operational within 30 days of order receipt. All shelving must include a minimum 10-year warranty against rust and corrosion, and substitutions require Contracting Officer approval.
The associated RFQ (Solicitation Number 36C25626Q0630) has been issued by the VA Veterans Health Administration Veterans Integrated Service Network 16 and is 100% set aside for service-disabled veteran-owned small businesses under NAICS code 337215 (Showcase, Partition, Shelving, and Locker Manufacturing). This is a simplified acquisition for commercial items under FAR Parts 12 and 13. The contract point of contact is Marcus Sidney (Marcus.Sidney@va.gov), and quotes must be submitted electronically with multiple response deadlines noted as May 15, 2026; June 3, 2026; and June 5, 2026, all by 8:00 a.m. Central Time. Questions must be submitted via email no later than May 6, 2026; May 22, 2026; or May 28, 2026, respectively. The Contracting Officer's Representatives are Whitney Withem (Primary) and Brittany Hawkins (Alternate) from the facility's National Food Service operations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQ Amendment 0004.pdf | ||
| QandA Sesssion 2.docx | DOCX document | |
| 36C25626Q0630 0004_1.docx | DOCX document | |
| 36C25626Q0630 0003.pdf | ||
| 36C25626Q0630 0003_1.docx | DOCX document | |
| Site Visit Information.docx | DOCX document | |
| 36C25626Q0630 0002_1.docx | DOCX document | |
| 36C25626Q0630 0002 - Final.pdf | ||
| Question and Answer Sheet - Final.docx | DOCX document | |
| 36C25626Q0630 0001_1.docx | DOCX document | |
| 36C25626Q0630 Amendment 0001 - Word Version.docx | DOCX document | |
| 36C25626Q0630 Amendment 0001 PDF Version.pdf | ||
| RFQ 36C25626Q0630 - Word Version.docx | DOCX document | |
| Evaluation Criteria Template - LPTA - Final.docx | DOCX document | |
| RFQ 36C25626Q0630 - PDF Version.pdf | ||
| 36C25626Q0630_1.docx | DOCX document |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
Anti-Microbial Shelving Units Department of Veterans Affairs Overton Brooks VA Medical Center Shreveport, LA (Station 667)
1. Introduction / Background The Overton Brooks VA Medical Center (OBVAMC), Station 667, requires the replacement of all shelving units currently installed in the facility’s walk‑in freezers and refrigerators. Existing shelving is at end-of-life and no longer meets operational needs. The contractor shall provide only the quantities and specifications detailed in this SOW; no additional shelving is required unless formally directed by the Contracting Officer.
2. Scope of Work The contractor shall furnish all labor, materials, equipment, transportation, and supervision necessary to remove existing shelving and install new anti‑microbial shelving units that strictly conform to the specifications in Section 7.
The contractor shall:
- Remove all existing shelving units.
- Dispose of removed shelving per all federal, state, local, and VA requirements.
- Provide and install Forty-one (41) new shelving units meeting all specifications listed in this SOW.
- Ensure all units are fully assembled, leveled, and operational upon installation.
3. Major Requirements
- All packing materials must be removed from the VA facility.
- Installed shelving must be fully operational.
4. Contracting Officer’s Representative (COR) Primary COR: Whitney Withem, Administrative Officer, NFS – 318‑990‑5233 – whitney.withem@va.gov Alternate COR: Brittany Hawkins, NFS Food Operations Supervisor – 318‑990‑5234 – brittany.hawkins@va.gov
Only the Contracting Officer may change or modify contract requirements.
5. Place of Performance Overton Brooks VA Medical Center 510 East Stoner Avenue Shreveport, LA 71101-4243 Station 667
6. Period of Performance All deliverables shall be delivered and installed NLT: 30 Days After Receipt of Order.
7. Salient Characteristics
· Please Note that shelving unit height measurements below include caster height (5’’) referenced below. Shelving units should not be higher than the height measurements stated below.
· Eight (8) Antimicrobial aluminum shelving units (24" D x 48" W x 74" H)
· Ten (10) Antimicrobial aluminum shelving units (24" D x 48" W x 69" H)
· Special Height 69''
· Twelve (12) Stainless steel slotted shelving units (48" W x 24" D x 74" H)
· Eleven (11) Stainless steel slotted shelving units (48" W x 24" D x 69" H
· Special Height 69''
· Louvered/embossed shelf design
· Donut bumpers
· Fall arresting bars
· Wire (48"W)
· Horizontal Plastic Label Holder Clips (Approximately 2.24" x 1.57" (57 mm x 40 mm)
· Adjustable shelf heights and adjustable feet
· Four (4) 5’’ casters per shelving unit
· 2 swivel casters
· 2 casters with brakes
· Clear Label Cover (Flat Dimensions: Approximately 2.24" x 1.57" (57 mm x 40 mm)
· Factory-assembled prior to shipping (unless access prevents)
· Minimum 10-year warranty against rust/corrosion (longer if available)
All specifications in this section are mandatory. Substitutions require CO approval.
8. Site Conditions & Pre‑Installation Verification The contractor shall verify all site measurements and installation conditions before beginning work. Any discrepancies must be reported to the Contracting Officer.
9. Final Acceptance The COR will inspect all installed shelving. Acceptance requires proper assembly, cleanup, and operational readiness.