RFI QUESTIONS AND ANSWERS FOR PROJECT 578-20-002 IFB SOLICITATION 36C25225B0014.docx

DOCX document 20 KB Posted

Attached to
Z1DA--578-20-002 Renovations to Building 217 (CON) at Edward Hines Jr. VA Hospital, Hines, IL.
Solicitation number
36C25225B0014
Issued by

About this file

This document is a Request for Information (RFI) Questions and Answers for Solicitation 36C25225B0014, a renovation project at Edward Hines Jr. VA Hospital in Hines, IL. The project involves renovations to Building 217 and will be completed within 330 calendar days from the Notice to Proceed. Key technical details include specifications for building automation systems (BAS), with clarifications that the existing system uses Johnson Controls Facility Explorer, and Metasys is not to be used in new installations.

The RFI addresses multiple technical questions from potential contractors, including details about pre-bid conferences (which were held on May 13 and 14, 2025 and were not mandatory), control system integration requirements, and system communications protocols. TL Services is noted as the current controls maintenance contractor, and the VA provided additional guidance through an attached "SOW Requirements for AC Shop" document. The project is being managed by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 12, with a focus on precise technical specifications for building systems renovations.

View the file

Other files

File Type Posted
HINES VA SITE PLAN - Contractor Parking.pdf PDF
578-20-002_Addendum2_06102025.pdf PDF
578-20-002_Addendum1_Specifications_060225.pdf PDF
RFI FINAL QUESTIONS AND RESPONSES -IFB SOLICITATION 36C25225B0014.docx DOCX document
36C25225B0014 0004.docx DOCX document
36C25225B0014 0003.docx DOCX document
SOW Requirements for AC Shop 4-13-2023.docx DOCX document
36C25225B0014 0002.docx DOCX document
18- Building 217 - Clinic Details.pdf PDF
36C25225B0014 0001.docx DOCX document
P09 - 578-20-002 Construction SOW Rev2 5-12-25.docx DOCX document
16c- 578-20-002 Basis of Design -BOD Part 3.pdf PDF
16b- 578-20-002 Basis of Design -BOD Part 2.pdf PDF
14d- 578-20-002 100percent Bid Drawings -Part 4.pdf PDF
2- Contractor Badging - Fingerprint Request Form 2025.pdf PDF
1- Contractor Parking.pdf PDF
14c- 578-20-002 100percent Bid Drawings -Part 3.pdf PDF
12- Interim Life Safety Measures -ILSM.pdf PDF
13- VHA ICRA-1.3 -Dec 9 2024.pdf PDF
P07 Wage determination IL20250009 03-07-2025.pdf PDF
16- 578-20-002 Basis of Design -BOD Part 1.pdf PDF
14b- 578-20-002 100percent Bid Drawings -Part 2.pdf PDF
14e- 578-20-002 100percent Bid Drawings -Part 5.pdf PDF
36C25225B0014.docx DOCX document
16d- 578-20-002 Basis of Design -BOD Part 4.pdf PDF
6- Infection Control Barrier Sample.pdf PDF
9- OIT Horizontal Cable Requirements.pdf PDF
14f- 578-20-002 100percent Bid Drawings -Part 6.pdf PDF
4- No Smoking Policy 10-1-19.pdf PDF
3- Emergency Contact List - Template.docx DOCX document
17- Building 217 Colored Space Drawings.pdf PDF
P01 - 578-20-002 Construction SOW Rev1 5-1-25.docx DOCX document
5- Safety and Health During Construction Activities.pdf PDF
15- 57820002_100CD_Specifications_12092024 r1.pdf PDF
7- Cutting Welding and Other Hot Work.pdf PDF
11- VHA PCRA-1.1 -May 21 2024.pdf PDF
14- 578-20-002 100percent Bid Drawings -Part 1.pdf PDF
10- Pre-Construction Checklist.pdf PDF
8- Above Ceiling Entry and Wall Construction Permits.pdf PDF
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation # 36C25225B0014 578-20-002 Building 217 Renovations (CON) at Edward Hines Jr VA Hospital RFI Questions and Answers (As of 05/22/2025)

Question #: 01 Question will be published soon A: Answer will be published soon Question #: 02 I’m reaching out regarding the VA project 36C25225B0014 Renovations to Building 217. I wanted to confirm that the Pre-bid meeting was not mandatory.

A: No, it is not mandatory. We had two of them.

PRE-BID CONFERENCE:

A pre-bid conference will occur on Tuesday, May 13, 2025, at 11:00 AM CST, and a second one on Wednesday, May 14, 2025 at 11:00AM CST. The location is at the Edward Hines Jr. VA Hospital, 5000 S. Fifth Avenue Hines, IL 610141 All participants will meet the Contracting Officer Representative (COR) at Bldg. 217 lobby.

Question #: 03 In the specifications, Section 23 09 23, PART 1 – GENERAL, 1.1 DESCRIPTION, Paragraph E. – It states “This facility’s existing direct-digital control (DDC) system is manufactured by Johnson Control. The existing system’s top-end communications is via Metasys.”

We don’t believe the existing system’s top-end communications is Johnson Control Metasys. We believe it is a Johnson Controls Facility Explorer BACnet System. Please clarify what the top-end communications system actually is.

A: The existing system’s top-end communications is Johnson Controls Facility Explorer. Metasys is not to be used in any new installations. See attached “SOW Requirements for AC Shop 4-13-2023” for A/C Shop Controls requirements.

Question #: 04 In the specifications, Section 23 09 23, PART 1 – GENERAL, 1.1 DESCRIPTION, Paragraph E. – It states “This facility’s existing direct-digital control (DDC) system is manufactured by Johnson Control. The existing system’s top-end communications is via Metasys.”

Will the Hines VAMC accept JCI Metasys for BAS Temperature Controls on this project?

A: The existing system’s top-end communications is Johnson Controls Facility Explorer. Metasys is not to be used in any new installations. See attached “SOW Requirements for AC Shop 4-13-2023” for A/C Shop Controls requirements.

Question #: 05 In the specifications, Section 23 09 23, PART 1 – GENERAL, 1.1 DESCRIPTION, Paragraph E. – It states “Provide a new BACnet ECC, communications network, and controllers. Provide a programmable internetworking gateway allowing for real time communication between the existing direct-digital control system and the new BACnet control system. Real-time communication shall provide all object properties and read/write services shown on VA-approved interoperability schedules.”

The CLC Building has an existing JCI Facility Explorer BACnet ECC already in place. Does the VA want a “new BACnet ECC” or is the existing BACnet ECC to be utilized?

A: Utilize the existing BACnet ECC. Do not install a new BACnet ECC.

Question #: 06 In the specifications, Section 23 09 23, PART 1 – GENERAL, 1.1 DESCRIPTION, Paragraph A. First paragraph, states “A System Integrator and Direct Digital Controls Contractor shall be two separate direct subcontractors of General Contractor.”

Who (what company) is the Hines VAMC’s BAS System Integrator?

A: TL Services is the current controls maintenance contractor. As long as the requirements in the attached “SOW Requirements for AC Shop 4-13-2023” are met, there does not need to be a separate system integrator.

Question #: 07 Do the “Hines AC Shop Controls Requirements” apply to this project? See attached document labeled “36C25223R0068-25 Hines AC Shop HAVC Controls Requirements”.

A: See attached “SOW Requirements for AC Shop 4-13-2023” for Hines A/C Shop Controls requirements.