RFI FINAL QUESTIONS AND RESPONSES -IFB SOLICITATION 36C25225B0014.docx

DOCX document 43 KB Posted

Attached to
Z1DA--578-20-002 Renovations to Building 217 (CON) at Edward Hines Jr. VA Hospital, Hines, IL.
Solicitation number
36C25225B0014
Issued by

About this file

This document is a Request for Information (RFI) containing questions and answers for Solicitation 36C25225B0014, a renovation project for Building 217 at Edward Hines Jr. VA Hospital in Hines, IL. The solicitation is a 100% set-aside for Service-Disabled Veteran-Owned Small Business (SDVOSB) firms, with a project duration of 330 calendar days from the Notice to Proceed. The project involves comprehensive renovations across multiple Contract Line Item Numbers (CLINs), including work in areas such as the Primary Care Clinic, Entrance Lobby, Dining Room, and Second Floor Patio.

Key details include a bid opening on June 24, 2025, at 1:00 PM CST, with multiple pre-bid conferences held in May 2025. The project requires contractors to manage their own site security, badging (with a one-month processing time), and background checks. Specific requirements include AISC certification for structural steel, on-site staffing minimums, and adherence to VA Technical Inspection Letter (TIL) guidelines. Contractors must provide their own construction trailer, portable facilities, and coordinate utility tie-ins and crane lifts with the Contracting Officer Representative. The VA will award a single contract based on the Base Bid, Alternate Bid 1, or Alternate Bid 2, depending on available funding.

View the file

Other files

File Type Posted
HINES VA SITE PLAN - Contractor Parking.pdf PDF
578-20-002_Addendum2_06102025.pdf PDF
578-20-002_Addendum1_Specifications_060225.pdf PDF
36C25225B0014 0004.docx DOCX document
36C25225B0014 0003.docx DOCX document
RFI QUESTIONS AND ANSWERS FOR PROJECT 578-20-002 IFB SOLICITATION 36C25225B0014.docx DOCX document
SOW Requirements for AC Shop 4-13-2023.docx DOCX document
36C25225B0014 0002.docx DOCX document
18- Building 217 - Clinic Details.pdf PDF
36C25225B0014 0001.docx DOCX document
P09 - 578-20-002 Construction SOW Rev2 5-12-25.docx DOCX document
16c- 578-20-002 Basis of Design -BOD Part 3.pdf PDF
16b- 578-20-002 Basis of Design -BOD Part 2.pdf PDF
14d- 578-20-002 100percent Bid Drawings -Part 4.pdf PDF
2- Contractor Badging - Fingerprint Request Form 2025.pdf PDF
1- Contractor Parking.pdf PDF
14c- 578-20-002 100percent Bid Drawings -Part 3.pdf PDF
12- Interim Life Safety Measures -ILSM.pdf PDF
13- VHA ICRA-1.3 -Dec 9 2024.pdf PDF
P07 Wage determination IL20250009 03-07-2025.pdf PDF
16- 578-20-002 Basis of Design -BOD Part 1.pdf PDF
14b- 578-20-002 100percent Bid Drawings -Part 2.pdf PDF
14e- 578-20-002 100percent Bid Drawings -Part 5.pdf PDF
36C25225B0014.docx DOCX document
16d- 578-20-002 Basis of Design -BOD Part 4.pdf PDF
6- Infection Control Barrier Sample.pdf PDF
9- OIT Horizontal Cable Requirements.pdf PDF
14f- 578-20-002 100percent Bid Drawings -Part 6.pdf PDF
4- No Smoking Policy 10-1-19.pdf PDF
3- Emergency Contact List - Template.docx DOCX document
17- Building 217 Colored Space Drawings.pdf PDF
P01 - 578-20-002 Construction SOW Rev1 5-1-25.docx DOCX document
5- Safety and Health During Construction Activities.pdf PDF
15- 57820002_100CD_Specifications_12092024 r1.pdf PDF
7- Cutting Welding and Other Hot Work.pdf PDF
11- VHA PCRA-1.1 -May 21 2024.pdf PDF
14- 578-20-002 100percent Bid Drawings -Part 1.pdf PDF
10- Pre-Construction Checklist.pdf PDF
8- Above Ceiling Entry and Wall Construction Permits.pdf PDF
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation # 36C25225B0014 578-20-002 Building 217 Renovations (CON) at Edward Hines Jr VA Hospital RFI Questions and Answers (As of 06/10/2025)

Question #: 01

1.The Specifications Table of Contents lists several specifications, but they are not included in the issued documents. Please confirm if the following are required for this project, and if required issue the following specification sections:
•07 72 00 Roof Accessories - Added to Specifications
•22 08 00 Commissioning of Plumbing Systems – Removed from Table of Contents
•25 10 10 Advanced Utility - Removed from Table of Contents
•27 05 11 Requirements for Communications Installations- Added to Specifications
•27 05 26 Grounding and Bonding for Communications Systems- Added to Specifications
•27 05 33 Raceways and Boxes for Communications Systems- Added to Specifications
•27 08 00 Commissioning of Communications Systems- Added to Specifications
•27 10 00 Control, Communication, and Signal Wiring- Added to Specifications
•27 11 00 Communications Equipment Room Fittings- Added to Specifications
•27 15 00 Communications Structured Cabling – Removed from Table of Contents
•27 41 31 Master Antenna Television Equipment and Systems– Removed from Table of Contents
•27 51 16 Public Address and Mass Notification – Removed from Table of Contents
•27 52 23 Nurse Call and Code Blue Systems- Added to Specifications
•27 52 41 Miscellaneous Medical Systems– Removed from Table of Contents
•28 13 00 Physical Access Control System- Added to Specifications
•28 13 53 Security Access Detection– Removed from Table of Contents
•28 16 00 Intrusion Detection System– Removed from Table of Contents
•28 23 00 Video Surveillance- Added to Specifications
•28 26 00 Electronic Personal Protection System– Removed from Table of Contents
•28 52 31 Emergency Call System– Removed from Table of Contents
•31 20 11 Earthwork (Short Form) – Removed from Table of Contents
•32 90 00 Planting– Removed from Table of Contents

A: See Addendum #1 for updated specification book (578-20-002_Addendum1_Specifications_060225).

Question #: 02 I’m reaching out regarding the VA project 36C25225B0014 Renovations to Building 217. I wanted to confirm that the Pre-bid meeting was not mandatory.

A: No, it is not mandatory. We had two of them.

PRE-BID CONFERENCE:

A pre-bid conference will occur on Tuesday, May 13, 2025, at 11:00 AM CST, and a second one on Wednesday, May 14, 2025, at 11:00AM CST. The location is at the Edward Hines Jr. VA Hospital, 5000 S. Fifth Avenue Hines, IL 610141 All participants will meet the Contracting Officer Representative (COR) at Bldg. 217 lobby.

Question #: 03 In the specifications, Section 23 09 23, PART 1 – GENERAL, 1.1 DESCRIPTION, Paragraph E. – It states “This facility’s existing direct-digital control (DDC) system is manufactured by Johnson Control. The existing system’s top-end communications is via Metasys.”

We don’t believe the existing system’s top-end communications is Johnson Control Metasys. We believe it is a Johnson Controls Facility Explorer BACnet System. Please clarify what the top-end communications system actually is.

A: The existing system’s top-end communications is Johnson Controls Facility Explorer. Metasys is not to be used in any new installations. See attached “SOW Requirements for AC Shop 4-13-2023” for A/C Shop Controls requirements.

Question #: 04 In the specifications, Section 23 09 23, PART 1 – GENERAL, 1.1 DESCRIPTION, Paragraph E. – It states “This facility’s existing direct-digital control (DDC) system is manufactured by Johnson Control. The existing system’s top-end communications is via Metasys.”

Will the Hines VAMC accept JCI Metasys for BAS Temperature Controls on this project?

A: The existing system’s top-end communications is Johnson Controls Facility Explorer. Metasys is not to be used in any new installations. See attached “SOW Requirements for AC Shop 4-13-2023” for A/C Shop Controls requirements.

Question #: 05 In the specifications, Section 23 09 23, PART 1 – GENERAL, 1.1 DESCRIPTION, Paragraph E. – It states “Provide a new BACnet ECC, communications network, and controllers. Provide a programmable internetworking gateway allowing for real time communication between the existing direct-digital control system and the new BACnet control system. Real-time communication shall provide all object properties and read/write services shown on VA-approved interoperability schedules.”

The CLC Building has an existing JCI Facility Explorer BACnet ECC already in place. Does the VA want a “new BACnet ECC” or is the existing BACnet ECC to be utilized?

A: Utilize the existing BACnet ECC. Do not install a new BACnet ECC.

Question #: 06 In the specifications, Section 23 09 23, PART 1 – GENERAL, 1.1 DESCRIPTION, Paragraph A. First paragraph, states “A System Integrator and Direct Digital Controls Contractor shall be two separate direct subcontractors of General Contractor.”

Who (what company) is the Hines VAMC’s BAS System Integrator?

A: TL Services is the current controls maintenance contractor. As long as the requirements in the attached “SOW Requirements for AC Shop 4-13-2023” are met, there does not need to be a separate system integrator.

Question #: 07 Do the “Hines AC Shop Controls Requirements” apply to this project? See attached document labeled “36C25223R0068-25 Hines AC Shop HAVC Controls Requirements”.

A: See attached “SOW Requirements for AC Shop 4-13-2023” for Hines A/C Shop Controls requirements.

Question #: 08 Please provide a copy of the Site Visit Attendance Sheet.

A: Please see Solicitation Amendment 002 for Pre-bid site visit attendance sheets.

Question #: 09 In the event of contract modifications, should bond premiums be applied to the individual modification or wait until the end of the job, when a final modification is issued, to reimburse the contractor for all bond overruns for all mods? We ask this because there is a particular clause that states bond premium overruns are to be invoiced at the end of the project for all modifications.

A: A final modification will be issued to cover any additional performance and payment bonds resulting from contract modifications before closing out project.

Question #: 10 If a Prime Contractor is awarded multiple projects at the same VA Medical Center location: Can the Superintendent be shared across multiple projects at the same site/location, or should they only be dedicated to this project and this project only?

A: The Superintendent is dedicated to the project they are assigned. They must be at the project site whenever any work is taking place, and thus cannot share multiple projects.

Question #: 11 Since the Super can’t be the SSHO, can a subcontractor fulfill the SSHO role?

A: The Site Superintendent may also serve as the SSHO, but then the QCM must be a different person. A minimum of two people must occupy the Superintendent, SSHO, and QCM positions.

Question #: 12 How long is the badging process anticipated to take?

A: Contractors should expect one month’s time from submission of the required paperwork to receipt of their badges. A temporary badge will be issued if the permanent badge is not ready in that timeframe.

Question #: 13 Will background checks be required for any scope of work related to this project?

A: Yes, background checks are standard for all VA contractor badging.

Question #: 14 How long is the turnaround time for background check results?

A: Ten calendar days is the standard background check time.

Question #: 15 How many hours should the prime contractor and subcontractors budget for on-site badging, safety training, orientation, etc.?

A: Time will vary based on individual applicant, travel distance, and accuracy of documentation.

Question #: 16 Please confirm if influenza vaccines are required for all contractors and subcontractors employees who work on the site or if masks will be required.

A: Influenza vaccine is required for all contractors working on Hines campus.

Question #: 17 Will the government provide call-in details and instructions for the bid opening to ensure transparency for all bidders?

A: No, there is no call-in information. Per solicitation, as of today, Bid opening will be held in-person at the Great Lakes Acquisition Center (GLAC), Milwaukee, WI. Bid Opening will occur on Tuesday, June 24, 2025 at 1:00PM CST. Contractors will check-in at the front desk and escorted to a designated area. It is the responsibility of all contractors to arrive prior to the Bid Opening time, as the Bid Opening will start promptly at the time listed above.

Question #: 18 Please provide the point of contact information for the BMS integration contractor.

A: TL Services Question #: 19 Please provide the point of contact information for the Fire Alarm integration contractor.

A: JCI

Question #: 20 Will the VA consider waiving the AISC (American Institute of Steel Construction) requirement for structural steel fabrication and erection for this project? This requirement makes steel procurement on the project exponentially more difficult and costly.

A: No waiving of requirement - AISC is required.

Question #: 21 Are any AISC substitute certifications acceptable instead of AISC certification?

A: No waiving of requirement - AISC is required.

Question #: 22 Will the VA allow the use of Zip Wall (plastic sheathing with support poles) for barriers and containment anywhere on this project?

A: Zip Walls may only be using in specific circumstances as approved by the COR. Contractor should plan to use EdgeGuard for all IC barriers.

Question #: 23 If fire-rated walls are required, can we use one-hour-rated temp walls, which are ASTM-certified?

A: For temporary construction use EdgeGuard Barriers and follow NFPA standards.

Question #: 24 Where ICRA Walls / Fire Rated Walls are required, will the government accept ICRA Walls / Fire Rated Walls to the drop ceiling and fire-retardant plastic from the drop ceiling to the deck above?

A: Yes, above ceiling grid fire-retardant plastic may be utilized assuming all other IC/LS requirements are met.

Question #: 25 If necessary, will negative air machines be permitted to exhaust though HEPA filter into the occupied space? If not, please provide locations where negative air machines can be exhausted.

A: Yes, negative air machines may exhaust through HEPA filter where exhaust to the outside is no possible. See attached ICRA.

Question #: 26 Is any scope of work for this project required to be performed outside of regular work hours?

If so, what trades or scopes will be required to be performed outside of regular work hours?

If so, what will the work hours and days be for scopes required to be performed outside of regular work hours?

A: Off hours work requirements described on drawing GI003 “Construction Period Staging of Work – General Notes”. Building 217 is a 24/7 facility so work is to be performed during normal business hours. Any utility disruptions or shutdowns are to be performed overnight.

Question #: 27 Are contractors required to set a pole and meter electric usage?

A: Contractor to provide their own pole. Meter is not required as electricity has no cost.

Question #: 28 Will the VA provide space for the Prime Contractor’s Superintendent to set up, or should we add costs to our bid for a mobile office?

A: Contractor must supply their own construction trailer/office.

Question #: 29 Where can the mobile office be located? Where is the electrical connection for power to the mobile office? Are contractors required to set a pole and meter for electric usage in the mobile office?

A: Mobile office to be located over in the contractor village area, around McCoy drive; Space 25 may be utilized for this contract. See attached HINES VA SITE PLAN – Contractor Parking. Contractor required to provide their own portable toilet, and electricity is available via a nearby transformer to connect free of charge; to be coordinated with the Hines Energy Manager. The contractor must supply their own pole, disconnect switch, trenching, costs and labor for the connection.

Question #: 30 Is space available for a 8’ x 40’ temporary ground-level office near the electrical connection?

A: Yes, final location around McCoy Drive, Lot 25. See attached HINES VA SITE PLAN – Contractor Parking.

Question #: 31 Will the VA provide space for a 20-yard dumpster? Where shall contractor dumpsters be located?

A: Locate dumpster in the grass next to Building 218 generator building. Contractor must repair any landscape and hardscape damage after project.

Question #: 32 Will the VA allow contractors to use VA indoor restrooms?

A: No, contractor may install second Porta John next to dumpster.

Question #: 33 Can contractors perform crane lifts during regular hours?

A: Yes, to be coordinated with COR and Hines safety minimum of 45 days in advance of lift.

Question #: 34 Can utility tie-ins be performed during regular hours?

A: Any shutdowns impacting patient care to be performed overnight. All other tie-ins may be performed during normal business hours.

Question #: 35 Can system commissioning activities be performed during regular hours?

A: Yes, assuming no disruptions to patient care.

Question #: 36 Will the VA allow for stored material so that we can procure and lay down long lead items and/or critical path material/equipment? Will the VA fully pay for this material/equipment if stored onsite?

A: In addition to office trailer, contractor may provide a Conex box for storage on McCoy Drive, Lot 25. See attached HINES VA SITE PLAN – Contractor Parking.

Question #: 37 Please confirm that the current design documents meet current VA TIL guidelines.

A: Design documents meet VA TIL guidelines. Contractor to identify any discrepancies prior to bidding.

Question #: 38 Is there any work not included in the drawings or contract documents that will need to be performed under the contract?

A: No, all work is contained within the solicitation package.

Question #: 39 Is temporary construction fencing required anywhere on the project or at the laydown area? If so, please confirm that 6’ tall temporary construction fencing is acceptable. We ask this because the standard VA specification is a minimum of 2.1m (seven feet) tall, which is not an industry standard height and would require a custom fence to be made at that height. Alternatively, an 8’ high fence generally tends to blow over even with sandbags on the bases when the fabric is required to be fastened to the fence, since 8’ tall panels with fabric have to potential to cause damage to property and injury to personal, we strongly recommend using 6’ tall temporary construction fencing.

A: 6’ fencing is acceptable. Contractor is responsible for securing construction trailer lot and laydown area.

Question #: 40 Please provide drawings showing the routes for electrical wiring.

A: Electrical wiring will run above ceiling in corridors to the closet(s) identified in drawings. Contractor to document installed locations and routes in as-builts.

Question #: 41 Please clarify: Is that allocated Contractor’s parking is free and in case extra paring is required by GC is there any fee will be charged?

A: Contractor parking identified in Attachment 1 is free. Vehicles will be ticketed if parked in unauthorized locations.

Question #: 42 Can a Superintendent service be utilized for quality control management as well?

A: The Site Superintendent may also serve as the QCM, but then the SSHO must be a different person. A minimum of two people must occupy the Superintendent, SSHO, and QCM positions.

Question #: 43 Please clarify: Is that testing laboratory and inspections are provided by GOV. and Coordination is by Contractor?

A: Any required testing and inspection per the specifications is to be performed by the contractor.

Question #: 44 What extent is the site security being by GC?

A: Question is unclear. Contractor is responsible for site security.

Question #: 45 Is there any Minority requirement on this project?

A: This solicitation is a 100% set-aside for CVE Verified Service-Disabled Veteran-Owned Small Business Firms (SDVOSB). You should follow VAAR 852.219.75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023) (DEVIATION).

Question #: 46 Please Clarify if the following divisions are included in this project as printed in the table of content section 00 01 10 03, 04, 05, 06, 11, 13, 14,33, 34, and 48.

A: See Addendum #1 for complete updated specification book (578-20-002_Addendum1_Specifications_060225).

Question #: 47 Please provide roofing details per AD411 & AE 410.5 A: Roofing details provide on AE521.

Question #: 48 MVD 401.9-Please provide weight of existing AHU to be removed.

A: Weight unknown; estimate 10,000-12,000 lbs

Question #: 49 MVD 401.10 & MV401.11 Please confirm which exhaust fans are part of CLIN1,2,3 & which ones are a part of CLIN4.

A: All work in scope is limited to A section, so EF-04, -05, and -6 on MVD401.10, and EF-04, -05, -6, and CU-108A on MV401.11 are associated with CLIN1, 2, and 3.

Question #: 50 Please confirm that there is no asbestos pipe or duct insulation that needs to be abated.

A: Confirmed. No ACM in Building 217.

Question #: 51 Please confirm that ASBESTOS ABATEMENT is not part of this project.

A: Confirmed. No ACM in Building 217.

Question #: 52 Please confirm that there is no lead based paint abatement as part of this project.

A: The VA is unaware of any lead based paint in Building 217 and remediation is not part of the base scope. If the contractor encounters any hazardous material (confirmed via testing), remediation will require a change.

Question #: 53 M503-Please confirm that only the glycol fill system & glycol make up system require 4” concrete housekeeping pads.

A: A 4” concrete housekeeping pad is required for the glycol fill system to be installed in the second floor mechanical room. Refer to Addendum #2 for additional information.

Question #: 54 M601-Please confirm AHU-1,ERC-1,ACCU-1,DFSS-108A are part of CLIN1,2,3 and confirm if any equipment is part of CLIN4.

A: Confirmed. All equipment related to the new AHU are part of CLIN2. Refer to “Dining Room 1A118” mechanical drawings for CLIN4 equipment.

Question #: 55 AE552-Please provide specifications for LUMICOR PANELS.

A: Lumicor panel description in finish legend.

Question #: 56 6&7/AE561-Please provide height and thickness of swing up grab bar tubular supports and also confirm these are required for CLIN1,2,3 of CLIN 4.

A: See drawing AE561 in Addendum #2 for revised detail.

(578-20-002_Addendum2_06102025).

Question #: 57 3/AE402.1-Please confirm south wall of dinning room A118 is the folding glass partition detailed on AE602.Please also provide specifications for glass folding partition.

A: Confirmed. Please see Addendum #2 for specifications (578-20-002_Addendum2_06102025).

Question #: 58 AF110-Please confirm therapy storage rm 1A108B &RM 1A108A are to be included as part of CLIN1.

A: Confirmed. Rooms 1A108A & 1A108B are included in CLIN1.

Question #: 59 AF611-ROOM FINISH SCHEDULE- CLIN1 list of rooms does not match specification SOW rooms. Please revise CLIN1 ROOM FINISH SCHEDULE to match scope of work we are to include as part of CLIN1.

A: Room finish schedule contains all rooms in SOW.

Question #: 60 AE401-Please confirm toilet rm A112 & SOCIAL WKR RM 1A111 are not to be included as part of CLIN4 since these rooms are not listed in the specification SOW.

A: Rooms 1A111, 1A112, and all work shown on “Primary Care Clinic & Entrance Lobby” drawings are included in CLIN2.

Question #: 61 AE402-Please confirm if KITCHEN SUPPORT RM 1A127A is to be included as part of CLIN4(1ST FLOOR DINNING RM) A: Confirmed. Kitchen Support Room 1A127A and all work shown on “Dining Room 1A118” drawings is included in CLIN4.

Question #: 62 Please confirm deck height for clin1,2,3& 4 areas of work.

A: 12’-11” to underside of deck was measured on site.

Question #: 63 AE406 Please confirm if the 2 new planter boxes are part of CLIN3 if so please provide specifications and details.

A: See Addendum #2 for additional information and specification (578-20-002_Addendum2_06102025).

Question #: 64 AE407-Please confirm nurse stations and nourishment rms are NOT IN CONTRACT.

A: AE407 is not in this solicitation. See SOW for CLIN1, 2, 3, and 4 scope.

Question #: 65 AE411-Please confirm playground work is not in contract.

A: AE411 is not in this solicitation. See SOW for CLIN1, 2, 3, and 4 scope.

Question #: 66 Please confirm all ceiling work on AC401 is part of CLIN2 including toilet rm 1A112 & 1A111.

A: Confirmed. All work on AC401 is in scope and included in CLIN2.

Question #: 67 AC402 Please confirm ceiling type at north side of dinning room is linear metal ceiling which is not on the legend.

A: Confirmed. See AC402 in Addendum #2 (578-20-002_Addendum2_06102025).

Question #: 68 AC408-Please confirm if exposed ceiling and ductwork are to be painted.

A: Confirmed.

Question #: 69 AE521-Please provide specification section for wood paver deck system.

A: See Addendum #2 for specification section (578-20-002_Addendum2_06102025).

Question #: 70 2/AE551-Please provide specification section for column covers including height and gauge of material.

A: Use WP-20. Install from floor to ceiling in Primary Care Entrance Lobby. Install as described in finish legend in all other locations.

Question #: 71 Please confirm that we will need at a minimum 2 full time employees on site at all times. A SUPERINTENDANT who can also serve as QC MANAGER and separate individual to serve as SSHO.

A: Confirmed. Minimum of two FTEs to cover all three roles.

Question #: 72 Please confirm that we can use the building elevators.

A: Contractor may use building elevators, but must give priority use to patients, visitors, and staff.

Question #: 73 Bid form does not provide a space to list Pricing separately for CLIN1,2&3. Please confirm no breakout is required and that CLIN1,2&3 will be awarded as one contract if alternate bid is accepted and if not CLIN1,2,3 & 4 will be awarded as a lump sum.

A: Per solicitation Bid Schedule, you should provide a lump sum amount for BASE bid which includes CLIN 1, CLIN 2, CLIN 3 and CLIN 4. Also, you should provide a lump sum amount for ALTERNATE bid 1 which only includes CLIN 1, CLIN 2 and CLIN 3. Finally, you should provide a lump sum amount for ALTERNATE bid 2 which only includes CLIN 1 and CLIN 2.

A SINGLE AWARD WILL BE MADE ON BASE BID, ALTERNATE BID 1, OR ALTERNATE BID 2 DEPENDING ON FUNDING.

Question #: 74 Please confirm bid drawings are the 12/6/2024 100% Construction drawings.

A: Confirmed. Bid Drawings are dated 12/06/2024.

Question #: 75 G1003 list scope of work item A through K ,Please confirm that we are to only include CLIN1,CLIN2,CLIN3 & CLIN 4 per SPECIFICATION SECTION sow. Please confirm the following:

CLIN1 is the same as ITEM A CLIN2 is the same as ITEM B CLIN3 (2ND FLOOR PATIO)is not referenced in items A through K CLIN4 is the same as ITEM C with the exception that CLIN4 SOW says 1st floor dinning room not 1st and second floor dinning room. Please confirm second floor dinning rm is not part of CLIN4.

A: Confirmed. Second floor dining room is not part of CLIN4 and not included in the scope of this project.

Question #: 76 Please confirm if moisture mitigation will be required under all new floor tile areas.

A: Yes, moisture barrier is required.

Question #: 77 AD401-Please confirms that rms 1A115.1A-112 & 1/A-113 are not part of CLIN 2 scope of work since these rooms are not listed in the specification SOW.

A: Rooms 1A112, 1A113, and 1A115 are all included in CLIN2. All “Primary Care Clinic and Entrance Lobby” drawings are in CLIN2 scope.

Question #: 78 AD402-Please confirm REHABILITATION THERAPY RM 1A43 is not part of CLIN4 scope of work.

A: Confirmed. Rehabilitation Therapy Room 1A43 is part of CLIN1 scope.

Question #: 79 AD406-Please confirm depth of concrete toping to be removed.

A: Assume minimum 1 ½” thickness to maximum 3” thickness with 1/8” slope to drains.

Question #: 80 Please provide specifications for the following missing specifications sections:

07 72 00 – Roof Accessories 09 06 00 – Schedule For Finishes 12 32 00 – Casework 25 10 10 – Advanced Utility Metering System 32 90 00 – Painting A: 07 72 00 – Roof Accessories – Included in Addendum #1 09 06 00 – Schedule For Finishes – All finishes shown on finish legend on Drawing AF601 12 32 00 – Casework – Included in original Issue for Bid specifications 25 10 10 – Advanced Utility Metering System – Removed from Table of Contents and not needed for scope of work.

32 90 00 – Painting – Removed from Table of Contents and not needed for scope of work.

Question #: 81 Ref: Spec 014500, 3.4 Quality Control Organization Will an onsite CQC manager with 20 plus years supervision experience be acceptable in lieu of a graduate engineer, graduate architect, or graduate of construction management CQC Manager?

Can the prime contractor superintendent dual hat and fulfill the CQC Manager role for this contract?

A: QCM requirements are directed by the TIL and cannot be altered. The Site Superintendent may also serve as the QCM, but then the SSHO must be a different person. A minimum of two people must occupy the Superintendent, SSHO, and QCM positions.

Question #: 82 Ref: Spec 013526, SSHO Please verify that the SSHO should be a separate individual from the prime superintendent.

A: The Site Superintendent may also serve as the SSHO, but then the QCM must be a different person. A minimum of two people must occupy the Superintendent, SSHO, and QCM positions.

Question #: 83 Ref: Sheet MVD401.9 Is there an existing warranty for the Easy Street roof? If so, who carries the current warranty?

A: No existing warranty for Easy Street roof. Surrounding 217 roof is Hydrotech roofing under warranty.

Question #: 84 Ref: Spec 078400, 1.5 Quality Assurance Please confirm the installer requirements for firestop or can firestop be installed by an installer who holds a manufacturer’s certification from 3M?

Please verify that firestop inspections are required for this contract.

A: Firestop inspections are required for this contract. Installer qualifications are clearly defined in 078400 1.5.

Question #: 85 Ref: Sheet AD406 What should be assumed for the thickness of the existing concrete topping at the Patio? Can additional specs or details of the new topping and waterproofing be provided?

A: Assume minimum 1 ½” thick at low point and maximum 3” thick at high point. See Addendum #2 for details.

Question #: 86 Ref: Existing Conditions Will the VA be removing furnishings and equipment prior to construction, such as: desks, tables, chairs, vending machines, dining equipment, office furnishings, refrigerators, stored items, etc.?

A: See contract document phasing instruction. Contractor responsible for all furnishing and equipment relocation and storage.

Question #: 87 Ref: Laydown/Staging Is there a designated laydown and staging area for the project? Please provide location for a construction dumpster, trailers, and crane set up.

A: See answers above. Laydown area located on McCoy Drive, Lot 25. Dumpster to be located in grass next to Building 218. See attached HINES VA SITE PLAN – Contractor Parking.

Question #: 88 Ref: Sheet AC402 Please provide the ceiling type in the east half of Dining Room 1A118.

A: Basis of design added to drawing. See Addendum #2 (578-20-002_Addendum2_06102025).

Question #: 89 Ref: Elevation 1/AE402.1 Please provide the window frame type or provide section details of the window frame on elevation 1/AE402.1 A: See revisions to finish legend and additional details on Addendum #2 (578-20-002_Addendum2_06102025).

Question #: 90 Ref: Elevation 2/AE401 Please provide the window frame type and panel type at the Wheelchair Corral Elevation 2/AE401.

A: Provide detail similar to 4/AE542 for Wheelchair Corral.

Question #: 91 Ref: Elevation 2/AE401.4 Please provide the window panel type at the Reception Desk Elevation 2/AE401.4.

A: PNL-3. See Addendum #2 (578-20-002_Addendum2_06102025).

Question #: 92 I noticed that the specifications call for Solyx Beach Grass Gradient film; however, I was unable to locate the elevations needed to obtain the proper measurements for quoting. Could you please provide the relevant elevation drawings or any additional details that would help us proceed accurately with our estimate?

A: FLM-1 called out on AE407.3-AE407.5. See Addendum #2 for dimensions. VIF Question #: 93 There is a note that says all Fire Protection piping should be shown on submittal drawings. Are Fire Protection as-built drawings available? If as-built drawings are not provided, this will require significant survey time by a designer with access above all ceilings in scope areas.

A: As-builts may be available, but contractor must field verify. Read SOW to confirm areas in scope.

Question #: 94 Will the VA be handling drains and fills of Fire Protection? A: No, contractor to drain and fill system.

Question #: 95 Can any phases be run concurrently, or do they need to be completed sequentially (1 through 10)?

A: Please read the SOW.

Question #: 96 How much time will the VA need between phases? Can phases start immediately following the completion of the previous phase?

A: Assume 1 week between Requirements 1 and 2. All others can be performed immediately following completion of the previous phase.

Question #: 97 Would the VA consider doing another site visit?

A: No, not at this time.