14e- 578-20-002 100percent Bid Drawings -Part 5.pdf
PDF 6 MB Posted
- Attached to
- Z1DA--578-20-002 Renovations to Building 217 (CON) at Edward Hines Jr. VA Hospital, Hines, IL.
- Solicitation number
- 36C25225B0014
View the file
Other files
Show all 39
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DSD
12x24
R D
H
FLEXIBLE DUCT CONNECTION
MANUAL SINGLE BLADE OR OPPOSED BLADE DAMPER
MOTOR OPERATED DAMPER
VERTICAL FIRE DAMPER WITH ACCESS DOOR
AIR FLOW
DUCT SIZE FREE AREA
CROSS-SECTION OF SUPPLY OR
CROSS-SECTION OF RETURN DUCT
INCLINED RISE (R) OR DROP (D)
90° ELBOW WITH TURNING VANES
90° BRANCH TAKE-OFF W/45 DEGREE ENTRY
EQUIPMENT TAG
ROUND FLEXIBLE DUCT
SQUARE OR RECTANGLE DUCT TRANSITION
SQUARE OR RECTANGLE TO ROUND
WALL THERMOSTAT OR TEMPERATURE SENSOR
ROUND
CHILLED WATER SUPPLY
CHILLED WATER RETURN
DUCT UP TO ROOF MOUNTED EXHAUST FAN
THERMOMETER (WITH PIPE WELL)
FLOW SWITCH (WITH THREAD OR WELD-O-LET)
PRESSURE GAUGE AND NEEDLE VALVE
PRESSURE SWITCH (WITH THREAD OR WELD-O-LET)
CONCENTRIC PIPE REDUCER OR INCREASER
PIPE UNION (OR FLANGES IF 2 1/2" OR LARGER PIPE)
DRAIN VALVE WITH HOSE THREADED OUTLET
CIRCUIT BALANCING VALVE W/BALANCING PORTS (8" AND UNDER)
CIRCUIT FLOW INDICATOR W/BALANCING PORTS AND MEMORY STOP
BUTTERFLY VALVE FOR BALANCING (10" AND ABOVE)
2 WAY CONTROL VALVE
3 WAY CONTROL VALVE
BALL VALVE (2" & SMALLER)
CHECK VALVE
GATE VALVE
GLOBE VALVE
LOW PRESSURE STEAM (UP TO 15 PSIG)
LOW PRESSURE CONDENSATE (UP TO 15 PSIG)
DRAIN LINE
DIRECTION OF FLOW
PITCH OF PIPE (DOWN)
PIPE ELBOW (TURNED UP)
PIPE ELBOW (TURNED DOWN)
PIPE TEE DOWN (DROP)
PIPE TEE UP
PIPE TEE UP OR ANGLE
PIPE TEE DOWN OR ANGLE
NEW CONNECTION
SOLENOID VALVE
PRESSURE REDUCING VALVE
PRESSURE RELIEF VALVE (PIPE TO FLOOR DRAIN)
AUTOMATIC BALL OR BUTTERFLY VALVE
STEAM TRAP ASSEMBLY
THERMOMETER WELL
REFRIGERANT EXPANSION VALVE
PLUG VALVE (GAS COCK)
(HEATING) HOT WATER SUPPLY
(HEATING) HOT WATER RETURN
WALL HUMIDISTAT
WALL THERMOSTAT OR TEMPERATURE
BUTTERFLY VALVE (2 1/2" & LARGER)
TEMPERATURE WELL WITH DDC SENSOR
STRAINER
PRESSURE WELL WITH DDC SENSOR
PRESSURE/TEMPERATURE PLUG WITH CAP
STRAINER WITH BLOWDOWN VALVE
DUCT SMOKE DETECTOR
PUMPED CONDENSATE RETURN
VACUUM CONDENSATE
CROSS-SECTION OF EXHAUST DUCT
HIGH PRESSURE STEAM SUPPLY
HIGH PRESSURE CONDENSATE RETURN
BUTTERFLY VALVE
(1ST FIGURE, SIDE OF DUCT SHOWN)
OUTSIDE AIR INTAKE DUCT
DUCT TRANSITION
OR VENTILATOR
SENSOR WITH GUARD
MEDIUM PRESSURE STEAM SUPPLY
MEDIUM PRESSURE STEAM RETURN
CHWS
CHWR
FS
PS
D
LPS
LPR
D
NC
PITCH
S
HWS
HWR
T
PCR
VC
HPS
HPR
MPS
MPR
FD
MECHANICAL SYMBOLS AND ABBREVIATIONSMECHANICAL GENERAL NOTES:
ENGINEERING DISCIPLINE
REFERENCE NOTES
XXX-1
1. THIS CONTRACTOR SHALL REVIEW ENTIRE SET OF CONTRACT DOCUMENTS: INCLUDING BUT NOT NECESSARILY LIMITED TO ALL ARCHITECTURAL, ALL STRUCTURAL, ALL MECHANICAL, ALL ELECTRICAL DRAWINGS AND ENTIRE PROJECT MANUAL. THIS CONTRACTOR SHALL ACKNOWLEDGE AND INCLUDE IN THE SCOPE OF WORK (CONTRACT) ALL CONDITIONS PERTINENT TO THE COMPLETION OF HIS WORK. THIS CONTRACTOR SHALL FULLY COORDINATE HIS WORK WITH THE INSTALLATION OF WORK BY OTHER
TRADES AND MAKE NECESSARY FIELD ADJUSTMENTS AS REQUIRED TO ACCOMMODATE THE
INSTALLATION. ALL OF THE ABOVE SHALL BE INCLUDED IN THE SCOPE OF WORK AT NO ADDITIONAL
CHARGE TO THE VA.
2. THIS CONTRACTOR SHALL CAREFULLY EXAMINE THE DRAWINGS AND SPECIFICATIONS, VISIT THE SITE OF THE WORK AND FULLY INFORM THEMSELVES AS TO ALL CONDITIONS AND MATTERS THAT CAN, IN ANY WAY, AFFECT THE WORK OR THE COST THEREOF. SHOULD THIS CONTRACTOR FIND DISCREPANCIES IN, OR OMISSIONS FROM THE DRAWINGS, SPECIFICATIONS OR OTHER DOCUMENTS, OR BE IN DOUBT AS TO THEIR MEANING, NOTIFY THE VA/CO AT ONCE, IN WRITING, OF ANY DISCREPANCIES BETWEEN EXISTING CONDITIONS AND WORK, OR BETWEEN THEIR WORK AND THE WORK OF THEIR TRADES AND OBTAIN CLARIFICATION PRIOR TO SUBMITTING ANY BID. LACK OF SUCH NOTIFICATION SHALL BE CONSTRUED AS TO INDICATE NO DISCREPANCIES OR CONFLICTING CONDITIONS EXIST. ADDITIONAL COMPENSATION WILL NOT BE GRANTED AFTER AWARD OF CONTRACT FOR ANY WORK REQUIRED TO COMPLY WITH THESE
REQUIREMENTS.
3. DRAWINGS ARE GENERALLY DIAGRAMMATIC. ROUTING OF PIPING, CONDUITS, RACEWAYS, ETC., AS SHOWN ON DRAWINGS, DOES NOT INTEND TO SHOW EVERY RISE, DROP, OFFSET, FITTING NOR EVERY STRUCTURAL ELEMENT THAT MAY BE ENCOUNTERED DURING THE INSTALLATION OF THIS WORK. EACH CONTRACTOR SHALL MAKE ANY REQUIRED CHANGES FROM THE GENERAL ROUTING SHOWN ON THESE DRAWINGS, SUCH AS OFFSETS, BENDS OR CHANGES IN ELEVATION DUE TO COORDINATION WITH THE WORK OF OTHER TRADES AND BUILDING CONSTRUCTION. ALL CHANGES SHALL BE MADE WITHOUT
ADDITIONAL COST TO THE VA OR DELAY IN COMPLETION DATE OF THE PROJECT.
4. IT IS THE INTENT OF THESE DOCUMENTS THAT THE MECHANICAL CONTRACTOR PROVIDE ALL LABOR, MATERIAL, EQUIPMENT AND TOOLS FOR THE COMPLETE INSTALLATION OF ALL WORK SHOWN ON THE
PLANS AND/OR DESCRIBED HEREIN, INCLUDING ALL DEVICES, CONTROLS AND APPURTENANCES
REQUIRED TO SET SYSTEMS INTO OPERATION.
5. SHOULD CONDITIONS NECESSITATE ANY REARRANGEMENTS, OR IF PIPING CAN BE RUN TO BETTER ADVANTAGE, PREPARE AND SUBMIT SHOP DRAWINGS SHOWING THE CHANGES BEFORE PROCEEDING WITH THE WORK. IF SUCH CHANGES ARE APPROVED BY THE VA/COR, THEY SHALL BECOME A PART OF
THE CONTRACT AFTER THEIR APPROVAL.
6. THIS CONTRACTOR SHALL VERIFY ALL MOUNTING, ALL ARRANGEMENTS, HEIGHTS AND LOCATIONS PRIOR TO ROUGH-IN. ANY MENTION OF A SPECIFIC MOUNTING ARRANGEMENT, WEIGHT OR LOCATION SHALL NOT RELIEVE THE CONTRACTOR OF THE RESPONSIBILITY TO VERIFY THE SPECIFIC REQUIREMENT FURNISHED OR THE OTHER TRADES WORKING IN THE SAME AREA. NO ADDITIONS TO THE CONTRACT SUM WILL BE PERMITTED FOR ITEMS INSTALLED IMPROPERLY, IN WRONG LOCATIONS, IN CONFLICT WITH
OTHER WORK, ETC.
7. ALL WORK SHALL BE DONE IN ACCORDANCE WITH ALL CURRENT FEDERAL BUILDING CODES,
REGULATIONS, AND REQUIREMENTS, LOCAL UTILITY COMPANY REQUIREMENTS, AND ASHRAE
STANDARDS.
8. THIS CONTRACTOR SHALL PAY ALL PERMIT FEES, PLAN REVIEW FEES, LICENSE FEES, INSPECTIONS, AND TAXES APPLICABLE TO THEIR DIVISION AND SHALL BE INCLUDED IN THE BASE BID AS PART OF THEIR
CONTRACT.
9. THIS CONTRACTOR SHALL BE LICENSED, BONDED, INSURED AND CAPABLE OF PERFORMING QUALITY WORKMANSHIP. THIS CONTRACTOR GUARANTEES ALL OF HIS WORK AND MATERIALS FOR THE PERIOD
AS REQUIRED IN THE SPECIFICATIONS FROM FINAL ACCEPTANCE BY THE VA/COR.
10. THIS CONTRACTOR SHALL ESTABLISH SAFE WORKING PROCEDURES FOR THE PROTECTION OF THE WORKMEN IN ALL PHASES OF WORK, COMPLYING WITH ALL APPLICABLE PROVISIONS OF CITY, STATE, AND FEDERAL SAFETY LAWS (OSHA) AND AS RECOMMENDED IN THE "MANUAL OF ACCIDENT PREVENTION IN CONSTRUCTION" AS ISSUED BY THE ASSOCIATION OF GENERAL CONTRACTORS OF AMERICA, IN., 20TH
AND E. STREETS, N.W. WASHINGTON, D.C.
11. CONTRACTOR SHALL CHECK DRAWINGS OF OTHER TRADES TO VERIFY THAT SPACES IN WHICH THEIR WORK WILL BE INSTALLED ARE CLEAR OF OBSTRUCTIONS. WORK SHALL BE INSTALLED TO MAINTAIN MAXIMUM HEADROOM AND SPACE CONDITIONS AT ALL POINTS IN THE BUILDING. WHERE HEADROOM OR SPACE CONDITIONS APPEAR INADEQUATE, CONTRACTOR SHALL NOTIFY VA/COR BEFORE PROCEEDING
WITH THE INSTALLATION OF THEIR WORK.
12. THE SEQUENCE FOR THE INSTALLATION OF ALL WORK SHALL BE COORDINATED BETWEEN ALL CONTRACTORS ON THE PROJECT AND IN STRICT ACCORDANCE WITH VA STIPULATIONS AS DIRECTED BY
SAME.
13. CONTRACTOR SHALL BE RESPONSIBLE AND PAY FOR ALL CORING, CUTTING, PATCHING, REPAIRING, REFINISHING AND REMOVAL/REPLACEMENT OF NEW OR EXISTING BUILDING CONSTRUCTION REQUIRED TO ACCOMMODATE THE INSTALLATION OR REMOVAL OF THEIR WORK. CONTRACTOR SHALL XRAY ALL SLABS PRIOR TO CORING. ALL PATCHING, REPAIRING AND REFINISHING WORK SHALL BE PERFORMED BY THOSE REGULARLY INVOLVED IN THAT TRADE AND SHALL MATCH THE ADJACENT CONSTRUCTION AS CLOSELY AS POSSIBLE. CARE SHALL BE TAKEN SO AS NOT TO DAMAGE ANY EXISTING BUILDING CONSTRUCTION OR ITEMS THAT ARE TO REMAIN. ANY EXISTING FINISHES THAT ARE DAMAGED DURING THE INSTALLATION OF NEW WORK OR REMOVAL OF EXISTING WORK SHALL BE REPAIRED, REPLACED AND PAID FOR BY THE INSTALLING CONTRACTOR, TO THE SATISFACTION OF THE VA/COR. REFER TO
ARCHITECTURAL DRAWINGS FOR EXISTING BUILDING CONSTRUCTION THAT IS TO REMAIN AND,
THEREFORE, SUBJECT TO PATCHING, REPAIRING, REFINISHING, AND REMOVAL/REPLACEMENT. WHERE THERE IS EVIDENCE THAT WORK OF ONE TRADE WILL INTERFERE WITH WORK OF OTHER TRADES, ALL
TRADES SHALL MEET ON JOB SITE TO WORK OUT SPACE CONDITIONS AND MAKE SATISFACTORY
ADJUSTMENTS TO INSTALLATION OF THE NEW WORK. CONTRACTORS SHALL VERIFY EXACT LOCATIONS OF ALL DEVICES AND EQUIPMENT WITH FIELD CONDITIONS, SHOP DRAWINGS, AND WORK OF OTHER TRADES PRIOR TO ROUGH-IN. EACH CONTRACTOR SHALL BE RESPONSIBLE, AT THEIR OWN EXPENSE, FOR THE REMOVAL AND REINSTALLATION OF ANY PART OF THEIR WORK IF SAME WAS INSTALLED
WITHOUT CONSULTING WITH OTHER TRADES BEFORE INSTALLING THEIR WORK.
14. CONTRACTOR SHALL STORE ALL MATERIALS AND EQUIPMENT SHIPPED TO THE SITE IN A PROTECTED AREA. IF MATERIAL IS STORED OUTSIDE OF THE BUILDING, IT MUST BE STORED OFF THE GROUND A MINIMUM OF SIX INCHES (6") SET ON 6 X 6 PLANKS AND/OR WOOD PALLETS. ALL MATERIAL AND EQUIPMENT MUST BE COMPLETELY COVERED WITH WATERPROOF TARPS OR VISQUIN. ALL PIPING AND DUCTWORK WILL HAVE THE ENDS CLOSED TO KEEP OUT DIRT AND OTHER DEBRIS. NO EQUIPMENT WILL BE ALLOWED TO BE STORED OUTSIDE THE BUILDING ON THE SITE UNLESS IT IS SUPPORTED OFF THE
GROUND AND COMPLETELY PROTECTED WITH WEATHERPROOF COVERS.
15. THIS CONTRACTOR SHALL SUBMIT SHOP DRAWINGS AS REQUIRED IN THE SPECIFICATIONS PRIOR TO
THE START OF INSTALLATION FOR VA/COR APPROVAL AND THE SUCCESSFUL REVIEW BY THE
ARCHITECT/ENGINEER.
16. THIS CONTRACTOR SHALL FURNISH AS-BUILT DRAWINGS TO THE VA BEFORE FINAL PAYMENT WILL BE ISSUED. THE AS-BUILT DRAWINGS SHALL BE SUBMITTED IN ELECTRONIC REPRODUCIBLE FORM.
17. THIS CONTRACTOR SHALL BE RESPONSIBLE FOR THE STARTUP AND TESTING OF ALL EQUIPMENT.
18. THIS CONTRACTOR SHALL PROVIDE A COMPETENT OPERATING TECHNICIAN TO INSTRUCT THE VA IN THE
OPERATION AND MAINTENANCE OF THE EQUIPMENT.
19. UPON COMPLETION OF THE WORK, THIS CONTRACTOR SHALL REVIEW AND CHECK THE ENTIRE PORTION OF WORK, CLEAN EQUIPMENT AND DEVICES. REMOVE SURPLUS MATERIALS AND RUBBISH FROM THE PROPERTY AND LEAVE THE WORK IN NEAT AND CLEAN ORDER AND IN COMPLETE WORKING CONDITION.
EACH RESPECTIVE CONTRACTOR SHALL BE RESPONSIBLE FOR THE REMOVAL OF ANY CARTONS,
DEBRIS, EQUIPMENT, ETC., INSTALLED BY THIS CONTRACTOR INCLUDING EQUIPMENT FURNISHED BY
OTHERS AND UNPACKED OR REMOVED FROM CARTONS BY THIS CONTRACTOR.
20. ALL ITEMS THAT REQUIRE ACCESS, SUCH AS FOR OPERATING, CLEANING, SERVICING, MAINTENANCE, AND CALIBRATION, SHALL BE EASILY AND SAFELY ACCESSIBLE BY PERSONS STANDING AT FLOOR LEVEL, OR STANDING ON PERMANENT PLATFORMS, WITHOUT THE USE OF PORTABLE LADDERS. EXAMPLES OF THESE ITEMS INCLUDE, BUT ARE NOT LIMITED TO: ALL TYPES OF VALVES, FILTERS AND STRAINERS, TRANSMITTERS, CONTROL DEVICES. PRIOR TO COMMENCING INSTALLATION WORK, REFER CONFLICTS BETWEEN THIS REQUIREMENT AND CONTRACT DRAWINGS TO THE VA/COR FOR RESOLUTION. FAILURE OF THE CONTRACTOR TO RESOLVE, OR POINT OUT ANY ISSUES WILL RESULT IN THE CONTRACTOR
CORRECTING AT NO ADDITIONAL COST TO THE VA.
21. UNLESS INDICATED OTHERWISE, THE ARCHITECT/ENGINEER MAKES NO REPRESENTATION AS TO WHETHER OR NOT ANY HAZARDOUS OR CONTAMINATED MATERIALS (INCLUDING BUT NOT LIMITED TO ASBESTOS, PCB'S, LEAD, CONTAMINATED SOILS, ETC.) ARE PRESENT WITHIN THE EXISTING BUILDING OR ON THE SITE. WORK SHOWN ON THE DRAWINGS AND/OR INDICATED IN THE SPECIFICATIONS SHALL NOT BE CONSTRUED TO CALL FOR CONTACT WITH ANY OF THESE MATERIALS. IF THESE MATERIALS ARE ENCOUNTERED OR SUSPECTED, THE CONTRACTOR SHALL NOT DISTURB THEM AND SHALL CONTACT THE
VA/COR IMMEDIATELY.
22. IT IS MANDATORY THAT THE COMPLETE EXISTING BUILDING REMAIN IN CONTINUOUS AND NON- INTERRUPTED OPERATION DURING REMODELING/ALTERING OF SAID EXISTING BUILDING. THE SPECIFIC AREA(S) BEING REMODELED/ALTERED AT ANY SCHEDULED TIME ARE OBVIOUSLY EXCLUSIVE OF THIS STATEMENT. SERVICES TO EXISTING BUILDING SHALL BE KEPT IN CONTINUOUS OPERATION INCLUDING POWER, SIGNAL SYSTEMS, LIGHTING, TELEPHONE, HEATING, COOLING, VENTILATING, TEMPERATURE
CONTROL, SEWERS AND HOT AND COLD WATER. ANY ABSOLUTELY NECESSARY INTERRUPTION OF
THESE SERVICES TO ACCOMPLISH CONTRACT WORK SHALL BE ARRANGED WITH THE VA/COR A MINIMUM OF TEN (10) WORKING DAYS IN ADVANCE. SUCH INTERRUPTIONS SHALL BE KEPT TO AN ABSOLUTE MINIMUM AS FAR AS TIME INTERVAL IS INVOLVED AND TEMPORARY SERVICES SHALL BE FURNISHED AND INSTALLED UNDER THIS CONTRACT WHERE NECESSARY TO ACCOMPLISH THIS PURPOSE. TEMPORARIES SHALL BE REMOVED BY THE CONTRACTOR ONLY AFTER NEW PERMANENT SERVICES ARE INSTALLED
AND FULLY OPERATIONAL.
23. IN CASE OF CONFLICTS OR DISCREPANCIES WITHIN OR AMONG THE CONTRACT DRAWINGS, THE BETTER QUALITY, MORE STRINGENT REQUIREMENTS, OR GREATER QUANTITY OF WORK, AS DETERMINED BY THE
GOVERNMENT/CONTRACTING OFFICER, SHALL BE PROVIDED.
1. ALL EQUIPMENT/DEVICES SHALL BE OF FIRST RATE QUALITY (UNLESS OTHERWISE SPECIFIED) AND ARE TO BEAR THE APPROPRIATE AGA, CSA OR UL APPROVED LABELS, LISTINGS, AND CERTIFICATIONS FOR THE
SPECIFIC DESIGN PURPOSE.
2. ALL EQUIPMENT SOUND LEVELS SHALL NOT EXCEED 50 DB AT PROPERTY LINE.
3. ALL INTERCONNECTING WIRING AT UNIT SHALL BE FACTORY PRE-WIRED AND REQUIRE ONLY ONE (1) POWER CONNECTION TO THE UNIT BY THE ELECTRICAL CONTRACTOR. DISCONNECT SWITCH SHALL BE BY THE
ELECTRICAL CONTRACTOR.
4. SUBMIT THE REQUIRED NUMBER OF COPIES OF EACH CATALOG CUT, FOR THE EQUIPMENT SPECIFIED, TO THE VA/COR FOR APPROVAL AND TO THE ARCHITECT /ENGINEER FOR HIS/HER SUCCESSFUL REVIEW PRIOR TO THE BEGINNING OF CONSTRUCTION. THIS CONTRACTOR SHALL ALSO ASSEMBLE PRINTED INSTRUCTIONS FOR THE OPERATION AND MAINTENANCE OF EACH ITEM INSTALLED AND BIND TOGETHER WITH EQUIPMENT CUTS AND CONTROL WIRING DIAGRAMS. SUBMIT THE REQUIRED NUMBER OF COPIES TO THE VA/COR FOR
HIS/HER SUCCESSFUL REVIEW.
5. THE DRAWINGS, SCHEDULES AND SPECIFICATIONS HAVE BEEN PREPARED USING ONE MANUFACTURER FOR EACH PIECE OF EQUIPMENT AS THE BASIS OF DESIGN INCLUDING ALL DIMENSIONAL DESIGN. IF THE CONTRACTOR PURCHASES EQUIPMENT FROM A SPECIFIED ACCEPTABLE MANUFACTURER, BUT NOT THE SCHEDULED MANUFACTURER USED FOR THE BASE DESIGN, THE CONTRACTOR SHALL BE RESPONSIBLE FOR CHECKING ALL THE DIMENSIONS OF THE EQUIPMENT TO VERIFY THAT IT WILL FIT IN THE SPACE SHOWN ON THE DRAWINGS. MINOR DEVIATIONS IN DIMENSIONS WILL BE PERMITTED, PROVIDED THE RATINGS MEET THOSE SHOWN ON THE DRAWINGS AND EQUIPMENT WILL PHYSICALLY FIT INTO THE SPACE ALLOCATED WITH SUITABLE ACCESS AROUND EQUIPMENT FOR OPERATION AND MAINTENANCE OF THE EQUIPMENT. WHEN EQUIPMENT SUBMITTED FOR REVIEW DOES NOT MEET THE PHYSICAL SIZE OR ARRANGEMENT OF THAT SCHEDULED AND SPECIFIED, CONTRACTOR SHALL BE RESPONSIBLE FOR ALL ALTERATIONS REQUIRED TO ACCOMMODATE SUCH EQUIPMENT AT NO ADDITIONAL COST TO THE VA. CONTRACTOR WILL ALSO PAY ALL COSTS FOR ADDITIONAL WORK REQUIRED BY OTHER CONTRACTORS AND THE VA TO MAKE CHANGES WHICH
WOULD ALLOW THE EQUIPMENT TO FIT IN THE SPACE AND TO FUNCTION AS INTENDED.
6. CONTRACTOR AND/OR MANUFACTURER SHALL VERIFY THAT THE CHARACTERISTICS OF THE EQUIPMENT HE SUBMITS FOR REVIEW MEET THE CAPACITY AND DUTY SPECIFIED. WHEN EQUIPMENT SUBMITTED FOR REVIEW REQUIRES MODIFICATIONS TO THE WORK OF OTHER CONTRACTORS, SUBMITTING CONTRACTOR SHALL PAY FOR ALL COSTS FOR ADDITIONAL WORK REQUIRED BY OTHER CONTRACTORS, VA, ARCHITECT OR ENGINEER TO MAKE CHANGES WHICH WOULD ALLOW THE EQUIPMENT FUNCTION SAFELY AND PROPERLY.
7. CONTRACTOR MUST FIELD VERIFY SIZES, CAPACITIES, WEIGHTS, HORSEPOWERS, ETC. ON ALL EQUIPMENT.
NOTIFY THE VA/COR IF ANY DISCREPANCIES EXIST BETWEEN THE ACTUAL FIELD CONDITIONS AND THE
DRAWINGS.
MECHANICAL EQUIPMENT NOTES:
SEE ALL PROJECT GENERAL NOTES AND OTHER REQUIREMENTS INCLUDING THE LIFE SAFETY AND INFECTION CONTROL WORK LOCATED WITHIN THE GENERAL DRAWINGS SECTION. COMPLY WITH ALL REQUIREMENTS AS THEY ARE A DIRECT PART OF THIS SECTION AS IF THEY WERE DIRECTLY INCLUDED AND PROVIDED HEREIN.
EQUIVALENCY SUBSTITUTIONS: THE "BASIS OF DESIGN" (BOD) COMPLIANCE PROTOCOLS" ARE TO BE FOLLOWED FOR ALL MATERIALS, EQUIPMENT, ASSEMBLIES AND SYSTEMS SPECIFIED AND DETAILED THROUGHOUT ALL DRAWINGS AND SPECIFICATION SECTIONS, WHETHER THE BOD DESIGNATE IS SPECIFICALLY REFERENCED THEREIN OR NOT. SEE THE GENERAL DRAWINGS SECTION FOR THE SPECIFIC BOD COMPLIANCE REQUIREMENTS AND
PROTOCOLS TO BE FOLLOWED.
AD
A.F.F.
BAS
BHP
BOP
BTU
BTUH
CC
CFM
CHWR
CHWS
D
DB
DN
(E)
EA
EAT
EF
ESP
EWT
F
FPF
FPM
FV
GC
GPM
HP
HWC
HTS
HTR
HWR
HWS
LAT
LWT
MCA
MOCP
MTHWS
MTHWR
NK
NTS
PCR
PD
PH
PHC
PSI
RA
RPM
RPR
RPS
SA
SF
SP
TC
TSP
TYP.
VD
VFD
WB
W.C.
WG
ACCESS DOOR
ABOVE FINISHED FLOOR
BUILDING AUTOMATION SYSTEM
BRAKE HORSEPOWER
BOTTOM OF PIPE
BRITISH THERMAL UNIT
BRITISH THERMAL UNIT PER HOUR
COOLING COIL
CUBIC FEET PER MINUTE
CHILLED WATER RETURN
CHILLED WATER SUPPLY
DRAIN LINE
DRY BULB
DOWN
EXISTING
EXHAUST AIR
ENTERING AIR TEMPERATURE
EXHAUST FAN
EXTERNAL STATIC PRESSURE
ENTERING WATER TEMPERATURE
FAHRENHEIT
FINS PER FOOT
FEET PER MINUTE
FACE VELOCITY
GENERAL CONTRACTOR
GALLONS PER MINUTE
HORSEPOWER
HOT WATER COIL
HIGH TEMPERATURE HOT WATER SUPPLY
HIGH TEMPERATURE HOT WATER RETURN
HOT WATER RETURN
HOT WATER SUPPLY
LEAVING AIR TEMPERATURE
LEAVING WATER TEMPERATURE
MINIMUM CURRENT AMPS
MAXIMUM OVERCURRENT PROTECTION
MEDIUM TEMPERATURE HOT WATER SUPPLY
MEDIUM TEMPERATURE HOT WATER RETURN
NECK
NOT TO SCALE
PUMPED CONDENSATE RETURN
PRESSURE DROP
PHASE
PREHEAT COIL
POUNDS PER SQUARE INCH
RETURN AIR
REVOLUTIONS PER MINUTE
RADIANT PANEL (CHILLED WATER/HOT WATER) RETURN
RADIANT PANEL (CHILLED WATER/HOT WATER) SUPPLY
SUPPLY AIR
SUPPLY FAN
STATIC PRESSURE
TEMPERATURE CONTROL
TOTAL STATIC PRESSURE
TYPICAL
VOLUME DAMPER
VARIABLE FREQUENCY DRIVE
WET BULB
WATER COLUMN
WATER GAUGE
PIPING, DUCTWORK, OR EQUIPMENT TO BE REMOVED
HIGH TEMPERATURE (HEATING) HOT WATER SUPPLYHTS
HIGH TEMPERATURE (HEATING) HOT WATER RETURNHTR
MEDIUM TEMPERATURE (HEATING) HOT WATER SUPPLY (140-220°F)MTHWS
MEDIUM TEMPERATURE (HEATING) HOT WATER RETURN (140-220°F)MTHWR
MAKE-UP WATERMU
CONDENSER WATER SUPPLYCWS
CONDENSER WATER RETURNCWR
NEW CONNECTION POINT
XX
S-SUPPLY
R-RETURN
E-EXHAUST
DIFFUSER/GRILLE
IDENTIFICATION
DIFFUSER/GRILLE SIZE
CFMDIFFUSER/GRILLE
AIRFLOW RATE
DIFFUSER TAG
THESE LISTS OF SYMBOLS AND ABBREVIATIONS ARE
GENERAL. NOT ALL SYMBOLS AND ABBREVIATIONS MAY BE
APPLICABLE TO THIS PROJECT.
1 2 3 4 5 6 7 8 9 10
1 2 3 4 5 6 7 8 9 10
A
B
C
D
E
F
A
B
C
D
E
F
CONSULTANT ARCHITECT/ENGINEER OF RECORD STAMP Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
Drawing Title
Approved: Project Director
Phase Project Title Project Number
Building Number
Drawing NumberLocation
Issue Date Checked Drawn
VA FORM 08-6231
FULLY SPRINKLERED
REVIEW ONLY - NOT FOR CONSTRUCTION
Bancroft Project No. VA CONTRACT NO.
MECHANICAL - GENERAL NOTES, SYMBOLS
AND ABBREVIATIONS
RENOVATIONS TO
BUILDING 217
EDWARD J. HINES JR. VAMC
12/06/2024 RH RBB
578-20-002
M001
100% CONSTRUCTION
DOCUMENTS
23-00936C25223C0071
Revisions: Date:
30% SCHEMATIC DESIGN 11/23/2023
60% DESIGN DEVELOPMENT 05/08/2024
90% CONSTRUCTION DOCUMENTS 08/23/2024
100% CONSTRUCTION DOCUMENTS 12/06/2024
1515.11617
K
M
L
N
O
P
Q
S
R
(E)VAV-B-Z06
VAV-B-Z05
VAV-B-Z09B
VAV-B-Z03
VAV-B-Z01
VAV-B-Z08
VAV-B-Z02
VAV-B-Z04
VAV-B-Z07
2 2
(E)16"ø
N.I.C.
(E)56"x20"
EXISTING MECHANICAL
EQUIPMENT, DUCTWORK, ETC.
THIS AREA TO REMAIN
(E)72"x16"
ELEVATOR
1C268
ELEVATOR MACHINE
RM.
1A40
LAUNDRY
1A110
NURSING HOME
SUPERVISOR
1A105
LOUNGE
1A104
OFFICE
1A106
OFFICE
1A107
CONFERENCE & CLASS
1A109
WOMEN
1A142
MEN
1A141
RECREATION ROOM
1A108
WOMEN
1A113
MEN
1A112
H.A.C.
1A111
NOURISH. KITCHEN
1A115
STORAGE
1A108A
MECHANICAL DEMOLITION KEY NOTES
1. REMOVE ALL DUCTWORK, DIFFUSERS, REGISTERS, HANGERS, INSULATION, ETC.
SHOWN DASHED.
2. REMOVE EXISTING VAV BOX AND ASSOCIATED DUCTWORK, PIPING, SUPPORTS,
VALVING, CONTROLS, ETC.
3. EXISTING DUCTWORK, DIFFUSERS, REGISTERS, AND GRILLES TO REMAIN. PROTECT
DURING CONSTRUCTION.
4. REMOVE ALL DUCTWORK, DIFFUSERS, REGISTERS, HANGERS, INSULATION, ETC.
SHOWN DASHED AND CAP AT MAIN.
5. NEW CONNECTION TO BE MADE AT THIS LOCATION. REMOVE ALL DUCTWORK,
DIFFUSERS, REGISTERS, HANGERS, INSULATION, ETC. SHOWN DASHED BEYOND THIS
POINT.
6. EXISTING VAV BOX TO REMAIN.
7. MAIN DUCT CONTINUES UP HALLWAY.
X
GENERAL NOTES
A. COORDINATE A MINIMUM 3 WEEKS ADVANCE NOTICE FOR ALL MECHANICAL SERVICE
OUTAGES WITH COR.
B. ANY DUCTWORK WITHIN THE PROJECT AREA, THAT IS EXISTING TO REMAIN, WHETHER
OR NOT SHOWN ON THESE DRAWINGS, THAT IS CRUSHED OR DAMAGED IN ITS
CURRENT CONDITION OR AS A RESULT OF CONSTRUCTION, SHALL BE REPLACED WITH
NEW.
C. THE CONTRACTOR, AT HIS OWN DISCRETION, MAY REUSE OR REPLACE WITH NEW, ANY
DUCTWORK THAT IS SHOWN ON THESE DRAWINGS AS EXISTING TO REMAIN. ANY
EXISTING MEDIUM PRESSURE DUCTWORK THAT IS REUSED, IS SUBJECT TO THE SAME
PRESSURE TESTING AND CONSTRUCTION STANDARDS AS NEW DUCTWORK, FROM THE
AIR HANDLING UNIT TO THE VAV BOX INLETS, AS PER SPECIFICATIONS. REUSE OF
EXISTING DUCTWORK DOES NOT EXCUSE THE HVAC CONTRACTOR FROM MEETING THE
SAME STANDARDS AS NEW DUCTWORK CONSTRUCTION.
1 2 3 4 5 6 7 8 9 10
1 2 3 4 5 6 7 8 9 10
A
B
C
D
E
F
A
B
C
D
E
F
CONSULTANT ARCHITECT/ENGINEER OF RECORD STAMP Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
Drawing Title
Approved: Project Director
Phase Project Title Project Number
Building Number
Drawing NumberLocation
Issue Date Checked Drawn
VA FORM 08-6231
FULLY SPRINKLERED
REVIEW ONLY - NOT FOR CONSTRUCTION
Bancroft Project No. VA CONTRACT NO.
BUILDING 217 KEY PLAN
MECHANICAL - ENLARGED VENTILATION
DEMOLITION PLAN - PRIMARY CARE CLINIC &
ENTRANCE LOBBY
RENOVATIONS TO
BUILDING 217
EDWARD J. HINES JR. VAMC
12/06/2024 RH RBB
578-20-002
MVD401.1
100% CONSTRUCTION
DOCUMENTS
23-00936C25223C0071
N 1/8" = 1'-0"
MECHANICAL - ENLARGED VENTILATION DEMOLITION PLAN - PRIMARY CARE CLINIC & ENTRANCE LOBBY
Revisions: Date:
30% SCHEMATIC DESIGN 11/23/2023
60% DESIGN DEVELOPMENT 05/08/2024
GENERAL NOTES
A. COORDINATE A MINIMUM 3 WEEKS ADVANCE NOTICE FOR ALL MECHANICAL SERVICE
OUTAGES WITH COR.
B. ANY DUCTWORK WITHIN THE PROJECT AREA, THAT IS EXISTING TO REMAIN, WHETHER
OR NOT SHOWN ON THESE DRAWINGS, THAT IS CRUSHED OR DAMAGED IN ITS
CURRENT CONDITION OR AS A RESULT OF CONSTRUCTION, SHALL BE REPLACED WITH
NEW.
C. THE CONTRACTOR, AT HIS OWN DISCRETION, MAY REUSE OR REPLACE WITH NEW, ANY
DUCTWORK THAT IS SHOWN ON THESE DRAWINGS AS EXISTING TO REMAIN. ANY
EXISTING MEDIUM PRESSURE DUCTWORK THAT IS REUSED, IS SUBJECT TO THE SAME
PRESSURE TESTING AND CONSTRUCTION STANDARDS AS NEW DUCTWORK, FROM THE
AIR HANDLING UNIT TO THE VAV BOX INLETS, AS PER SPECIFICATIONS. REUSE OF
EXISTING DUCTWORK DOES NOT EXCUSE THE HVAC CONTRACTOR FROM MEETING THE
SAME STANDARDS AS NEW DUCTWORK CONSTRUCTION.
10.11111.1 11.212131415
K
M
L
N
VAV-C-Z03A
VAV-C-Z03B
(E)VAV-C-Z04A(E)VAV-C-Z01
(E )5
4" x2
2"
(E )3
2" x1
4" (E
)2 6" x1 0"
(E )1
6" ø
(E )1
4" ø
(E )2
5" ø
(E )2
6" x2
0"
54"x20"
(E )1
4" ø
(E )1
2" ø
1 41
DINING ROOM
1A118
REHABILITATION
THERAPY ROOM
1A43
MECHANICAL DEMOLITION KEY NOTES
1. REMOVE ALL DUCTWORK, DIFFUSERS, REGISTERS, HANGERS, INSULATION, ETC.
SHOWN DASHED.
2. REMOVE EXISTING VAV BOX AND ASSOCIATED DUCTWORK, PIPING, SUPPORTS,
VALVING, CONTROLS, ETC.
3. EXISTING DUCTWORK, DIFFUSERS, REGISTERS, AND GRILLES TO REMAIN. PROTECT
DURING CONSTRUCTION.
4. REMOVE ALL DUCTWORK, DIFFUSERS, REGISTERS, HANGERS, INSULATION, ETC.
SHOWN DASHED AND CAP AT MAIN.
5. EXISTING VAV BOX TO REMAIN.
X
1 2 3 4 5 6 7 8 9 10
1 2 3 4 5 6 7 8 9 10
A
B
C
D
E
F
A
B
C
D
E
F
CONSULTANT ARCHITECT/ENGINEER OF RECORD STAMP Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
Drawing Title
Approved: Project Director
Phase Project Title Project Number
Building Number
Drawing NumberLocation
Issue Date Checked Drawn
VA FORM 08-6231
FULLY SPRINKLERED
REVIEW ONLY - NOT FOR CONSTRUCTION
Bancroft Project No. VA CONTRACT NO.
BUILDING 217 KEY PLAN
MECHANICAL - ENLARGED VENTILATION
DEMOLITION PLAN - DINING ROOM 1A118
RENOVATIONS TO
BUILDING 217
EDWARD J. HINES JR. VAMC
12/06/2024 RH RBB
578-20-002
MVD401.2
100% CONSTRUCTION
DOCUMENTS
23-00936C25223C0071
N 1/4" = 1'-0"
MECHANICAL - ENLARGED VENTILATION DEMOLITION PLAN - DINING ROOM 1A118
Revisions: Date:
30% SCHEMATIC DESIGN 11/23/2023
60% DESIGN DEVELOPMENT 05/08/2024
OUTAGES WITH COR.
B. ANY DUCTWORK WITHIN THE PROJECT AREA, THAT IS EXISTING TO REMAIN, WHETHER
OR NOT SHOWN ON THESE DRAWINGS, THAT IS CRUSHED OR DAMAGED IN ITS
CURRENT CONDITION OR AS A RESULT OF CONSTRUCTION, SHALL BE REPLACED WITH
NEW.
C. THE CONTRACTOR, AT HIS OWN DISCRETION, MAY REUSE OR REPLACE WITH NEW, ANY
DUCTWORK THAT IS SHOWN ON THESE DRAWINGS AS EXISTING TO REMAIN. ANY
EXISTING MEDIUM PRESSURE DUCTWORK THAT IS REUSED, IS SUBJECT TO THE SAME
PRESSURE TESTING AND CONSTRUCTION STANDARDS AS NEW DUCTWORK, FROM THE
AIR HANDLING UNIT TO THE VAV BOX INLETS, AS PER SPECIFICATIONS. REUSE OF
EXISTING DUCTWORK DOES NOT EXCUSE THE HVAC CONTRACTOR FROM MEETING THE
SAME STANDARDS AS NEW DUCTWORK CONSTRUCTION.
10.111.1 11.212131415
K
M
L
N
VAV-C-Z02
VAV-C-Z06
(E)20"x16"
(E )5
4" x2
2"(E)36"x14"(E)20"x14"(E)16"ø(E)12"ø
(E)8"ø (E)12"ø (E)18"x16"
(E )3
2" x1
4" (E
)2 6" x1 0"
(E )1
6" ø
(E )1
4" ø
444 4
3 3 3
1 1
(E )2
5" ø
(E )1
4" ø
(E)54"x20"
(E)48"x16"(E )5
4" x2
0"
DINING
2A26
MECHANICAL DEMOLITION KEY NOTES
1. REMOVE ALL DUCTWORK, DIFFUSERS, REGISTERS, HANGERS, INSULATION, ETC.
SHOWN DASHED.
2. REMOVE EXISTING VAV BOX AND ASSOCIATED DUCTWORK, PIPING, SUPPORTS,
VALVING, CONTROLS, ETC.
3. EXISTING DUCTWORK, DIFFUSERS, REGISTERS, AND GRILLES TO REMAIN. PROTECT
DURING CONSTRUCTION.
4. REMOVE ALL DUCTWORK, DIFFUSERS, REGISTERS, HANGERS, INSULATION, ETC.
SHOWN DASHED AND CAP AT MAIN.
X
1 2 3 4 5 6 7 8 9 10
1 2 3 4 5 6 7 8 9 10
A
B
C
D
E
F
A
B
C
D
E
F
CONSULTANT ARCHITECT/ENGINEER OF RECORD STAMP Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
Drawing Title
Approved: Project Director
Phase Project Title Project Number
Building Number
Drawing NumberLocation
Issue Date Checked Drawn
VA FORM 08-6231
FULLY SPRINKLERED
REVIEW ONLY - NOT FOR CONSTRUCTION
Bancroft Project No. VA CONTRACT NO.
BUILDING 217 KEY PLAN
MECHANICAL - ENLARGED VENTILATION
DEMOLITION PLAN - DINING ROOM 2A26
RENOVATIONS TO
BUILDING 217
EDWARD J. HINES JR. VAMC
12/06/2024 RH RBB
578-20-002
MVD401.3
100% CONSTRUCTION
DOCUMENTS
23-00936C25223C0071
N 1/4" = 1'-0"
MECHANICAL - ENLARGED VENTILATION DEMOLITION PLAN - DINING ROOM 2A26
Revisions: Date:
30% SCHEMATIC DESIGN 11/23/2023
60% DESIGN DEVELOPMENT 05/08/2024
OUTAGES WITH COR.
B. ANY DUCTWORK WITHIN THE PROJECT AREA, THAT IS EXISTING TO REMAIN, WHETHER
OR NOT SHOWN ON THESE DRAWINGS, THAT IS CRUSHED OR DAMAGED IN ITS
CURRENT CONDITION OR AS A RESULT OF CONSTRUCTION, SHALL BE REPLACED WITH
NEW.
C. THE CONTRACTOR, AT HIS OWN DISCRETION, MAY REUSE OR REPLACE WITH NEW, ANY
DUCTWORK THAT IS SHOWN ON THESE DRAWINGS AS EXISTING TO REMAIN. ANY
EXISTING MEDIUM PRESSURE DUCTWORK THAT IS REUSED, IS SUBJECT TO THE SAME
PRESSURE TESTING AND CONSTRUCTION STANDARDS AS NEW DUCTWORK, FROM THE
AIR HANDLING UNIT TO THE VAV BOX INLETS, AS PER SPECIFICATIONS. REUSE OF
EXISTING DUCTWORK DOES NOT EXCUSE THE HVAC CONTRACTOR FROM MEETING THE
SAME STANDARDS AS NEW DUCTWORK CONSTRUCTION.
1010.11111.1 11.212
O
P
VAV-C-Z54
VAV-C-Z56
(E)14"ø (E)12"ø
(E )1
2" ø
(E )1
2" ø
(E )1
4" ø
(E)14"ø
(E )1
2" ø
(E )1
0" ø
(E)8"ø
(E)6"x6"
H.A.C.
2A11
SANCTUARY ROOM
2A12
CONFERENCE ROOM
2A13
MECHANICAL DEMOLITION KEY NOTES
1. REMOVE ALL DUCTWORK, DIFFUSERS, REGISTERS, HANGERS, INSULATION, ETC.
SHOWN DASHED.
2. REMOVE EXISTING VAV BOX AND ASSOCIATED DUCTWORK, PIPING, SUPPORTS,
VALVING, CONTROLS, ETC.
3. EXISTING DUCTWORK, DIFFUSERS, REGISTERS, AND GRILLES TO REMAIN. PROTECT
DURING CONSTRUCTION.
4. REMOVE ALL DUCTWORK, DIFFUSERS, REGISTERS, HANGERS, INSULATION, ETC.
SHOWN DASHED AND CAP AT MAIN.
X
1 2 3 4 5 6 7 8 9 10
1 2 3 4 5 6 7 8 9 10
A
B
C
D
E
F
A
B
C
D
E
F
CONSULTANT ARCHITECT/ENGINEER OF RECORD STAMP Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
Drawing Title
Approved: Project Director
Phase Project Title Project Number
Building Number
Drawing NumberLocation
Issue Date Checked Drawn
VA FORM 08-6231
FULLY SPRINKLERED
REVIEW ONLY - NOT FOR CONSTRUCTION
Bancroft Project No. VA CONTRACT NO.
BUILDING 217 KEY PLAN
MECHANICAL - ENLARGED VENTILATION
DEMOLITION PLAN - LIBRARY 2A12
RENOVATIONS TO
BUILDING 217
EDWARD J. HINES JR. VAMC
12/06/2024 RH RBB
578-20-002
MVD401.4
100% CONSTRUCTION
DOCUMENTS
23-00936C25223C0071
N 1/4" = 1'-0"
MECHANICAL - ENLARGED VENTILATION DEMOLITION PLAN - LIBRARY 2A12
Revisions: Date:
30% SCHEMATIC DESIGN 11/23/2023
60% DESIGN DEVELOPMENT 05/08/2024
OUTAGES WITH COR.
B. ANY DUCTWORK WITHIN THE PROJECT AREA, THAT IS EXISTING TO REMAIN, WHETHER
OR NOT SHOWN ON THESE DRAWINGS, THAT IS CRUSHED OR DAMAGED IN ITS
CURRENT CONDITION OR AS A RESULT OF CONSTRUCTION, SHALL BE REPLACED WITH
NEW.
C. THE CONTRACTOR, AT HIS OWN DISCRETION, MAY REUSE OR REPLACE WITH NEW, ANY
DUCTWORK THAT IS SHOWN ON THESE DRAWINGS AS EXISTING TO REMAIN. ANY
EXISTING MEDIUM PRESSURE DUCTWORK THAT IS REUSED, IS SUBJECT TO THE SAME
PRESSURE TESTING AND CONSTRUCTION STANDARDS AS NEW DUCTWORK, FROM THE
AIR HANDLING UNIT TO THE VAV BOX INLETS, AS PER SPECIFICATIONS. REUSE OF
EXISTING DUCTWORK DOES NOT EXCUSE THE HVAC CONTRACTOR FROM MEETING THE
SAME STANDARDS AS NEW DUCTWORK CONSTRUCTION.
E
D
S17
N9N8
VAV-B-Z51
(E)12"x8"
(E)10"ø (E)8"ø
(E)6"x6"
VERTICAL DUCTWORK TO
BE DEMOLISHED UP TO
SECOND FLOOR, NEW
CONNECTION TO BE MADE
E
D
VAV-C-Z30
(E)12"x8"
(E )1
6" x1
0"
(E)10"ø (E)8"ø
(E)6"x6"
3 5
TOILET
1B148
BEDROOM
1B149
BEDROOM
1C149
TOILET
1C148
MECHANICAL DEMOLITION KEY NOTES
1. REMOVE ALL DUCTWORK, DIFFUSERS, REGISTERS, HANGERS, INSULATION, ETC.
SHOWN DASHED.
2. REMOVE EXISTING VAV BOX AND ASSOCIATED DUCTWORK, PIPING, SUPPORTS,
VALVING, CONTROLS, ETC.
3. EXISTING DUCTWORK, DIFFUSERS, REGISTERS, AND GRILLES TO REMAIN. PROTECT
DURING CONSTRUCTION.
4. CAP DUCTWORK AT THIS LOCATION. REMOVE ALL DUCTWORK, DIFFUSERS, REGISTERS,
HANGERS, INSULATION, ETC. SHOWN DASHED AND CAP AT MAIN.
5. NEW CONNECTION TO BE MADE AT THIS LOCATION. REMOVE ALL DUCTWORK,
DIFFUSERS, REGISTERS, HANGERS, INSULATION, ETC. SHOWN DASHED BEYOND THIS
POINT.
X
1 2 3 4 5 6 7 8 9 10
1 2 3 4 5 6 7 8 9 10
A
B
C
D
E
F
A
B
C
D
E
F
CONSULTANT ARCHITECT/ENGINEER OF RECORD STAMP Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
Drawing Title
Approved: Project Director
Phase Project Title Project Number
Building Number
Drawing NumberLocation
Issue Date Checked Drawn
VA FORM 08-6231
FULLY SPRINKLERED
REVIEW ONLY - NOT FOR CONSTRUCTION
Bancroft Project No. VA CONTRACT NO.
BUILDING 217 KEY PLAN
MECHANICAL - ENLARGED VENTILATION
DEMOLITION PLAN - BARIATRIC ROOMS
RENOVATIONS TO
BUILDING 217
EDWARD J. HINES JR. VAMC
12/06/2024 RH RBB
578-20-002
MVD401.5
100% CONSTRUCTION
DOCUMENTS
23-00936C25223C0071
N 1/4" = 1'-0"
ENLARGED VENTILATION DEMOLITION PLAN - BARIATRIC ROOM B149
N 1/4" = 1'-0"
ENLARGED VENTILATION DEMOLITION PLAN - BARIATRIC ROOM C149
Revisions: Date:
30% SCHEMATIC DESIGN 11/23/2023
60% DESIGN DEVELOPMENT 05/08/2024
90% CONSTRUCTION DOCUMENTS 08/23/2024
100% CONSTRUCTION DOCUMENTS 12/06/2024
UNIT B UNIT C
UNIT A
OUTAGES WITH COR.
B. ANY DUCTWORK WITHIN THE PROJECT AREA, THAT IS EXISTING TO REMAIN, WHETHER
OR NOT SHOWN ON THESE DRAWINGS, THAT IS CRUSHED OR DAMAGED IN ITS
CURRENT CONDITION OR AS A RESULT OF CONSTRUCTION, SHALL BE REPLACED WITH
NEW.
C. THE CONTRACTOR, AT HIS OWN DISCRETION, MAY REUSE OR REPLACE WITH NEW, ANY
DUCTWORK THAT IS SHOWN ON THESE DRAWINGS AS EXISTING TO REMAIN. ANY
EXISTING MEDIUM PRESSURE DUCTWORK THAT IS REUSED, IS SUBJECT TO THE SAME
PRESSURE TESTING AND CONSTRUCTION STANDARDS AS NEW DUCTWORK, FROM THE
AIR HANDLING UNIT TO THE VAV BOX INLETS, AS PER SPECIFICATIONS. REUSE OF
EXISTING DUCTWORK DOES NOT EXCUSE THE HVAC CONTRACTOR FROM MEETING THE
SAME STANDARDS AS NEW DUCTWORK CONSTRUCTION.
15.1
171819202122
J
K
H
G
F1
E
D
C
B
A
S17
N15 S18
S16.1
S15.1
S14.1
N14
N13
N12
N11
N10
N9
N8
N6
(E)76"x20"
(E)34"x14"(E)14"ø (E)34"x14"
(E )5
4" x2
2"
VAV-B-Z38
VAV-B-Z39
VAV-B-Z37
VAV-B-Z40
VAV-B-Z41
VAV-B-Z42
VAV-B-Z43
VAV-B-Z44
VAV-B-Z45
VAV-B-Z46
VAV-B-Z47
VAV-B-Z36
VAV-B-Z35
VAV-B-Z34
VAV-B-Z26A
VAV-B-Z33
(E)VAV-B-Z32
VAV-B-Z51
(E)VAV-B-Z25
(E)VAV-B-Z24
(E)VAV-B-Z52
(E)VAV-B-Z49
(E)VAV-B-Z28
(E)VAV-B-Z29
(E)VAV-B-Z10
(E)VAV-B-Z30
(E)VAV-B-Z31
VAV-B-Z27
VAV-B-Z50
(E)24"x14"
(E)19"x14"
(E)15"ø
(E )1
2" ø
(E )1
6" ø
(E)24"x14"
(E)24"x14"
(E)15"ø
(E)16"ø
(E )5
6" x2
0"
(E )1
2" ø
(E)72"x16"
5 3
1 1
4 4
MECHANICAL
1A114
O.T. OFFICE
1A116
2 BEDROOM
1B162
BATH
1B163
PANTRY
1B136
SOILED UTILITY
1B146
HAC
1B147
SHOWER
1B135
CONFERENCE ROOM
1B133
BEDROOM
1B130
BEDROOM
1B131
TOILET
1B132
TOILET
1B148
BEDROOM
1B149
TOILET
1B150
BEDROOM
1B152
TOILET
1B153
BEDROOM
1B155
BEDROOM
1B156
TOILET
1B157
BEDROOM
1B159
TOILET
1B161
BEDROOM
1B160
BEDROOM
1B164
TOILET
1B165
BATH
1B166
BEDROOM
1B167
BEDROOM
1B168
TOILET
1B169
BEDROOM
1B171
BEDROOM
1B172
BEDROOM
1B175
BEDROOM
1B176
TOILET
1B177
BEDROOM
1B178
TOILET
1B179
TOILET
1B173
TOILET
1B174
TOILET
1B170
TOILET
1B158
TOILET
1B154
EQUIP. ROOM
1B151A
OFFICE
1B139
OFFICE
1B141
MEDS
1B138
ELECT.
1B143
SUPPLY
1B142
STORAGE
1B145
EMS
1B145A
LOUNGE
1B80
MECHANICAL DEMOLITION KEY NOTES
1. REMOVE ALL DUCTWORK, DIFFUSERS, REGISTERS, HANGERS, INSULATION, ETC.
SHOWN DASHED.
2. REMOVE EXISTING VAV BOX AND ASSOCIATED DUCTWORK, PIPING, SUPPORTS,
VALVING, CONTROLS, ETC.
3. EXISTING DUCTWORK, DIFFUSERS, REGISTERS, AND GRILLES TO REMAIN. PROTECT
DURING CONSTRUCTION.
4. NEW CONNECTION TO BE MADE AT THIS LOCATION. REMOVE ALL DUCTWORK,
DIFFUSERS, REGISTERS, HANGERS, INSULATION, ETC. SHOWN DASHED BEYOND THIS
POINT.
5. EXISTING VAV BOX TO REMAIN.
6. REMOVE EXISTING VERTICAL EXHAUST DUCTWORK UP TO 2ND FLOOR.
X
1 2 3 4 5 6 7 8 9 10
1 2 3 4 5 6 7 8 9 10
A
B
C
D
E
F
A
B
C
D
E
F
CONSULTANT ARCHITECT/ENGINEER OF RECORD STAMP Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
Drawing Title
Approved: Project Director
Phase Project Title Project Number
Building Number
Drawing NumberLocation
Issue Date Checked Drawn
VA FORM 08-6231
FULLY SPRINKLERED
REVIEW ONLY - NOT FOR CONSTRUCTION
Bancroft Project No. VA CONTRACT NO.
BUILDING 217 KEY PLAN
MECHANICAL - ENLARGED VENTILATION
DEMOLITION PLAN - DEMENTIA UNIT
RENOVATIONS TO
BUILDING 217
EDWARD J. HINES JR. VAMC
12/06/2024 RH RBB
578-20-002
MVD401.6
100% CONSTRUCTION
DOCUMENTS
23-00936C25223C0071
N 1/8" = 1'-0"
MECHANICAL - ENLARGED VENTILATION DEMOLITION PLAN - DEMENTIA UNIT
Revisions: Date:
30% SCHEMATIC DESIGN 11/23/2023
60% DESIGN DEVELOPMENT 05/08/2024
OUTAGES WITH COR.
B. ANY DUCTWORK WITHIN THE PROJECT AREA, THAT IS EXISTING TO REMAIN, WHETHER
OR NOT SHOWN ON THESE DRAWINGS, THAT IS CRUSHED OR DAMAGED IN ITS
CURRENT CONDITION OR AS A RESULT OF CONSTRUCTION, SHALL BE REPLACED WITH
NEW.
C. THE CONTRACTOR, AT HIS OWN DISCRETION, MAY REUSE OR REPLACE WITH NEW, ANY
DUCTWORK THAT IS SHOWN ON THESE DRAWINGS AS EXISTING TO REMAIN. ANY
EXISTING MEDIUM PRESSURE DUCTWORK THAT IS REUSED, IS SUBJECT TO THE SAME
PRESSURE TESTING AND CONSTRUCTION STANDARDS AS NEW DUCTWORK, FROM THE
AIR HANDLING UNIT TO THE VAV BOX INLETS, AS PER SPECIFICATIONS. REUSE OF
EXISTING DUCTWORK DOES NOT EXCUSE THE HVAC CONTRACTOR FROM MEETING THE
SAME STANDARDS AS NEW DUCTWORK CONSTRUCTION.
1111.1 11.212
H
G
VAV-C-Z09
(E )3
6" x1
6" (E
)1 8" ø
6"x6"
(E)6"x6"
(E )2
8" x1
4"
K
M
L
S6
VAV-C-Z45
(E)8"x6"
(E)6"x6"
(E)36"x16" (E)18"ø
3 4
(E)34"x14"
1111.1 11.212
H
G
VAV-C-Z354
(E )3
6" x1
6" (E
)1 8" ø
(E)6"x6"
(E)6"x6"
(E )2
8" x1
4"
K
M
L
S6
VAV-C-Z460
(E)36"x16" (E)18"ø
(E)8"x6"
(E)6"x6"
(E)34"x14"
TOILET
1C179
PATIENT ROOM
1C178
TOILET
1C103
PATIENT ROOM
1C104
PATIENT ROOM
2C4
TOILET
2C3
TOILET
2C79
PATIENT ROOM
2C78
MECHANICAL DEMOLITION KEY NOTES
1. REMOVE ALL DUCTWORK, DIFFUSERS, REGISTERS, HANGERS, INSULATION, ETC.
SHOWN DASHED.
2. REMOVE EXISTING VAV BOX AND ASSOCIATED DUCTWORK, PIPING, SUPPORTS,
VALVING, CONTROLS, ETC.
3. EXISTING DUCTWORK, DIFFUSERS, REGISTERS, AND GRILLES TO REMAIN. PROTECT
DURING CONSTRUCTION.
4. REMOVE ALL DUCTWORK, DIFFUSERS, REGISTERS, HANGERS, INSULATION, ETC.
SHOWN DASHED AND CAP AT MAIN.
X
1 2 3 4 5 6 7 8 9 10
1 2 3 4 5 6 7 8 9 10
A
B
C
D
E
F
A
B
C
D
E
F
CONSULTANT ARCHITECT/ENGINEER OF RECORD STAMP Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
Drawing Title
Approved: Project Director
Phase Project Title Project Number
Building Number
Drawing NumberLocation
Issue Date Checked Drawn
VA FORM 08-6231
FULLY SPRINKLERED
REVIEW ONLY - NOT FOR CONSTRUCTION
Bancroft Project No. VA CONTRACT NO.
BUILDING 217 KEY PLAN
MECHANICAL - ENLARGED VENTILATION
DEMOLITION PLAN - HIGH FALL RISK ROOMS
RENOVATIONS TO
BUILDING 217
EDWARD J. HINES JR. VAMC
12/06/2024 RH RBB
578-20-002
MVD401.7
100% CONSTRUCTION
DOCUMENTS
23-00936C25223C0071
N 1/4" = 1'-0"
ENLARGED VENTILATION DEMOLITION PLAN - HIGH FALL RISK 1C104
N 1/4" = 1'-0"
ENLARGED VENTILATION DEMOLITION PLAN - HIGH FALL RISK 1C178
N 1/4" = 1'-0"
ENLARGED VENTILATION DEMOLITION PLAN - HIGH FALL RISK 2C4
N 1/4" = 1'-0"
ENLARGED VENTILATION DEMOLITION PLAN - HIGH FALL RISK 2C78
Revisions: Date:
30% SCHEMATIC DESIGN 11/23/2023
60% DESIGN DEVELOPMENT 05/08/2024
OUTAGES WITH COR.
B. ANY DUCTWORK WITHIN THE PROJECT AREA, THAT IS EXISTING TO REMAIN, WHETHER
OR NOT SHOWN ON THESE DRAWINGS, THAT IS CRUSHED OR DAMAGED IN ITS
CURRENT CONDITION OR AS A RESULT OF CONSTRUCTION, SHALL BE REPLACED WITH
NEW.
C. THE CONTRACTOR, AT HIS OWN DISCRETION, MAY REUSE OR REPLACE WITH NEW, ANY
DUCTWORK THAT IS SHOWN ON THESE DRAWINGS AS EXISTING TO REMAIN. ANY
EXISTING MEDIUM PRESSURE DUCTWORK THAT IS REUSED, IS SUBJECT TO THE SAME
PRESSURE TESTING AND CONSTRUCTION STANDARDS AS NEW DUCTWORK, FROM THE
AIR HANDLING UNIT TO THE VAV BOX INLETS, AS PER SPECIFICATIONS. REUSE OF
EXISTING DUCTWORK DOES NOT EXCUSE THE HVAC CONTRACTOR FROM MEETING THE
SAME STANDARDS AS NEW DUCTWORK CONSTRUCTION.
1515.116
H
G
VAV-B-Z46
1515.116
H
G
VAV-C-Z347
(E )3
2" x1
6" (E
)1 8" ø
(E)6"x6"
(E )2
8" x1
4"BEDROOM
1B178
TOILET
1B179
TOILET
2B79
FAMILY ROOM
2B78
MECHANICAL DEMOLITION KEY NOTES
1. REMOVE ALL DUCTWORK, DIFFUSERS, REGISTERS, HANGERS, INSULATION, ETC.
SHOWN DASHED AND CAP AT MAIN.
2. REMOVE EXISTING VAV BOX AND ASSOCIATED DUCTWORK, PIPING, SUPPORTS,
VALVING, CONTROLS, ETC.
3. EXISTING DUCTWORK, DIFFUSERS, REGISTERS, AND GRILLES TO REMAIN. PROTECT
DURING CONSTRUCTION.
4. REMOVE ALL DUCTWORK, DIFFUSERS, REGISTERS, HANGERS, INSULATION, ETC.
SHOWN DASHED AND CAP AT MAIN.
X
1 2 3 4 5 6 7 8 9 10
1 2 3 4 5 6 7 8 9 10
A
B
C
D
E
F
A
B
C
D
E
F
CONSULTANT ARCHITECT/ENGINEER OF RECORD STAMP Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
Drawing Title
Approved: Project Director
Phase Project Title Project Number
Building Number
Drawing NumberLocation
Issue Date Checked Drawn
VA FORM 08-6231
FULLY SPRINKLERED
REVIEW ONLY - NOT FOR CONSTRUCTION
Bancroft Project No. VA CONTRACT NO.
BUILDING 217 KEY PLAN
MECHANICAL - ENLARGED VENTILATION
DEMOLITION PLAN - EQUIPMENT STORAGE
RENOVATIONS TO
BUILDING 217
EDWARD J. HINES JR. VAMC
12/06/2024 RH RBB
578-20-002
MVD401.8
100% CONSTRUCTION
DOCUMENTS
23-00936C25223C0071
N 1/4" = 1'-0"
ENLARGED VENTILATION DEMOLITION PLAN - EQUIPMENT 1B178 N
1/4" = 1'-0"
ENLARGED VENTILATION DEMOLITION PLAN - FAMILY 2B78
Revisions: Date:
30% SCHEMATIC DESIGN 11/23/2023
60% DESIGN DEVELOPMENT 05/08/2024
1010.11111.1 11.21213141515.1
M
N
O
1 23
6 6
MECHANICAL DEMOLITION KEY NOTES
1. DEMOLISH EXISTING AHU AND ALL ASSOCIATED PIPING, CONTROLS AND DUCTWORK.
CONTRACTOR TO DEMOLISH EXISTING ROOF CURB AND PREPARE ROOF FOR NEW
ROOF CURB CONNECTION.
2. DEMOLISH EXISTING AIR COOLED CHILLER UNIT AND ALL ASSOCIATED PIPING,
CONTROLS AND ROOF CURB.
3. DEMOLISH EXISTING PLENUM.
4. DEMOLISH EXISTING CHILLED WATER SUPPLY AND RETURN CONNECTED TO AHU AND
AIR COOLED CHILLER UNIT. REMOVE ALL ASSOCIATED PIPE STANDS, INSULATION AND
VALVES.
5. DEMOLISH EXISTING STEAM PIPING BACK TO MECHANICAL ROOM 2A 5. REMOVE ALL
ASSOCIATED PIPE STANDS, INSULATION AND VALVES. REFER TO MPD402.9 FOR
SECOND FLOOR CONTINUOUS DEMOLISH STEAM PIPING.
6. DEMOLISH EXISTING DUCTWORK AND ALL LINEAR DIFFUSERS IN CEILING AREA OF EASY
STREET.
X
GENERAL NOTES
A. COORDINATE A MINIMUM 3 WEEKS ADVANCE NOTICE FOR ALL MECHANICAL SERVICE
OUTAGES WITH COR.
B. REMOVE ALL CLAMPS, HANGERS, SUPPORTS, ETC., ASSOCIATED WITH PIPING
REMOVAL.
C. PIPING MAY BE SHOWN OFFSET FROM ITS ACTUAL LOCATION FOR CLARITY. FIELD
VERIFY EXACT LOCATIONS. PIPING AND EQUIPMENT SHOWN ON THIS DRAWING IS
BASED ON AS-BUILT DOCUMENTATION PROVIDED BY THE VA AND A CURSORY ON SITE
REVIEW OF EXISTING CONDITIONS. IF IT IS DISCOVERED THAT ANY PIPING OR
EQUIPMENT, INDICATED TO BE DEMOLISHED, SERVES OTHER AREAS BEYOND THIS
PROJECT SCOPE, THE CONTRACTOR MUST BE IMMEDIATELY STOP DEMOLITION OF SAID
PIPING OR EQUIPMENT, NOTIFY THE COR AND ENGINEER, AND WAIT FOR FURTHER
INSTRUCTIONS.
1 2 3 4 5 6 7 8 9 10
1 2 3 4 5 6 7 8 9 10
A
B
C
D
E
F
A
B
C
D
E
F
CONSULTANT ARCHITECT/ENGINEER OF RECORD STAMP Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
Drawing Title
Approved: Project Director
Phase Project Title Project Number
Building Number
Drawing NumberLocation
Issue Date Checked Drawn
VA FORM 08-6231
FULLY SPRINKLERED
REVIEW ONLY - NOT FOR CONSTRUCTION
Bancroft Project No. VA CONTRACT NO.
BUILDING 217 KEY PLAN
MECHANICAL - ENLARGED DEMOLITION PLAN
- EASY STREET ROOF
RENOVATIONS TO
BUILDING 217
EDWARD J. HINES JR. VAMC
12/06/2024 RH RBB
578-20-002
MVD401.9
100% CONSTRUCTION
DOCUMENTS
23-00936C25223C0071
N 1/4" = 1'-0"
ENLARGED VENTILATION DEMOLITION PLAN - EASY STREET ROOF PLAN
Revisions: Date:
30% SCHEMATIC DESIGN 11/23/2023
60% DESIGN DEVELOPMENT 05/08/2024
3456789
1010.11111.111.21213141515.11617
181920212223242526
J
K
H
M
L
N
O
P
Q
S
R
G
F1
E
D
C
B
A
S17
S16
S15
S14 S13
S12
S11
S10
S9
S8
S7 S6
S5
S4 S3
S2
S1
N19
N17
N15.1
N14.1
N16 N15
S19
S18
S16.1
S15.1
S14.1
N14 N13
N12
N11
N10
N9
N8
N7 N6
N5
N4 N3
N2
N1
(E)EF-07
(E)EF-05
(E)EF-04
(E)EF-6
(E)EF-18
(E)EF-17
(E)EF-14
(E)EF-19(E)EF-12
(E)EF-10
(E)EF-13
(E)EF-15
(E)EF-16
MECHANICAL DEMOLITION KEY NOTES
1. REMOVE EXISTING EXHAUST FAN AND EXISTING CURB. DEMLOSH ALL ASSOCIATED
DUCTWORK AND CONTROLS.
2. EXISTING EXHAUST FAN AND CURB TO REMAIN.
X
GENERAL NOTES
A. COORDINATE A MINIMUM 3 WEEKS ADVANCE NOTICE FOR ALL MECHANICAL SERVICE
OUTAGES WITH COR.
B. ANY DUCTWORK WITHIN THE PROJECT AREA, THAT IS EXISTING TO REMAIN, WHETHER
OR NOT SHOWN ON THESE DRAWINGS, THAT IS CRUSHED OR DAMAGED IN ITS
CURRENT CONDITION OR AS A RESULT OF CONSTRUCTION, SHALL BE REPLACED WITH
NEW.
C. THE CONTRACTOR, AT HIS OWN DISCRETION, MAY REUSE OR REPLACE WITH NEW, ANY
DUCTWORK THAT IS SHOWN ON THESE DRAWINGS AS EXISTING TO REMAIN. ANY
EXISTING MEDIUM PRESSURE DUCTWORK THAT IS REUSED, IS SUBJECT TO THE SAME
PRESSURE TESTING AND CONSTRUCTION STANDARDS AS NEW DUCTWORK, FROM THE
AIR HANDLING UNIT TO THE VAV BOX INLETS, AS PER SPECIFICATIONS. REUSE OF
EXISTING DUCTWORK DOES NOT EXCUSE THE HVAC CONTRACTOR FROM MEETING THE
SAME STANDARDS AS NEW DUCTWORK CONSTRUCTION.
1 2 3 4 5 6 7 8 9 10
1 2 3 4 5 6 7 8 9 10
A
B
C
D
E
F
A
B
C
D
E
F
CONSULTANT ARCHITECT/ENGINEER OF RECORD STAMP Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
Drawing Title
Approved: Project Director
Phase Project Title Project Number
Building Number
Drawing NumberLocation
Issue Date Checked Drawn
VA FORM 08-6231
FULLY SPRINKLERED
REVIEW ONLY - NOT FOR CONSTRUCTION
Bancroft Project No. VA CONTRACT NO.
BUILDING 217 KEY PLAN
MECHANICAL - EXHAUST FAN VENTILATION
DEMOLITION PLAN - ROOF
RENOVATIONS TO
BUILDING 217
EDWARD J. HINES JR. VAMC
12/06/2024 RH RBB
578-20-002
MVD401.10
100% CONSTRUCTION
DOCUMENTS
23-00936C25223C0071
N 1/16" = 1'-0"
EXHAUST FAN VENTILATION DEMOLITION PLAN - ROOF
Revisions: Date:
30% SCHEMATIC DESIGN 11/23/2023
60% DESIGN DEVELOPMENT 05/08/2024
T
T
T T
GENERAL NOTES
A. COORDINATE A MINIMUM 3 WEEKS ADVANCE NOTICE FOR ALL MECHANICAL SERVICE
OUTAGES WITH COR.
B. REMOVE ALL CLAMPS, HANGERS, SUPPORTS, ETC., ASSOCIATED WITH PIPING
REMOVAL.
C. PIPING MAY BE SHOWN OFFSET FROM ITS ACTUAL LOCATION FOR CLARITY. FIELD
VERIFY EXACT LOCATIONS. PIPING AND EQUIPMENT SHOWN ON THIS DRAWING IS
BASED ON AS-BUILT DOCUMENTATION PROVIDED BY THE VA AND A CURSORY ON SITE
REVIEW OF EXISTING CONDITIONS. IF IT IS DISCOVERED THAT ANY PIPING OR
EQUIPMENT, INDICATED TO BE DEMOLISHED, SERVES OTHER AREAS BEYOND THIS
PROJECT SCOPE, THE CONTRACTOR MUST BE IMMEDIATELY STOP DEMOLITION OF SAID
PIPING OR EQUIPMENT, NOTIFY THE COR AND ENGINEER, AND WAIT FOR FURTHER
INSTRUCTIONS.
1515.11617
K
M
L
N
O
P
Q
S
R
VAV-B-Z08
VAV-B-Z02
VAV-B-Z01
VAV-B-Z03
VAV-B-Z09B
VAV-B-Z05
(E)VAV-B-Z06
VAV-B-Z07VAV-B-Z04
4 4
SEE DRAWING
'MPD-402.2' FOR
CONTINUATION
SEE DRAWING
'MPD-402.6' FOR
CONTINUATION
(E ) H
W S
(E ) H
W R
(E) HWR
(E) HWS
(E ) H
W R
(E ) H
W S
(E ) H
W R
(E ) H
W S
(E ) H
W S
(E ) H
W R
(E) HWS
(E) HWS
(E) HWR
(E ) H
W R
(E) HWR
(E) HWS
(E) MPR
(E) MPS
(E ) H
W R
(E ) H
W R
(E ) M
PS
(E
) M
PR
(E ) M
PS
(E) MPR
(E) MPS
(E ) M
PS
(E
) M
PR
(E ) H
W S
EXISTING MECHANICAL
EQUIPMENT, DUCTWORK, ETC.
THIS AREA TO REMAIN
(E) HWR
(E) HWR
(E ) H
W R
(E ) H
W R
(E ) H
W R
ELEVATOR
1C268
ELEVATOR MACHINE
RM.
1A40
LAUNDRY
1A110
NURSING HOME
SUPERVISOR
1A105
LOUNGE
1A104
OFFICE
1A106
OFFICE
1A107
CONFERENCE & CLASS
1A109
WOMEN
1A142
MEN
1A141
RECREATION ROOM
1A108
WOMEN
1A113
MEN
1A112
H.A.C.
1A111 NOURISH. KITCHEN
1A115
STORAGE
1A108A
MECHANICAL DEMOLITION KEY NOTES
1. REMOVE ALL PIPING, VALVING, HANGERS, INSULATION, ETC. SHOWN DASHED AND CAP
AT MAIN.
2. EXISTING PIPING AND VALVING TO REMAIN. PROTECT DURING CONSTRUCTION.
3. REMOVE EXISTING THERMOSTAT INCLUDING ALL ASSOCIATED CONDUIT, WIRING,
PNEUMATIC TUBING, ETC. LOCATED ABOVE ANY ACCESSIBLE CEILING BETWEEN
THERMOSTAT AND THE UNIT IT CONTROLS. PROVIDE BLANK COVER PLATE OVER ALL
ABANDONED JUNCTION BOXES IN WALLS THAT ARE TO REMAIN.
4. REMOVE EXISTING VAV BOX AND ASSOCIATED BRANCH PIPING, VALVING, CONTROLS,
ETC.
5. EXISTING VAV BOX TO REMAIN.
6. REMOVE FINNED TUBE RADIATION ENCLOSURE, FINNED ELEMENT, AND ALL
ASSOCIATED PIPING, VALVING AND CONTROLS.
X
1 2 3 4 5 6 7 8 9 10
1 2 3 4 5 6 7 8 9 10
A
B
C
D
E
F
A
B
C
D
E
F
CONSULTANT ARCHITECT/ENGINEER OF RECORD STAMP Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
Drawing Title
Approved: Project Director
Phase Project Title Project Number
Building Number
Drawing NumberLocation
Issue Date Checked Drawn
VA FORM 08-6231
FULLY SPRINKLERED
REVIEW ONLY - NOT FOR CONSTRUCTION
Bancroft Project No. VA CONTRACT NO.
BUILDING 217 KEY PLAN
MECHANICAL - ENLARGED PIPING
DEMOLITION PLAN - PRIMARY CARE CLINIC &
ENTRANCE LOBBY
RENOVATIONS TO
BUILDING 217
EDWARD J. HINES JR. VAMC
12/06/2024 RH RBB
578-20-002
MPD402.1
100% CONSTRUCTION
DOCUMENTS
23-00936C25223C0071
N 1/8" = 1'-0"
MECHANICAL - ENLARGED PIPING DEMOLITION PLAN - PRIMARY CARE CLINIC & ENTRANCE LOBBY
Revisions: Date:
30% SCHEMATIC DESIGN 11/23/2023
60% DESIGN DEVELOPMENT 05/08/2024
A. COORDINATE A MINIMUM 3 WEEKS ADVANCE NOTICE FOR ALL MECHANICAL SERVICE
OUTAGES WITH COR.
B. REMOVE ALL CLAMPS, HANGERS, SUPPORTS, ETC., ASSOCIATED WITH PIPING
REMOVAL.
C. PIPING MAY BE SHOWN OFFSET FROM ITS ACTUAL LOCATION FOR CLARITY. FIELD
VERIFY EXACT LOCATIONS. PIPING AND EQUIPMENT SHOWN ON THIS DRAWING IS
BASED ON AS-BUILT DOCUMENTATION PROVIDED BY THE VA AND A CURSORY ON SITE
REVIEW OF EXISTING CONDITIONS. IF IT IS DISCOVERED THAT ANY PIPING OR
EQUIPMENT, INDICATED TO BE DEMOLISHED, SERVES OTHER AREAS BEYOND THIS
PROJECT SCOPE, THE CONTRACTOR MUST BE IMMEDIATELY STOP DEMOLITION OF SAID
PIPING OR EQUIPMENT, NOTIFY THE COR AND ENGINEER, AND WAIT FOR FURTHER
INSTRUCTIONS.
10.11111.1 11.212131415
K
M
L
N
VAV-C-Z03A VAV-C-Z03B
1 1
5 (E)VAV-C-Z04A5(E)VAV-C-Z01
4 4
SEE DRAWING
'MPD-402.1' FOR
CONTINUATION
SEE DRAWING 'MPD-402.7'
FOR CONTINUATION
(E) HWR
(E) HWS
(E ) H
W R
(E ) H
W S
(E ) H
W R
(E ) H
W S
(E) HWS
(E) HWR
(E) HWS
(E) HWR
(E) HWS
(E) HWR
(E) HWS
(E) HWR
(E ) H
W S
(E ) H
W R
(E ) H
W R
(E ) H
W R
(E ) H
W S
(E ) H
W R
(E) MPS (E) MPS
(E ) H
W R
(E ) H
W R
(E ) H
W S
FUTURE TR ROOM,
CONTRACTOR TO AVOID
RUNNING NEW PIPING THRU
THIS AREA
TO (E) VAV-C-Z02
EXISTING TO REMAIN
SEE DRAWING
'MPD-402.6' FOR
CONTINUATION
DINING ROOM
1A118
REHABILITATION
THERAPY ROOM
1A43
MECHANICAL DEMOLITION KEY NOTES
1. REMOVE ALL PIPING, VALVING, HANGERS, INSULATION, ETC. SHOWN DASHED AND CAP
AT MAIN.
2. EXISTING PIPING AND VALVING TO REMAIN. PROTECT DURING CONSTRUCTION.
3. REMOVE EXISTING THERMOSTAT INCLUDING ALL ASSOCIATED CONDUIT, WIRING,
PNEUMATIC TUBING, ETC. LOCATED ABOVE ANY ACCESSIBLE CEILING BETWEEN
THERMOSTAT AND THE UNIT IT CONTROLS. PROVIDE BLANK COVER PLATE OVER ALL
ABANDONED JUNCTION BOXES IN WALLS THAT ARE TO REMAIN.
4. REMOVE EXISTING VAV BOX AND ASSOCIATED BRANCH PIPING, VALVING, CONTROLS,
ETC.
5. EXISTING VAV BOX TO REMAIN.
X
1 2 3 4 5 6 7 8 9 10
1 2 3 4 5 6 7 8 9 10
A
B
C
D
E
F
A
B
C
D
E
F
CONSULTANT ARCHITECT/ENGINEER OF RECORD STAMP Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
Drawing Title
Approved: Project Director
Phase Project Title Project Number
Building Number
Drawing NumberLocation
Issue Date Checked Drawn
VA FORM 08-6231
FULLY SPRINKLERED
REVIEW ONLY - NOT FOR CONSTRUCTION
Bancroft Project No. VA CONTRACT NO.
BUILDING 217 KEY PLAN
MECHANICAL - ENLARGED PIPING
DEMOLITION PLAN - DINING ROOM 1A118
RENOVATIONS TO
BUILDING 217
EDWARD J. HINES JR. VAMC
12/06/2024 RH RBB
578-20-002
MPD402.2
100% CONSTRUCTION
DOCUMENTS
23-00936C25223C0071
N 1/4" = 1'-0"
MECHANICAL - ENLARGED PIPING DEMOLITION PLAN - DINING ROOM 1A118
Revisions: Date:
30% SCHEMATIC DESIGN 11/23/2023
60% DESIGN DEVELOPMENT 05/08/2024
GENERAL NOTES
A. COORDINATE A MINIMUM 3 WEEKS ADVANCE NOTICE FOR ALL MECHANICAL SERVICE
OUTAGES WITH COR.
B. REMOVE ALL CLAMPS, HANGERS, SUPPORTS, ETC., ASSOCIATED WITH PIPING
REMOVAL.
C. PIPING MAY BE SHOWN OFFSET FROM ITS ACTUAL LOCATION FOR CLARITY. FIELD
VERIFY EXACT LOCATIONS. PIPING AND EQUIPMENT SHOWN ON THIS DRAWING IS
BASED ON AS-BUILT DOCUMENTATION PROVIDED BY THE VA AND A CURSORY ON SITE
REVIEW OF EXISTING CONDITIONS. IF IT IS DISCOVERED THAT ANY PIPING OR
EQUIPMENT, INDICATED TO BE DEMOLISHED, SERVES OTHER AREAS BEYOND THIS
PROJECT SCOPE, THE CONTRACTOR MUST BE IMMEDIATELY STOP DEMOLITION OF SAID
PIPING OR EQUIPMENT, NOTIFY THE COR AND ENGINEER, AND WAIT FOR FURTHER
INSTRUCTIONS.
10.11111.1 11.212131415
K
M
L
N
VAV-C-Z02
VAV-C-Z06
(E)VAV-C-Z482(E)VAV-C-Z501
(E) HWS
(E) HWR
(E) HWS
(E) HWR
(E) HWS
(E) HWR
(E) HWS
(E) HWR
(E) HWR
(E) HWS
(E ) H
W R
(E ) H
W S
(E ) H
W S
(E ) H
W R
FUTURE TR ROOM,
CONTRACTOR TO AVOID
RUNNING NEW PIPING THRU
THIS AREA
(E ) H
W R
(E ) H
W R
(E ) H
W R
(E ) H
W S
(E ) H
W R
(E ) H
W S
(E ) H
W R
(E ) H
W R
(E ) H
W R
(E ) H
W S
(E ) H
W R
(E ) H
W S
DINING
2A26
MECHANICAL DEMOLITION KEY NOTES
1. REMOVE ALL PIPING, VALVING, HANGERS, INSULATION, ETC. SHOWN DASHED AND CAP
AT MAIN.
2. EXISTING PIPING AND VALVING TO REMAIN.
3. REMOVE EXISTING THERMOSTAT INCLUDING ALL ASSOCIATED CONDUIT, WIRING,
PNEUMATIC TUBING, ETC. LOCATED ABOVE ANY ACCESSIBLE CEILING BETWEEN
THERMOSTAT AND THE UNIT IT CONTROLS. PROVIDE BLANK COVER PLATE OVER ALL
ABANDONED JUNCTION BOXES IN WALLS THAT ARE TO REMAIN.
4. REMOVE EXISTING VAV BOX AND ASSOCIATED BRANCH PIPING, VALVING, CONTROLS,
ETC.
5. EXISTING VAV BOX OR FINNED TUBE RADIATION HEAT ELEMENT TO REMAIN.
X
1 2 3 4 5 6 7 8 9 10
1 2 3 4 5 6 7 8 9 10
A
B
C
D
E
F
A
B
C
D
E
F
CONSULTANT ARCHITECT/ENGINEER OF RECORD STAMP Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
Drawing Title
Approved: Project Director
Phase Project Title Project Number
Building Number
Drawing NumberLocation
Issue Date Checked Drawn
VA FORM 08-6231
FULLY SPRINKLERED
REVIEW ONLY - NOT FOR CONSTRUCTION
Bancroft Project No. VA CONTRACT NO.
BUILDING 217 KEY PLAN
MECHANICAL - ENLARGED PIPING
DEMOLITION PLAN - DINING ROOM 2A26
RENOVATIONS TO
BUILDING 217
EDWARD J. HINES JR. VAMC
12/06/2024 RH RBB
578-20-002
MPD402.3
100% CONSTRUCTION
DOCUMENTS
23-00936C25223C0071
N 1/4" = 1'-0"
MECHANICAL - ENLARGED PIPING DEMOLITION PLAN - DINING ROOM 2A26
Revisions: Date:
30% SCHEMATIC DESIGN 11/23/2023
60% DESIGN DEVELOPMENT 05/08/2024
GENERAL NOTES
A. COORDINATE A MINIMUM 3 WEEKS ADVANCE NOTICE FOR ALL MECHANICAL SERVICE
OUTAGES WITH COR.
B. REMOVE ALL CLAMPS,…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .