This document outlines a federal contract opportunity for replacing obsolete fire alarm devices at the Jesse Brown VA Medical Center in Chicago, Illinois. The contractor shall provide all tools, materials, components, labor and supervision to construct and remodel a fully functional fire alarm system and exit signs in accordance with design documents. Work must be completed within 581 calendar days of receiving a notice to proceed and include a one-year parts and labor warranty. Competition is restricted to Service-Disabled-Veteran-Owned-Small-Businesses. The solicitation will be posted on November 25, 2020 with bids due by January 14, 2021. The project magnitude ranges from $2,000,000 to $5,000,000. Offerors must represent that they are an eligible SDVOSB, small business, and verified in the Vendor Information Pages database prior to award.
View the file
Other files for this federal contract opportunity
Show all 33
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. CHANGED: Section 28 31 00: 1.2 SCOPE A. A fully addressable fire alarm system shall be designed and installed in accordance with the specifications and drawings. Provide the devices as shown in plan.
B. Remove all old equipment and those conduits, wire molding, boxes and wiring that are readily accessible. Existing exposed conduit and conduit between drop-in tiles and the floor slab above is considered accessible. All fire alarm panels, initiation and indication devices shall be new. Except as outlined in Section 28 31 00 1.2C, D and E.
1. Conduit and boxes located in wall spaces shall be cut off inside the ceiling space, marked and left in place.
2. In locations where existing wall mounted devices have been removed the existing backbox shall be covered by a blank stainless-steel cover plate.
3. Where duct detectors have been removed the duct shall be repaired with screwed-on sheet metal, sealant and insulation.
4. After removal of existing wall mounted devices the old box shall be covered by a blank brushed stainless-steel cover plate.
5. Furnish and install new ceiling tiles where existing equipment has been removed as a result of this work.