Attach IV - RFI - IMS.doc

DOC document 55 KB Posted

Attached to
Z1DA--Upgrade Campus Electrical Systems. Project No. 610A4-23-101.
Solicitation number
36C25026B0006_1
Issued by

About this file

This is a Request for Information (RFI) document issued by the Department of Veterans Affairs, Network 10 Contracting Office for solicitation 36C25026B0006, Project Number 610A4-23-101, related to an upgrade of the campus electrical system at VA Northern Indiana Healthcare System in Fort Wayne, Indiana.

The RFI addresses three contractor questions regarding the design and construction methodology for the generator exhaust system and related components. Question 1 clarifies that flanged exhaust pipe connections are acceptable, with either an engineered pre-fabricated factory-built system or field-built black steel pipe per ASTM A-53 standard with welded fittings permissible; both options require submitted shop drawings showing calculations for supports, expansion joints, and wall guides per specification 26 32 13. Question 2 explains that welded support brackets are intended to attach wall guides (not the exhaust pipe itself) to allow the exhaust pipe to float during thermal expansion and contraction, with the contractor responsible for providing wall guides whether attached to steel structure or brick facade. Question 3 clarifies responsibility for muffler and expansion joint procurement and installation, noting that generator manufacturers typically provide mufflers and flexible connectors while mechanical contractors provide downstream components including expansion joints; the pre-engineered factory-built system allows the factory to provide all expansion bellows, while field-fabricated systems require contractor-submitted calculations, product cutsheets, installation details, and insulation specifications. The government response was posted as an attachment to Amendment No. 3 of the solicitation on January 22, 2026.

View the file

Other files

File Type Posted
Attach I - RFI CM Buck 3.pdf PDF
36C25026B0006 0010.pdf PDF
Attach I - VAAR 852.236-92.pdf PDF
36C25026B0006 0009.pdf PDF
36C25026B0006 0008.pdf PDF
Attach IV - Revised Bid Schedule 2.24.2026.pdf PDF
Attach I - Addendum 1 - Summary.docx DOCX document
Attach III - Addendum 1 - Drawings.zip ZIP file
Attach V - RFI CMBuck Rd. 2 - Revised.pdf PDF
Attach II - Addendum 1 - Specs.zip ZIP file
36C25026B0006 0007.pdf PDF
36C25026B0006 0006.pdf PDF
36C25026B0006 0005.pdf PDF
Attach II - Bid Schedule Revised 2.11.2026.pdf PDF
Attach I - RFI Response CMBuck 2.pdf PDF
36C25026B0006 0004.pdf PDF
Attach I - RFI - CMBuck.doc DOC document
Attach V - RFI - Powergen.pdf PDF
Attach VII - RFI Valiant.docx DOCX document
Attach II - RFI - Cornerstone.doc DOC document
36C25026B0006 0003.pdf PDF
Attach III - RFI - Geotech.pdf PDF
Attach VI - RFI Richards.docx DOCX document
36C25026B0006 0002.pdf PDF
Attach IV - Fort Wayne Generator Information.pdf PDF
Attach VIII - Fort Wayne PA information.pdf PDF
Attach I - Wage Determination 1.30.2026.txt TXT text file
Attach III - Notice to Bidders on Bid Depth for Piles.docx DOCX document
Attach VI - 3W Data Closet Example.pdf PDF
Attach VII - IT standards ver 3.0 21 Aug 20.pdf PDF
Attach II - Final Geotechnical Report - 610A4-23-101.pdf PDF
Attach V - Fort Wayne ATS information.pdf PDF
Attach II - Site Visit Notes.pdf PDF
Attach I - Sign in Sheet.pdf PDF
36C25026B0006 0001.pdf PDF
Attach VII - Specs Combined 610A4-23-101.pdf PDF
Attach IX - Wage Determination - Allen County 12.5.25.txt TXT text file
Attach X - VAAR 852.219-75 - 610A4-23-101.pdf PDF
Attach II - Appendix A.pdf PDF
Attach III - Appendix B.pdf PDF
Attach I - SOW - 610A4-23-101.pdf PDF
Attach IV - Appendix C.pdf PDF
Attach VI - Drawings Combined 610A4-23-101.pdf PDF
IFB 36C25026B0006_1.pdf PDF
Attach V - Appendix D.pdf PDF
Attach VIII - VHA Directive 1192-01.pdf PDF
Attach XI - RFI 610A4-23-101.doc DOC document
Show all 47

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR INFORMATION (RFI)

36C25026B0006

PROJECT NUMBER:
610A4-23-101
Please ensure that before submitting questions or requests for clarification that you thoroughly read the solicitation, specifications, drawings and other pertinent documents. When submitting questions on this project the Government requires contractors to specifically identify the specification and/or solicitation section(s) or drawing number(s) in reference to the question or request for clarification submitted. No question or request for clarification will be answered by the Government unless the above requirements are met. Failure to comply may prevent the Government from responding in a timely manner.
PROJECT TITLE:
Upgrade Campus Electrical System
PROJECT LOCATION:
VA Northern Indiana Healthcare System

2121 Lake Ave

Fort Wayne IN 46805-5100

Contractor Name Contact Info (Phone & Address)

TO: Brian Rosciszewski, Contract Specialist Department of Veterans Affairs Network 10 Contracting Office

Brian.Rosciszewski@VA.gov INFORMATION NEEDED: Write each in the form of a question. Use one document for all questions. Specify any referenced specs/drawings. Submit all questions on one document only to Brian.Rosciszewski@VA.gov. Subject of the email must be: “RFI – {Solicitation #} – Firm Name” 1.Drawing M300- Can we flange the exhaust pipe that goes up side o building?

Our design shows an engineered pre-fabricated/factory-built system which does utilize the flange-to-flange inner pipe connection. The method of field-built black steel pipe, ASTM A-53 standard weight with welded fittings is also acceptable. For either option (engineered pre-fab or field-built black steel), shop drawings shall be submitted showing calculations for supports, expansion joints, and wall guides per specification 26 32 13 Engine Generator. In summary, flange connecting the exhaust pipe is acceptable.

2. Drawing SE507- Detail 2 show support bracket. I the intent to weld out the exhaust pipe to these and is the general to provide the 9 brackets that are below the steel structure?

Detail 2 is showing the welding of the horizontal angles to the vertical angles. The intent is to attach the wall guides (not the exhaust pipe) to the steel backet. The wall guides then allow the exhaust pipe to “float” up and down during expansion and contraction. The only item “supporting” the vertical stack is at the bottom of the stack (support plate). Contractor is expected to provide the wall guides whether they are attached to the steel structure or the 9 that are attached through the brick facade.

3. Ref generator- Should the muffler and expansion joint be provided by the generator manufacturer and mechanical contractor install?

Generator manufacturer usually provides the muffler and flexible connector before the muffler. The mechanical contractor usually provides everything downstream of the muffler including the expansion joints. But this is a GC project and it is up to the GC as means and methods of how equipment is purchased. For the pre-engineered factory-built system, the design allows the factory to provide all expansion bellows needed throughout the system. For the field-fabricated system, it is even more critical that the contractor provide calculations showing where expansion joints are needed and include cutsheets for the actual expansion product, details on the installation, insulation details, etc.

Government Response: Posted as attachment to amendment no. three of solicitation.

REPLY FROM: CG / FFE

DATE: 1/22/2026

ATTACHMENTS:

COPY TO:

IMS Contracting

Tim Sayers- Escanaba MI

906 789 9021