These are site visit notes for Solicitation 36C25026B0006, Amendment 0001, documenting key details from a project site visit. The notes outline critical timelines and project specifications, including an RFI due date of 1/20/26 and a bid opening date of 2/12/26, both subject to potential amendments. The document highlights several adjacent ongoing and planned construction projects at the site, such as basement renovation, 3W renovation, and a Specialty Care building construction, with completion dates ranging from March 2026 to March 2027. Additional important site visit details include requirements for two-week notices for utility outages, mandatory recording and correction of firewall penetrations, and designation of the south side of building 1 as a likely lay down and connex storage area. All communication regarding the solicitation is to be directed to Brian Rosciszewski via RFI, and vendors are instructed to include bid deducts in their bid schedule.
View the file
Other files
Show all 47
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attach II – 1/7/26 Site Visit Notes – Solicitation 36C25026B0006 Amd. 0001
Additional comments made during the site visit:
1. No project specific questions shall be answered today
2. 1/20/26 RFI due date (subject to amendment)
3. 2/12/26 bid opening (subject to amendment)
4. All communication goes to Brian Rosciszewski as an RFI
5. Vendors should include bid deducts per bid schedule
6. Adjacent projects
a. Renovate Basement (in progress) completion scheduled Dec
b. Renovate 3W (in progress) completion scheduled Mar 2026
c. Build Specialty care (in progress) completion scheduled Mar 2027
d. Replace Boilers (not awarded) start scheduled in FY27
7. South side of building 1 will most likely be lay down & connex storage area.
a. Most existing connexes will be removed by start of this project
b. Exact location will be determined with COR
8. All utility outages require a two-week notice
9. All fire wall penetrations must be recorded and corrected
10. The Specialty Care Building switch gear has not been installed in building 16 at this time, but will be by time of this award.
BDR. 1/7/26.