This is a Request for Information (RFI) with government responses regarding Solicitation 36C25026B0006, Project 610A4-23-101, for an Upgrade Campus Electrical System at VA Northern Indiana Healthcare System in Fort Wayne, Indiana. The RFI document contains seven contractor questions and corresponding government answers addressing technical specifications and design clarifications for the electrical upgrade project.
Key clarifications provided by the government include: (1) new generator exhaust stacks require lightning protection per drawing SE507; (2) demo and rework in existing buildings may occur during regular hours, but cutover work must be bid as after-hours with coordination required with the Contracting Officer's Representative regarding noise and infection control risk assessment (ICRA) due to the hospital setting; (3) concrete encased Schedule 40 PVC is specified for underground ductbanks with rigid turn-ups, with no EP108 drawing referenced; (4) contractors should refer to distribution schedules for feeder sizes rather than requesting feeder tags on drawing E211; (5) the 96-hour onsite fuel requirement for temporary generators cannot be modified with external refueling services or external fuel tanks; (6) temporary generators must have critical grade sound attenuated housing; and (7) there is no nurse call system or new mass notification system on this project, with speakers tied into existing circuits per Plan Note 4 on Sheet T201. The RFI was submitted by Cornerstone Contracting Inc and responded to by Matt Graham of HEAPY on January 19, 2026.
View the file
Other files
Show all 47
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR INFORMATION (RFI)
36C25026B0006
| PROJECT NUMBER: |
| 610A4-23-101 |
| Please ensure that before submitting questions or requests for clarification that you thoroughly read the solicitation, specifications, drawings and other pertinent documents. When submitting questions on this project the Government requires contractors to specifically identify the specification and/or solicitation section(s) or drawing number(s) in reference to the question or request for clarification submitted. No question or request for clarification will be answered by the Government unless the above requirements are met. Failure to comply may prevent the Government from responding in a timely manner. |
| PROJECT TITLE: |
| Upgrade Campus Electrical System |
| PROJECT LOCATION: |
| VA Northern Indiana Healthcare System |
2121 Lake Ave
Fort Wayne IN 46805-5100
Contractor Name Contact Info (Phone & Address)
TO: Brian Rosciszewski, Contract Specialist Department of Veterans Affairs Network 10 Contracting Office
Brian.Rosciszewski@VA.gov INFORMATION NEEDED: Write each in the form of a question. Use one document for all questions. Specify any referenced specs/drawings. Submit all questions on one document only to Brian.Rosciszewski@VA.gov. Subject of the email must be: “RFI – {Solicitation #} – Firm Name”
1. Does the new generator exhaust stacks shown on SE507 require lightning protection?
2. Can the demo and rework in the existing building be done during regular hours?
3. Is PVC schedule 40 allowed for under slab duct banks with GRC/RMC stub ups, drawing EP108?
4. Drawing E211 EM one line shows feeders without feeder tags. Can the VA please provide feeder tags?
5. In temporary power plan, rental generator requirements shown as 96-hour sub base tank. Under normal load, industry standard size is rated for 24 hours. Can refueling service be used or an external fuel tank be supplied?
6. What is the sound rating for the two pad-mounted temporary generators shown on ES100.1?
7. Is there a preferred manufacturer or basis of design for the Nurse Call/PA & Mass Notification Systems (275116)?
Government Response: RFI’s will be answered by amendment(s) issued to SAM.gov or via email.
1. Yes.
2. Yes, however cutover work needs to be bid as after-hours. Contractor will need to coordinate with COR regarding noise and ICRA as the work site is a hospital. - VA
3. Concrete encased Schedule 40 is what is specified for underground ductbanks with rigid turn ups. There is no sheet EP108.
4. No, refer to distribution schedules for feeder sizes. If some are still found to be missing, please be specific.
5. No. VA design criteria requires 96 hours of onsite fuel.
6. Critical grade sound attenuated housing.
7. There is no nurse call on this project. Plan note 4, Sheet T201 has speakers tied into the existing speaker circuit. There is no new mass notification system required for this project. Note 4 on T201 shown in a corridor junction box.
Matt Graham, HEAPY, 2/3/26
| REPLY FROM: |
| DATE: 01/19/2026 |
ATTACHMENTS:
COPY TO:
Cornerstone Contracting Inc
500 W Algonquin Rd
Mount Prospect, IL 60056
847-593-0001
File details come from the government source that posted it. Updated .