Questions and Answers 2 of 2 - Pre-bid RFIs.xlsx
XLSX spreadsheet 93 KB Posted
- Solicitation number
- 36C24921R0086
About this file
This is a presolicitation notice for a construction project to correct various mechanical system deficiencies at the Lexington VA Medical Center in Troy Bowling Division. The project involves general construction and alterations, with mechanical work including replacing security camera systems. The estimate range is $1-3 million. The requirement will use LPTA source selection and be set aside for SDVOSBs. The solicitation will be released on or around June 12, 2020. Questions must be submitted in writing by the specified date. Only SDVOSBs verified in the CVE database and with active SAM registration will be considered. The awarded contractor must enroll in VETS4212 and be determined responsible per FAR Part 9. The agency is the Department of Veterans Affairs VHA VISN 9.
View the file
Other files
Show 40 more
Latest 50 of 55 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Comment-Response Log Project Name: 596A4-19-102 Correct Varions Mechanical System Deficiencies
| Pre-bid RFI's | 31-Dec-99 | |
| 23-Jun-21 |
| Cal | REQUIRED | Calculated | ||||
| Item | ||||||
| # | Design Submission | Question | Entry | |||
| Date | Target | |||||
| Date | Finish | |||||
| Date | Name of AE Responder | AE Response | Status |
CLOSED /
| OPEN | Days Open | ||||||
| 1 | Page 7 of 66 of the solicitation states that the Offeror’s Technical proposal shall be no more than 50 pages total. Please confirm that if the Contractor includes a proposal binder cover, cover letter, table of contents, acronym list, and page dividers in its technical proposal, that these items will not count against the 50-page limit. | 10-Jun-21 | VA | The binder cover, cover letter, table of contents, acronym list and page dividers will not count against the page limit stated in the solicitation. | CLOSED | 10 | |
| 2 | On page 18 of 66, the solicitation shows the Representations and Certifications. On page 7 of 66 of the solicitation, it states the offeror’s price proposal shall be no more than 25 pages inclusive of the bid bonds required….and the “price schedule” attached worksheet shall be considered as 20 pages. Please note the following: |
Contractor Binder Cover and Cover Letter Identifying the Price Volume (2 pages) Complete Representations and Certifications (4 pages) Complete 52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment (OCT 2020) (3 pages) Complete 52.209-7 Information Regarding Responsibility Matters (OCT 2018) (1 page) Complete SF1442 (2 pages) Our Bid Bond is (6 pages) and can’t be reduced per our bonding company Complete Pre-award Contractor Safety and Environmental Record Evaluation Form (1 page) Price Schedule (20 pages) Breakout of General Conditions (1 page)
| If the contractor submits in its Price Volume, these bulleted items as listed above, the total price volume will exceed 39 pages. Will the Government please wave this 25-page limit for the price volume and increase the price volume page limit to 45 pages, there is no way to provide the requested information within this 25-page limit. | 10-Jun-21 | VA | No | CLOSED | 10 | ||||||
| 3 | In Section 13 of the SF1442, the section says to submit the proposal in original and 1 copies. Please confirm that our price and technical proposal can be submitted via email, and if the contractor can submit the original hard copy of bid bonds before the proposal due date/time in block 13 and to the contract specialist at the address in block 8. | 10-Jun-21 | VA | Yes, proposals should be submitted electronically via email to Scheronica.cochran@va.gov. The hard copy of the bid bonds can be submitted before the proposal due date/time. | CLOSED | 10 | |||||
| 4 | Phasing plan indicates there are 3 phases (1. Install new hydronic piping throughout the scope of the work. 2. Install new VAV boxes throughout the scope of work and 3. Remove old hydronic piping after connection and activation of new piping) and 9 sub phases (A-1) | 10-Jun-21 | 15-Jun-21 | RCM | Correct. | CLOSED | 4 | ||||
| 5 | Please confirm that the PPQ don’t count against the 50-page limit allowed for the Technical proposal. | 10-Jun-21 | VA | No, submit PPQs separately via email to scheronica.cochran@va.gov. | CLOSED | 10 | |||||
| 6 | Will any phases (and sub-phases) be allowed to run concurrent with each other or must they run sequentially? | 10-Jun-21 | 15-Jun-21 | RCM | Phases can run concurrent however, Phase 2 work can procede only wher Phase 1 work is completed. For instance where Phase 1 piping on a floor is connected to a riser and made active, then Phase 2 work can commence for all VAV boxes that show connected to that piping. | CLOSED | 4 | ||||
| 7 | On drawing A101 Phasing Notes it states where indicated, all work to be done in single phase. SPS, Pharmacy and Radiology are to have new piping installed, and old piping removed in one phase. Infection control barriers and work are not to stop functional activities of these spaces unless coordinated with the COR and the department heads. Where is that note applicable ? | ||||||||||
| 10-Jun-21 | 15-Jun-21 | RCM/TJS | Work in these areas was removed from the scope by the VA. Disregard this note. | CLOSED | 4 | ||||||
| 8 | How much notification will be required for the VA to coordinate with each department? | 10-Jun-21 | 15-Jun-21 | RCM | 14 days notice minimum or as determined by the COR. | CLOSED | 4 | ||||
| 9 | Please provide priority list for the phasing/sub phasing. | 10-Jun-21 | 16-Jun-21 | TJS | Priority of the subphasing is to be determined by the GC working with the COR to best accomodate the construction schedule and primary phasing | CLOSED | 5 | ||||
| 10 | On drawing GI102 on the sheet notes Note E- states Infection control barriers are to be type “A” hard wall construction with type “D” barriers used to create antechambers. Work shift dependent barriers that are to be installed for only a few hours at a time are to be type “B” barriers sealed to the floor and ceiling assembly. Please provide these details. Found barrier type “R”, “N”, “T” & “P” details on drawing GI101. | 10-Jun-21 | 16-Jun-21 | TJS | These "A" and "D" references are typos. Note "E" on GI sheets 102 thorugh 113 should have read, "INFECTION CONTROL BARRIERS ARE TO BE "R" HARD WALL CONSTRUCTION WITH TYPE "P" BARRIERS USED TO CREATE ANTECHAMBERS. WORK SHIFT DEPENDENT BARRIERS THAT ARE TO BE INSTALLED FOR ONLY A FEW HOURS AT A TIME ARE TO BE TYPE "N" BARRIERS SEALED TO THE FLOOR AND CEILING ASSEMBLY." However, in lieu of "constructed hard barriers" types "R", "N", and "T", a panelized wall system terminating and sealing at the ceiling plane can be substitued. Systems can be, or be similar to, Starc Systems panels. Systems must be approved by the COR prior to construction. On type "R" and "T" panels, a plastic sheet barrier needs to be used above the ceiling to separate the area of work from the occupied area. This barrier above the ceiling will need to be sealed to the panelized wall system and the structure above. | CLOSED | 5 | ||||
| 11 | On drawing GI102 on the sheet notes - Note F – states where indicted all work is to be done in a single phase. Does this mean in a single shift? please clarify. | 10-Jun-21 | 16-Jun-21 | TJS | The work in locations to be done in a single phase means that phases 1, 2, and 3 will be performed at one time - removal of piping, removal of equipment & ductwork, and reinstallation of equipment & ductwork and piping will be performed while those infection control barriers are present. This may occur over several work shifts. | CLOSED | 5 | ||||
| 12 | On the GI drawings (Infection Control) it is indicated in many locations that type “R” barrier is adjacent to type “N” barrier, may type “R” barriers be replaced with type “N”? | 10-Jun-21 | 16-Jun-21 | TJS | Type "N" barriers can be used, however, for type "R" and "T", a sheet barrier above the ceiling needs to be installed to create a separation in the celing plenum space between the area of work and the occupied space. In addition, Type "R", "N", and "T" barriers can be substitued with a panelized wall system similar to Starc Systems panels. | CLOSED | 5 | ||||
| 13 | Please provide Pre-tab report. | 10-Jun-21 | 15-Jun-21 | RCM | This is a requirement of the Contractor and shall be completed prior to demolition. | CLOSED | 4 | ||||
| 14 | On GI 102 detail 9 – First Floor D164 IT Equip Rm does not indicate which phase, please provide | 10-Jun-21 | 16-Jun-21 | TJS | This should be PHASE 2 | CLOSED | 5 | ||||
| 15 | On GI 102 detail 8 – is titled “First Floor D137 Supply Rm Phase 2” but shows not work in D137 but in D139, please confirm this is correct. | 10-Jun-21 | 16-Jun-21 | TJS | This is a typo. The title for detail 8, sheet GI102 should read, "FIRST FLOOR - D139 SUPPLY ROOM - PHASE 2" | CLOSED | 5 | ||||
| 16 | On GI 103 detail 1 – on the left side of the detail there is a type “N” barrier shown across a hallway on the outside of the containment, with a keynote 2, confirm that this barrier is in the correct location. | 10-Jun-21 | 16-Jun-21 | TJS | This barrier should not be present. Please disregard the type "N" barrier going across the corridor on the detail mentioned. | CLOSED | 5 | ||||
| 17 | On GI 107 there is not a subphase I indicated, please confirm this is correct. | 10-Jun-21 | 16-Jun-21 | TJS | Correct. Third Floor, North/South, Phase 2 does not have a Subphse "I". The legend on sheet A-104 does show a Subphase "I" but it is not used this sheet or phase. | CLOSED | 5 | ||||
| 18 | On GI 108 detail 9 does not indicate a subphase, please confirm this is correct | 10-Jun-21 | 16-Jun-21 | TJS | This is a typo. The title for detail 9, sheet GI108 should read, "FOURTH FLOOR WEST ICRA PLAN - SUBPHASE I - PHASE 1 AND 3" | CLOSED | 5 | ||||
| 19 | On GI 111 there is not a subphase I indicated, please confirm this is correct. | 10-Jun-21 | 16-Jun-21 | TJS | Correct. Fourth Floor North/South, Phase 2 does not have a Subphase "I". The legend on sheet A-107 does show a Subphase "I" but it is not used this sheet or phase. | CLOSED | 5 | ||||
| 20 | On MD 103, room A413 appears to have demo work but is also in the shaded area (which states shaded area not in scope), please confirm scope. Please provide infection control and phasing plan. | 10-Jun-21 | 15-Jun-21 | RCM/TJS | Demolition work for Room A413 is shown on MD404 and is part of the Contract. Expand scope of infection control for room A415 to include this space during the appropriate subphase. | CLOSED | 4 | ||||
| 21 | On MD 103 room A458A appears to have demo work but is also in the shades area (which states shaded area not in scope), please confirm scope. Please provide infection control and phasing plan | 10-Jun-21 | 15-Jun-21 | RCM/TJS | Demolition work for Room A458A is shown on MD404 and is part of the Contract. Provide type N infection control barrier or approved equivilant at this location. Provide filtration for negative pressure, access door, sticky mats. | CLOSED | 4 | ||||
| 22 | On MD 402 it indicates there are various rooms on the second floor that will have demolition. Please provide the following for these rooms; Infection control plan, architectural floor plan & phasing plan | 10-Jun-21 | 17-Jun-21 | TJS | Will provide a plan that shows the area of work in this wing. | CLOSED | 6 | ||||
| 23 | On MD 403 it indicates rooms D314 & CU333 on the third floor will have demolition. Please provide the following for these rooms; Infection control plan, architectural floor plan & phasing plan | 10-Jun-21 | 17-Jun-21 | TJS | Will provide a plan that shows the area of work in this wing. | CLOSED | 6 | ||||
| 24 | On MD 404 it indicates rooms D440 & C411 on the fourth floor will have demolition. Please provide the following for these rooms; Infection control plan, architectural floor plan & phasing plan. | 10-Jun-21 | 17-Jun-21 | TJS | Will provide a plan that shows the area of work in this wing. | CLOSED | 6 | ||||
| 25 | On MD 405 it indicates rooms C519 & C580 on the fifth floor will have demolition. Please provide the following for these rooms; Infection control plan, architectural floor plan & phasing plan. | 10-Jun-21 | 17-Jun-21 | TJS | Will provide a plan that shows the area of work in this wing. | CLOSED | 6 | ||||
| 26 | On MD 406 it indicates rooms A616, A627 & A638C will have demolition. Please provide the following for these rooms; Infection control plan, architectural floor plan & phasing plan. | 10-Jun-21 | 17-Jun-21 | TJS | Will provide a plan that shows the area of work in this wing. | CLOSED | 6 | ||||
| 27 | Due to portion of the corridor ceiling to be removed inside of the infection control areas please provide existing reflective ceiling plans, so ceiling demolition/reinstallation can be quantified. | 10-Jun-21 | 20-Jun-21 | TJS | See response to item 28 below | CLOSED | 9 | ||||
| 28 | Provide reflective ceiling plans indicating light fixtures, fire alarm devices, nurse call, speakers, etc. that will need to be removed and reinstalled | 10-Jun-21 | 11-Jun-21 | DS | It is the contractor's responsibility to a) identify the affected ceiling tiles to be removed for demolition, b) disconnect the affected light fixtures, fire alarm devices, nurse call, speakers, etc, c) store them safe from damage, d) as ceiling tiles are reinstalled, reconnect them, e) test them in the ceiling to confirm they are functional again. | CLOSED | 2 | ||||
| 29 | Provide structural steel details and specifications as required for the new exhaust fans on the roof. | 10-Jun-21 | 15-Jun-21 | RCM | Provide 3x3x 1/4" support angle where there is no structural member as shown on M-501, Detail 11. | CLOSED | 4 | ||||
| 30 | Provide confirmation that there are three or four EF? EF-13, EF-14, EF-52 and EF-53 are shown on MH 501. There are no details provided for EF-53 or included in the mechanical schedules. | 10-Jun-21 | 17-Jun-21 | EF-53 is existing to remain and is not part of this project. | CLOSED | 6 | |||||
| 31 | Since this is primarily an HVAC/ Mechanical project can the NAICs code be changed to 238220? | 10-Jun-21 | VA | No, the NAICS will not change. | CLOSED | 10 | |||||
| 32 | Can the site superintendent also serve as the quality control manager and site safety officer? | 10-Jun-21 | 21-Jun-21 | VA | Yes. | CLOSED | 8 | ||||
| 33 | Can HEPA carts be utilized instead of traditional ICRA containments? | 10-Jun-21 | 21-Jun-21 | VA | Yes. | CLOSED | 8 | ||||
| 34 | What work will have to conducted at nights or weekends? | 10-Jun-21 | 15-Jun-21 | RCM | See Phasing plans and Notes on drawings A-101 to A-108. "All Work to be performed during Off Peak hours." | CLOSED | 4 | ||||
| 35 | Who has the current roof warranty on the areas where the roofing work is required? | 10-Jun-21 | 21-Jun-21 | VA | VA does. | CLOSED | 8 | ||||
| 36 | Will the VA be providing a commissioning agent | 10-Jun-21 | 21-Jun-21 | VA | Yes. We have a third party Cx Contract. | CLOSED | 8 | ||||
| 37 | The Phasing Plans shown on sheets “A-architectural”, such as A-103 denote Phases 1, 2 and 3, with 9 additional subphases for each of the 3 phases. The notes for Phases 1, 2 and 3 state that work shall be performed “throughout entire scope of work”. For example: Phase 1 Install new hydronic lines. Is the intent of the phasing plan for all hydronic piping to be installed in all subphases (work areas) on each floor, before moving on to Phase 2 Replace VAV’s? And all VAV’s in all subphases must be replaced before moving on to Phase 3 Remove all existing hydronic piping? | 10-Jun-21 | 15-Jun-21 | RCM | YES, All Phase 1 work connected to the same pipe riser should be complete before moving to Phase 2 or 3 work for VAV boxes connected to this riser. There are more than one pipe risers serving each floor. | CLOSED | 4 | ||||
| 38 | The layout of the ICRA barriers and the areas of work will not allow the negative air machines to be vented outside the building. Please provide the acceptable alternative negative air venting procedure (i.e. venting heap scrubbed air outside the ICRA barrier). | 10-Jun-21 | 15-Jun-21 | RCM | Contact the VA COR to determine a nearby exhaust duct to connect the negative air machine discharge. | CLOSED | 4 | ||||
| 39 | When the ICRA plans are crossed referenced with the Phasing Plans and the Mechanical Plans, it appears there is work outside of the ICRA barriers in many of the subphases. Please How is the work outside of the ICRA barriers to be accomplished without compromising the adjacent areas? | 10-Jun-21 | 16-Jun-21 | TJS | Use of type "P" barriers erected temporarily for small portions of work outside of the ICRA barriers is permitted. | CLOSED | 5 | ||||
| 40 | Please provide a drawing overlay showing all ICRA and the phasing plans, together in their entirety, for each wing rather than broken into small areas. | 10-Jun-21 | 17-Jun-21 | TJS | We will not be providing coordination style drawings at this time. | CLOSED | 6 | ||||
| 41 | Please How is the work outside of the ICRA barriers to be accomplished without compromising the adjacent areas? | 10-Jun-21 | 16-Jun-21 | TJS | Use of type "P" barriers erected temporarily for small portions of work outside of the ICRA barriers is permitted. | CLOSED | 5 | ||||
| 42 | Is it necessary for the ICRA barrier framing to be 16 ga stud? | 10-Jun-21 | 16-Jun-21 | TJS | No, it can be a lighter guage metal. | CLOSED | 5 | ||||
| 43 | After a detailed evaluation of the ICRA plans, Phasing and Sub-phasing plans and the SOW to be performed in each area, it does not appear that the barriers can be installed in the method designed and allow the work to progress within the time allowed. It appears the ICRA barriers in the corridors, as designed, will require much work to the ceilings in the corridors. For example, the Type R ICRA barrier, which is most of the barriers, shows the wall extending to the deck above the finished ceiling and the ceiling will need to be reinstalled with wall molding to each side of the ICRA barrier. Just to install the barrier, the lights in the corridor will need to be relocated, any fire alarm devices, WAPS, etc. relocated, temporary lights hung inside the barrier, framing for the barrier, cutting, hanging and taping/mudding of the drywall, and sealing of all penetrations through the barrier. With the barriers removed, the lights and other devices will need to be relocated back to original locations, and the ceiling grid, in large part, will likely need to be replaced. The act of modifying ceiling, installing barriers, removing barriers and fixing the ceilings will definitely take much more time the work for each phase within the barriers, will create significantly more dust and debris, and will impact the patient and staff to a greater degree than that of the work associated with installing new piping, replacing VAV’s, and removing old piping. The SOW can easily be done by closing off small sections of the corridor or rooms with plastic barriers or Starc Panels (still following the phasing plans 1, 2, and 3) establishing negative air, removing only a few ceiling tiles at a time, performing the work, replacing the ceiling tile, and removing the plastic barriers before the start of each shift. The layout of each wing will allow egress to be maintained at all times even when the plastic barriers are up on nights and weekends. This will allow the work to be performed faster and more efficiently (cheaper to the GOV), with less disruption to the patients and staff, and with less dust and debris. Overall more efficient and less invasive. If the currently ICRA barriers and sub-phasing plan is attempted as designed, it is likely to not be Overall more efficient and less invasive. If the currently ICRA barriers and sub-phasing plan is attempted as designed, it is likely to not be constructable within the time constraints of the project and to cost as much or more as the mechanical SOW itself. Please advise if this alternate work plan is acceptable. | 10-Jun-21 | 16-Jun-21 | TJS | In lieu of "constructed hard barriers" types "R", "N", and "T", a panelized wall system terminating and sealing at the ceiling plane can be substitued. Systems can be, or be similar to, Starc Systems panels. Systems must be approved by the COR prior to construction. However, on type "R" and "T" panels, a plastic sheet barrier needs to be used above the ceiling to separate the area of work from the occupied area. This barrier above the ceiling will need to be sealed to the panelized wall system and the structure above. We were informed by the VA during design that an ICRA analysis will be provided by the VA prior to construction. It is assumed, though, that the majority of the work will be "Class III/IV" with pockets of "Class II" in isolated and low risk areas. The Class III/IV assumption is due to the work being performed in patient rooms, patient treatment areas, and locations directly adjacent to the previously mentioned. | CLOSED | 5 | ||||
| 44 | The sheet note #2 on mechanical drawings, such as sheet MD101, reference installing new balance dampers in all diffusers/register takeoffs. Is it part of the SOW to remove all registers/grilles in rooms where VAV’s get replaced, install balance dampers, and reinstall existing diffusers/register? | 10-Jun-21 | 15-Jun-21 | Some diffusers and grilles are reused. All new work is shown on the MH drawings. Some new balance dampers are needed as shownon MH drawings. | CLOSED | 4 | |||||
| 45 | The sheet note #4 on mechanical drawings, such as sheet MD101, says to coordinate final ceiling diffuser locations with all other ceiling mounted equipment. It does not appear the ceiling diffusers are to be replaced. Do the ceiling diffusers, registers or grilles get replaced in the rooms with replaced VAV’s? | 10-Jun-21 | 15-Jun-21 | See MH drawings for diffusers and grilles to remain and new diffusers and grilles to be installed. | CLOSED | 4 | |||||
| 46 | The sheet note #6 on mechanical drawings, such as sheet MD101, reference installing new thermostats at the location of existing. Do all thermostats get replaced at locations of replaced VAV’s? | 10-Jun-21 | 15-Jun-21 | Yes replace all thermostats at locations of replaced VAV's. | CLOSED | 4 | |||||
| 47 | If the thermostats get replaced, can the existing wire be reused or will new wire be required to be pulled? | 10-Jun-21 | 15-Jun-21 | RCM | New thermostats will need connected to the Building Automtion System (BAS). Most existing thermostats are pneumatic and there is no wiring. | CLOSED | 4 | ||||
| 48 | If the thermostats get replaced and new wire is required, will the new wire need to be fully in conduit? | 10-Jun-21 | 15-Jun-21 | RCM | Reference the Specifications 23 0923 for wiring requirements. | CLOSED | 4 | ||||
| 49 | Or, do all 3 of the Phases of work (i.e. install new hydronic piping, replace VAV’s, and remove existing piping) occur in each subphase (work area) before moving on to the next subphase (work area)? | 10-Jun-21 | 15-Jun-21 | RCM | The Phase 1 pipng will need installed in all subphases and be active before Phase 2 work can proceed. | CLOSED | 4 | ||||
| 50 | Regarding the VAV’s located above hard ceilings. Do these ceilings have existing access panels to allow work to be performed on the hydronic lines and VAV boxes without demo of the hard ceilings? | 10-Jun-21 | 15-Jun-21 | RCM | Demolition and replacement of hard ceilings will be required unless the Contractor can perform the Work through the existing access doors. | CLOSED | 4 | ||||
| 51 | If no existing access doors exist, should new access doors be installed at these locations. If so, please provide an actual or assumed quantity to ensure all bidders are bidding apples to apples. | 10-Jun-21 | 15-Jun-21 | RCM | See response to item 50 above. | CLOSED | 4 | ||||
| 52 | Specs | Specification Section 01 00 00, 1.24 Tests states that the contractor shall provide a written testing and commissioning plan. Section 01 91 00, 1.12 States that the Commissioning Plan is to be prepared by the Commissioning Agent which section 1.9 states that this is appointed by the VA. Is the contractor to prepare the Commissioning Plan? | 10-Jun-21 | 21-Jun-21 | VA | Cx Plan will be completed by the Cx Agent. | CLOSED | 8 | |||
| 53 | Specs | Specification Section 01 00 00, 1.34 VA Tririga CPMS states the contractor is required to access this management software. The VA no longer uses this software. Can this be removed from the specifications? | 10-Jun-21 | 15-Jun-21 | RCM | Disregard references to Tririga CPMS software. | CLOSED | 4 | |||
| 54 | Specs | Specification Section 01 81 13, 3.1, A, 4 Building Flush-Out requires the contractor to flush-out by supplying a total volume of 14000 cu. ft. of outdoor air per sq. ft. of floor area while maintaining an internal temperature of at least 60 degrees Fahrenheit and a relative humidity no higher than 60 percent. Is this required? | 10-Jun-21 | 15-Jun-21 | RCM | No, flushing the Building is not required. | CLOSED | 4 | |||
| 55 | Specs | There are specifications for asbestos and lead paint which refer to an Existing Conditions Report and the drawings for performing this work. Can you provide us with any reports and drawings showing these locations and sampling analysis? | 10-Jun-21 | 21-Jun-21 | VA | The VA does have an Existing Conditions Report available. See attached. If asbestos or lead paint is discovered during construction exceeding the amount stated in the specifications, an RFP will be requested. | CLOSED | 8 | |||
| 56 | Specs | Specification Section 07 84 00, 1.5, B Installer Qualifications requires the firm to have been approved by FM Global or evaluated by UL. We typically have our installers be approved by the firestopping product manufacturer. Is this sufficient? | 10-Jun-21 | 16-Jun-21 | TJS | Yes, that is sufficent | CLOSED | 5 | |||
| 57 | Specs | There are door and hardware specifications, but we cannot find any doors or hardware to be replaced in the drawings. Can you let us know what actual work this specification refers to? | 10-Jun-21 | 16-Jun-21 | TJS | These specifications are for the doors to be installed in the ICRA barrier types "R", "N", and "T". See GI101 For ICRA Door Types. | CLOSED | 5 | |||
| 58 | Spec Section 09 22 16, 2.2 Steel Studs and Runners calls for 30 mil studs. If this is for a temporary ICRA wall, can we use a 25 GA stud? The 30 mil studs are for permanent high impact walls and have a longer lead time and are more expensive. | 10-Jun-21 | 16-Jun-21 | TJS | Yes, lower GA studs are acceptable. | CLOSED | 5 | ||||
| 59 | Will a pre-TAB and Post-TAB be required for the new VAV boxes in each room? | 10-Jun-21 | 15-Jun-21 | RCM | Yes. We want to confirm the existing airflow before demolition and identify possible issues early in the project. Contractor to provide this report prior to demolition. | CLOSED | 4 | ||||
| 60 | Will a pre-TAB and Post-TAB be required for the new hydronic piping? | 10-Jun-21 | 15-Jun-21 | RCM | Yes. We want to confirm the existing water gpm before demolition and identify possible issues early in the project. Contractor to provide this report prior to demolition. | CLOSED | 4 | ||||
| 61 | The spec 02 82 11 Asbestos Abatement identifies 400 sf of asbestos plaster ceiling to be removed. Please identify the location of this asbestos plaster. What areas is it in? Is it above the finished ACT or is it the finished/exposed ceiling? | 10-Jun-21 | 21-Jun-21 | VA | The VA does have an Existing Conditions Report available. See attached. If asbestos or lead paint is discovered during construction exceeding the amount stated in the specifications, an RFP will be requested. | CLOSED | 8 | ||||
| 62 | Approximately, how much qty of asbestos plaster ceiling is at each location? It makes a big difference on price if it is 2 sf per location or 50 sf per location? | 10-Jun-21 | 21-Jun-21 | VA | The VA does have an Existing Conditions Report available. See attached. If asbestos or lead paint is discovered during construction exceeding the amount stated in the specifications, an RFP will be requested. | CLOSED | 8 | ||||
| 63 | The spec 02 82 11 Asbestos Abatement identifies 100 sf of asbestos sprayed-on insulation to be removed. Please identify the location of this asbestos sprayed-on insulation. What areas is it in? Is it on pipe, in wall cavity, on structural steel, etc.? | 10-Jun-21 | 21-Jun-21 | VA | The VA does have an Existing Conditions Report available. See attached. If asbestos or lead paint is discovered during construction exceeding the amount stated in the specifications, an RFP will be requested. | CLOSED | 8 | ||||
| 64 | Approximately, how much qty of asbestos sprayed-on insulation is at each location? It makes a big difference on price if it is 2 sf per location or 50 sf per location? | ||||||||||
| 10-Jun-21 | 21-Jun-21 | VA | The VA does have an Existing Conditions Report available. See attached. If asbestos or lead paint is discovered during construction exceeding the amount stated in the specifications, an RFP will be requested. | CLOSED | 8 | ||||||
| 65 | There is a spec for lead paint removal 02 82 33.13, however, no lead paint appears to be identified in the specs or on the plans. What items and at what locations are expected or known to have lead paint? | 10-Jun-21 | 21-Jun-21 | VA | The VA does have an Existing Conditions Report available. See attached. If asbestos or lead paint is discovered during construction exceeding the amount stated in the specifications, an RFP will be requested. | CLOSED | 8 | ||||
| 66 | Drawing MH103 “Fourth Floor North/South HVAC Plan – Phase 2” shows no work in the grayed out areas; however, drawing EP104 “Fourth Floor North/South Power Plan” shows electrical work in the areas which are grayed out on the mechanical drawings. Please clarify if the electrical work is to follow the same phasing plan as shown on the mechanical drawings. | 10-Jun-21 | 15-Jun-21 | RCM | Yes. Electrical work follows the same phasing. See Phasing Plans A-101 to A-108. | CLOSED | 4 | ||||
| 67 | Will work inside the IT rooms be conducted during off-hours? | 10-Jun-21 | 15-Jun-21 | RCM | See Phasing plans and Notes on drawings A-101 to A-108. "All Work to be performed during Off Peak hours." | CLOSED | 4 | ||||
| 68 | Will all areas have to be operational the next day? | 10-Jun-21 | 15-Jun-21 | RCM | Yes. | CLOSED | 4 | ||||
| 69 | Is the roof under warranty? If so, who holds the warranty? | 10-Jun-21 | 21-Jun-21 | VA | Roof is not under warranty; however, during this project, we intend to put on a new roof that will be under warranty. Information will be provided as it comes available. | CLOSED | 8 | ||||
| 70 | Can multiple locations be worked on concurrently? | 10-Jun-21 | 15-Jun-21 | RCM | Yes , with approval of the COR. | CLOSED | 4 | ||||
| 71 | Can multiple phases be conducted at once as long as they occur on separate floors? | 10-Jun-21 | 15-Jun-21 | RCM | Yes, So lang as Phase 1 piping connected to the same pipe riser is cmplete before work on Phase 2 and 3 begin. | CLOSED | 4 | ||||
| 72 | Will the VA parking garage be available for contractors during off-hour work? | 10-Jun-21 | 16-Jun-21 | VA | Contact the VA COR for this response | CLOSED | 5 | ||||
| 73 | Arch/Int | Please provide paint color for room B128. | 10-Jun-21 | 16-Jun-21 | TJS | Paint color is to match existing. Use Sherwin Williams as a manuf BOD, eggshell finish, two finish coats, low VOC for walls, Flat White for any gypsum board ceilings. | CLOSED | 5 | |||
| 74 | Please confirm that the VA facility will be providing all required permits and inspections. | 10-Jun-21 | 16-Jun-21 | VA | Contact the VA COR for this response | CLOSED | 5 | ||||
| 75 | Please confirm that all duct work is to be conducted during phase 2. | 10-Jun-21 | 15-Jun-21 | RCM | Yes. New ductwork is anticiapted to be installed in Phase 2. | CLOSED | 4 | ||||
| 76 | On MH-401, is there supposed to be a difference between notes 10 and 14? | 10-Jun-21 | 15-Jun-21 | RCM | These are duplicate notes. | CLOSED | 4 | ||||
| 77 | Please provide Roofing Specification. | 10-Jun-21 | 17-Jun-21 | TJS | VA will need to provide specifications for the current Roofing installed. | CLOSED | 6 | ||||
| 78 | Note 3 on MD104, and other locations, notes that the hard ceiling above the drop ceiling is to be removed as required to perform new. | 10-Jun-21 | 15-Jun-21 | RCM | Correct. IN Surgical B526 the hard ceiling abov e the ACT shall be removed to perform the Work. | CLOSED | 4 | ||||
| 79 | Please provide roofing details for new ACCU’s to be installed on roofs. | 10-Jun-21 | 17-Jun-21 | TJS | See Mechanical Sheet M-501 | CLOSED | 6 | ||||
| 80 | Please show the connection route for ACCU -1519 as noted on detail 3 on MH-405. | 10-Jun-21 | 15-Jun-21 | RCM | The existing refrigerant piping is to remain. Connect new equipment to the existing piping per note 1 and 3. Charge with refrigerant and make new equipment fully operational. | CLOSED | 4 | ||||
| 81 | Please indicate where access panels (5/M-501) are to be installed. | 10-Jun-21 | 15-Jun-21 | RCM | Access panels are required where needed to access items for maintenance and adjustment. | CLOSED | 4 | ||||
| 82 | Is the bid time in EST or CST? | 15-Jun-21 | 15-Jun-21 | VA | The proposal is due CST. | CLOSED | 1 | ||||
| 83 | As a result of the effect of COVID-19 throughout the U.S., and the resulting Federal, State, and local governments’ responses /requirements of safe distancing and potential advocations of working remotely and/or complete organization closures, please advise how the Government intends to address delays resulting there as it pertains to the current solicitation schedule for this and all future projects. | 15-Jun-21 | 15-Jun-21 | VA | COVID-19 issues will be addressed as they arise. There is no way we can foresee what may happen in the future and they will be addressed accordingly at that time. | CLOSED | 1 | ||||
| 84 | As there will be no in-person bid opening for this project, can the CO or COR provide a conference line number to call into, so bidders can listen to the bid opening? This has been done in other VISNs and has worked well. | 15-Jun-21 | 15-Jun-21 | VA | Per Page 1 of the solicitation - The official bid opening will be June 24, 2021 at 12:30 PM CT. and will occur via Microsoft Teams call in. Please call 872-701-0185 Conf #190386158 five minutes before the bid opening to be present for the bid opening. | CLOSED | 1 | ||||
| 85 | Can we submit our bid via email, if we mail the original hardcopy Bid Bond prior to the due date? | 15-Jun-21 | 15-Jun-21 | VA | Per page 1 of the solicitation - Submit one (1) electronic copy of bids with a copy of bid bond via email to Scheronica.cochran@va.gov and one (1) original hard copy bid bond on or before the due date/time stated in Block 13. Bid bond must be received at the following address: Department of Veterans Affairs, Network Contracting office (NCO) 9, Attn: Scheronica Cochran 1639 Medical Center Parkway, Suite 400, Murfreesboro, TN 37129 | CLOSED | 1 | ||||
| 86 | Is this project tax exempt, and will the CO/COR provide the necessary tax-exempt certificates? | 15-Jun-21 | 15-Jun-21 | VA | No, this project is not tax exempt. Reference FAR 52.229-3, Federal, State, and local taxes which is in the solicitation. | CLOSED | 1 | ||||
| 87 | The Contracting Officer will then NTP to the awardee after the contract award is made. What is the approximant duration between issuing the award and issuing the NTP? | 15-Jun-21 | 15-Jun-21 | VA | The NTP will be issued once performance and payment bonds are received. | CLOSED | 1 | ||||
| 88 | For planning the preliminary project schedule, can you please provide an anticipated award date? | 15-Jun-21 | 15-Jun-21 | VA | Your proposal should be good for 120 calendar days. | CLOSED | 1 | ||||
| 89 | What is the anticipated duration between issuance of contract award and issuance of the NTP? | 15-Jun-21 | 15-Jun-21 | VA | The NTP will be issued once performance and payment bonds are received. | CLOSED | 1 | ||||
| 90 | Contractor feels this project warrants a Senior Project Manager. This is not a position noted in the solicitation for Proposal. Can our Senior Project Manager be added to the project organization portion of the proposal? | 15-Jun-21 | 21-Jun-21 | VA | Yes. | CLOSED | 5 | ||||
| 91 | Contractor feels this project warrants a QA/QC Super. This is not a position noted in the solicitation for Proposal. Can a QA/QC Super requirement be added to the required staffing plan? | 15-Jun-21 | 17-Jun-21 | VA | Contractor can add any personnel they think they need. | CLOSED | 3 | ||||
| 92 | How many calendar days should be included in the critical-path method schedule for owner and A/E review and respond to RFIs? | 15-Jun-21 | 15-Jun-21 | VA | This project is for 450 calendar days. | CLOSED | 1 | ||||
| 93 | How many calendar days should be included in the critical-path method schedule for owner and A/E submittal review? | 15-Jun-21 | 15-Jun-21 | VA | This project is for 450 calendar days. Spec Section 01 33 23 Paragraph 1.10 D. VA review period is 15 working days for submittals. E. VA review period is 10 working days for RFIs on page 7. | CLOSED | 1 | ||||
| 94 | Provide 3-D REVIT Design model in native file foreman, for creation of coordination documentations. | 15-Jun-21 | 17-Jun-21 | VA | These will be provided after award. | CLOSED | 3 | ||||
| 95 | Will the owner provide the contract drawings in the native Revit format for use by the GC? | 15-Jun-21 | 17-Jun-21 | VA | Yes | CLOSED | 3 | ||||
| 96 | Will owner require GC’s to develop and submit coordination drawings in Revit? | 15-Jun-21 | 17-Jun-21 | VA | Yes | CLOSED | 3 | ||||
| 97 | Will the owner provide as-built drawings for the existing structures/work area of the project? | 15-Jun-21 | 17-Jun-21 | VA | If needed and provided we have them, yes. Our drawings may not be totally up to date though. | CLOSED | 3 | ||||
| 98 | Where will the designated parking & laydown area be for workers accessing the construction site? | 15-Jun-21 | 16-Jun-21 | VA | There will be a contractor staging area provided in the rear of the main building. Space is very limited at the Bowling campus. | CLOSED | 2 | ||||
| 99 | Can the owner please provide a single drawing that clearly states room dimensions, corridor dimensions, building footprint dimensions, etc? | 15-Jun-21 | 21-Jun-21 | VA | See attached PDF drawings | CLOSED | 5 | ||||
| 100 | Can the owner please provide a single drawing that clearly states floor to ceilings heights for the construction area? This is used to ensure that the above ceiling utilities will fit in the above ceiling space. | 15-Jun-21 | 21-Jun-21 | VA | See attached PDF Drawings | CLOSED | 5 | ||||
| 101 | Will the contractor be authorized to build a temporary office inside the space in lieu of renting an office trailer for the duration of the project? | 15-Jun-21 | 17-Jun-21 | VA | No | CLOSED | 3 | ||||
| 102 | What is the approximate Square Footage of the project? Please confirm that the space will be free from debris and free-standing medical equipment, office supplies, etc. | 15-Jun-21 | 17-Jun-21 | TJS | The approximate square footage of the affected areas is 48,000 square feet. This isn't the total square footage of the levels but the areas within each phase. Some spaces will have equipment and supplies moved out, but many won't. IT rooms for instance will still have their racks and equipment. Coordinate with the end users via the COR to have any thing moved out. I would estimate that about 1/2 the spaces will still have furniture in it during the phases of excecution. | CLOSED | 3 | ||||
| 103 | Does the contract include liquidated damages? If the owner temporarily shuts down or suspends the project (i.e. for noise), will extended general conditions cost and time be added to the contract? | 15-Jun-21 | 15-Jun-21 | VA | No | CLOSED | 1 | ||||
| 104 | We anticipate certain construction activities to generate high levels of noise. Please confirm that only the Contracting Officer can suspend work via written notification to the Contractor. | 15-Jun-21 | 15-Jun-21 | VA | This will be addressed when the issue arises during construction of the project. | CLOSED | 1 | ||||
| 105 | Can the owner confirm that the General Contractor is to not include any Asbestos or Lead Removal? | 15-Jun-21 | 21-Jun-21 | VA | The specifications state a quantity of asbestos and lead paint removal. Any more than that, the VA will request an RFP. | CLOSED | 5 | ||||
| 106 | Has the work area been checked for asbestos, lead based materials and/or other hazardous materials? Is there a report available? | 15-Jun-21 | 21-Jun-21 | VA | The VA does have an Existing Conditions Report available. See attached. If asbestos or lead paint is discovered during construction exceeding the amount stated in the specifications, an RFP will be requested. | CLOSED | 5 | ||||
| 107 | What is the Governments’ policy if asbestos products are encountered during construction? | 15-Jun-21 | 17-Jun-21 | VA | If asbestos is assumed, the contractor shall test the material. If it’s not asbestos, proceed with construction. If the tested material does contain asbestos, submit an RFP for the abatement and testing fees. | CLOSED | 3 | ||||
| 108 | Is AISC (American Iron and Steel Certification) required for the structural steel fabrication and/or erection for this project? | 15-Jun-21 | 21-Jun-21 | VA | Yes. | CLOSED | 5 | ||||
| 109 | Please confirm that there are no expansion joints required for this project. | 15-Jun-21 | 16-Jun-21 | TJS | Correct, there are no expansion joins necessary for floors, walls, ceilings, or roofs. | CLOSED | 2 | ||||
| 110 | Please provide the existing roof warranty, manufactures data, and POC. | 15-Jun-21 | 21-Jun-21 | VA | Roof is not under warranty; however, during this project, we intend to put on a new roof that will be under warranty. Information will be provided as it comes available. | CLOSED | 5 | ||||
| 111 | Please provide a full signage schedule indicating room numbers and names. | 15-Jun-21 | 16-Jun-21 | TJS | Room signage is not be necessary for this project. | CLOSED | 2 | ||||
| 112 | Are there any locked units? If there are what rooms are locked and are a different sign type required. | 15-Jun-21 | 16-Jun-21 | TJS | Yes, there are areas that are behind controlled access and locks. These areas will be coordinated with the end users for access via the COR. All signage required identified on sheet GI101. No room signage requried. | CLOSED | 2 | ||||
| 113 | Please provide seismic bracing details for pipe and systems support. | 15-Jun-21 | 19-Jun-21 | RCM | Seismic bracing details are not required for this site. | CLOSED | 5 | ||||
| 114 | Please confirm that the owner will provide fire watch during the period of time that the fire suppression system is not in service. | 15-Jun-21 | 17-Jun-21 | VA | The contractor shall provide any and all fire watches for the shutdown of any fire suppression systems. | CLOSED | 3 | ||||
| 115 | Please provide time duration at the owner expects for AHU to be offline, the specification on indicate the work hours and not the timeframe allowable for service interruption to the air handlers. | 15-Jun-21 | 21-Jun-21 | VA | AHU shall be offline for the shift of the work only. | CLOSED | 5 | ||||
| 116 | Please confirm that the owner will be contracting directly with a third-party commissioning agent for commissioning the project and that the Contractor is only to include participation/coordination with the Commissioning Agent. | 15-Jun-21 | 17-Jun-21 | VA | The VA has contracted with a third-party Cx Agent. | CLOSED | 3 | ||||
| 117 | Is there any work required for adding or altering to an existing nurse call system? If so, please confirm the system currently used is the Hill Rom NaviCare nurse call with RTLS (real time locating services) for staff and patients. | 15-Jun-21 | 16-Jun-21 | TJS | No, there is no work that would affect the Nurse Call system. | CLOSED | 2 | ||||
| 118 | Who is the owners’ service provider for the fire alarm system? Can you please provide contract information? | 15-Jun-21 | 21-Jun-21 | VA | Johnson Controls. | CLOSED | 5 | ||||
| 119 | Is a bond required? What is the % required? | 15-Jun-21 | 15-Jun-21 | VA | Yes, a bid bond is required with the bid. A performance and payment bond are required when the award is made from the awardee. Reference page 1 of the solicitation 13b and page 2 block 18. Pages 14 and 15 states the bid guarantee information. |
| BID GUARANTEE: A bid guarantee is required in an amount not less than 20 percent of the bid price but shall not exceed $3,000,000. Failure to furnish the required bid guarantee in the proper form and amount, by the time set for opening of bids, shall require rejection of the bid in all cases except those listed in Federal Acquisition Regulation (FAR) 28.101-4. Bid Bonds must be provided using Standard Form 24 (see FAR 28.106-1) and the form must be provided in original (no white outs, faxed or copied signatures, seals) with ‘wet ink’ signatures and contain the proper solicitation number, bid opening date, and be from a corporate surety listed in Department of Treasury Circular 570. Individual sureties shall be determined acceptable to the Contracting Officer (see FAR 28.203) and be accompanied by Standard Form 28 Affidavit of Individual Surety. Other forms of bid security may be acceptable as denoted in FAR Part 28.203-2. | CLOSED | 1 | |||||||||
| 120 | Please confirm that only the original sealed bid is required. | 15-Jun-21 | 15-Jun-21 | VA | This is not seal bidding. | CLOSED | 1 | ||||
| 121 | When are final RFI's due? | 15-Jun-21 | 15-Jun-21 | VA | Questions received after 12:00 ET June 10, 2021 will not be answered unless it is determined to be in the best interest of the government. | CLOSED | 1 | ||||
| 122 | Can CPAR's be used in place of PPQ's? | 15-Jun-21 | 15-Jun-21 | VA | No | CLOSED | 1 | ||||
| 123 | Who is the owner’s rep for temperature controls on site? | 15-Jun-21 | 21-Jun-21 | VA | Contractor shall communicate solely to COR for project. | CLOSED | 5 | ||||
| 124 | Who is the owner’s rep for low voltage on site? | 15-Jun-21 | 21-Jun-21 | VA | Contractor shall communicate solely to COR for project. | CLOSED | 5 | ||||
| 125 | Please provide asbestos report including the locations of asbestos materials to be removed, this directly affects the phasing plan. | 15-Jun-21 | 21-Jun-21 | VA | The VA does have an Existing Conditions Report available. See attached. If asbestos or lead paint is discovered during construction exceeding the amount stated in the specifications, an RFP will be requested. | CLOSED | 5 | ||||
| 126 | Please provide lead paint report including the locations of the lead paint to be removed, this directly affects the phasing plan. | 15-Jun-21 | 21-Jun-21 | VA | The VA does have an Existing Conditions Report available. See attached. If asbestos or lead paint is discovered during construction exceeding the amount stated in the specifications, an RFP will be requested. | CLOSED | 5 | ||||
| 127 | Were the power cables tested for asbestos containing material, i.e. power cables that feed lights? Please provide asbestos report for this including locations. | ||||||||||
| 15-Jun-21 | 21-Jun-21 | VA | The VA does have an Existing Conditions Report available. See attached. If asbestos or lead paint is discovered during construction exceeding the amount stated in the specifications, an RFP will be requested. | CLOSED | 5 | ||||||
| 128 | Phasing plan indicates there are 3 phases (1. Install new hydronic piping throughout the scope of work 2. Install new VAV boxes throughout the scope of work and 3. Remove old hydronic piping after connection and activation of new piping.) and 9 sub-phases (A – I). | 15-Jun-21 | 16-Jun-21 | TJS | Correct. | CLOSED | 2 | ||||
| 129 | Will any phases (and sub-phases) be allowed to run concurrent with each other or must they run sequentially? | 15-Jun-21 | 16-Jun-21 | TJS | Subphases can run concurrently within each phase, however, areas affected by the work need to be coordinated with the end users via the COR to make sure the hospital functions normally. | CLOSED | 2 | ||||
| 130 | On drawing A101 Phasing Notes it states where indicated, all work to be done in single phase. SPS, Pharmacy and Radiology are to have new piping installed, and old piping removed in one phase. Infection control barriers and work are not to stop functional activities of these spaces unless coordinated with the COR and the department heads. Where is that note applicable ? | 15-Jun-21 | 16-Jun-21 | TJS | This note should be disregarded entirely. No work to be done in areas mentioned. | CLOSED | 2 | ||||
| 131 | On drawing G102 - Note H – states when working on OIT, IT, Comm or Data rooms, GC and all subs to have member of OIT present at all times. Coordinate with COR. Will an OIT member be available during Off Peak Hours? | 15-Jun-21 | 16-Jun-21 | TJS | Yes, assume a member of OIT will be available off hours. COR to confirm requirements prior to construction. | CLOSED | 2 | ||||
| 132 | What are the specs for the existing doors and hardware throughout the existing space? | 15-Jun-21 | 16-Jun-21 | TJS | VA to Answer | CLOSED | 2 |