Attachment 18 26-0604-Addendum 1 Narrative.pdf
PDF 305 KB Posted
- Attached to
- Z1DA--534-CSI-714 / CARDIAC CATHETERIZATION LAB #1 SITE PREP - CONSTRUCTION / (VA-26-00042281)
- Solicitation number
- 36C24726B0003
About this file
This is an addendum to a Department of Veterans Affairs construction solicitation for site preparation work related to Cath Lab 1 at the Ralph H. Johnson VA Medical Center in Charleston, South Carolina. The addendum, issued June 4, 2026, by Moon Tree Consulting, documents revisions and clarifications to the original solicitation documents.
The addendum addresses three categories of changes: general clarifications based on pre-bid RFI responses and drawing/specification updates, specification modifications, and drawing revisions. Specification changes include a revision to specification 08 80 00 R1, addition of specification 28 31 00 R1, and addition of Appendix A addressing alternatives to outdoor exhaust requirements for the ICRA Infection Prevention and Control Construction/Renovation/Maintenance Permit. Drawing changes modify Sheet 1-AD012R1 to include additional demolition scope related to wall protection and revise Sheet 1-AE105R1 to change door material specifications from hollow metal to wood. The addendum also notes inclusion of a takeform signage supplement for Cath Lab 2 as requested by the VA.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
534-CSI-714
CATH LAB 1 SITE PREP
ADDENDUM NO. 1
Cath Lab 1 Site Prep
Department of Veterans Affairs
Ralph H. Johnson VA Medical Center - Charleston SC
Prepared By:
Moon Tree Consulting
ADDENDUM NO. 1
June 4, 2026
CATH LAB 1 SITE PREP
DESCRIPTION OF CHANGES
1. Pre-Bid RFI Responses and Drawings/Specifications minor clarifications.
2. Included takeform signage supplement for Cath :Lab 2 as requested by VA.
SPECIFICATION CHANGES
1. Revised specification 08 80 00 R1
2. Added Specification 28 31 00 R1
3. Added Appendix A-Alternatives to outdoor exhaust requirements to the ICRA Infection
Prevention and Control Construction/Renovation/Maintenance Permit
DRAWING CHANGES
1. Sheet 1-AD012R1: Revised scope of work to include additional demo scope related to wall protection.
2. Sheet 1-AE105R1: Revised scope of work to modify door material from hollow metal to wood as noted in specifications.
END ADDENDUM 01