Attachment 0011C - PLUMBING DETAIL REV.1.pdf
PDF 566 KB Posted
- Attached to
- Y1DA--521-23-121 | SPS Renovation Phase 2
- Solicitation number
- 36C24725R0079
About this file
This document is a detailed plumbing details drawing for the Birmingham SPS Phase II project at the Birmingham VA Medical Center, located at 700 South 19th Street, Birmingham, AL. The drawing, prepared by DavEnergy Solutions, includes multiple technical diagrams and specifications for various plumbing system components, including a Reverse Osmosis (RO) package detail, floor drain details, lavatory mounting instructions, pipe support and anchor systems, and configurations for clean steam generators and in-line pumps. The drawing is dated 01/28/2025 with pre-bid RFI responses added on 06/06/2025, and is part of the project number 521-23-121, drawing number P-502. The technical drawings provide comprehensive engineering specifications for plumbing infrastructure, including detailed schematics for water treatment systems, piping configurations, equipment mounting, and system integration requirements for the VA medical facility renovation project.
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WATER
THERMOSTATIC
MIXING VALVEFILTERED
LT
2" RO
REJECTION
WATER TO
DRAIN WITH
AIR GAP
CPVC
PIPE
TAPPING
CPVC PIPE
TAPPING
WITH NC SHUTOFF
VALVE
PIPED TO DRAIN.
CPVC
PIPE TAPPING
AND 1" CPVC
PIPE TO
CIRCULATING
PUMPS
LEVEL
TRANSMITTER
2" NPT FOR
CONTROL
STACK
CARBON
WATER
SOV
CPVC PIPE RO
RETURN
FROM RO DISTRIBUTION
LINE
WATER
SOFTENER
CARBON
WATER
TANK
#1
SOFTENER
TANK
#2
1" CPVC FROM WATER
SOFTENER TO CARBON
FILTERS
BRINE
TANK
2" VENT WITH
HEPA FILTER.
CPVC
PIPE
TAPPING
RO
UNIT
LT
LAH
LAH
ENGAGE, WITHIN 8" OF
BOTTOM
LOW LEVEL ALARM, WITHIN
4" OF BOTTOM
DISENGAGE, WITHIN 10"
OF TOP
HIGH LEVEL ALARM #1,
WITHIN 6" OF TOP
LAH HIGH LEVEL ALARM #2,
WITHIN 3" OF TOP
[1 m m
DUPLEX
FILTER
DUPLEX
FILTER
#1 #2
DUPLEX
RO BUFFER
TANK WITH CONICAL
BOTTOM WATER
DUPLEX
6" M
IN
LAL
NOTE:
1. HIGH LEVEL ALARM, LOW LEVEL ALARM, AND LOW FLOW ALARM SHALL BE SENT TO FACILITY BAS (METASYS).
2. PIPES TO BE SIZED TO ENSURE SCOURING VELOCITY.
3. TEST PORT REQUIRED AT EACH USE POINT. TEST PORT REQUIRED AT LOOP RETURN.
4. SIZE TANK TO ACCOMODATE EQUIPMENT LOAD AND RO WATER PRODUCTION CAPABILITY.
TEST PORT VALVE.
RO
UNIT
N+1
SOV
UV DISINFECTION
ENDOTOXIN FILTER
CPVC PIPE RO
SUPPLY
REFERENCE
VIEW 2/PW-101
FOR RO LOOP
TEST
PORT
VALVE.
RAW TEPID
WATER 77
DEGREES
CW HW
PI PI
PIPI
PI
PI
PRE-FILTER
FS
CONDUCTIVITY METER
PI PI
N+1 REDUNDANT
PUMP. PUMPS SHALL
NOT OPERATE IN
PARALLEL
N+1 N+1
TEST
PORT
VALVE.
TEST PORT VALVE.
TEST
PORT
VALVE.
OPTIONAL, VERIFY WITH
VA FOR REQUIREMENT.
INLET
SPRAY
HEADER
NICKLE BRONZE
ADJUSTABLE STRAINER
(FLUSH WITH FINISHED
FLOOR)
CEMENT
BED
TILE FLOOR
CONCRETE
FILL
STRUCTURAL SLAB
FLASHING
CLAMP WITH
WEEP HOLES
THREADED, CAULKED OR
NO-HUB CONNECTION
WATERPROOF MEMBRANE
PROVIDE A METAL SUPPORT PLATE
WHEN DRAIN IS INSTALLED IN AN
EXISTING FLOOR - CAULK AROUND
DRAIN PRIOR TO RE-GROUTING
CLAMP WATERPROOF
MEMBRANE INSIDE OF DRAIN
BODY TO DRAIN TO WEEP
HOLES
NOTE:
SLOPE MEMBRANE LINER 2% TO DRAIN.
LOOSE GRAVEL AT
WEEP HOLES
3mm to 6mm SIZE
EXTERIOR SKIN
PREFAB. WALL PANEL
AS SPECIFIED
MASTIC
INTERIOR SKIN
GASKET
S.S. WALL PLATE SECURED
WITH S.S. SCREWS
PIPE
INSULATION AS
SPECIFIED
SEAL INSULATION
AGAINST SKIN OF
WALL PANEL
TUBING, PIPING
OR CONDUIT
S.S. WALL PLATE SECURED
WITH S.S. SCREWS
FIELD APPLIED INSULATION AFTER
INSERTION OF RESPECTIVE SERVICE
FACILITY THRU REFRIGERATOR OR
FREEZER WALL
DESIGNER'S NOTE:
SHOW REQUIRED ANCHORS ON PLAN,
SECTIONS OR DIAGRAMS.
NOTES:
1. PROVIDE ANCHORS ONLY WHERE SHOWN
ON DRAWINGS.
2. EXTEND SLEEVE ABOVE FLOOR WHERE
SPECIFIED.
INSULATION BOLT (TYPICAL)
FLOOR
SLAB
FIRE-STOPPING
MATERIAL
BOLT
PIPE
PIPE SLEEVE
WHERE SPECIFIED
RISER
CLAMP
PIPE
PIPE SLEEVE
WHERE SPECIFIED
RISER CLAMP. BOTTOM
CLAMP REQUIRED AT
ANCHOR POINTS ONLY.
ELEVATION
PLAN
RISER CLAMP
RO / DI
WATER MAIN
BALL
VALVE
3/4" FEMALE
1" MALE IPS
MINIMUM 16 GAGE GALVANIZED
STEEL PLATE 12"x48" [300x1200mm] MIN. SECURED TO
A MIN. 4 STUDS PER LAVATORY
1/4" [6mm]∅ MOLLY BOLT HOLLOW
WALL ANCHOR (1 EA. SIDE OF LAV)
MIN. (3) 1/4"
[6mm] MACHINE
BOLTS W/DOUBLE
LOCK NUTS ON
BACK SIDE
MIN. 5 1/4"
[131mm]∅ GALV.
MACHINE BOLTS
WELDED TO PLATE
[6mm]
TYP. 1/8" 1/4"
A A
PLAN
SECTION
A
NOTE:
1.
2.
AT LAVS WITH FOOT PEDAL CONTROLS
PROVIDE AN ADDITIONAL 16 GAGE
GALVANIZED STEEL PLATE 12"x16" [300x600mm] SECURED TO A MINIMUM
OF 2 STUDS PER FOOT PEDAL.
PROVIDE 20 GAGE STUDS WHEN HEIGHT
EXCEEDS 12'-0" [3600mm]
STEEL HANGER BY LAV MFGR
STEEL WALL
PLATE
WALL ANCHOR
STUDS
FOR FIXTURE
HEIGHT SEE
ARCHITECTURAL
DRAWINGS
VA
R
IE
S
3' -3
[9 m m
TO
F
LO
O
R
TYP. [3mm]
DESIGNER NOTE:
PREHEAT HEAT EXCHANGER IS OPTIONAL.
PREHEAT PLATE & FRAME HEAT EXCHANGER
TO CONDENSATE RETURN
TO HUMIDIFIER(S)
SET @138kPa
[20 PSIG]
LT LC
STEAM CONTROL
VALVE
HPS
DI FEED WATER F&T TRAP ASSEMBLY
DI
FEEDWATER
PREHEATED
MIST ELIMINATOR
SHUTOFF VALVE
PTPC
MODULATING LEVEL
CONTROL VALVE
LPS
SEE PLUMBING
DWG FOR DI
SYSTEM
SET @103kPa
[15 PSIG]
WATER LEVEL
PRESSURE SAFETY
VALVE
TO OUTSIDE AIR
VENT MANIFOLD
DESIGNER NOTE:
PREHEAT HEAT EXCHANGER IS OPTIONAL.
PREHEAT PLATE & FRAME HEAT EXCHANGER
TO CONDENSATE RETURN
TO STERIS EQUIPMENT
SET @138kPa
[20 PSIG]
LT LC
STEAM CONTROL
VALVE
HPS
SOFT WATER OR
REVERSE OSMOSIS
FEED WATER
F&T TRAP ASSEMBLY
RO
FEEDWATER
PREHEATED
MIST ELIMINATOR
SHUTOFF VALVE
PTPC
MODULATING LEVEL
CONTROL VALVE
LPS
SEE PLUMBING
DWG FOR R.O.
SYSTEM
SET @103kPa
[15 PSIG]
WATER LEVEL
PRESSURE SAFETY
VALVE
TO OUTSIDE AIR
VENT MANIFOLD
AIR STORAGE TANK OR
DRYER
10mm [3/8"]
MANUAL VALVE
10mm [3/8"] O.D.
COPPER TUBING RUN
TO NEAREST FLOOR
DRAIN
DRAIN TRAP FURNISHED
WITH EQUIPMENT
PIPE HANGERS - PROVIDE DOUBLE
DEFLECTION NEOPRENE (TYPE HN)
FOR FIRST TWO ON EACH SIDE OF
PUMP (SEE NOTE NO. 1)
PRESSURE
GAGE
1/2" [15mm]
FLEXIBLE
CONNECTION
BALL OR
BUTTERFLY
TYP.
NOTES:
1. SUPPORT PUMP FROM PIPING ONLY. DO NOT SUPPORT PUMP FROM MOTOR.
BALANCING
DEVICE
Location
Issue Date
Project Number
Building Number
Drawing Number
Project Title
Checked Drawn
Drawing Title
Approved:
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
PhaseDESIGNER OF RECORD STAMPCONSULTANT
Revisions: Date:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
A/E:
321 4 5 6 7 8 9 10
DAVENERGY SOLUTIONS
2207 GARNET AVE, SUITE I
SAN DIEGO, CA 92109
619-770-8552
6/ 6/
:4
4:
P M
Au to de sk
D oc s:
//D
AV
V
A
AL
B irm in gh am S
PS
/5
-2
3-
1-
7-
Bi rm in gh am S
PS
-M ec ha ni ca l.r vt
PRE-BID RFI
RESPONSES
521-23-121
ONE
P-502
MDMD
700 SOUTH 19TH STREET, BIRMINGHAM, AL 35233-1927
BIRMINGHAM SPS PHASE II
01/28/2025
PLUMBING DETAILS
Approver
DAVENERGY SOLUTIONS
2207 GARNET AVE, SUITE I
SAN DIEGO, CA 92109
619-770-8552
1 REVERSE OSMOSIS PACKAGE DETAIL
2 TYPE "C" FLOOR DRAIN DETAIL
TUBING, PIPING, AND CONDUIT
PASSING THROUGH PRE-FAB
INSULATED WALL PANELS
6 SUPPORT/ANCHOR FOR PIPE RISERS
4 CRITICAL TEST PORT DETAIL
3 LAVATORY MOUNTING DETAIL
7 TRAP PRIMER DETAIL5 TYPICAL PIPE HANGERS 9 MOP SINK DETAIL
10 DI CLEAN STEAM GENERATOR
11 RO CLEAN STEAM GENERATOR 12
TYPICAL DRAIN FOR AIR COMPRESSOR
AND DRYER
BID SET 01/28/2025
PRE-BID RFI RESPONSES 06/06/2025
13 IN-LINE PUMPS - CONNECTIONS