This document is a Request for Proposal (RFP) Amendment 0011 for the VA SPS Renovation Phase 2 project (Solicitation Number 36C24725R0079) issued by the Department of Veterans Affairs VISN 7 Network Contracting Activity. The amendment addresses multiple Request for Information (RFI) submissions, providing clarifications on technical specifications including electrical disconnects (NEMA 4X rating), Reverse Osmosis/Deionized (RO/DI) water system details, pre-filter requirements, RO filter redundancy, and specific equipment specifications for sterilization and plumbing systems.
Key technical clarifications include specifying a 20" 10-micron cartridge pre-filter, a 3.00 cubic foot carbon filter, RO filters that operate in redundancy with monitored run hours, and inline transfer pumps with a flow rate of 24.7 PSI at 43 GPM. The project involves renovations at the Birmingham, AL VAMC, with the VA indicating they will no longer accept additional RFIs for this solicitation. The amendment includes several attachments providing supplemental technical drawings and equipment specifications to support bidders in preparing their proposals.
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C24725R0079
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
06-09-2025
521-23-121 36C247 Department of Veterans Affairs VISN 7 Network Contracting Activity 501 Greene Street Hatcher Building - Suite 2 Augusta GA 30901
36C247 Department of Veterans Affairs VISN 7 Network Contracting Activity 501 Greene Street Hatcher Building - Suite 2 Augusta GA 30901 To all Offerors/Bidders
36C24725R0079
X
The purpose of this modification is to answer RFIs. See continuation pages.
NOTE: The VA is unable to accept any more RFIs for this solicitation.
Gregory Snyder Contracting Officer
VA-VHA-RPOE-2024-0090
RFP AMENDMENT 0011 RFI ANSWERS (in red)
1) Spec Section 2.33 B: I see the revisions to the cart lifts but new entrances were left in. Currently there are those peele floor sensors/plates in each floor. Those will have to be torn out and then the floor repoured at each landing they are removed from. Are those to be removed? It is part of the entrance's and specs call for all new entrances so I just need to know if that can be left behind or if you guys want it torn out in which case the flooring will have to be repoured and covered on every landing. It can be left in place if that's what you want. But technically it is apart of the new entrances that are being called for.
· Leave the existing floor entrances in place. Reconnect to existing.
2) The specifications for the electrical disconnects for the AMSCO Equipment refer you to the drawings for the NEMA rating. The drawings do not provide a NEMA rating for the disconnects. A NEMA 3R is for a waterproof rating and a NEMA 4X is for Stainless Steel. There is a big price difference between the 2. Please clarify what the NEMA rating is for the electrical disconnects for the AMSCO equipment?
· Disconnect is to be NEMA 4X.
3) There is Fume Hood shown on P-001, however I cannot find any information about the fume hood on the drawings or specs. Can you please clarify if there is a Fume Hood in the Project?
· Fume Hood shown on P-001 is on a master symbol list.
4) Can you please confirm if GE-1 through GE-6 are exhaust valves or clarify what they are?
· See attached revised drawing labeled “Attachment 0011A - Pre-Bid RFI Response Sheets.”
5) Can you please clarify the exhaust hoods above the sterilizers (quantity, size, cfm requirements, basis of design product)?
· See attached revised drawing labeled “Attachment 0011A - Pre-Bid RFI Response Sheets.”
6) For the RO/DI, I’d need to know the following:
i) Pre-filter type (cartridge, bag, etc.) and size?
ii) Carbon filter size (tank and/or media volume)?
iii) Do the RO units operate together or not?
iv) RO buffer tank size?
v) Transfer pump discharge flow rate and pressure?
(1) Are these skid mounted?
· Pre-filter should be a 20”, 10-micron cartridge filter.
· Carbon filter DC-1465 DriSteem. 3.00 cubic foot media volume.
· The RO filters run in redundancy;
· RUN HOURS FOR EACH OF THE RO FILTERS SHALL BE MONITORED AND TOTALIZED FOR BOTH THE CURRENT PERIOD AND LIFETIME OF THE FILTER.
· THE LEAD RO FILTER SHALL BE DEFINED ON THE FIRST OF THE MONTH TO BE THE FAN WITH THE LOWEST TOTALIZED RUN HOURS.
· The pumps are inline type and will not be skid mounted. Flow rate and discharge pressure for each is 24.7 PSI at 43 GPM. Attached it the cutsheet for the inline transfer pumps. File is labeled “Attachment 0011B - UPS_50240_F_B.”
7) We would size the UV sterilizer based on the transfer pump discharge flow rate?
· The UV sterilizer filter and endotoxin filter should be sized for the transfer pump discharge.
8) A plumbing detail drawing showing how all of this is piped would be great, too, if it has been designed already?
· See attached drawings labeled “Attachment 0011C - PLUMBING DETAIL REV.1” and “Attachment 0011D - RODI ROOM ISO REVISED.”