36C24122R0135 0013.pdf

PDF 152 KB Posted

Attached to
Z2DA--405-13-104 | Inpatient Ward Renovation
Solicitation number
36C24122R0135
Issued by

About this file

This document contains responses to questions regarding solicitation number 36C24122R0135 for an inpatient ward renovation project. The solicitation involves renovating an inpatient ward at the Veterans Affairs Medical Center in White River Junction, Vermont. Key details include confirmation that fully engineered drawings are required for all new exterior wall framing and interior partitions with unique or unusual conditions. Reflected ceiling plans take precedence in instances of conflict regarding ceiling materials. The response also clarifies fireproofing requirements for existing columns and provides guidance on acceptable blocking and electrical control methods. Substitution requests will be reviewed during the shop drawing process. The response aims to address contractor questions to facilitate accurate bidding on the inpatient ward renovation for the Veterans Affairs Medical Center in White River Junction, Vermont.

View the file

Other files

File Type Posted
36C24122R0135 0016.docx DOCX document
36C24122R0135 0015.docx DOCX document
Fingerprint Request Form.pdf PDF
Sign-in Sheet 07-06-2023.pdf PDF
36C24122R0135 0014.docx DOCX document
Sign-in Sheet 06-01-2023.pdf PDF
Owners Equipment Schedule updated 6-20-2023.xlsx XLSX spreadsheet
36C24122R0135 0012.docx DOCX document
36C24122R0135 0011.docx DOCX document
S02 36C24122R0135 0010.pdf PDF
36C24122R0135 0009.pdf PDF
Wage Determination VT20230023 02-24-2023.pdf PDF
WRJ Campus Map Inpatient Ward Site Visit Meeting Location 03.21.2023.pdf PDF
36C24122R0135 0008.pdf PDF
36C24122R0135 0007.docx DOCX document
36C24122R0135 0006.docx DOCX document
VHA COVID-19 Operational Plan 1-27-2023.pdf PDF
Building 31 Abatement Diagrams REV-1 02072023.pdf PDF
36C24122R0135 0005.docx DOCX document
Bldg 31 Exterior Elevations _ Building Sections.pdf PDF
Pre-bid site visit sign-in 01-24-2023.pdf PDF
Bldg 31 Basement Intended Route Debris Removal.pdf PDF
Revised Spec 117313 Patient Lifts 20230201.pdf PDF
36C24122R0135 0004.docx DOCX document
Original Building Ground _ 1st Floor Plan_Wall Types.pdf PDF
Pre-bid site visit sign-in 01-19-2023.pdf PDF
36C24122R0135 0003.pdf PDF
WRJ Campus Map Inpatient Ward Site Visit Meeting Location 1.24.2023.pdf PDF
Renovate Inpatient Ward Site Visit 1.12.2023.pdf PDF
36C24122R0135 0002.pdf PDF
WRJ Campus Map Inpatient Ward Site Visit Meeting Location 1.19.2023.pdf PDF
WRJ Campus Map Inpatient Ward Site Visit Meeting Location.pdf PDF
36C24122R0135 0001.docx DOCX document
36C24122R0135 Solicitation Final (1).pdf PDF
S02 Inpatient Drawings 09302022 Final Architectural Int Design.pdf PDF
S02 Inpatient Drawings 09302022 Final Plumb FirePro Mech Elec.pdf PDF
S02 EXHIBIT B Subcontractor Information and Consent Form.pdf PDF
S02 EXHIBIT A Project Information Sheet for Contractors.pdf PDF
VAMC-WRJ Building 31 Nursing Unit Renovation Project Manual Vol-1 09302022 Final.pdf PDF
VAMC-WRJ Building 31 Nursing Unit Renovation Project Manual Vol-2 09302022 Final.pdf PDF
VAAR 852.219-75 VA Notice of Limitations on Subcontracting_Certificate of Compliance for Services and Construction 02.docx DOCX document
S02 VHA Supplemental Contract Requirements for Combatting COVID-19.pdf PDF
S02 Inpatient Drawings 09302022 Final Gen LifeSafety Structural.pdf PDF
S02 EXHIBIT C Past Performance Questionnaire.pdf PDF
WD VT20220023 Building.pdf PDF
Show all 45

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

1 4

0013 06/26/2023

405-13-104

Department of Veterans Affairs VAMC Togus

1 VA Center Augusta ME 04330

Department of Veterans Affairs VAMC Togus

1 VA Center Augusta ME 04330

To all Offerors/Bidders

36C24122R0135

12-30-2022

X

X X

7/14/2023 1:00PM EDT

X 1

The purpose of this amendment is to provide additional RFI responses.

The additional site visit is still scheduled for June 27, 2023 at 9:00AM EDT at Bldg 37.

The RFI deadline remains Thursday, June 29, 2023 at 3:00PM EDT.

The proposal due date remains Friday, July 14, 2023 at 1:00PM EDT.

See attached RFI responses.

Stephen Slaby Contracting Officer

RFI Questions Submitted with Answers 36C24122R0135

Amendment 0013

405-13-104 Renovate Inpatient Ward, White River Junction, VT

Questions #1 - #106 Appear in earlier amendments

Question# 107 The specs are asking for all the CFMF framing to be engineered including both exterior wall infills and all interior partitions. Is that the intent?

Answer: Fully engineer all new exterior wall framing. The framing manufacturer’s loading data will be sufficient for most interior framing conditions; however, engineer all unique and/or unusual conditions to ensure that they have been fully designed and will perform as expected. Examples of this include extra wide and heavy doors, large expanses of interior borrowed lights and partitions bearing heavy loads.

Question# 108 The RCP is showing GWB ceilings in some of the rooms that the specs call for ACT? Can we get an updated RCP or can we get a definitive list of what rooms receive GWB ceilings and what rooms receive ACT and what type?

The reflected ceiling plans govern where there may be conflicts.

Question# 109 The titles for electrical drawings 31-ED-113/31-EP-113/31-EL-113 indicate that all work shown on these drawings is a deduct alternate. Where on the bid form should this deduct alternate be listed?

Answer:

There are no deductive alternates included in the solicitation. The drawings are mislabeled. Delete reference to “Deduct Alternate” and price the work shown as Base Scope.

Question# 110 Since there are none shown on the power/signal, patient room or fire alarm plans we want to confirm that there are no fire alarm system devices required in the patient rooms?

Answer: There are no fire alarm devices in the patient rooms. The nurse call station(s) are provided with manual pull stations, and it is understood all patients will need nursing assistance to exit the building or fire zone during a fire event.

Therefore, fire alarm devices are not required.

Question# 111 There is a contradiction in the plans regarding the fireproofing at the existing columns.

Details 4 and 6 on 31-AS-201 call for the existing gypsum wallboard fire-resistant construction to remain in tact. The note on 31-AS-106 instructs us to remove the gypsum wallboard and apply a 2-hour fire rated spray-applied cementitious fireproofing to the identified columns. Please clarify the intent.

Answer: Expose the existing columns and Furnish & Install spray-applied fireproofing as indicated on drawing 31-AS-106.

Question# 112

Verify that AutoCAD files in the proper format will be made available free of charge to the awarded general contractor for use during the project and to create the requested record documents. Refer the specification section 01999 Part 1.4.

Answer: Individual AutoCAD files will be made available at no cost to the general contractor upon formal request and submission of a properly completed release form. The Architectural & Engineering group has been contracted to provide the Electronic Record Drawings based on the general contractor’s record markups.

Preparation and delivery of Electronic Record Drawings, including CDs, PDFs and Reproducible Mylars will not be part of the general contractor’s scope of work.

Question# 113 Confirm that the requirement of printing 8 complete sets of CAD quality drawings on vellum is a requirement as per 019999 Part 1.4.B.1. Also confirm that AutoCAD and Adobe Acrobat files of the drawings are to be submitted on PC CD disks. Are the O&M Manuals as per 019999 Part 1.5 also to be submitted on PC CD disks?

Answer: The Architectural & Engineering group has been contracted to provide the Electronic Record Drawings based on the general contractor’s record markups.

Preparation and delivery of Electronic Record Drawings, including CDs, PDFs and Reproducible Mylars will not be part of the general contractor’s scope of work. VA will accept O&M Manuals and other submittal documents less than 100 MB in file size though a VA approved file sharing site.

Question# 114 The blocking schedule in 061000 calls for 3/4" plywood blocking extending floor to top of wall framing for "products bracketed to walls (sinks, cabinets, and similar products)".

Sheets 31-AS-901, 31-AS-902, and 31-AS-903 show 2x horizontal blocking for all the millwork items. Please verify the intent. What, if any, items located in the patient rooms require this 3/4" plywood blocking as the enlarged plans do not clearly identify items bracketed to the wall such as items located at the headwalls, patient wardrobes, equipment rails, etc.

Answer: 2x horizonal fire-retardant lumber blocking is acceptable. The methods and means of reliably securing heavy loads to the wall shall be at the discretion of the contractor in accordance with industry Best Practice to satisfy each condition.

See also the response to Item 1 above.

Question# 115 In typical patient rooms would it be acceptable to use low voltage [4] zone scene controllers in lieu of individual dimming switches in locations where multiple individual switches are currently shown? (see detail 4B on 31-EP-411 for typical).

Answer: VA will not accept low voltage [4] zone scene controllers in lieu of individual dimming switches.

Question# 116 Will product substitution (or equal) requests be reviewed post bid?

Many specification sections list only 1 manufacturer or supplier. Some reference us to sheet 31-ID-104 and only 1 manufacturer is listed there or there is the comment "shall be" in the finish notes.

It is not uncommon to receive "or equal" bids and we need to know if these will be reviewed by the VA and design team for acceptance during the shop drawing process or if the listed manufacturer/supplier is a sole source with no exceptions.

Answer: Substitutions for finish items proposed by the contractor will be reviewed and may be accepted by the VA.

File details come from the government source that posted it. Updated .