36C24122R0135 0004.docx

DOCX document 87 KB Posted

Attached to
Z2DA--405-13-104 | Inpatient Ward Renovation
Solicitation number
36C24122R0135
Issued by

About this file

This document contains questions submitted in response to a solicitation for the renovation of an inpatient ward at a Veterans Affairs medical center, along with the corresponding answers provided by the contracting officer. Key details include:

  • The solicitation is for the renovation of an inpatient ward at the Veterans Affairs Medical Center in Togus, Maine, involving the phased renovation of three patient zones on the first floor over multiple years. Renovations will include demolition work, installation of new finishes, and upgrades to mechanical and electrical systems.

  • The work will be conducted in three sequential phases to ensure sufficient bed capacity remains available. Each phase must be fully completed before the next phase can begin to allow patients and staff to relocate between areas. The basement and ground floor may involve concurrent utility work as needed.

  • Questions seek clarification on abatement requirements, existing wall and ceiling types, routing for debris removal, coordination needs with other contractors and vendors, and project schedule assumptions. Answers provide additional detail to inform responsive bids for the planned renovations.

The document provides contractors potential questions to consider and the contracting officer's responses to inform competitive bids for the medical center inpatient ward renovation project.

View the file

Other files

File Type Posted
36C24122R0135 0016.docx DOCX document
36C24122R0135 0015.docx DOCX document
Fingerprint Request Form.pdf PDF
Sign-in Sheet 07-06-2023.pdf PDF
36C24122R0135 0014.docx DOCX document
36C24122R0135 0013.pdf PDF
Sign-in Sheet 06-01-2023.pdf PDF
Owners Equipment Schedule updated 6-20-2023.xlsx XLSX spreadsheet
36C24122R0135 0012.docx DOCX document
36C24122R0135 0011.docx DOCX document
S02 36C24122R0135 0010.pdf PDF
36C24122R0135 0009.pdf PDF
Wage Determination VT20230023 02-24-2023.pdf PDF
WRJ Campus Map Inpatient Ward Site Visit Meeting Location 03.21.2023.pdf PDF
36C24122R0135 0008.pdf PDF
36C24122R0135 0007.docx DOCX document
36C24122R0135 0006.docx DOCX document
VHA COVID-19 Operational Plan 1-27-2023.pdf PDF
Building 31 Abatement Diagrams REV-1 02072023.pdf PDF
36C24122R0135 0005.docx DOCX document
Bldg 31 Exterior Elevations _ Building Sections.pdf PDF
Pre-bid site visit sign-in 01-24-2023.pdf PDF
Bldg 31 Basement Intended Route Debris Removal.pdf PDF
Revised Spec 117313 Patient Lifts 20230201.pdf PDF
Original Building Ground _ 1st Floor Plan_Wall Types.pdf PDF
Pre-bid site visit sign-in 01-19-2023.pdf PDF
36C24122R0135 0003.pdf PDF
WRJ Campus Map Inpatient Ward Site Visit Meeting Location 1.24.2023.pdf PDF
Renovate Inpatient Ward Site Visit 1.12.2023.pdf PDF
36C24122R0135 0002.pdf PDF
WRJ Campus Map Inpatient Ward Site Visit Meeting Location 1.19.2023.pdf PDF
WRJ Campus Map Inpatient Ward Site Visit Meeting Location.pdf PDF
36C24122R0135 0001.docx DOCX document
36C24122R0135 Solicitation Final (1).pdf PDF
S02 Inpatient Drawings 09302022 Final Architectural Int Design.pdf PDF
S02 Inpatient Drawings 09302022 Final Plumb FirePro Mech Elec.pdf PDF
S02 EXHIBIT B Subcontractor Information and Consent Form.pdf PDF
S02 EXHIBIT A Project Information Sheet for Contractors.pdf PDF
VAMC-WRJ Building 31 Nursing Unit Renovation Project Manual Vol-1 09302022 Final.pdf PDF
VAMC-WRJ Building 31 Nursing Unit Renovation Project Manual Vol-2 09302022 Final.pdf PDF
VAAR 852.219-75 VA Notice of Limitations on Subcontracting_Certificate of Compliance for Services and Construction 02.docx DOCX document
S02 VHA Supplemental Contract Requirements for Combatting COVID-19.pdf PDF
S02 Inpatient Drawings 09302022 Final Gen LifeSafety Structural.pdf PDF
S02 EXHIBIT C Past Performance Questionnaire.pdf PDF
WD VT20220023 Building.pdf PDF
Show all 45

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 02-02-2023 405-13-104 Department of Veterans Affairs VAMC Togus 1 VA Center Augusta ME 04330 Department of Veterans Affairs VAMC Togus 1 VA Center Augusta ME 04330 To all Offerors/Bidders

36C24122R0135 12-30-2022

X X X ** HOUR & DATE for Receipt of Offers is EXTENDED to: 02-23-2023 13:00 EST X The purpose of this amendment is to provide RFI responses and to extend the RFI and proposal due dates.

See attached RFI responses. A further amendment with additional RFI responses will be forthcoming.

This amendment adjusts the RFI deadline to 02-07-2023 and the proposal due date to 02-23-2023 at 13:00EST.

Stephen Slaby Contracting Officer RFI Questions Submitted with Answers 36C24122R0135 Amendment 0004 405-13-104 Renovate Inpatient Ward, White River Junction, VT Questions #1 - #4 Appear in earlier amendments Question# 5 The SF 1442 and page 14 of 66, 8. states “Offerors must be both VISIBLE and VERIFIED by the Department of Veterans Affairs Center for Verification and Evaluation (CVE) at time of submission of offer and at time of award.” Please note that effective January 1, 2023, Section 862 of the National Defense Authorization Act (NDAA) for Fiscal Year (FY) 2021 transferred responsibility for VOSB and SDVOSB certification from the VA to SBA. Although our CVE verification is still active, does the government want a copy of our SBA VetCert record showing we are listed as a certified SDVOSB in the new system submit in addition to the CVE verification?

Answer: This amendment removes the quoted text from the solicitation. The VA Contracting Officer will manually verify SDVOSB/VOSB certification status in the Veteran Small Business Certification (VetCert) database at https://veterans.certify.sba.gov.

Question# 6 Page 9 of 66, 3.2.1 and 3.2.3 General Instructions states “Include the question before each narrative” and “Each question should be covered in sufficient detail to clearly address all required information.” Please clarify what the government means by “question”. There are no specific “questions” listed in the Volume 1 instructions

Answer: There word “question” in this case means the “factor” or “subfactor.” Please list the factor or subfactor title prior to any required narrative or information.

Question# 7 Page 10 of 66, 3.5.3 Subfactor C. Personnel and Organization list “Infection Control Manager” as a personnel category. Please provide the government’s expectation for this role and their desired qualifications.

Answer: Expectations and desired qualifications for the role are discussed in Section 013526, Section 1.12 and Section 013533 Part 3 and include:

· Educated and trained in infection control prevention measures.

· Experience participating in and adhering to ICRA permit requirements.

· Ability to recognize potential causes, hazards and mitigations needed when disturbing areas that could introduce dust into the healthcare environments.

· Experience training & educating staff in infection control measures per (as required by Section 013526, Part 1.12, paragraph E).

· Has prepared dust control programs as outlined in Section 013526, part 1.12, paragraph F.

· Experience maintaining preventative measures selected to avoid introduction of dust similar to Section 013526, Part 1.12, paragraphs H, I & J.

Question# 8 Page 13 of 66, 3.7.1 Volume II Price Information Submission Requirements states that the Volume II Price submission should contain a signed and completed SF 1442, acknowledgement of all amendments, the pricing schedule (A.3 PRICE/COST SCHEDULE), and a VAAR 852.219-75 VA Notice of Limitations on Subcontracting—Certificate of Compliance for Services and Construction. Please confirm that these are the only documents to be provided within the Volume II Price proposal.

Answer: Confirmed. Offerors are also authorized, but not required, to provide any additional pricing information to include subcontractor quotes.

Question# 9

Regarding HVAC controls/building automation, is there a brand that we must use? Siemens? JCI? Honeywell?

Answer: As noted in Section 23 09 00, Part 2.1, the building automation system manufacturer used at this campus is Siemens.

Question# 10 Interior walls to be demolished, noted by Demolition Note #8 on sheet 31-AS-106, please confirm whether these [are] stud and drywall partitions, masonry, or lath and plaster?

Answer: Interior partitions appear to be a mix of metal stud with gypsum board or metal stud with gypsum plaster on metal lathe. The distribution and quantities of each type have not been inventoried. Attached, for general reference are PDF scans of the original building Ground & First Floor construction floor plans and wall/partition types, 3 drawings.

Question# 11 Existing walls noted by Demolition Note #8 on sheet 31-AS-106, do all these walls extend to the deck above? If so, what are the floor-to-floor heights? If not, what is their height?

Answer: The existing partition heights vary although it appears that the significant majority extends to ceiling height with some exceptions. The distribution and quantities of different partition heights have not been inventoried. Attached, for general reference, are PDF scans of the original building Ground & First Floor construction floor plans and wall/partitions types, 3 drawings. See existing building structural drawings included in the bidding documents to determine floor-to-floor dimensions.

Question# 12

Ceilings to be demolished, noted by Demolition Note #5 on sheet 31-AS-106, are these drywall on studs/grid, acoustical, or lath and plaster?

Answer: The existing ceilings, based upon limited site photographs, appear to be a mix of lay-in acoustical panels in a standard suspension grid and gypsum wallboard or gypsum plaster on lathe and suspension system. The distribution and quantities of each ceiling type have not been inventoried and all bidders have been encouraged to visit the project site to ascertain existing conditions first-hand.

Question# 13 Is there a preferred, or mandated, route for removal of demolition debris? If so, please specify for each level: basement, ground and first.

Answer: There is no mandated route for removal of demolition debris. The intended route for each phase is as follows: Ground Floor/Phase 1: Exit the ground floor through stairway #4 (use of this stairway will require compliance with any ILSMs required for fire safety in the facility while the stairway is dedicated to contractor’s use). 1st floor South-east Patient Zone/Phase 2: Per drawing 31-AS-104 an elevator (elevator #3) will be reserved for contractor use. Contractor may load carts into elevator and travel to basement level. Carts can be rolled through the basement to the exit door located adjacent to the loading dock (see attached plan of intended route). 1st floor North-west Patient Zone/Phase 3: Per drawing 31-AS-104 an elevator (elevator #1) will be reserved for contractor use. Contractor may load carts into elevator and travel to basement level. Carts can be rolled through the basement to the exit door located adjacent to the loading dock (see attached plan of intended route).

Contractor may propose other means of debris removal that does not impact healthcare functions. Any proposal must be approved by VA.

Question# 14 Is there any mold remediation required?

Answer: The VA is not aware of any mold remediation required with this project.

Question# 15 Page 13 of 66, 3.7.1.2 states “Offerors shall provide all price information necessary to provide a meaningful basis for Government's analysis and evaluation of price for the project.” Are any other pricing documents in addition to The Price/Cost Schedule and page 2 of the SF 1442 required to be submitted, or are these all that are required?

Answer: See response to Question (8) above. All required forms to be submitted with the Volume 2 Price Information are listed in item 3.7 Volume II – Price Information. The intent of that paragraph was to allow offerors the ability to provide additional price information, such as subcontractor quotes, if the offeror would like to.

Question# 16 How high is the asbestos wall tile present on the 1st floor? What rooms is it present in? From the site visit, it appears that tile is present in rooms other than hallways and rooms not indicated on the drawings.

Answer: Updated abatement drawings to follow in a future amendment.

Question# 17 Is it the intent to keep the ICU operational during Phase 3? If so, when should the renovation of the corridor in front of the ICU Door occur?

Answer: The ICU shall remain operational and occupied at all times, no exceptions. The contractor shall coordinate with the Owner the specific sequencing of sub-activities within the overall phasing strategy and these special situations shall be reflected in the contractor’s construction schedule.

Question# 18 Is it the intent for Phase 1 to be completed before Phase 2, or can both Phase 1 and Phase 2 happen concurrently?

Answer: The phasing is sequential, one following the other, to ensure sufficient bed capacity throughout the duration of the project.

Question# 19 If Phase 1 is to happen before Phase 2, there is Phase 2 work required in the area of Phase 1 ceilings. If occupied, acknowledge that this will require extreme coordination and access for work, specifically in areas with hard ceilings. A minimum of a week will be needed for access each time for all hard ceiling areas due to the process of demo, above ceiling work, patch back, paint, and touchup/clean. This will most likely require patients or staff to vacate the given areas.

Answer: The contractor shall coordinate with the Owner the specific sequencing of sub-activities within the overall phasing strategy and these special situations shall be reflected in the contractor’s construction schedule.

Question# 20 Will the ground floor be occupied or unoccupied during the 1st floor piping work in Phases 2 and 3? If occupied, acknowledge that this will require extreme coordination and access for work, specifically in areas with hard ceilings. A minimum of a week will be needed for access each time for all hard ceiling areas due to the process of demo, above ceiling work, patch back, paint, and touchup/clean. This will most likely require patients or staff to vacate the given areas.

Answer: All spaces of the Ground Floor during Phase 2 & 3 shall be occupied at all times but it is well understood that certain invasive activities will render specific limited areas un-occupiable on a short-term basis. The contractor shall coordinate with the Owner the specific sequencing of sub-activities within the overall phasing strategy and these special situations shall be reflected in the contractor’s construction schedule.

Question# 21 The Phasing Plan doesn’t mention anything about the Basement level. Is that work to be performed concurrently with Phase 1 as needed, or some other way?

Answer: Peripheral utility work shall be implemented at a time appropriate to the overall phasing strategy with the understanding that each phase shall be fully completed and occupied prior to the commencement of the next phase. The contractor shall coordinate with the Owner the specific sequencing of sub-activities within the overall phasing strategy and these special situations shall be reflected in the contractor’s construction schedule.

Question# 22 Who is the current vendor(s) on campus that facilitate(s) access controls hardware and programming and security? Are they to be used for the access controls and security for this contract, or can other firms be used?

Answer: Refer to General Note 16 of Doors, Frames & Hardware Schedule, Drawing 31-AS-602, as follows:

Question# 23 What type of key cores are utilized on this campus? Are the new cores to be consistent with existing campus cores?

Answer: VAMC key cores are 7-pin, TE Keyway. New cores to be consistent with existing campus cores.

Question# 24 Confirm that work areas of each phase will be unoccupied during the renovation of each phase.

Answer: Generally, this is the intent but it is inevitable that there will be brief periods of time when it becomes necessary for supportive work to occur in occupied areas. The contractor shall coordinate with the Owner the specific sequencing of sub-activities within the overall phasing strategy and these special situations shall be reflected in the contractor’s construction schedule.

Question# 25 Is it the intention of the VA to move out of the South-East patient zone and into the renovated Ground Floor Nursing Unit? If so, how much time should be figured between Phase 1 and Phase 2 for the VA to clear the South-East patient zone and occupy the Ground Floor Nursing Unit so that work in Phase 2 can begin?

Answer: This is the intent. The contractor shall assume 1 week for the Owner to transition between phases, measured from the time that the new work is fully complete and ready for occupancy.

Question# 26 How much time should be figured between Phase 2 and Phase 3 for the VA to clear the North-West patient zone and occupy the South-East patient zone so that work in Phase 3 can begin?

Answer: The contractor shall assume 1 week for the Owner to transition between phases, measured from the time that the new work is fully complete and ready for occupancy.

Question# 27 No abatement plan or notes were found for the basement. Are there any hazardous materials in the basement that will require abatement? If so, please provide information on such.

Answer: Updated abatement drawings to follow in a future amendment.

Question# 28 AS-501 discusses work with a Sure Hands Lift & Care Systems, an outside vendor, with some work under us and some under the existing POs with the VA. What are the terms of this purchase order as far as mobilizations and timeframes? Please provide the terms of this purchase order, or confirm that scheduling and progression of install will be as determined by the Contractor.

Answer: The contractor shall coordinate with the SureHands representatives named here:

Carol M. Lavelle, Regional Sales Representative, Northern New England SureHands Lift & Care Systems C. 845-978-0565; email: c.lavelle@surehands.com www.surehands.com

Shane Thompson, Director of Strategic Initiatives SureHands Lift & Care Systems C. 407-310-4004; email: Sthompson@surehands.com www.surehands.com

Question# 29 Sheet AS-105 B abatement plan legend does not appear to be consistent with field conditions from the site visit specifically with the ceramic wall tile in rooms and corridors please review and confirm legend is correct.

Answer: Updated abatement drawings to follow in a future amendment.

Question# 30 Sheet AS-105 A abatement plan only indicates Floor tile mastic and HVAC Duct Caulking please confirm no wall tile to be abated and removed on ground floor. During site visit ceramic tile was noted in hallways and bathrooms.

Answer: Updated abatement drawings to follow in a future amendment.

Question# 31 On Drawing 31-AS-109 (Ground Floor Proposed Plan) the floor type is shown as RS-1 in Bedrooms G-83,G-84,G-85, G86. On Drawing 31-ID-105 – Interior Finish Schedule 3 (Ground Floor) the floor finish for these rooms is shown as ETR. On Drawing 31-ID-104 ( Interior Finish Legend) there is no floor covering finish code for ETR. What is the correct floor type for these rooms?

Answer: The floor covering in bedrooms G-83, G-84, G-85 and G-86 shall be existing to remain (ETR) and appears to be 12”x12” vinyl composition tile based upon inspection of site photographs. Match exist floor covering where patching is necessary due to construction activities.

Question# 32 On Drawing 31-AS-109 (Ground Floor Proposed Plan) the floor type is shown as RS-1 in Bathrooms G-83A, G-84A ,G-85A, G86A. On Drawing 31-ID-105 – Interior Finish Schedule 3 (Ground Floor) the floor finish for these rooms is shown as TL (Tile Flooring). What is the correct floor type for these rooms?

Answer: The floor covering in toilet rooms G-83A, G-84A, G-85-A and G-86A shall be RS-1 to minimize the potential for toilet re-setting issues due to tile flooring thickness.

Question# 33 On drawing 31-AS-601- /Details 7-9/ Borrowed Light- BL-1, BL-2, BL-3 there are no details giving pertaining to these other than dimensions, no basis of design, and no specifications in the Project Manual. Please provide this missing information.

Answer: Borrowed Lights BL-1, BL-2 and BL-3 are standard hollow metal frames pursuant to details 5 & 6 on Drawing 31-AS-601.

Question# 34 Per details 5 and 6 on AS-601, the window frames are hollow metal. What type of glass is required for these HM window frames?

Answer: Use impact-and-fire-rated ceramic safety glass in rated openings. Use impact-resistant laminated safety glass in non-rated openings. This is consistent with General Note 12 of the Door, Frame and Hardware Schedule, Drawing 31-AS-602.

Question# 35 Who is responsible for contracting with the Commissioning Agent (CxA), the VA or the General Contractor?

Answer: The Commissioning Agent has been engaged by the Owner through the A-E contract.

Question# 36 Reference 01 00 00, 1.21, E. Is a meter required for temporary electrical?

Answer: A meter shall not be required for temporary electrical service to a job trailer or for electricity used within the inpatient ward when used for renovation activities.

Question# 37
23.Reference the RFP, Instructions, Conditions and Other Statements to Bidder/Offerors, Part 3.5.3 under Key Personnel. Are the Site Superintendent, Quality Control Manager, Infection Control Manager and Safety Manager required to all be separate dedicated personnel on this project, or can some positions be dual hat?

Answer: Section 014500, 3.4, A, stipulates that the site specific safety officer cannot be the CQC manager. Section 013526 1.7, D, indicates that SSHO or an equally qualified Designated Rep will maintain a presence on the site during construction operations. Section 013526 1.7 F requires the site specific health officer to be separate from the superintendent. There is no requirement that the Site Superintendent, QC manger and infection control manager be separate dedicated personnel. There is no requirement that the infection control manager and safety manager be separate dedicated personnel.

Question# 38 Reference the RFP, Instructions, Conditions and Other Statements to Bidder/Offerors, Part 3.5.3 under Organizational Hierarchy. With this project being publicly available on Sam.gov for any subcontractor to retrieve and assemble a bid, it is extremely difficult for us as a general contractor to know what all subcontractors are going to provide a proposal until we receive all of them, and most of the time that occurs within the last hours before our bids are due. This makes it virtually impossible for us to get their information and provide it in the technical proposal. Is it absolutely required that we submit a list of major subcontractors and their information with our proposal? If so, could this portion of the technical proposal be delayed 48 hours for submission to give us time to see what all subcontractors provide proposals and be able to gather the needed information?

Answer: Offers are required to be submitted in accordance with the Solicitation. The proposal due date is extended as a result of this amendment (see first page of this amendment).

Question# 39 On Drawing 31-AS-110A between Sections 2.2 and 2.7 there appears to be 2 windows that are not marked. Should these be Type A Windows?

Answer: Yes. These openings were inadvertently overlooked and should be replaced with Type A windows.

Question# 40 Reference 01 45 00, 3.4.B. Is the CQC Manager required to be a dedicated person with no other duties, or can they be dual hat with the superintendent?

Answer: There is no requirement that the Site Superintendent and CQC manager be separate dedicated personnel.

Question# 41 On Drawings 31AS-110A and 31-AS-601 Detail 11 there are notes stating: ” TYPICAL AT ALL EXTERIOR WINDOWS: Contractor shall furnish and install exterior window shades”

Answer: This is correct as noted.

Question# 42 Drawing 31-AS-407 Detail 8 states: “WINDOW BLINDS BY OWNER (Typical)”. Please clarify. Are all window blinds OFOI??

Answer: This is an error. Contractor shall furnish and install window blinds.

Question# 43 Reference 01 45 02. Is there a specific QCS desired by this VA?

Answer: Section 01 45 02 references the 3-Phase QC system but the contractor may propose an alternate QC system.

Question# 44 Are there any liquidated damages associated with this project / project duration?

Answer: No.

Question# 45 Reference spec section 11 73 13. Is there a point of contact with Sure Hands Lift & Care Systems you can share? Specification 117313-2.1.B states that a portion of the patient lift scope is provided and installed under an existing contract while the remainder is to be included in our pricing for this project. We need to coordinate with Sure Hands to ensure that we provide the necessary components for the owner-furnished portion and to get accurate pricing for the models required in our bid.

Answer: Bidders may contact the following:

Carol M. Lavelle, Regional Sales Representative, Northern New England SureHands Lift & Care Systems C. 845-978-0565; email: c.lavelle@surehands.com www.surehands.com

Shane Thompson, Director of Strategic Initiatives SureHands Lift & Care Systems C. 407-310-4004; email: Sthompson@surehands.com www.surehands.com

Question# 46 Reference sheet 31-AS-602 Door Schedule. Door DFH-6 refers to deleting doors under a deductive alternate. The Bid Schedule calls for a one lump sum price and mentions nothing of any deductive alternates. Please clarify.

Answer: There are no deductive alternates. The reference to Deductive Alternate DA-5 in DFH-6 is an error.

Question# 47 Specification 12 24 00 Window Shade System/ Part 2 / Products /A / Basis of Design calls for: Mecho 5 System Roller Shade w/ translucent and blackout fabric to be Alkenz 4000 series. Drawing 31-AS-104 Miscellaneous Finish Note #10 calls for: Mecho 5 double roll w/ Fabric 1: Ecoveil 0950 Series and Fabric 2: Equinox Blackout Series 0100. Which is correct?

Answer: Miscellaneous Finish Note 10 on Drawing 31-AS-104 is correct.

Question# 48 Regarding finishes for the ground floor, the corridor is not labeled and there are no floor or wall finishes designated on the plan, sheet AS-109, nor the finish schedule, ID-105. Please provide finish selections.

Answer: Match existing where not otherwise identified. There is no intent to replace or change these finish materials.

Question# 49 Sheet AS-109 depicts proposed renovations to the ground floor and shows some, not all, of the proposed floor finishes. It lacks wall finishes. ID-101 and ID-102 seem to have all finishes covered for the first floor. Please provide similar drawings for the ground floor with complete finish designations for all surfaces.

Answer: Match existing where not otherwise identified. There is no intent to replace or change these finish materials.

Question# 50 Drawings clearly indicate that first floor patient rooms are to receive plastic laminate / vinyl acrylic covered headwalls (e.g. AS-416 and ID-103), but it appears that ground floor rooms do not (e.g. AS-420). Please confirm this is correct. Are the plastic laminate headwalls OFOI?

Answer: The Ground Floor patient rooms do not receive plastic laminate / vinyl acrylic covered headwalls. The plastic laminate / vinyl acrylic covered headwalls throughout the First Floor are contractor furnished and installed.

Question# 51 Specification section 11 73 13 Patient Lifts is confusing as written. Can you verify it is correct.

Answer: The entire specification section 11 73 13 Patient Lifts is replaced in entirety by the attached specification dated February 2, 2023. Please see plan sheet AS-501 which contain the notes explaining the arrangement between bidder, VA, and the sole source overhead lift manufacturer/installer.

Question# 52 019113 mentions in a couple of locations “Cx Associates” including the project directory. Please confirm that Cx Associates is NOT the named or otherwise required Cx agent and that this function is to be provided by the GC via any acceptably qualified subconsultant?

Answer: Cx Associates is the commissioning agent for the project. Cx Associates is contracted through the A/E team as part of “Type C Services,” and a separate Cx agent will NOT be required to be provided by the GC. Requirements for participation in the commissioning process by the GC and applicable sub-contractors are outlined in spec section 019113.

Question# 53 019113 mentions the use of “CxAlloy” in numerous locations.

a. Is use of this tool a requirement? Typically we distribute via email a pdf issues log / status report.

b. Will the government provide access or will we need to obtain a suitable level of access (Subscription)?

Answer: CxAlloy is a centralized, online software that Cx Associates uses to track all commissioning-related activities. This includes prefunctional checklists, functional performance tests, the commissioning issues log, and field visit reports. Cx Associates hosts this software, so there is no additional cost to the GC or subcontractors. All applicable team members will be given access. Per the specifications, it is a requirement that CxAlloy be used by the team (including GC and subcontractors) for the communication of and resolution to commissioning related issues as well as for completion of commissioning related documentation including prefunctional checklists and functional performance tests. Details about how to use this software will be provided in the commissioning plan and during the commissioning kick off meeting.

Question# 54 Will there be a list of contractors published who will be bidding on this project? We would like to offer our proposal to as many as possible. My contact information is: gcarr@smrtinc.com

Answer: The site visit sign-in sheets have been distributed in Amendments 0002 and 0003.

Question# 55 Are we required to submit hard copies of the Bid Guarantee, or will scanned copies be acceptable with the electronic version of the proposal? If hard copies are required, are they to be received by your office prior to the submission deadline?

Answer: Scanned copies are acceptable with the electronic version of the proposal.

Question# 56 Will the VA provide a Form CERT-134 to the awarded contractor for sales tax exemptions?

Answer: A tax exempt certificate will be provided for this project.

Question# 57 Under Part 4.10 Clauses Incorporated by Reference, please include / add FAR Clause 52.216-4 for Economic Price Adjustment for Labor & Materials due to the current economic climate.

Answer: The VA does not intend to insert this clause into the contract. There are other remedies available in the resulting contract to both parties regarding any changes that may occur during performance.

See attached document: Original Building Ground _ 1st Floor Plan_Wall Types.

See attached document: Bldg 31 Basement Intended Route Debris Removal.

See attached document: Revised Spec 117313 Patient Lifts 20230201.

image1.png image2.png