This document provides details for a federal construction solicitation for the Fort Logan National Cemetery Phase 1A Expansion project. The solicitation is seeking a firm-fixed price construction contract valued between $20-50 million to provide all labor, materials, equipment and supervision for expanding the cemetery as shown in the project plans, drawings and specifications. The solicitation is fully set aside for Service-Disabled Veteran Owned Small Businesses and is subject to the Davis Bacon Act and Buy American Act. The proposal due date is May 16, 2023 by 3:00PM Eastern time. Anticipated contract award is July 31, 2023 with a notice to proceed to follow. The period of performance is 730 calendar days from notice to proceed.

View the file

Other files

File Type Posted
S06 - 36C10F23R0013 0001 Amendment -PPI Response.pdf PDF
S06 - DOL Wage Determination CO20230002 04-07-2023.pdf PDF
S06 - Ft. Logan Sign-in 4-19-23.pdf PDF
Bid Docs - Reports - Phase 1 Expansion Geotechnical Report.pdf PDF
S06 - 36C10F23R0013 Pre-Proposal Inquiry Responses.docx DOCX document
S02 FT LOGAN NC PHASE 1A-ALT4 - 2023 02 10(5 of 5).pdf PDF
S02 FT LOGAN NC PHASE 1A-ALT3 - 2023 02 10(2 of 2).pdf PDF
S02 FT LOGAN NC PHASE 1A-ALT1 - 2023 02 10 (4of5).pdf PDF
S02 FT LOGAN NC PHASE 1A SPECIFICATIONS - 2023 02 21.pdf PDF
S02 FT LOGAN NC PHASE 1A-ALT4 - 2023 02 10(4 of 5).pdf PDF
S02 FT LOGAN NC PHASE 1A-ALT2 - 2023 02 10(1 of 2).pdf PDF
S02 - DOL Wage Determination CO20230002 2-24-2023.pdf PDF
S02 FT LOGAN NC PHASE 1A-ALT4 - 2023 02 10(2 of 5).pdf PDF
S02 Pre-Proposal Inquiry (PPI) Form 36C10F23R0013.docx DOCX document
S02 FT LOGAN NC PHASE 1A-Base - 2023 02 10 (6 of 6).pdf PDF
S02 FT LOGAN NC PHASE 1A-ALT1 - 2023 02 10 (3of5).pdf PDF
S02 FT LOGAN NC PHASE 1A-ALT3 - 2023 02 10(1 of 2).pdf PDF
S02 FT LOGAN NC PHASE 1A-Base - 2023 02 10 (4 of 6).pdf PDF
S02 FT LOGAN NC PHASE 1A-Base - 2023 02 10 (5 of 6).pdf PDF
S02 FT LOGAN NC PHASE 1A-ALT1 - 2023 02 10 (5of5).pdf PDF
S02 FT LOGAN NC PHASE 1A-ALT4 - 2023 02 10(1 of 5).pdf PDF
S02 FT LOGAN NC PHASE 1A-ALT4 - 2023 02 10(3 of 5).pdf PDF
S02 - VAAR 852.219-75 VA Notice of Limitations on Subcontracting - Certification.pdf PDF
S02 - DOL Wage Determination CO20230009 2-24-2023.pdf PDF
S02 FT LOGAN NC PHASE 1A-Base - 2023 02 10 (3 of 6).pdf PDF
S02 Past Performance Questionnaire 36C10F23R0013.docx DOCX document
S02 FT LOGAN NC PHASE 1A-ALT1 - 2023 02 10 (1of5).pdf PDF
S02 FT LOGAN NC PHASE 1A-Base - 2023 02 10 (2 of 6).pdf PDF
S02 FT LOGAN NC PHASE 1A-Base - 2023 02 10 (1 of 6).pdf PDF
S02 FT LOGAN NC PHASE 1A-ALT2 - 2023 02 10(2 of 2).pdf PDF
S02 FT LOGAN NC PHASE 1A-ALT1 - 2023 02 10 (2of5).pdf PDF
S02 - 36C10F23R0013 - Final - RFP - Ft Logan Phase 1A.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IAS

FORT LOGAN

NATIONAL CEMETERY

PHASE 1A CEMETERY EXPANSION

LAKEWOOD, COLORADO

SOLICITATION 36C10F23R0013

PROJECT # 888-043

PRE-PROPOSAL CONFERENCE

APRIL 19, 2023

1 Office of Construction and Facilities Management

Agenda

Opening Remarks NCA Mission Solicitation Summary Milestones Project Scope and Overview Site walkthrough

2 Office of Construction and Facilities Management

Opening Remarks

Introductions VA Representatives

VA CFM: David Bullerwell, Contracting Officer

VA CFM: Rachel Beason, Contract Specialist

VA CFM: Rob Newstead, Resident Engineer

FLNC: Roderick (Tony) Thomas, Director

3 Office of Construction and Facilities Management

NCA Mission The National Cemetery Administration honors Veterans and their families with final resting places in national shrines and lasting tributes that commemorate their service and sacrifice to our Nation.

In 1865, during his second inaugural address, President Abraham

Lincoln pledged: “To care for him who shall have borne the battle and for his widow and his orphan.”

In 2023, the VA upholds this pledge through the mission:

“To fulfill President Lincoln’s promise to care for those who have served in our nation’s military and for their families, caregivers, and survivors.”

4 Office of Construction and Facilities Management

Solicitation Overview

Solicitation is set aside for Service Disabled Veteran Owned Small Business (SDVOSB) in accordance with 38 U.S.C. 8127(d).

SDVOSB Offerors must be registered in SAM and registered & verified in VetCert prior to submission Annual Representation and Certification https://www.sam.gov/SAM/ Small Business Administration Veteran Certification

(VetCert) https://veterans.certify.sba.gov/ https://veterans.certify.sba.gov/

5 Office of Construction and Facilities Management

Service-Disabled

Veteran-Owned Small Business VA Office of Small and Disadvantaged

Business Utilization (OSDBU) Washington, D.C.

http://www4.va.gov/osdbu/

Contact OSDBU for information on Joint Ventures Teaming Agreement Mentor Protégée (See VAAR 819-71) SBA Veteran Certification (VetCert) http://www4.va.gov/osdbu/

6 Office of Construction and Facilities Management

Project Cost Range Between $20,000,000 - $50,000,000

Contract Type: Firm Fixed Price Evaluation Method: Best Value/Tradeoff

Federal , State, and Local Tax (FAR Clause 52.229-3) Is the Responsibility of the Contractor, include it in your proposal price Construction Wage Rate Requirements (Davis

Bacon Act) Applies Buy American Act Applies

7 Office of Construction and Facilities Management

Contract Line Item Numbers (CLINs 001-006)

CLIN 001: Base Bid - All work necessary to construct the base project CLIN 002: Base Bid - Furnish and deliver pre-placed crypts CLIN 003: Add Alternate #1 – Repair Roadway, Phases 1 - 5 CLIN 004: Add Alternate #2 – Renovate Public Information Center, Honor

Guard Building and Public Restroom CLIN 005 : Add Alternate #3 – Renovate admin/maint building 1301, and additional misc. maint. buildings CLIN 006 : Add Alternate #4 – Repair Roadways, Phases 6 - 8

Period of Performance 730 calendar days after the Notice to Proceed for base bid and any/all add alternate work.

8 Office of Construction and Facilities Management

Bid Bond/Bid Guarantee (SF 24)

See Solicitation pages 9 & 13 Bond amount 20% of the offer price but shall not exceed $3,000,000 Volume II, TAB 2, of your emailed proposal must contain a legible, scanned copy of your Executed Bid Guarantee (SF-24). Please shade any raised seals with pencil lead to make them legible before you scan the bond.

An original, hard copy, executed Bid Guarantee (on form SF-24) must be mailed to the Contracting Officer not later than 5 business days after the proposal due date/time. See page Solicitation pg 13

Make sure your bond is in compliance with Far Part 28

Performance & Payment Bonds (SF 25) Required Penal sum = 100% of award amount Required of awardee within 10 calendar days of award.

9 Office of Construction and Facilities Management

Liquidated Damages $2,465.60 for each calendar day of delay

Insurance See Solicitation pages 59 Certificate of Insurance required prior to commencing work

Worker’s compensation and employers liability General Liability Automobile Liability

10 Office of Construction and Facilities Management

Pre-Proposal Inquiries (PPI)/Requests for Information (RFI’S) Use Solicitation PPI Form (Attachment ) Questions Due: April 25, 2023 at 4:00PM (Eastern)

Email to:

David.Bullerwell@va.gov, and Rachel.Beason@va.gov

The subject line to read “Ft. Logan Phase 1A | 36C10F23R0013”

Answers posted on or about: May 2, 2023 mailto:David.Bullerwell@va.gov mailto:Rachel.Beason@va.gov

11 Office of Construction and Facilities Management

Submission Instructions

Volume I – Technical Proposal (limit 80 pages) Title Page (see Solicitation) Factor 1 – Firm Experience (40 pages)

Sub-factor 1.1 – Project Experience Sub-factor 1.2 – Project Organizational Chart and Key Personnel

Factor 2 – Construction/Project Management (30 pages) Sub-factor 2.1 – Technical Approach Sub-factor 2.2 – Capacity to Perform Sub-factor 2.3 – Schedule

Factor 3 – Past Performance (6 pages) Factor 4 – Union Participation (4 pages)

12 Office of Construction and Facilities Management

Submission Instructions

Volume II – Price Proposal (limit 40 pages) Title Page (see Solicitation) Tab 1 –

Executed Solicitation, Offer and Award Form (SF1442) (pages 1-2).

Offeror shall complete Blocks 14-20C.

Completed Offer Schedule (page 3).

Solicitation Amendments – complete boxes 15A-C (SF 30) for each amendment issued & include a copy in your proposal.

Tab 2 –

Scanned, legible, copy of Executed Bid Guarantee (SF-24) Tab 3 –

Printed copy “Representations and Certifications” as submitted on https://www.sam.gov/SAM/

13 Office of Construction and Facilities Management

Submission Instructions

Proposal Submission Instructions Email:

• Submit one (1) copy of the Technical Proposal (Volume I), & one (1) copy of their Price Proposal (Volume II).

Emailed proposals shall be sent to the Contracting Officer at Rachel.Beason@va.gov and David.Bullerwell@va.gov by the due date & time shown in Box 13a of solicitation form SF 1442 (or as subsequently amended).

40 mb max file size limit If the file size is greater than 40MB, separate document into multiple files and label files logically & sequentially, for example Volume 1-part 1, Volume 1-part 2, etc.

Adobe PDF is the only file format that will be accepted.

mailto:Rachel.Beason@va.gov mailto:David.Bullerwell@va.gov

14 Office of Construction and Facilities Management

Milestones 1 Solicitation Issued April 4, 2023

2 Proposal Due Date May 16, 2023, 3:00PM Eastern

3 Contract Award (TENTATIVE) July 31, 2023

4 Notice To Proceed (TENTATIVE) TBD

15 Office of Construction and Facilities Management

Project Scope/Overview

VA Office of Construction & Facilities Management

Rob Newstead, RE

16 Office of Construction and Facilities Management

QUESTIONS???

No technical questions will be answered today or during the pre-proposal site visit.

Submit all technical Requests for Information in writing per the solicitation.

Questions

Slide Number 1
Agenda
Opening Remarks
NCA Mission
Solicitation Overview
Solicitation Overview�Service-Disabled�Veteran-Owned Small Business
Solicitation Overview
Solicitation Overview
Solicitation Overview
Solicitation Overview
Solicitation Overview
Solicitation Overview�Submission Instructions
Solicitation Overview�Submission Instructions
Solicitation Overview�Submission Instructions
Milestones
Project Scope/Overview
Questions???��No technical questions will be answered today or during the pre-proposal site visit. ���Submit all technical Requests for Information in writing per the solicitation.