About this file

This is a pre-bid meeting presentation for the Kenton County Airport Board (KCAB) regarding the Concourse A Apron Reconstruction - Bid Package 2 project at Cincinnati/Northern Kentucky International Airport in Boone County, Kentucky. The project involves the demolition, removal, and replacement of Portland Cement Concrete (PCC) pavement and bituminous pavement around Concourse A, encompassing approximately 57,100 square yards of work. Major project elements include utility modifications, grading improvements, pavement markings installation, electrical modifications, and coordination with hydrant fueling work performed by others. The work will span four construction seasons from 2026 through 2029, with phasing designed to impact only two gates at a time. A pre-bid meeting was held on January 8, 2026, at 10:00 am at CVG Centre, Admin. Offices in Erlanger, Kentucky. Written questions are due by 11:59 pm on January 20, 2026, with answers posted by January 22, 2026. The bid submission deadline is Thursday, February 5, 2026, at 2:00 pm, submitted electronically through the owner's online bidding system.

The project involves approximately 200 line items across four construction years, suggesting a comprehensive infrastructure investment potentially exceeding $24 million in total value. Bidders must submit a Proposal Bond of at least 5% of the total bid amount and provide Payment and Performance Bonds for 100% of the contract value from a surety company authorized to do business in Kentucky. Contractors must demonstrate expertise in airport pavement construction and establish a Contractor Quality Control Program (CQCP) with a full-time Program Administrator possessing a minimum of five years of quality control pavement construction experience and appropriate professional credentials. The project is federally funded through the Airport Improvement Program (AIP) and subject to federal requirements including Buy American Preference provisions, Davis-Bacon prevailing wage standards, and civil rights regulations. Disadvantaged Business Enterprise (DBE) participation is required under 49 CFR Part 26, with bidders required to demonstrate good faith efforts to include DBE contractors. Liquidated damages are assessed at $2,500 per day for each phase for failure to meet schedule deadlines.

View the file

Other files for this state and local contract opportunity

Other files attached to Concourse A Apron Reconstruction - Bid Package 2, newest first.
File Type Posted
Concourse_A_Apron_Reconstruction_-_Bid_Package_2_(Addendum_#5_Revision).pdf PDF
25-075-ITB_Conc_A_Apron-BP2_-_Exh_A-Prop_Forms_(AIP)-Add_#5_02.10.26.pdf PDF
25-075-ITB_Conc_A_Apron-BP2_-_Exh_B-Contract&Bonds-Add#5_02.10.26.pdf PDF
25-075-ITB_Conc_A_Apron_Reconstr-BP2_-_Tech_Specs_-_Add_#5_02.10.26.pdf PDF
25-075-ITB_Conc_A_Apron_Reconstr-BP2_Dwgs_Add_#5_02.10.26.pdf PDF
25-075-ITB_Davis-Bacon_Wage_Rates_-_Highway_01.02.2026.pdf PDF
Concourse_A_Apron_Reconstruction_-_Bid_Package_2_(Addendum_#1_Revision).pdf PDF
25-075-ITB_Conc_A_Apron_Reconst-Bid_Pkg_2-Exh_A_-_Proposal_Forms_(AIP)_01.16.26.pdf PDF
25-075-ITB_Conc_A_Apron_Reconst-Bid_Pkg_2_-_Exh_B-Contract_&_Bonds_01.16.26.pdf PDF
25-075-ITB_Conc_A_Apron_Reconstr-Bid_Pkg_2_-_Addendum_#1_Tech_Specs_01.16.26.pdf PDF
25-075-ITB_Conc_A_Apron_Reconstr-Bid_Pkg_2_-_Addendum_#1_Drawings_01.16.26.pdf PDF
25-075-ITB_Pre-Bid_Meeting_Sign-In_Sheets.pdf PDF
25-075-ITB_Pre-Bid_Meeting_Sign-In_Sheets.pdf PDF
25-075-ITB_Pre-Bid_Meeting_-_Teams_Attendance_01.08.26.pdf PDF
25-075-ITB_Pre-Bid_Meeting_Presentation.pptx PPTX presentation
25-075-ITB_Pre-Bid_Meeting_-_Teams_Attendance_01.08.26.pdf PDF
25-075-ITB_Pre-Bid_Meeting_Agenda.pdf PDF
25-075-ITB_Pre-Bid_Meeting_Agenda.pdf PDF
Concourse_A_Apron_Reconstruction_-_Bid_Package_2.pdf PDF
25-075-ITB_Conc_A_Apron_Reconst-Bid_Pkg_2_-_Ad.pdf PDF
25-075-ITB_Conc_A_Apron_Reconst-Bid_Pkg_2_-_Ad.pdf PDF
25-075-ITB_Conc_A_Apron_Reconst-Bid_Pkg_2_-_Ad.pdf PDF
KCAB_-_RSVP_Instructional_Guide_for_OpenGov.pdf PDF
KCAB_-_RSVP_Instructional_Guide_for_OpenGov.pdf PDF
KCAB_-_RSVP_Instructional_Guide_for_OpenGov.pdf PDF
25-075-ITB_Conc_A_Apron_Reconst-Bid_Pkg_2_-_Exhibit_A_-_Proposal_Forms_(AIP).pdf PDF
CVG_Concourse_A_BP_2_IFB_Bid_Schedule.xlsx XLSX spreadsheet
CVG_Concourse_A_BP_2_IFB_Bid_Schedule.xlsx XLSX spreadsheet
CVG_Concourse_A_BP_2_IFB_Bid_Schedule.xlsx XLSX spreadsheet
CVG_Concourse_A_BP2_IFB_Technical_Specifications_R1.pdf PDF
CVG_Concourse_A_BP2_IFB_Technical_Specifications_R1.pdf PDF
25-075-ITB_Conc_A_Apron_Reconstruction_-_Bid_Pkg_2_-_Tech_Specifications.pdf PDF
CVG_Concourse_A_BP2_IFB_Technical_Specifications_R1.pdf PDF
25-075-ITB_Conc_A_Apron_Reconst-Bid_Pkg_2_-_Exhibit_B_-_Contract_&_Bonds.pdf PDF
Davis_Bacon_Wage_Rates_-_Heavy.pdf PDF
Davis_Bacon_Wage_Rates_-_Heavy.pdf PDF
25-075-ITB_Conc_A_Apron_Reconstruction_-_Bid_Pkg_2_-_Drawings.pdf PDF
CVG_CONCOURSE_A_BP2_IFB_Plans_FINAL.pdf PDF
CVG_CONCOURSE_A_BP2_IFB_Plans_FINAL.pdf PDF
CVG_CONCOURSE_A_BP2_IFB_Plans_FINAL.pdf PDF
Q4_2025_-_Business_Case_-_Concourse_A_Apron_Reconstruction_-_Construction_Phase_2_-_signed.pdf PDF
CVG_Concourse_A_BP2_IFB_Technical_Specifications.pdf PDF
Q4_2025_-_Business_Case_-_Concourse_A_Apron_Reconstruction_-_Construction_Phase_2_-_signed.pdf PDF
CVG_Concourse_A_BP2_IFB_Technical_Specifications.pdf PDF
Q4_2025_-_Business_Case_-_Concourse_A_Apron_Reconstruction_-_Construction_Phase_2_-_signed.pdf PDF
CVG_Concourse_A_BP2_IFB_Technical_Specifications.pdf PDF
Show all 46

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONCOURSE A APRON RECONSTRUCTION - BID PACKAGE 2

#25-075-ITB

PRE-BID MEETING

KENTON COUNTY AIRPORT BOARD (KCAB)

CINCINNATI/NORTHERN KENTUCKY INTERNATIONAL AIRPORT

BOONE COUNTY, KENTUCKY

January 8, 2026

General Project Description Concourse A – Apron Reconstruction – Bid Package 2 Major Project Goals:

Replace PCC pavement around Concourse A over the course of 4 years Perform replacement while impacting only 2 Gates at one time Major Project Elements:

Removal and replacement of PCC pavement Removal and replacement of Bituminous pavement Utility modifications Grading improvements Installation of pavement markings Electrical modifications Hydrant Fueling work by others, coordination required

PROJECT LAYOUT PLAN

OVERALL PHASING

OVERALL PHASING - ENLARGED

2026 OVERALL PHASING

PHASE 26-1

PHASE 26-2

PHASE 26-3/4

PHASE 27-1/8

PHASE 28-1/5

PHASE 28-5/8

PHASE 29-1/2

TYPICAL SECTIONS

image1.jpg image4.png image5.png image2.jpg image6.png image7.png image8.png image9.png image10.png image11.png image12.png image13.png image14.png image15.png image16.png image17.png image18.png image19.png image3.jpg

File details come from the government source that posted it. Updated .