Structural Repairs & Tunnel Improvements – IDIQ Contract Bid Form – Solicitation Number: AOCACB21R0004
Unit Price Bid Form
Project Name: Capitol Power Plant: UDS Tunnels IDIQ Contract Structural Repairs & Tunnel Improvements (2021-2028) Solicitation Number: AOCACB21R0004 Base Bid for restoration items to be performed in the Structural Repairs & Tunnel Improvements – IDIQ Contract
Bid Form – Table of Contents
YEAR 1 - SCHEDULE OF UNIT / HOURLY RATES
YEAR 2 - SCHEDULE OF UNIT / HOURLY RATES
YEAR 3 – SCHEDULE OF UNIT / HOURLY RATES
YEAR 4 – SCHEDULE OF UNIT / HOURLY RATES
YEAR 5 – SCHEDULE OF UNIT / HOURLY RATES
YEAR 6 – SCHEDULE OF UNIT / HOURLY RATES
YEAR 7 – SCHEDULE OF UNIT / HOURLY RATES
DEFINITIONS OF UNIT RATES
YEAR 1 - SCHEDULE OF UNIT / HOURLY RATES
ITEM DESCRIPTION UNIT RATE
00001 Mobilization/General Conditions $_________LS 00002 Protection and Dust Containment (Set-Up & Maintenance) $_________LS 00003 Concrete Restoration – Vertical (Wall Surfaces) $_________SF 00006 Concrete Restoration – Overhead Surfaces $_________SF 00007 Concrete Restoration – Floor Repairs $_________SF 00008 Curtain Grouting $_________SF 00009 Pipe Support/Steel Cleaning & Repainting $_________EA 00010 Pipe Support/Steel Cleaning & Repair $_________EA 00011 Pipe Support/Steel Replacement $_________EA 00012 Expansion Joint Restoration $_________LF
ITEM DESCRIPTION HOURLY RATE
00013 Project Manager $_________ 00014 Site Superintendent $_______________ 00015 Safety Officer $_________ 00016 Quality Manager $_________ 00017 Certified Shotcrete Nozzleman $_________ 00018 Skilled Laborer $_________ 00019 General Laborer $_________ 00020 00020A
Electrical Journeyman Electrical Apprentice
00021 Administrative Support $_________ 00022 Corporate G&A % Rate $_________ 00023 Profit % Rate $_________
YEAR 1: ADDITIONAL QUANTITIES - SCHEDULE OF UNIT / HOURLY RATES
00024 Additional Concrete Restoration $_________SF 00025 Vertical (Wall Surfaces) $_________SF 00026 Overhead Surfaces $_________SF 00027 Floor Repairs $_________SF 00028 Additional Curtain Grouting $_________SF 00029 Additional Pipe Support/Steel Cleaning & Repainting $_________EA 00030 Additional Pipe Support/Steel Replacement $_________EA 00031 Additional Expansion Joint Restoration $_________LF
YEAR 2 - SCHEDULE OF UNIT / HOURLY RATES
ITEM DESCRIPTION HOURLY RATE
00032 Mobilization/General Conditions $_________LS 00033 Protection and Dust Containment (Set-Up & Maintenance) $_________LS
00034 Concrete Restoration – Vertical (Wall Surfaces) $_________SF 00035 Concrete Restoration – Overhead Surfaces $_________SF 00036 Concrete Restoration – Floor Repairs $_________SF 00037 Curtain Grouting $_________SF 00038 Pipe Support/Steel Cleaning & Repainting $_________EA 00039 Pipe Support/Steel Cleaning & Repair $_________EA 00040 Pipe Support/Steel Replacement $_________EA 00041 Expansion Joint Restoration $_________LF
ITEM DESCRIPTION HOURLY RATE
00042 Project Manager $_________ 00043 Site Superintendent $_________ 00044 Safety Officer $_________ 00045 Quality Manager $_________ 00046 Certified Shotcrete Nozzleman $_________ 00047 Skilled Laborer $_________ 00048 General Laborer $_________ 00049 00049A
Electrical Journeyman Electrical Apprentice
00050 Administrative Support $_________ 00051 Corporate G&A % Rate $_________ 00052 Profit % Rate $_________
YEAR 2 - ADDITIONAL QUANTITIES - SCHEDULE OF UNIT / HOURLY RATES
00053 Additional Concrete Restoration $_________SF 00054 Vertical (Wall Surfaces) $_________SF 00055 Overhead Surfaces $_________SF 00056 Floor Repairs $_________SF 00057 Additional Curtain Grouting $_________SF 00058 Additional Pipe Support/Steel Cleaning & Repainting $_________EA 00059 Additional Pipe Support/Steel Replacement $_________EA 00060 Additional Expansion Joint Restoration $_________LF
YEAR 3 – SCHEDULE OF UNIT / HOURLY RATES
00061 Mobilization/General Conditions $_________LS 00062 Protection and Dust Containment (Set-Up & Maintenance) $_________LS 00063 Concrete Restoration – Vertical (Wall Surfaces) $_________SF 00064 Concrete Restoration – Overhead Surfaces $_________SF 00065 Concrete Restoration – Floor Repairs $_________SF 00066 Curtain Grouting $_________SF 00067 Pipe Support/Steel Cleaning & Repainting $_________EA 00068 Pipe Support/Steel Cleaning & Repair $_________EA 00069 Pipe Support/Steel Replacement $_________EA
00070 Expansion Joint Restoration $_________LF
00071 Project Manager $_________ 00072 Site Superintendent $_________ 00073 Safety Officer $_________ 00074 Quality Manager $_________ 00075 Certified Shotcrete Nozzleman $_________ 00076 Skilled Laborer $_________ 00077 General Laborer $_________ 00078 00078A
Electrical Journeyman Electrical Apprentice
00079 Administrative Support $_________ 00080 Corporate G&A % Rate $_________ 00081 Profit % Rate $_________
YEAR 3 – ADDITIONAL QUANTITIES - SCHEDULE OF UNIT / HOURLY RATES
00082 Additional Concrete Restoration $_________SF 00083 Vertical (Wall Surfaces) $_________SF 00084 Overhead Surfaces $_________SF 00085 Floor Repairs $_________SF 00086 Additional Curtain Grouting $_________SF 00087 Additional Pipe Support/Steel Cleaning & Repainting $_________EA 00088 Additional Pipe Support/Steel Replacement $_________EA 00089 Additional Expansion Joint Restoration $_________LF
YEAR 4 – SCHEDULE OF UNIT / HOURLY RATES
00090 Mobilization/General Conditions $_________LS 00091 Protection and Dust Containment (Set-Up & Maintenance) $_________LS 00092 Concrete Restoration – Vertical (Wall Surfaces) $_________SF 00093 Concrete Restoration – Overhead Surfaces $_________SF 00094 Concrete Restoration – Floor Repairs $_________SF 00095 Curtain Grouting $_________SF 00096 Pipe Support/Steel Cleaning & Repainting $_________EA 00097 Pipe Support/Steel Cleaning & Repair $_________EA 00098 Pipe Support/Steel Replacement $_________EA 00099 Expansion Joint Restoration $_________LF
ITEM DESCRIPTION HOURLY RATE
00100 Project Manager $_________ 00101 Site Superintendent $_________ 00102 Safety Officer $_________ 00103 Quality Manager $_________
00104 Certified Shotcrete Nozzleman $_________ 00105 Skilled Laborer $_________ 00106 General Laborer $_________ 00107 00107A
Electrical Journeyman Electrical Apprentice
00108 Administrative Support $_________ 00109 Corporate G&A % Rate $_________ 00110 Profit % Rate $_________
YEAR 4 – ADDITIONAL QUANTITIES - SCHEDULE OF UNIT / HOURLY RATES
00111 Additional Concrete Restoration $_________SF 00112 Vertical (Wall Surfaces) $_________SF 00113 Overhead Surfaces $_________SF 00114 Floor Repairs $_________SF 00115 Additional Curtain Grouting $_________SF 00116 Additional Pipe Support/Steel Cleaning & Repainting $_________EA 00117 Additional Pipe Support/Steel Replacement $_________EA 00118 Additional Expansion Joint Restoration $_________LF
YEAR 5 – SCHEDULE OF UNIT / HOURLY RATES
00119 Mobilization/General Conditions $_________LS 00120 Protection and Dust Containment (Set-Up & Maintenance) $_________LS 00121 Concrete Restoration – Vertical (Wall Surfaces) $_________SF 00122 Concrete Restoration – Overhead Surfaces $_________SF 00123 Concrete Restoration – Floor Repairs $_________SF 00124 Curtain Grouting $_________SF 00125 Pipe Support/Steel Cleaning & Repainting $_________EA 00126 Pipe Support/Steel Cleaning & Repair $_________EA 00127 Pipe Support/Steel Replacement $_________EA 00128 Expansion Joint Restoration $_________LF
ITEM DESCRIPTION HOURLY RATE
00129 Project Manager $_________ 00130 Site Superintendent $_________ 00131 Safety Officer $_________ 00132 Quality Manager $_________ 00133 Certified Shotcrete Nozzleman $_________ 00134 Skilled Laborer $_________ 00135 General Laborer $_________ 00136 00136A
Electrical Journeyman Electrical Apprentice
00137 Administrative Support $_________ 00138 Corporate G&A % Rate $_________ 00139 Profit % Rate $_________
YEAR 5 – ADDITIONAL QUANTITIES - SCHEDULE OF UNIT / HOURLY RATES
00140 Additional Concrete Restoration $_________SF 00141 Vertical (Wall Surfaces) $_________SF 00142 Overhead Surfaces $_________SF 00143 Floor Repairs $_________SF 00144 Additional Curtain Grouting $_________SF 00145 Additional Pipe Support/Steel Cleaning & Repainting $_________EA 00146 Additional Pipe Support/Steel Replacement $_________EA 00147 Additional Expansion Joint Restoration $_________LF
YEAR 6 – SCHEDULE OF UNIT / HOURLY RATES
00148 Mobilization/General Conditions $_________LS 00149 Protection and Dust Containment (Set-Up & Maintenance) $_________LS 00150 Concrete Restoration – Vertical (Wall Surfaces) $_________SF 00151 Concrete Restoration – Overhead Surfaces $_________SF 00152 Concrete Restoration – Floor Repairs $_________SF 00153 Curtain Grouting $_________SF 00154 Pipe Support/Steel Cleaning & Repainting $_________EA 00155 Pipe Support/Steel Cleaning & Repair $_________EA 00156 Pipe Support/Steel Replacement $_________EA 00157 Expansion Joint Restoration $_________LF
ITEM DESCRIPTION HOURLY RATE
00158 Project Manager $_________ 00159 Site Superintendent $_________ 00160 Safety Officer $_________ 00161 Quality Manager $_________ 00162 Certified Shotcrete Nozzleman $_________ 00163 Skilled Laborer $_________ 00164 General Laborer $_________ 00165 00165A
Electrical Journeyman Electrical Apprentice
00166 Administrative Support $_________ 00167 Corporate G&A % Rate $_________ 00168 Profit % Rate $_________
YEAR 6 – ADDITIONAL QUANTITIES - SCHEDULE OF UNIT / HOURLY RATES
00169 Additional Concrete Restoration $_________SF 00170 Vertical (Wall Surfaces) $_________SF 00171 Overhead Surfaces $_________SF
00172 Floor Repairs $_________SF 00173 Additional Curtain Grouting $_________SF 00174 Additional Pipe Support/Steel Cleaning & Repainting $_________EA 00175 Additional Pipe Support/Steel Replacement $_________EA 00176 Additional Expansion Joint Restoration $_________LF
YEAR 7 – SCHEDULE OF UNIT / HOURLY RATES
00177 Mobilization/General Conditions $_________LS 00178 Protection and Dust Containment (Set-Up & Maintenance) $_________LS 00179 Concrete Restoration – Vertical (Wall Surfaces) $_________SF 00180 Concrete Restoration – Overhead Surfaces $_________SF 00181 Concrete Restoration – Floor Repairs $_________SF 00182 Curtain Grouting $_________SF 00183 Pipe Support/Steel Cleaning & Repainting $_________EA 00184 Pipe Support/Steel Cleaning & Repair $_________EA 00185 Pipe Support/Steel Replacement $_________EA 00186 Expansion Joint Restoration $_________LF
ITEM DESCRIPTION HOURLY RATE
00187 Project Manager $_________ 00188 Site Superintendent $_________ 00189 Safety Officer $_________ 00190 Quality Manager $_________ 00191 Certified Shotcrete Nozzleman $_________ 00192 Skilled Laborer $_________ 00193 General Laborer $_________ 00194 00194A
Electrical Journeyman Electrical Apprentice
00195 Administrative Support $_________ 00196 Corporate G&A % Rate $_________ 00197 Profit % Rate $_________
YEAR 7 – ADDITIONAL QUANTITIES - SCHEDULE OF UNIT / HOURLY RATES
00198 Additional Concrete Restoration $_________SF 00199 Vertical (Wall Surfaces) $_________SF 00200 Overhead Surfaces $_________SF 00201 Floor Repairs $_________SF 00202 Additional Curtain Grouting $_________SF 00203 Additional Pipe Support/Steel Cleaning & Repainting $_________EA 00204 Additional Pipe Support/Steel Replacement $_________EA 00205 Additional Expansion Joint Restoration $_________LF
DEFINITIONS OF UNIT RATES
Number Commodity Name Quantity Unit of
Issue
Unit Price
Total Cost ($, Inc.
disc)
1 Mobilization/General Conditions 1 LS $ $
Description: Mobilization/General Conditions – Scope of work includes all mobilization of equipment, materials, and construction of temporary enclosures at the locations identified in the Project Documents.
Pricing shall be all-inclusive and include overhead, profit, and general conditions cost spread over the duration of the contract.
2 Protection and Dust Containment 1 LS $ $
Description: Protection and Dust Containment – Scope of work includes installation, maintenance, and takedown of all protection required for existing utilities and dust control barriers and filters; air monitoring;
sampling; testing; protecting intake, exhaust fans within the tunnels; installing dust partitions at regular intervals and in areas of work; prevention of dust and debris run-off into sump pits; and ensuring prevention of dust into exhaust/intake grates. Pricing shall be all-inclusive and include overhead, profit, and incidental cost spread over the duration of the contract.
3 Concrete Restoration – Vertical (Wall) Surfaces
1 SF $ $
Description: Concrete Restoration – Vertical - Scope of work includes all labor, material, and equipment to perform concrete restoration at all overhead surfaces as indicated on the contract drawings. Pricing shall be all-inclusive and include overhead, profit, and incidental cost.
Note: Repair of approved additional quantities identified during the course of the work shall be performed and paid at the same unit rates above. Actual quantities are to be recorded to the nearest half square foot and adjusted up or down accordingly via change order. Quantities listed on the Drawings are as-measured quantities. Quantities in this Bid Form include anticipated growth. Full-depth repairs are not generally anticipated but may occur.
4 Concrete Restoration – Overhead Surfaces 1 SF $ $
Description: Concrete Restoration – Overhead – Scope of work includes all labor, material, and equipment to perform quantities of concrete restoration at overhead surfaces as indicated on the contract drawings.
Pricing shall be all-inclusive and include overhead, profit, and incidental cost.
Note: Repair of approved additional quantities identified during the course of the work shall be performed and paid at the same unit rates above. Actual quantities are to be recorded to the nearest half square foot and adjusted up or down accordingly via change order. Quantities listed on the Drawings are as-measured quantities. Quantities in this Bid Form include anticipated growth. Full-depth repairs are not generally anticipated but may occur.
5 Concrete Restoration – Floor Repairs 1 SF $ $
Description: Concrete Restoration – Floor – Scope of work includes all labor, material, and equipment to perform quantities of concrete restoration at horizontal surfaces. Pricing shall be all-inclusive and include overhead, profit, and incidental cost.
Note: Repair of approved additional quantities identified during the course of the work shall be performed and paid at the same unit rates above. Actual quantities are to be recorded to the nearest half square foot and adjusted up or down accordingly via change order. Horizontal repairs are not generally anticipated but may occur.
6 Curtain Grouting 1 SF $ $
Description: Curtain Grouting (by Square Feet as measured by the inside face of tunnel) – Scope of work includes all labor, material, and equipment to perform curtain grouting at the locations indicated on the contract drawings. Pricing shall be per square foot of tunnel surface area and shall include all steps in the process including, but not limited to; installation of injection ports, addressing large cracks and spalls, removal of ports, and all associated cleaning. Pricing shall be all-inclusive and include overhead, profit, and incidental cost.
Curtain grouting at cracks and control joints will be considered one-unit width.
Note: Repair of approved additional quantities identified during the course of the work shall be performed and paid at the same unit rates above. Actual quantities are to be recorded to the nearest half square foot and adjusted up or down accordingly via change order.
7 Pipe Support/Steel Cleaning and Repainting 1 EA $ $
Description: Pipe Support Cleaning and Repainting – Scope of work includes all labor, material, and equipment to remove corrosion from steel, prime with zinc oxide primer, and paint to match the existing paint.
Each item will be assumed to include 3 square feet of work. Pricing shall be all-inclusive and include overhead, profit, and incidental cost.
8 Pipe Support/Steel Cleaning and Repair 1 EA $ $
Description: Pipe Support/Steel Cleaning and Repair – Scope of work includes all labor, material, and equipment to remove corrosion from steel, and add supplementary steel as indicated in the contract drawings.
This includes priming the existing and new steel with a zinc oxide primer, and paint to match existing. Each item will assume to include one angle to supplement heavily corroded steel, and 3 square feet cleaning, priming, and painting. Pricing shall be all-inclusive and include overhead, profit, and incidental cost.
9 Pipe Support/Steel Replacement 1 EA $ $
Description: Pipe Support/Steel Replacement – Scope of work includes all labor, material, and equipment to replace existing pipe support/steel in kind. This includes priming the new steel with a zinc oxide primer and painting the steel to match existing.
10 Expansion Joint Restoration 1 LF $ $
Description: Expansion Joint Restoration – Scope of work includes all labor, material, and equipment to perform Expansion joint work at the locations indicated on the contract drawings. Quantities to be indicated on the contract drawings. Pricing shall be all-inclusive and include overhead, profit, and incidental costs
Total Price for Base Contract