This is a Signage Bid Package for the Franklin County Pavilion located at 365 S. High Street, Columbus, Ohio, issued by Franklin County. The project involves the design, fabrication, and installation of comprehensive signage throughout the pavilion facility, including room number signs, directional signage, evacuation maps, elevator identity dimensional signage, a digital wayfinding kiosk, campus directory, and overhead building identity signage. The bid package specifies a total of 14 signs to be installed across multiple zones and floor levels. The signage contractor must develop a phased project schedule that prioritizes completion of stairwell signage first, followed by floor-by-floor installation. The contractor is responsible for coordinating sign removal, wall patching, and painting in areas where existing signage is removed. Specific sign locations are withheld from the public bid document for security purposes and will be provided to the awarded bidder following contract award. Bi-weekly on-site meetings with the owner's representative and PLANIT will be required throughout the project duration.

The signage contractor must obtain a Sign Agent Mobile License and provide an iPad to installation crews for real-time project documentation and progress tracking, with daily synchronization of the master Sign Agent document required. The contractor bears full responsibility for final control drawings, engineering, materials selection, and compliance with current state and federal building codes. The contractor must provide temporary signage when removal and installation cannot occur on the same business day and must photograph each installed sign and document completion in Sign Agent before work is considered complete. The owner will provide paint colors and finishes for wall patching work. No pricing information, contract term, or award timeline is specified in this design intent document.

View the file

Other files

File Type Posted
4764BD72-A4C9-CB3B-C1392F63B1D7AA28.pdf PDF
CCC737E4-C815-7DA9-BAFDD4D8BCA83EAE.pdf PDF
47411393-E3B2-7F55-0865EAB909BEF818.xlsx XLSX spreadsheet
47647B12-EF69-CBAE-3877E615229CE346.pdf PDF
FAFB33F1-A49E-7354-6799AC07E5D29DA0.pdf PDF
600B193E-A6DE-E459-0374B7046DEB49BE.xlsx XLSX spreadsheet
48C51FFE-B1BA-D9DA-11337A7B04016CA4.pdf PDF
4ADC54F2-C74F-3F02-B4900398FFBEE5A5.xlsx XLSX spreadsheet
48FFC2CD-AEC5-7A21-3B4F6E3270F0429B.pdf PDF
E9905CF7-C973-40FC-678D5FD85143E735.pdf PDF
36771012-968A-47BA-49FB1CC4DFFFEC63.pdf PDF
44F2E64B-E391-5EAC-DD33927813E7BE98.xlsx XLSX spreadsheet
44B739A8-A554-F8F5-C38D97EF8EFBF991.xlsx XLSX spreadsheet
9124AC45-D403-5860-A4635A70C618C298.pdf PDF
8F3A405E-0241-7E43-C0DC0A6106AC42BB.pdf PDF
44F28715-E1AF-A884-828CBEAF47CBA5D7.xlsx XLSX spreadsheet
E990A518-E8F3-4318-3125803AC770B0DD.pdf PDF
1FF70774-E56E-EAC8-88A7694DAF5EB82C.pdf PDF
A46910BC-E967-DD22-10B71BADEA153824.docx DOCX document
DDA0BDC2-FA19-ADB6-FAD2DEA5AE6B4AEE.pdf PDF
8D7E2732-E2EF-8808-10498B0343D0DB6B.pdf PDF
47039A14-CC1D-3979-F8226F8E1E768343.pdf PDF
E93EE438-A2D2-AF8E-6F5941F303D00F6A.pdf PDF
A468D9BE-C742-A53B-A0E51044FC47530E.pdf PDF
96EE5830-0F4F-104B-FF1246192320CF51.pdf PDF
600B382B-92C2-EE01-36E3171A1CE23381.pdf PDF
ED338BF8-FCF8-7E6B-4327CDB3236D9A0A.pdf PDF
441C7CE8-FE79-FFAD-86876E5C9E330E9F.pdf PDF
56D1E25C-D6F7-A070-782594700401C348.docx DOCX document
D19B3093-A699-8107-EE175100DAB2A969.pdf PDF
39A8A9E3-F569-C6B6-B9E7BF50CFDC4F51.pdf PDF
1FF76D77-0146-31BD-B70AC2B9310C078F.pdf PDF
3CA5BBE9-A618-9D6F-45A1FE1B6F58F0BF.pdf PDF
4ADC244E-B24C-BEC2-4654E43F7ACFB8A4.xlsx XLSX spreadsheet
455CC78D-B78A-EC66-F7D6D71B8AF36042.pdf PDF
BEA8B132-08B9-5848-83E1018BFD8D09C5.xlsx XLSX spreadsheet
1FF8629C-E097-4138-B3B7BE56C0FCD3F5.pdf PDF
58DCD716-9EAC-9E14-6719EE5FDA607EE3.pdf PDF
600ACEFD-D8A4-EF86-6746123A35214FBD.pdf PDF
45745F40-E0BA-1577-1AE1A9CC2179CA13.pdf PDF
490005E7-0009-0FD7-0E92BD0F4BF1B987.xlsx XLSX spreadsheet
340E518F-B0A2-92CD-5CE67BE8C5C74ADC.pdf PDF
A4692B9C-E659-F33F-532C87A025A11AC2.pdf PDF
C0135AC1-FF9D-F3AC-BDB7FB4697056E65.pdf PDF
56D21EF1-090E-9236-DC87D4ABB226948A.pdf PDF
9188FC82-07E6-2A24-E7927A56369C067A.pdf PDF
5FEA932D-A443-F834-C369AEC7AD13A552.pdf PDF
F388F0B8-095B-81FD-4AB0A90CB30AE31F.pdf PDF
4703BAFF-A637-A4BC-D31224A6D85981B6.pdf PDF
379F0AFD-BC67-5833-47CED9B9F8A77644.pdf PDF
Show 40 more

Latest 50 of 148 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

365 S. High St., Columbus, OH 43215

Signage Bid Package - PAV Revision Date: 04.01.2026

Pavilion

760 Lakeview Plaza Blvd Suite 500 Worthington Ohio 43085

760 Lakeview Plaza Blvd, Suite 500 Worthington, Ohio 43085 phone: 614.505.0375 www.planitstudioscom

Sheet

Franklin County

Pavilion

365 S High St Columbus, Ohio 43215

Published 04.01.2026

The sole purpose of these design intent drawings are to provide visual design intent with development of the signage package. The sign vendor awarded the contract by Franklin County and its approved sub-contractors, accepts total responsibility for final: control drawings, engineering, materials selection, sign fabrication and installation based on latest state and federal building codes for this specific location.

The sign vendor is responsible for obtaining a Sign Agent Mobile License for the team working on this project. All final approved sign layouts and sign location plans will be provided in Sign Agent.

Removals

Existing Signage to Remain Existing signage to remain includes but is not limited to:

AED device signage Artwork descriptions Bulletin Boards Dedication plaques Digital Signage and Displays Dimensional Lettering* Donor recognition Vinyl lettering* *Unless otherwise noted

Existing Signage Removals Signage contractor is responsible for developing and coordinating a phased project schedule to minimize the time between signage removals and new signage installations. Phasing should be completed so that all stairwell signage is completed first and all other signage will be completed on a floor by floor basis. Signage Contractor will provide a written proposed schedule for the Owner’s rep approval.

There should be no gap in signage as a result of these removals.. Signage vendor is responsible for providing temporary signage when the sign removal and installation of the new sign cannot occur on the same business day.

Patch / Paint Signage contractor is responsible for patching walls and painting walls/doors in the area where signs were removed. If a subcontractor is used for this work, then Signage contractor will be responsible for coordinating those efforts and will be responsible for defining the subcontractor’s contract. Owner will provide paint colors and finish.

Bi-Weekly meetings Bi-Weekly meetings with the Owner’s rep and PLANIT will be held on site to walk through the upcoming phases of work and confirm precisely which signs are to be removed. Signage contractor’s project superintendent must regularly attend these meetings.

Sign Agent Signage contractor is responsible for obtaining a mobile license from Sign Agent and providing an iPad to the installation crew. The iPad must be synced with the master Sign Agent document at the end of each business day. This will be required to view the project documents and track progress during installation.

https://support.signagent.com/knowledge/paying-for-a-signagent-mobile-license

Questions during installation If questions arise (ex. sign removals or precise locations of new signs), please contact Owner’s rep and PLANIT immediately before proceeding with removal or new installation. Photograph(s) of the existing condition will be required to accompany each question.

Completion of work As each new sign is installed, Signage contractor is responsible for taking a photo and adding it as a comment in Sign Agent. Undocumented work will not be accepted as completed work.

As each phase is completed for each building (stairwell signage S1/S2 is to be completed first, then floor by floor), Signage contractor will ask for Owner’s rep to inspect and accept completed work.

Worthington, Ohio 43085 phone: 614.505.0375 www.planitstudioscom

Sheet

Franklin County

Pavilion

365 S High St Columbus, Ohio 43215

Published 04.01.2026

The sole purpose of these design intent drawings are to provide visual design intent with development of the signage package. The sign vendor awarded the contract by Franklin County and its approved sub-contractors, accepts total responsibility for final: control drawings, engineering, materials selection, sign fabrication and installation based on latest state and federal building codes for this specific location.

The sign vendor is responsible for obtaining a Sign Agent Mobile License for the team working on this project. All final approved sign layouts and sign location plans will be provided in Sign Agent.

Sign Locations

Note:

For security purposes, the building floor plans showing the location of each sign have been withheld from this public bid document. These locations will be provided to the bidder after the project is awarded.

Worthington, Ohio 43085 phone: 614.505.0375 www.planitstudioscom

Sheet

Franklin County

Pavilion

365 S High St Columbus, Ohio 43215

Published 04.01.2026

The sole purpose of these design intent drawings are to provide visual design intent with development of the signage package. The sign vendor awarded the contract by Franklin County and its approved sub-contractors, accepts total responsibility for final: control drawings, engineering, materials selection, sign fabrication and installation based on latest state and federal building codes for this specific location.

The sign vendor is responsible for obtaining a Sign Agent Mobile License for the team working on this project. All final approved sign layouts and sign location plans will be provided in Sign Agent.

SignÊID Message Artwork

PAV-LPÊ-ÊPlaza

K-P01

D1-P02 BuildingÊName Pavilion

ZoneÊColor White

D4-P03 BuildingÊName Pavilion

LevelÊNumber FloorÊ1

ZoneÊColor White

StairÊto 345ÊS.ÊHigh St.

CourtÊof Common Pleas

Building Exit Pavilion Elevator

M-P04

EID-P05 ElevatorÊName Pavilion

FloorÊRange FloorsÊLLÊ-Ê1

F1.1-P06 FlagÊIcon

ZoneÊColor White

O(10x36)-P07 ZoneÊColor White

C1-01137 BuildingÊName Pavilion

C1ÊRoomÊNumber 01-137

C1ÊRoomÊNumberÊBraille #ja-#acg

ZoneÊColor White

SignÊID Message Artwork

D3-01138 BuildingÊName Pavilion

LevelÊNumber

ElevatorÊName PavilionÊElevator

ZoneÊColor White

MichaelÊJ.

Dorrian Building

South HighÊSt.

OfficeÊTower South HighÊSt.

ExitÊtoÊSouth HighÊSt.

PAV-LTÊ-ÊTunnel

O(44.5x96)-T01

O(34x192)-T02

EID-T03 ElevatorÊName Pavilion

FloorÊRange FloorsÊLLÊ-Ê1

M-T04

C1-T10 BuildingÊName Pavilion

C1ÊRoomÊNumber T-10

C1ÊRoomÊNumberÊBraille ;t-#aj

ZoneÊColor White

Signage Message Schedule & Sign Count Summary

SignÊID Count

C1 RoomÊNumber 2

F1.1 FlagÊSignÊWallÊMountedÊ(IconÊOnly) 1

M EvacuationÊMap 2

EID ElevatorÊIdentityÊDimensionalÊType 2

K DigitalÊWayfindingÊKiosk 1

D1 CampusÊDirectory 1

D3 ElevatorÊDirectional 1

D4 DirectionalÊSmall 1

O(34x192) OverheadÊBldgÊIdentityÊtall 1

O(44.5x96) OverheadÊBldgÊIdentityÊtallest 1

O(10x36) OverheadÊDirectional 1

Subtotal:Ê14

SignÊID Count

C1 RoomÊNumber 2

F1.1 FlagÊSignÊWallÊMountedÊ(IconÊOnly) 1

M EvacuationÊMap 2

EID ElevatorÊIdentityÊDimensionalÊType 2

K DigitalÊWayfindingÊKiosk 1

D1 CampusÊDirectory 1

D3 ElevatorÊDirectional 1

D4 DirectionalÊSmall 1

O(34x192) OverheadÊBldgÊIdentityÊtall 1

O(44.5x96) OverheadÊBldgÊIdentityÊtallest 1

O(10x36) OverheadÊDirectional 1

Subtotal:Ê14