DDA0BDC2-FA19-ADB6-FAD2DEA5AE6B4AEE.pdf
PDF 183 KB Posted
- Attached to
- Professional Engineering Services S. Grener Avenue, Emmit Avenue, Mix Avenue, and Sullivant Avenue (
- Solicitation number
- RFQ No. 2025-09-03
- Issued by
- Franklin County, Ohio
About this file
This is Addendum No. 3 to a Request for Qualifications issued by the Franklin County Board of Commissioners for professional engineering services related to the GEMS Water Main Replacement Project. The project encompasses water main replacement on four streets in Columbus, Ohio: S. Grener Avenue (from Sullivant to Stiles), Mix Avenue (from Sullivant to Bunker), Emmit Avenue (from Stiles to Bunker), and Sullivant Avenue (from S. Grener to Emmit). The statement of qualifications submission deadline is April 24, 2025, at 2:00 PM EST. The design phase is anticipated to take eight months from contract award, with project bidding expected to occur around mid-February 2026 and construction award anticipated in late May 2026. The County intends to commence construction by the end of June 2026. Respondents must submit single-sided PDFs on flash drives and should reference the Franklin County Purchasing Department website for all published addenda.
The construction phase of the GEMS Water Main Replacement Project will be jointly funded by the Water Sewers and Locale Remediation Authority (WSLRA) and the Ohio Public Works Commission (OPWC). OPWC funding requirements mandate that construction commence by the end of June 2026, establishing a firm timeline constraint for the project schedule. This addendum clarifies project scope, submittal requirements, and anticipated timeline for prospective engineering firms submitting qualifications.
View the file
Other files
Show 40 more
Latest 50 of 148 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
cleanwater.franklincountyohio.gov
April 18, 2025
FRANKLIN COUNTY BOARD OF COMMISSIONERS
REQUEST FOR QUALIFICATIONS 2025-09-03
PROVISION OF PROFESSIONAL ENGINEERING SERVICES FOR S.GRENER AVENUE, EMMIT
AVENUE, MIX AVENUE, AND SULLIVANT AVENUE (GEMS) WATER MAIN REPLACEMENT
PROJECT
373 South High Street, 25th Floor Purchasing Department Columbus, Ohio 43215
Franklin County
Addendum No. 3
TO ALL BIDDERS:
This Addendum supplements and amends the original Request for Qualifications and shall be taken into account in preparing submissions. When returning your statement of qualifications, please sign and return the signature page of the Addendum with your response.
Company name and signature of authorized company representative Date
Provision of Professional Engineering Services for S. Grener Avenue, Emmit Avenue, Mix Avenue, and
Sullivant Avenue (GEMS) Water Main Replacement Project
RFQ 2025-09-03
Addendum No. 3
April 18, 2025
1. The Submittal Deadline Date/Time shall remain the same: April 24, 2025, at 2:00 PM (EST).
2. Question 1: What is the anticipated schedule for bidding of this project?
Response 1: Per Response 2 (below), the project should be ready for bid around mid-February 2026.
Bidding is anticipated to take 3 months, which makes the award for construction in late-May 2026.
3. Question 2: What is FCSE’s desired date of design completion for this project?
Response 2: The County anticipates Design will take 8 months from the Award of Contract to Bidding.
4. Question 3: For the flash drives requested for the GEMS Project, do you want single-sided PDF for ease of copying, rather than the double-sided we are using for our spiral-bound submittals?
Response 3: Please submit single-sided PDFs on the flash drives.
5. Question 4: I had trouble with my audio for the meeting. It seems pretty short, so I assume there were no changes/addendums to the requirements originally published.
Response 4: Please see the Purchasing Department’s website (https://bids.franklincountyohio.gov/) for all addenda published related to this RFQ.
6. Question 5: We understand that this is funding dependent, but is the intent to begin construction in 2026?
Response 5: Yes. The County would like to start construction by end of June 2026.
7. Question 6: Could you please confirm the extents of the water main replacement for each street?
From the exhibit included in the RFQ it appears that the project limits are:
• S. Grener from Sullivant to Stiles
• Mix from Sullivant to Bunker
• Emmit from Stiles to Bunker
• Sullivant from S. Grener to Emmit
Response 6: The extents listed above are correct.
https://bids.franklincountyohio.gov/
8. Question 7: Has funding been established for the construction phase of this project? If so, are there any constraints placed on the construction schedule due the funding source(s)?
Response 7: The construction phase of this project will be jointly funded by WSLRA and OPWC. Per the requirements of OPWC, construction is to commence by the end of June 2026.
ATTACHMENTS:
None.
END OF ADDENDUM
File details come from the government source that posted it. Updated .