List Selects
| Phase | Type |
| N/A | MSG |
| On Hold | TSU |
| Survey | HTP |
| Design | HTP-SP |
| Logistics | HTP-TOC |
| Installation | SP |
| Closeout | TOC |
| Closed | VB |
| Cancelled |
PME
| Project | |||||||||||||||
| Type | Project # | Post/Facility | Scope of Work | Project Phase | Baseline Install Start | Baseline Project Acceptance Finish | Projected Project Acceptance Finish | Install Completed | # PME Personnel Onsite | Comments | Region | City | Country | Survey Cost | Survey |
| Travel | Design | ||||||||||||||
| Cost | 30% |
CE
Install$ (update SOW) 100%
CE
Install$ Post Code
| TSU | 19022 | Tbilisi Embassy Compound HDVU | HDVU: Power, Cameras/HDVS, Infrastructure, SMSe | Survey | New Charter. | EUR | Tbilisi | Georgia | 301 | |||||||||
| TSU | 19023 | Tirana Embassy Compound HDVU | HDVU: Power, Cameras/HDVS, Infrastructure, SMSe | Survey | New Charter. | EUR | Tirana | Albania | 363 | |||||||||
| TSU | 19021 | Managua Embassy Per. HDVU | HDVU: Power, Cameras/HDVS, Infrastructure, SMSe | Survey | New Charter. | WHA | Managua | Nicaragua | 648 | |||||||||
| TSU | 19008 | Buenos Aires Embassy Compound TSU | TSU: ENS, IDNS, Cameras/HDVS, Infrastructure, SMSe, SIC Rms, Power, Post One, Safe Haven | Survey | 4/13/20 | 7/22/20 | 7/29/20 | 30% Design Review. | WHA | Buenos Aires | Argentina | 606 | ||||||
| TSU | 19010 | Lisbon Embassy Compound TSU | TSU: ENS, IDNS, Cameras/HDVS, Infrastructure, SMSe, SIC Rms, Power, Post One, Safe Haven | Survey | 4/13/20 | 7/22/20 | 7/29/20 | 30% Design Review. | EUR | Lisbon | Portugal | 335 | ||||||
| TSU | 19011 | Ho Chi Minh City Consulate Compound TSU | TSU: ENS, IDNS, Cameras/HDVS, Infrastructure, SMSe, SIC Rm, Power, Post One, Safe Haven | Survey | 4/27/20 | 8/5/20 | 7/30/20 | 30% Design Review. | EAP | Ho Chi Minh City | Vietnam | 211 | ||||||
| TSU | 19013 | Sarajevo Embassy Compound TSU | TSU: ENS, IDNS, Cameras/HDVS, Infrastructure, SMSe, SIC Rms, Power, Post One, Safe Haven | Survey | 5/25/20 | 9/2/20 | 9/2/20 | 0 | 30% Design. | EUR | Sarajevo | Bosnia and Herzegovina | 354 | |||||
| TSU | 19014 | Lagos Consulate Compound TSU | TSU: ENS, IDNS, Cameras/HDVS, Infrastructure, SMSe, SIC Rms, Power, Post One, Safe Haven | Survey | 5/25/20 | 9/2/20 | 9/2/20 | 0 | 30% Design. | AF | Lagos | Nigeria | 127 | |||||
| TSU | 19015 | Sao Paulo Consulate Compound TSU | TSU: ENS, IDNS, Cameras/HDVS, Infrastructure, SMSe, SIC Rms, Power, Post One, Safe Haven | Survey | 6/1/20 | 9/9/20 | 9/9/20 | 0 | 30% Design. | WHA | Sao Paulo | Brazil | 642 | |||||
| TSU | 19018 | Lomé Embassy Compound TSU | TSU: Power, ENS, IDNS, Cameras/HDVS, Infrastructure, SMSe, IDS, SIC Rms, RIC/IIC, MSG Posts, Safe Haven | Survey | 6/9/20 | 9/21/20 | 9/21/20 | 5 | AF | Lomé | Togo | 130 | ||||||
| TSU | 19009 | Bamako Embassy Compound TSU | TSU: ENS, IDNS, Cameras/HDVS, Infrastructure, SMSe, SIC Rms, Power, Post One, Safe Haven | Survey | 6/22/20 | 9/30/20 | 9/30/20 | AF | Bamako | Mali | 106 | |||||||
| TSU | 19016 | Bratislava Embassy Compound TSU | TSU: Power, ENS, IDNS, Cameras/HDVS, Infrastructure, SMSe, IDS, SIC Rms, RIC/IIC, MSG Posts, Safe Haven | Survey | 7/14/20 | 10/26/20 | 10/26/20 | EUR | Bratislava | Slovakia | 316 | |||||||
| TSU | 19019 | Dublin Embassy Compound TSU | TSU: Power, ENS, IDNS, Cameras/HDVS, Infrastructure, SMSe, SIC Rms, Safe Haven | Survey | 7/14/20 | 10/26/20 | 10/26/20 | New Charter. | EUR | Dublin | Ireland | 322 | ||||||
| TSU | 19017 | Chengdu Consulate Compound TSU | TSU: Power, ENS, IDNS, Cameras/HDVS, Infrastructure, SMSe, IDS, SIC Rms, RIC/IIC, MSG Posts, Safe Haven | Survey | 7/28/20 | 11/9/20 | 11/9/20 | EAP | Chengdu | China | 206 | |||||||
| TSU | 19020 | Ulaanbaatar Embassy Compound TSU | TSU: Power, ENS, IDNS, Cameras/HDVS, Infrastructure, SMSe, IDS, SIC Rms, Safe Haven | Survey | 7/28/20 | 11/9/20 | 11/9/20 | New Charter. | EAP | Ulaanbaatar | Mongolia | 238 | ||||||
| TSU | 19005 | Ciudad Juarez Consulate Compound TSU | Limited TSU: SIC Rms, Power, Infrastructure, Specific Post Requests | Design | 11/27/19 | 2/25/20 | 2/4/20 | 100% Design Review. | WHA | Ciudad Juarez | Mexico | $ 27,395 | $ 7,082 | $ 19,097 | $ 345,276 | 609 | ||
| TSU | 19007 | Baku Embassy Compound TSU | TSU: ENS, IDNS, Cameras, Infrastructure, SMSe, SIC Rms, Power, Post One, Safe Haven | Design | 1/6/20 | 4/17/20 | 4/24/20 | 90% Design Review. | EUR | Baku | Azerbaijan | $ 59,085 | $ 32,543 | $ 37,192 | $ 886,120 | 308 | ||
| TSU | 19006 | Berlin Embassy Compound TSU | TSU: ENS, IDNS, Cameras/HDVS, Infrastructure, Fiber Backbone, SMSe, SIC Rms, Power, Post One, Safe Haven | Design | 2/14/20 | 5/28/20 | 5/18/20 | 100% Design. | EUR | Berlin | Germany | $ 41,802 | $ 29,034 | $ 21,258 | $ 903,921 | 312 | ||
| TSU | 19004 | Bern Embassy Compound TSU | Limited TSU: SIC Rms, Power, Infrastructure, CCTV, IDS, Specific Post Requests | Design | 2/28/20 | 5/26/20 | 5/26/20 | 90% Design. | EUR | Bern | Switzerland | $ 36,625 | $ 23,748 | $ 53,966 | $ 506,404 | 313 | ||
| TSU | 19001 | Conakry Embassy Compound TSU | TSU: ENS, IDNS, Cameras/HDVS, Infrastructure, Fiber Backbone, SMSe, SIC Rms, Power, Post One, Safe Haven | Design | 3/2/20 | 7/24/20 | 7/24/20 | 90% Design. | AF | Conakry | Guinea | $ 69,511 | $ 37,877 | $ 67,471 | $ 1,353,370 | 113 | ||
| TSU | 19012 | Dili Embassy Compound TSU | TSU: ENS, IDNS, Cameras/HDVS, Infrastructure, SMSe, SIC Rms, Power, Post One, Safe Haven | Design | 4/6/20 | 7/15/20 | 7/7/20 | 90% Design. | EAP | Dili | Timor-Leste | $ 47,784 | $ 32,410 | $ 28,309 | $ 778,143 | update SOW | 241 | |
| TSU | 18021 | Muscat Embassy Compound TSU | Limited TSU: Infrastructure, Fiber Backbone, SIC Rms, Power, Post One, Specific Post Requests | Logistics | 4/29/19 | 7/24/19 | 7/24/19 | NEA | Muscat | Oman | $ 41,132 | $ 37,179 | $ 31,306 | $ 774,438 | 417 | |||
| TSU | 19002 | New Delhi Enclave Per. TSU | TSS Survey and Design for Fiber Backbone, SIC Rms, Cameras | Logistics | 5/6/19 | 6/23/19 | 6/24/19 | Replaced 18011 as of 8/24/2018. | SCA | New Delhi | India | $ 47,989 | $ 28,579 | $ 18,847 | $ 250,527 | 507.06 |
507.07
| TSU | 18005 | Munich Consulate Compound TSU | TSU: ENS, IDNS, Cameras/HDVS, Infrastructure, Fiber Backbone, SMSe, SIC Rms, Power, Post One, Safe Haven | Logistics | 5/13/19 | 9/20/19 | 9/20/19 | EUR | Munich | Germany | $ 50,755 | $ 29,906 | $ 80,225 | $ 1,200,693 | 344 | ||||
| TSU | 18022 | Riyadh Embassy Compound TSU | TSU: Infrastructure, SIC Rms, Power, Post One, Specific Post Requests | Logistics | 5/13/19 | 8/30/19 | 8/30/19 | NEA | Riyadh | Saudi Arabia | $ 33,169 | $ 37,799 | $ 27,895 | $ 807,993 | 419 | ||||
| TSU | 18019 | Toronto Consulate & Annex Compounds TSU | Limited TSU: Infrastructure, SIC Rms, Power, Post One, Specific Post Requests | Logistics | 5/14/19 | 7/9/19 | 7/8/19 | WHA | Toronto | Canada | $ 27,434 | $ 12,286 | $ 27,518 | $ 320,926 | 646 | ||||
| TSU | 17019 | Hermosillo Consulate Compound TSU | TSU: ENS, IDNS, Cameras, Infrastructure, Fiber Backbone, SMSe, SIC Rms, Power, Post One, Safe Haven | Logistics | 6/18/19 | 8/26/19 | 8/26/19 | WHA | Hermosillo | Mexico | $ 46,310 | $ 14,578 | $ 108,161 | $ 619,953 | 617 | ||||
| TSU | 18031 | Praia Embassy Compound TSU | Limited TSU: SIC Rms, Power, Infrastructure, ENS, IDNS, SMSe, Specific Post Requests | Logistics | 7/1/19 | 9/11/19 | 9/11/19 | AF | Praia | Cape Verde | $ 47,614 | $ 26,873 | $ 3,319 | $ 606,607 | 142 | ||||
| TSU | 18014 | Jerusalem Amer. Cultural Center TSU | TSU: ENS, Cameras, Infrastructure, SMSe, SIC Rms, Power, Post One, Safe Haven | Logistics | 7/8/19 | 9/20/19 | 9/20/19 | NEA | Jerusalem | Israel | $ - 0 | $ - 0 | $ 15,169 | $ 658,415 | 413.03 | ||||
| TSU | 18028 | Vancouver Consulate Compound TSU | Limited TSU: SIC Rms, Power, Infrastructure, Specific Post Requests | Logistics | 7/29/19 | 9/13/19 | 9/13/19 | WHA | Vancouver | Canada | $ 44,237 | $ 26,457 | $ 35,562 | $ 271,790 | 647 | ||||
| TSU | 18010 | Port-au-Prince Embassy Compound TSU | TSU: ENS, IDNS, Cameras/HDVS, Infrastructure, Fiber Backbone, SMSe, SIC Rms, Power, Post One, Safe Haven | Logistics | 8/13/19 | 12/16/19 | 12/16/19 | WHA | Port-au-Prince | Haiti | $ 63,137 | $ 29,995 | $ 94,417 | $ 1,008,104 | 632 | ||||
| TSU | 17015 | Rome Tri-Mission Compound TSU | TSU: IDNS, Cameras/HDVS, Infrastructure, Fiber Backbone, SMSe, SIC Rms, Power, Post One, Safe Haven | Logistics | 8/19/19 | 12/20/19 | 12/20/19 | US Embassy, USUN, Holy See. | EUR | Rome | Italy | $ 75,144 | $ 57,046 | $ 105,898 | $ 1,503,342 | 353 | |||
| TSU | 17017 | Jerusalem Consulate Compound TSU | TSU: ENS, Cameras/HDVS, Infrastructure, Fiber Backbone, SMSe, SIC Rms, Power, Post One, Safe Haven | Logistics | 9/9/19 | 1/10/20 | 12/13/19 | Agron Rd, Lazarus. | NEA | Jerusalem | Israel | $ 153,372 | $ 142,263 | $ 66,672 | $ 969,348 | 413.01 | |||
| TSU | 18025 | Dar es Salaam Embassy Compound TSU | Limited TSU: SIC Rms, Power, Infrastructure, Specific Post Requests | Logistics | 9/16/19 | 12/11/19 | 12/11/19 | AF | Dar es Salaam | Tanzania | $ 37,592 | $ 29,623 | $ 52,484 | $ 764,000 | 116 | ||||
| TSU | 18008 | Canberra Embassy Compound TSU | TSU: ENS, IDNS, Cameras/HDVS, Infrastructure, Fiber Backbone, SMSe, SIC Rms, Power, Post One, Safe Haven | Logistics | 9/16/19 | 1/31/20 | 5/29/20 | EAP | Canberra | Australia | $ 67,190 | $ 51,513 | $ 84,574 | $ 1,146,102 | 205 | ||||
| TSU | 18007 | Hanoi Embassy & Annex Compounds TSU | TSU: ENS, IDNS, Cameras/HDVS, Infrastructure, Fiber Backbone, SMSe, SIC Rms, Power, Post One, Safe Haven | Logistics | 9/23/19 | 1/23/20 | 1/24/20 | Tung Shing Annex and Rose Garden Annex. | EAP | Hanoi | Vietnam | $ 49,997 | $ 39,270 | $ 89,489 | $ 1,402,360 | 210 | |||
| TSU | 18015 | Jerusalem America House TSU | TSU: ENS, IDNS, Cameras, Infrastructure, SMSe, SIC Rms, Power, Post One, Safe Haven | Logistics | 9/23/19 | 12/20/19 | 12/20/19 | NEA | Jerusalem | Israel | $ - 0 | $ - 0 | $ 22,654 | $ 989,519 | 413.04 | ||||
| TSU | 18026 | Manama Embassy Compound TSU | TSU: ENS, IDNS, Cameras/HDVS, Infrastructure, Fiber Backbone, SMSe, SIC Rms, Power, Post One, Safe Haven | Logistics | 9/23/19 | 1/24/20 | 1/24/20 | NEA | Manama | Bahrain | $ 53,325 | $ 45,432 | $ 63,622 | $ 1,221,278 | 416 | ||||
| TSU | 18029 | Quebec City Consulate Compound TSU | Limited TSU: SIC Rms, Power, Infrastructure, IDS, Specific Post Requests | Logistics | 10/7/19 | 12/3/19 | 12/3/19 | WHA | Quebec City | Canada | $ 22,123 | $ 13,766 | $ 31,544 | $ 342,360 | 634 | ||||
| TSU | 18030 | Doha Embassy Compound TSU | Limited TSU: Infrastructure, Fiber Backbone, SIC Rms, Power, Specific Post Requests | Logistics | 10/10/19 | 2/3/20 | 1/17/20 | NEA | Doha | Qatar | $ 39,687 | $ 31,462 | $ 46,094 | $ 727,846 | 411 | ||||
| TSU | 18006 | Tashkent Embassy Compound TSU | TSU: ENS, IDNS, Cameras/HDVS, Infrastructure, Fiber Backbone, SMSe, SIC Rms, Power, Post One, Safe Haven | Logistics | 10/14/19 | 2/13/20 | 2/13/20 | SCA | Tashkent | Uzbekistan | $ 43,808 | $ 26,164 | $ 64,217 | $ 826,052 | 373 | ||||
| TSU | 18027 | Recife Consulate Compound TSU | TSU: ENS, IDNS, Cameras/HDVS, Infrastructure, SMSe, SIC Rms, Power, Post One, Safe Haven | Logistics | 10/18/19 | 2/20/20 | 2/19/20 | WHA | Recife | Brazil | $ 51,088 | $ 22,195 | $ 71,851 | $ 674,776 | 636 | ||||
| TSU | 18012 | Milan Consulate Compound TSU | TSU: ENS, Cameras, Infrastructure, SMSe, SIC Rms, Power, Post One, Safe Haven | Logistics | 12/16/19 | 4/10/20 | 4/13/20 | EUR | Milan | Italy | $ 53,564 | $ 47,843 | $ 46,923 | $ 760,353 | 341 | ||||
| TSU | 18003 | Frankfurt Consulate Compound TSU | TSU: ENS, Cameras/HDVS, Infrastructure, Fiber Backbone, SIC Rms, Power, Post One | Logistics | 1/10/20 | 6/4/20 | 6/4/20 | EUR | Frankfurt | Germany | $ 101,935 | $ 72,719 | $ 89,301 | $ 1,299,572 | 327 | ||||
| TSU | 17016 | Kyiv Embassy Compound TSU | TSU: Cameras/HDVS, Infrastructure, Fiber Backbone, SIC Rms, Power, Post One | Installation | 11/19/18 | 5/10/19 | 5/10/19 | 9 | Install Phase 92% complete. Holiday break 12/24/18-1/14/19; USG shutdown; restart 2/4/19. | EUR | Kyiv | Ukraine | $ 49,461 | $ 43,834 | $ 85,514 | $ 1,029,582 | 333 | ||
| TSU | 15068 | Managua Embassy Per. CCTV | TSU: CCTV/ECCTV/HDVS, Infrastructure, Fiber Backbone, SIC Rms, Power | Installation | 12/3/18 | 5/10/19 | 5/31/19 | 9 | Install Phase 75% complete. Holiday break 12/24/18-1/14/19; USG shutdown; retart 2/4/19. | WHA | Managua | Nicaragua | $ 38,610 | $ 14,345 | $ 127,730 | $ 909,434 | 648 | ||
| TSU | 17013 | Yerevan Embassy Compound TSU | TSU: ENS, IDNS, Cameras/HDVS, Infrastructure, Fiber Backbone, SIC Rms, Power, SMSe, Post One, Safe Haven | Installation | 2/11/19 | 9/13/19 | 8/16/19 | 9 | Install Phase 43% complete. | EUR | Yerevan | Armenia | $ 49,148 | $ 37,145 | $ 98,367 | $ 1,393,602 | 370 | ||
| TSU | 17020 | Phnom Penh Embassy Compound TSU | TSU: ENS, IDNS, Cameras/HDVS, Infrastructure, Fiber Backbone, SMSe, SIC Rms, Power, Post One, Safe Haven | Installation | 2/25/19 | 8/16/19 | 7/19/19 | 8 | Install Phase 43% complete. | EAP | Phnom Penh | Cambodia | $ 48,629 | $ 29,033 | $ 72,408 | $ 1,116,789 | 224 | ||
| TSU | 17014 | Algiers Embassy Compound TSU | TSU: ENS, IDNS, Cameras/HDVS, Infrastructure, Fiber Backbone, SMSe, SIC Rms, Power, Post One, Safe Haven | Installation | 3/4/19 | 6/21/19 | 6/21/19 | 8 | Install Phase 36% complete. | NEA | Algiers | Algeria | $ 56,039 | $ 22,430 | $ 99,116 | $ 955,207 | 403 | ||
| TSU | 17012 | Tbilisi Embassy Compound TSU | TSU: ENS, IDNS, Cameras/HDVS, Infrastructure, Fiber Backbone, SIC Rms, Power, SMSe, Post One, Safe Haven | Installation | 5/2/19 | 4/22/19 | 7 | Install Phase 98% complete. Holiday break 12/24/18-1/14/19; USG shutdown; restart 2/4/19. | EUR | Tbilisi | Georgia | $ 36,800 | $ 34,586 | $ 57,004 | $ 1,357,624 | 301 | |||
| TSU | 18001 | Brasilia Embassy Compound TSU | TSU: ENS, IDNS, Cameras, Infrastructure, SMSe, SIC Rms, Power, Post One, Safe Haven, AACS | Installation | 4/23/19 | 4/16/19 | 2 | Install Phase 98% complete. | WHA | Brasilia | Brazil | $ 46,591 | $ 18,388 | $ 74,578 | $ 728,363 | 604 | |||
| TSU | 17010 | Tirana Embassy Compound TSU | TSU: ENS, IDNS, Cameras/HDVS, Infrastructure, Fiber Backbone, SIC Rms, Power, SMSe, Post One, Safe Haven | Closeout | 4/9/19 | 0 | Holiday break 12/24/18-1/14/19; USG shutdown; restart 2/4/19. | EUR | Tirana | Albania | $ 39,296 | $ 20,182 | $ 56,709 | $ 1,018,185 | 363 | ||||
| TSU | 17011 | Chiang Mai Consulate Compound TSU | TSU: ENS, IDNS, Cameras/HDVS, Infrastructure, Fiber Backbone, SIC Rms, Power, SMSe, Post One, Safe Haven | Closeout | 12/4/18 | EAP | Chiang Mai | Thailand | $ 38,197 | $ 23,472 | $ 18,499 | $ 618,644 | 207 | ||||||
| HTP | 19003 | Cairo Embassy Compound Design | Survey/Design: AACS, Infrastructure, Fiber Backbone, SIC Rms, Power, Post One | Design | 1/13/20 | 3/25/20 | 4/29/20 | Survey/design only. Post-managed install. 90% Design Review. | NEA | Cairo | Egypt | $ 54,683 | $ 34,284 | $ 34,866 | $ 760,587 | 406 |
PME1H
| HTP | 18020 | Abuja Embassy Compound TSU | TSU: ENS, IDNS, Cameras/HDVS, Infrastructure, Fiber Backbone, SMSe, SIC Rms, Power, Post One, Safe Haven | Design | 11/11/19 | 3/13/20 | 3/26/20 | 100% Design Review. | AF | Abuja | Nigeria | $ 60,108 | $ 35,954 | $ 31,010 | $ 1,950,536 | 101 | |
| MSG | 17006 | Hyderabad Consulate MSG | Activation - TSU | On Hold | 10/7/19 | 11/22/19 | 11/22/19 | FY2019 | Nimmo | SCA | Hyderabad | India | $ 20,016 | $ 13,095 | $ 30,429 | $ 394,433 |
&G SENSITIVE BUT UNCLASSIFIED
Project Management & Engineering Technical Security Upgrades (TSUs)
SENSITIVE BUT UNCLASSIFIED &P of &N
SIM
| Project_ID | Post Name | Project Type | Scope of Work | Current Project Phase | Baseline Project Install Start | Actual Project Install Start | Baseline Project Acceptance Finish | Projected Project Install Finish | Actual Install Finish | Comments | # SIM Resources Onsite |
| 19556 | Cairo Embassy | OPC | Install | Survey | 5/13/20 | 7/30/20 | |||||
| 19539 | Erbil Consulate | OPC | Refresh | Survey | 6/9/20 | 8/27/20 | |||||
| 19549 | Erbil Consulate | TSI | CCR Room Buildout | Survey | 6/10/20 | 8/28/20 | |||||
| 19531 | BDSC | TSI | PAX AACS Upgrade | Survey | 7/16/20 | 10/5/20 | |||||
| 19544 | Camp Alvarado | TSI | CCR UPS Install | Design | 6/8/20 | 9/30/20 | |||||
| 19541 | Kabul Embassy | TSI | SDA 2 CCR UPS Install | Design | 6/1/20 | 10/6/20 | |||||
| 19534 | Islamabad Embassy | TSI | Fiber Upgrade | Survey | 5/7/20 | 7/27/20 | |||||
| 19537 | Islamabad Embassy | TSI | CCTV Upgrade | Survey | 4/1/20 | 7/24/20 | |||||
| 19546 | Quantico | TSI | MSAU Upgrade | Design | 1/15/20 | 3/5/20 | |||||
| 18599 | Baghdad Embassy | TSI | Fiber Upgrade | Survey | 3/4/20 | 5/20/20 | |||||
| 18510 | Baghdad Embassy | TSI | SMSe Network Upgrade | Design | 2/3/20 | 4/23/20 | |||||
| 19552 | Shanghai | INT | OBO Integration | Design | 7/1/19 | 7/15/19 | |||||
| 19551 | Berlin | INT | OBO Integration | Design | 9/18/19 | 10/14/19 | |||||
| 19542 | Lyon | INT | OBO Integration | Design | 9/14/19 | 9/27/19 | |||||
| 19553 | Wellington | INT | OBO Integration | Design | 8/28/19 | 9/11/19 | |||||
| 18592 | Ashgabat | INT | OBO Integration (HDVS/SMSe) | Design | 9/16/19 | 10/11/19 | |||||
| 18590 | SA-24 | SPR | Perimeter Trailer Buildout | Survey | 7/16/19 | 9/20/19 | |||||
| 19550 | SA-24 | SPR | MTOC Version 2 Buildout | Survey | 7/16/19 | 10/23/19 | |||||
| 19543 | SA-24 | SPR | Uncooled Thermal Camera Testing | Survey | 11/8/19 | 1/20/20 | |||||
| 19545 | SA-24 | SPR | Network Video Decoder Testing | Survey | 11/8/19 | 1/20/19 | |||||
| 19548 | SA-24 | SPR | All-in-One Camera System Testing | Survey | 11/8/19 | 1/20/19 | |||||
| 19557 | SA-24 | SPR | ATS Trailer Retrofit | Survey | 12/4/19 | 2/14/20 | |||||
| 19532 | Baghdad Embassy | TSI | OTR Install | Design | 11/18/19 | 5/26/20 | |||||
| 19529 | DSCC | TSI | Video Wall Upgrade | Design | 1/16/20 | 9/10/19 | |||||
| 19538 | DSCC | TSI | CTC Furniture and AV Upgrade | Design | 10/25/19 | 1/30/20 | |||||
| 19528 | DSCC | TSI | Fiber Patch Panel Upgrade | Design | 6/4/19 | 6/6/19 | |||||
| 18502 | Kabul Embassy | TSI | HDVS Integration | Design | 4/28/19 | 5/11/20 | Cost Estimates? Requested update 4/24 | ||||
| 18503 | Kabul Embassy | TSI | SMSe Server Farm Relocation | Design | 12/2/19 | 11/29/19 | Cost Estimates? Requested update 4/24 | ||||
| 18558 | Jerusalem Embassy | TSI | CAA Modular | Design | 10/16/19 | 5/17/20 | Requested update 4/24 | ||||
| 19540 | Mogadishu Embassy | INT | OBO Integration (HDVS/SMSe) | Design | 5/23/19 | 7/19/19 | Cost Estimates? | ||||
| 18593 | Reykjavik Embassy | INT | OBO Integration (HDVS/SMSe) | Design | 5/23/19 | 6/17/19 | |||||
| 19521 | Matamoros Consulate | INT | OBO Integration (HDVS/SMSe) | Design | 5/20/19 | 4/13/19 | 5/7/19 | ||||
| 18556 | Peshawar Consulate | OPC | OPC Install | Logistics | 11/13/19 | 5/3/20 | |||||
| 18517 | Baghdad Embassy | OPC | ALT OPC Install | Design | 12/11/19 | 5/14/20 | |||||
| 18551 | Islamabad Embassy | OPC | EOC Refresh | Logistics | 8/2/19 | 10/11/19 | |||||
| 17518 | Mogadishu Embassy | OPC | SOC Install | Logistics | 4/14/19 | 4/14/19 | 8/1/19 | 5 | |||
| 17501 | Karachi Consulate | OPC | SOC Install | Logistics | 7/1/19 | 8/13/19 | |||||
| 18568 | Fort Pickett | OPC | FAST-C TSU | Installation | 3/18/19 | 3/18/19 | 5/6/19 | ||||
| 16519 | Fort Pickett | TSI | Mock Embassy | Logistics | 5/17/19 | 6/27/19 | 7 | ||||
| 18585 | Islamabad Embassy | TSI | AACS Upgrade | Logistics | 9/10/19 | 9/6/19 | |||||
| 19504 | Kabul Embassy | TSI | TIFC AV Upgrade | Logistics | 7/25/19 | 6/25/19 | |||||
| 18570 | Amman | OPC | HVAC Modification | Logistics | 5/16/19 | 7/4/19 | |||||
| 19535 | Kabul Embassy | TSI | Fiber Upgrade (50 Micron) | Logistics | 5/20/19 | 8/22/19 | Will receive from PM 4/29 | 10 | |||
| 19530 | Camp Alvarado | TSI | ECP-1 TSU | Installation | 2/13/19 | 2/8/19 | 5/23/19 | 3 | |||
| 18552 | Baghdad Embassy | TSI | CCR UPS Install | Installation | 3/29/19 | 3/18/19 | 5/27/19 | ||||
| 18501 | Baghdad Embassy | TSI | AACS Upgrade | Logistics | 5/8/19 | 10/31/19 | |||||
| 17545 | Erbil Consulate | TSI | BIO/SMSe Upgrade | Logistics | 3/28/19 | 5/13/19 | |||||
| 18514 | Wuhan Consulate | INT | OBO Integration | Logistics | 5/6/19 | 1/24/20 | |||||
| 18515 | Shenyang Consulate | INT | OBO Integration | Logistics | 10/4/19 | 11/29/19 | |||||
| 18539 | Amman | INT | OBO (HDVS/SMSe) Integration | Logistics | 4/15/19 | 5/23/19 | |||||
| 18563 | Istanbul Consulate | OPC | OPC Install | Closeout | 2/14/19 | 2/14/19 | 4/8/19 | 3/23/19 | |||
| 15051 | Peshawar Consulate | INT | SAM/BIO Install | Logistics | 5/27/19 | 7/21/19 | |||||
| 17544 | BDSC | TSI | North Gate CAC2 Install | Logistics | 6/21/19 | 10/21/19 | |||||
| 17522 | BDSC | TSI | BIAP Gate Install | Logistics | 7/30/19 | 12/12/19 | |||||
| 17546 | BDSC | TSI | SMSe Upgrade | Logistics | 3/11/19 | 4/22/19 | 4/30/19 | ||||
| 18553 | BDSC | TSI | CCR UPS Install | Logistics | 4/4/19 | 6/21/19 | |||||
| 18598 | BDSC | TSI | Fiber Deployment | Installation | 1/28/19 | 1/28/19 | 8/30/19 | 2 | |||
| 15050 | Lahore Consulate | INT | SAM/BIO Install | Logistics | 4/27/19 | 7/31/19 | |||||
| 16513 | Camp Seitz | TSI | TSU/BIO Install | Installation | 1/14/19 | 1/9/19 | 5/17/19 | 1/31/19 | |||
| 16525 | BDSC | TSI | ENS Upgrade | Logistics | 1/25/119 | 1/28/19 | 2/6/20 | 5 | |||
| 18506 | Kabul Embassy | TSI | SDA 2&3 Install | Closeout | 9/15/18 | 9/15/18 | 3/28/19 | 3/28/19 | 3/28/19 | ||
| 18516 | Pristina Embassy | INT | OBO (HDVS/SMSe) Integration | Logistics | 3/14/19 | 6/14/19 | |||||
| 15531 | Montreal Consulate | INT | OBO (HDVS/SMSe) Integration | Logistics | 8/6/19 | 8/29/19 | |||||
| 14084 | Jeddah Consulate | INT | OBO Integration | Logistics | 4/30/19 | 10/7/19 | |||||
| 17551 | Taipei Consulate | INT | OBO (Phase 2) Integration | Logistics | 4/25/19 | 5/20/19 | |||||
| 17012 | Tbilisi Embassy | PME | HDVS/SMSe Integration | Installation | 4/2/19 | 4/17/19 | |||||
| 17010 | Tirana Embassy | PME | HDVS/SMSe Integration | Installation | 4/3/19 | 3/27/19 | |||||
| 17016 | Kyiv Embassy | PME | HDV Integration | Installation | 4/29/19 | ||||||
| 15068 | Managua Embassy | PME | Perimeter CCTV HDVS/SMSe Integration | Installation | 4/17/19 | ||||||
| 17013 | Yerevan Embassy | PME | Remote SMSe Integration | Installation | 2/11/19 | 2/11/19 | |||||
| 17014 | Algiers Embassy | PME | HDVS/SMSe Integration | Installation | 7/31/19 | ||||||
| 17020 | Phnom Penh Embassy | PME | HDVS/SMSe Integration | Installation | 5/28/19 | ||||||
| 19559 | Islamabad Embassy | OPC | SOC Install | Survey |
Key
| KEY |
| Master Schedule dates as of Friday PM meetings |
| Highlighted Cells: Indicates change from last report |
| Acronym & Abbreviation List | ||
| AACS | Automated Access Control System | |
| ACM | Access Control Module | |
| ACS | Access Control System | |
| BDSC | Baghdad Diplomatic Support Center | |
| CAA | Controlled Access Area (Section 8, classified area) | |
| CAC | Controlled Access Center | |
| CAD | Computer-Aided Design | |
| CCTV | Closed Circuit Television | |
| DCS | Door Control System | |
| ECCTV | Enhanced Closed Circuit Television | |
| ENS | Emergency Notification System | |
| HDVS | High Definition Video System | |
| HDVU | High Definition Video Upgrade | |
| HTP | High Threat Post | |
| IDNS | Imminent Danger Notification System | |
| IDS | Intrusion Detection System | |
| IOB | Interim Office Building | |
| IP | Internet Protocol | |
| JAO | Joint Administrative Office | |
| L&L | Lock & Leave | |
| LCP | Local Contractor Package | |
| MCESG | Marine Corps Embassy Security Group | |
| MSAU | Marine Security Augmentation Unit | |
| MSG | Marine Security Guard | |
| NCC | New Consulate Compound | |
| NEC | New Embassy Compound | |
| NOB / X | New Office Building / Annex | |
| PAO | Public Affairs Office | |
| PM | Project Manager/Management | |
| SAM | Supplemental Authentication and Monitoring | |
| SCC | Security Command Center | |
| SIC | Security Interface Cabinet | |
| SMSe | Security Management System enterprise | |
| SMSeNet | Security Management System enterprise Network | |
| TG | Tear Gas | |
| TSS / A | Technical Security Systems / Assessment | |
| TSU | Technical Security Upgrade | |
| VB | Vehicle Barriers | |
| VSOC | Visual Security Operations Console | |
| VSS | Video Surveillance System |