This document is a Question and Bureau of Reclamation (BOR) Response file addressing technical specifications for air compressor and surge tank components. The questions and responses focus on the acceptability of a Charlatte "bladder-type" surge tank, with BOR indicating that bladder-type air chambers are not acceptable. The technical details include specification references (Section 33 16 14 and Drawings 1695-D-62271 through 1695-D-62282), surge tank operating pressure requirements, and compressor performance specifications. Key technical clarifications include: the surge tank's steady-state operating pressure of 140 psi is below the maximum operating pressure of 175 psi, and the compressor's low flow rate of 15-20 CFM is considered acceptable since it allows for a total runtime of 5.25 to 7 hours, which meets the site's requirement of filling within 8 hours.

View the file

Other files

File Type Posted
Sol_140R4025R0023_Amd_0007.pdf PDF
River_Intake_and_Pumping_Plant_second_site_visit_attendance_record_0007.pdf PDF
Sol_140R4025R0023_Amd_0006.pdf PDF
140R4025R0023_Attachment_2_7_-_00_00_02_-_Drawings_12192025_0005.pdf PDF
Sol_140R4025R0023_Amd_0005.pdf PDF
140R4025R0023_Questions___Answers_-_Round_3_0005.pdf PDF
140R4025R0023_Attachment_1_2_-_00_00_01_-_Specifications_12192025_0005.pdf PDF
140R4025R0023_Attachment_2_6_-_00_00_02_-_Drawings_11212025_0004.pdf PDF
140R4025R0023_Questions___Answers_-_Round_2_0004.pdf PDF
NGWSP_-_River_Intake_PP_Site_Tour_-_8OCTOBER2025_(1)_0004.pdf PDF
140R4025R0023_Attachment_5_-_WD_NM20250046_Building_-_San_Juan_County__NM_19SEP25_0004.pdf PDF
140R4025R0023_Attachment_1_1_-_00_00_01_-_Specifications_11212025_0004.pdf PDF
Sol_140R4025R0023_Amd_0004.pdf PDF
Sol_140R4025R0023_Amd_0003.pdf PDF
Sol_140R4025R0023_Amd_0002.pdf PDF
140R4025R0023_Questions___Answers_-_Round_1_0002.pdf PDF
Intake_and_River_Pumping_Plant_Site_Visit_Sign-in_Sheet_0002.pdf PDF
Sol_140R4025R0023_Amd_0001.pdf PDF
140R4025R0023_Attachment_2_5_-_00_00_02_Dwgs-B_321-356_22x34_09-24-2025_0001.pdf PDF
140R4025R0023_Attachment_2_2_-_00_00_02_Dwgs-B_101-200_22x34_09-24-2025.pdf PDF
140R4025R0023_Intake___River_PP_24SEP25.pdf PDF
140R4025R0023_Attachment_2_3_-_00_00_02_Dwgs-B_201-285_22x34_09-24-2025.pdf PDF
140R4025R0023_Attachment_2_1_-_00_00_02_Dwgs-B_001-100_22x34_09-24-2025.pdf PDF
140R4025R0023_Attachment_5_-_WD_NM20250046_Building_-_San_Juan_County__NM.pdf PDF
140R4025R0023_Attachment_1_-_00_00_01_-_Specifications_09242025.pdf PDF
140R4025R0023_Attachment_7_-_Experience_Form.docx DOCX document
Sol_140R4025R0023.pdf PDF
140R4025R0023_Attachment_2_4_-_00_00_02_Standard_Dwgs-B_286-320_22x34_09-24-2025.pdf PDF
140R4025R0023_Attachment_6_-_Past_Performance_Questionnaire.pdf PDF
140R4025R0023_Attachment_4_-_WD_NM20250040_Heavy_-_San_Juan_County__NM.pdf PDF
140R4025R0023_Attachment_9_-_Subcontracting_Plan_Template.docx DOCX document
140R4025R0023_Attachment_3_-_00_00_02A_Geology_04102025.pdf PDF
140R4025R0023_Attachment_8_-_Key_Personnel_Form.docx DOCX document
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question BOR Response Would the Charlatte “bladder-type” surge tank be acceptable? Bladder-type air chambers are not acceptable.

Please provide volume, pressure rating, orientation, outlet size, diameter of Air Chambers Details of air chamber design are listed in specification Section 33 16 14, and on specification Drawings 1695-D-62271 through 1695-D-62282.

Please review Air Compressor requirements: if steady state operating pressure of the surge tanks will be 140psi will the compressor discharge pressure of 120psi be functional?

140 psi still comes in below the maximum operating pressure of the basis of design unit, which is 175 psi.

Will compressor low rate of 15 to 20CFM be sufficient for the operation, seems VERY low?

Sites generally have very broad requirements for fill time, as long as it comes in under 8 hours. 15-20 cfm means a total runtime of 5.25 to 7 hours.