This document is a Questions and Answers (Q&A) file related to a federal contract opportunity, specifically addressing small business participation requirements for the Bureau of Reclamation. The document contains one question focused on Evaluation Factor 4: Small Business Participation and Indian Preference Hiring Plan, with the contractor seeking clarification on small business subcontracting goals.

The Bureau of Reclamation's response confirms that small business subcontracting goals are set by the Department of Interior (DoI) and cannot be modified, even in consideration of remote work location or project complexity. The goals are established as a percentage of total planned subcontracting dollars, specifically 45.87%. Additionally, contractors are required to separately identify the percentages of small business and large business participation relative to the total contract value. The response indicates that while the percentage cannot be reduced from 45.87%, contractors must still provide detailed breakdowns of business category participation.

View the file

Other files

File Type Posted
Sol_140R4025R0023_Amd_0007.pdf PDF
River_Intake_and_Pumping_Plant_second_site_visit_attendance_record_0007.pdf PDF
Sol_140R4025R0023_Amd_0006.pdf PDF
140R4025R0023_Questions___Answers_-_Round_4_0006.pdf PDF
140R4025R0023_Attachment_2_7_-_00_00_02_-_Drawings_12192025_0005.pdf PDF
Sol_140R4025R0023_Amd_0005.pdf PDF
140R4025R0023_Questions___Answers_-_Round_3_0005.pdf PDF
140R4025R0023_Attachment_1_2_-_00_00_01_-_Specifications_12192025_0005.pdf PDF
140R4025R0023_Attachment_2_6_-_00_00_02_-_Drawings_11212025_0004.pdf PDF
140R4025R0023_Questions___Answers_-_Round_2_0004.pdf PDF
NGWSP_-_River_Intake_PP_Site_Tour_-_8OCTOBER2025_(1)_0004.pdf PDF
140R4025R0023_Attachment_5_-_WD_NM20250046_Building_-_San_Juan_County__NM_19SEP25_0004.pdf PDF
140R4025R0023_Attachment_1_1_-_00_00_01_-_Specifications_11212025_0004.pdf PDF
Sol_140R4025R0023_Amd_0004.pdf PDF
Sol_140R4025R0023_Amd_0003.pdf PDF
Sol_140R4025R0023_Amd_0002.pdf PDF
Intake_and_River_Pumping_Plant_Site_Visit_Sign-in_Sheet_0002.pdf PDF
Sol_140R4025R0023_Amd_0001.pdf PDF
140R4025R0023_Attachment_2_5_-_00_00_02_Dwgs-B_321-356_22x34_09-24-2025_0001.pdf PDF
140R4025R0023_Attachment_2_2_-_00_00_02_Dwgs-B_101-200_22x34_09-24-2025.pdf PDF
140R4025R0023_Intake___River_PP_24SEP25.pdf PDF
140R4025R0023_Attachment_2_3_-_00_00_02_Dwgs-B_201-285_22x34_09-24-2025.pdf PDF
140R4025R0023_Attachment_2_1_-_00_00_02_Dwgs-B_001-100_22x34_09-24-2025.pdf PDF
140R4025R0023_Attachment_5_-_WD_NM20250046_Building_-_San_Juan_County__NM.pdf PDF
140R4025R0023_Attachment_1_-_00_00_01_-_Specifications_09242025.pdf PDF
140R4025R0023_Attachment_7_-_Experience_Form.docx DOCX document
Sol_140R4025R0023.pdf PDF
140R4025R0023_Attachment_2_4_-_00_00_02_Standard_Dwgs-B_286-320_22x34_09-24-2025.pdf PDF
140R4025R0023_Attachment_6_-_Past_Performance_Questionnaire.pdf PDF
140R4025R0023_Attachment_4_-_WD_NM20250040_Heavy_-_San_Juan_County__NM.pdf PDF
140R4025R0023_Attachment_9_-_Subcontracting_Plan_Template.docx DOCX document
140R4025R0023_Attachment_3_-_00_00_02A_Geology_04102025.pdf PDF
140R4025R0023_Attachment_8_-_Key_Personnel_Form.docx DOCX document
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question # Question BOR Response

Specific Paragraph: Evaluation Factor 4: Small Business Participation and Indian Preference Hiring Plan; Question: Please confirm small business subcontracting goals for this acquisition. This paragraph outlines the minimum subcontracting goals as a percentage of total planned subcontracting dollars; however, the following paragraph and later sections ask to submit small business participation values as a percentage of the total contract value.

Would the Bureau of Reclamation consider reducing the percentage of participation in the small business category from 45.87% of total planned subcontracting dollars to 25% of total planned subcontracting dollars due to the remote area and complexity of associated work?

Goals are set by Department of Interior (DoI) and cannot be changed. The goals are based as a percentage of total planned subcontracting dollars. But contractors also need to separately identify the percentage of small business and large business percentages of the total contract value.