This document appears to be a solicitation for the Clear Creek Dam Fish Passage Facility project in Yakima, Washington. The Bureau of Reclamation, a civilian federal agency, is seeking proposals for this project in Fiscal Year 2024, with an anticipated award occurring in Fiscal Year 2025.
The solicitation outlines the requirement for a fish passage facility at the Clear Creek Dam on the Yakima River. Interested offerors must send all correspondence to the Contract Specialist and Contracting Officer. The solicitation includes amendments, a pre-proposal site visit, and active fires in the vicinity of the project site. Offerors are advised to monitor SAM.gov for any changes to the pre-proposal site visit.
View the file
Other files
Show all 40
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. Department of the Interior SPECIFICATIONS Bureau of Reclamation Technical Service Center Denver, Colorado August, 2024
Clear Creek Dam Fish Passage Facility
Yakima Project, Washington
Columbia-Pacific Northwest Region Solicitation No. 140R1024R0015
This solicitation issued by Contracting Officer
Pacific Northwest Region Bureau of Reclamation
1150 North Curtis Road, Suite 100 Boise ID 83706-1234
CLEAR CREEK DAM
Fish Passage Facility
Yakima Project, Washington
FOREWORD
Work is located at Clear Creek Dam, approximately 45 miles west of Yakima, Washington in Yakima County. Work is for construction of a fish passage. Principal components include intake structure, pump, concrete fish ladder, dam gate automation, site lighting, generator building, electrical upgrades, and access road.
SEE SECTION L FOR SITE VISIT INFORMATION. ATTENDEES WILL PROVIDE
THEIR OWN PERSONAL PROTECTION EQUIPMENT (PPE) TO INCLUDE: SAFETY
GLASSES, SAFETY BOOTS, HARD HATS, AND SAFETY VESTS.
FOR DATE AND PLACE OF BID OPENING, SEE “SOLICITATION, OFFER, AND
AWARD” STANDARD FORM 1442.
FOR INFORMATION REGARDING BUREAU OF RECLAMATION'S PUBLICATION
"RECLAMATION SAFETY AND HEALTH STANDARDS" (LATEST EDITION AS
REVISED, WITH REVISIONS AT ( https://www.usbr.gov/safety/rshs/index.html ).
WHICH IS APPLICABLE TO WORK UNDER THIS CONTRACT, SEE CLAUSE AT
"WBR 1452.223-81 SAFETY AND HEALTH."
This page intentionally left blank.
Clear Creek Dam Fish Passage Facility Solicitation No. 140R1024R0015 i
PART I THE SCHEDULE..................................................................................................... A-1
SECTION A SOLICITATION/CONTRACT FORM ........................................................ A-2
SECTION B SUPPLIES OR SERVICES AND PRICES/COSTS ..................................... B-1
SECTION C DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK ................ C-1
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work
01 12 40 Construction Sequencing
01 14 10 Use of Site
01 14 12 Work Restrictions
01 14 20 River Operations and Unwatering
01 29 00 Payment Procedures
01 31 13 Project Coordination
01 31 19 Project Management and Coordination
01 31 30 Contract Document Management System
01 32 10 Construction Program
01 33 00 Submittals
01 33 26 Electrical Drawings and Data
01 35 10 Safety Data Sheets
01 35 20 Safety and Health
01 35 30 Contractor’s Onsite Safety and Health Personnel
01 42 10 Reference Standards
01 46 00 Quality Procedures
01 46 20 Testing Agency Services
01 46 25 Special Inspections
01 51 00 Temporary Utilities
01 55 00 Vehicular Access and Parking
01 55 20 Traffic Control
01 56 15 Protection of Existing Utilities and Installations
01 56 20 Existing Fences
01 56 32 Temporary Safety Fence
01 57 20 Environmental Controls
01 57 30 Water Pollution Control
01 57 50 Tree and Plant Protection
01 57 60 Protected Species
01 57 90 Preservation of Historical and Archeological Data
01 60 00 Product Requirements
01 71 20 Surveying
01 74 00 Cleaning and Waste Management
01 78 30 Project Record Documents
01 91 13 Commissioning
DIVISION 02 – EXISTING CONDITIONS
ii
02 41 10 Demolition and Removal of Temporary Outfall
DIVISION 03 – CONCRETE
03 01 31 Stilling Basin Floor Concrete Repair
03 11 10 Concrete Forming
03 15 12 PVC Waterstops
03 15 14 PVC Retro-Fit Waterstop
03 20 00 Concrete Reinforcing
03 20 10 Fiber Reinforced Polymer (FRP) Reinforcement
03 20 30 Post-Installed Grouted Anchor Bars
03 30 00 Cast-In-Place Concrete
03 35 10 Concrete Floor Hardener
03 48 00 Precast Concrete Stairs
03 62 20 Nonshrink Grout for Equipment and Metalwork
03 81 10 Concrete Removal and Disposal
DIVISION 05 – METALS
05 40 00 Cold-Formed Metal Framing
05 50 00 Metal Fabrications
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 21 10 Board Insulation
07 41 13 Pre-Insulated Metal Roof Panels
07 42 13 Pre-Insulated Metal Wall Panels
07 84 00 Firestopping
07 92 00 Joint Sealants
DIVISION 08 – OPENINGS
08 11 10 Steel Doors and Frames
08 31 20 Floor Access Hatches
08 33 20 Roll-Up Door
08 51 10 Steel Windows
08 62 00 Unit Skylights
08 71 00 Door Hardware
DIVISION 09 – FINISHES
09 29 00 Gypsum Board
09 30 10 Ceramic Tile
09 51 00 Acoustical Ceilings iii
09 65 10 Resilient Wall Base
09 81 16 Acoustic Blanket Insulation
09 96 20 Coatings
DIVISION 10 – SPECIALTIES
10 14 00 Accessibility Guidelines
10 14 16 Signage - Plaques
10 14 26 Entry Signs
10 14 45 Photoluminescent Signs
10 14 46 Photoluminescent Strips and Markers
10 28 13 Toilet Accessories
10 44 20 Fire Extinguishers
10 51 13 Metal Lockers
10 56 17 Wall Mounted Standards and Shelving
10 90 00 Dimensional Letter Signage
DIVISION 12 – FURNISHINGS
12 35 30 Casework
12 36 61 Countertops
DIVISION 13 - SPECIAL CONSTRUCTION
13 34 21 Metal Building System
DIVISION 14 - CONVEYING EQUIPMENT
14 11 10 Davit Arm Systems
14 42 00 Vertical Platform Lift
DIVISION 22 – PLUMBING
22 05 48 Vibration and Seismic Controls for Plumbing, Piping and Equipment
22 11 00 Facility Water Distribution
22 11 10 Auxiliary Water Systems
22 11 20 Service Water Equipment
22 11 23 Domestic Water Booster System
22 13 00 Facility Sanitary Sewage
22 13 13 On-Site Sewage System
22 13 16 Drain, Waste, and Vent Piping Systems
22 13 17 Oil-Water Separator System
22 14 00 Facility Storm Drainage
22 15 12 Pneumatic Operating System for Transfer Flume Flippers
22 30 11 Domestic Water Storage Tank iv
22 42 10 Plumbing Fixtures
DIVISION 23 - HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)
23 00 00 Heating, Ventilating, and Air-Conditioning (HVAC) System
23 05 13 Common Motor Requirements for HVAC Equipment
23 05 48 Vibration and Seismic Controls for HVAC Equipment
23 05 53 Identification-HVAC
23 09 00 Instrumentation and Control for HVAC
23 31 00 HVAC Ducts and Casings
23 33 00 Air Duct Accessories
23 34 00 HVAC Fans
23 37 00 Air Outlets and Inlets
23 81 00 Direct Expansion Refrigeration Air Conditioners/Heat Pumps
23 82 39 Unit Heaters
DIVISION 25 - INTEGRATED AUTOMATION
25 00 01 System Control and Monitoring
DIVISION 26 – ELECTRICAL
26 05 02 Basic Electrical Materials and Methods
26 05 10 Conductors and Cables
26 05 22 Medium Voltage Power Cable
26 05 26 Grounding and Bonding
26 05 33 Raceways and Boxes
26 05 36 Cable Trays
26 05 80 Wiring Checkout and Tests
26 16 14 Unit Substation
26 20 10 Temporary Power
26 24 16 Distribution Panelboards
26 24 20 Control Boards
26 24 43 600 Volt Motor Control Center
26 26 10 Transformer Load Center
26 27 40 Wiring Devices
26 30 10 Automatic Transfer Switches
26 32 10 Engine-Generator Set
26 51 10 Interior Lighting
26 52 20 Emergency Lighting
26 56 60 Exterior Lighting
DIVISION 27 – COMMUNICATIONS
v
27 30 01 Telephone System
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 10 01 Security and Surveillance Equipment
28 31 00 Fire Alarm System
DIVISION 31 - EARTHWORK
31 02 10 Dust Abatement
31 03 10 Diversion and Care of Flows
31 03 15 Temporary Outlet Works Diversion
31 03 33 Removal and Control of Water
31 11 00 Clearing and Grubbing
31 12 00 Removing Material in Stilling Basin
31 13 13 Remove and Salvage Trees
31 14 10 Stripping
31 23 02 Compacting Earth Materials
31 23 11 Earthwork
31 23 13 Sand Bedding
31 23 22 Pipe Trench Earthwork
31 23 39 Disposal of Excavated Materials
31 23 70 Controlled Low Strength Material (CLSM)
31 32 32 Geotextile
31 32 37 Biaxial Geogrid
31 37 00 Riprap
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 15 10 Gravel Surfacing
32 31 04 Remove and Reinstall Existing Chain Link Fence
32 91 19 Placing Topsoil
32 92 20 Seeding
DIVISION 33 – UTILITIES
33 09 16 Water Level Measuring Devices
33 12 71 Attraction Vertical Pumping Units
33 12 72 Trench Sump Vertical Pumping Units
33 22 14 Valves and Equipment for Intake Pipes, and Discharge Pipes
33 42 30 Reinforced Concrete Pipe Culverts
33 43 32 Geocomposite Strip Drains vi
33 44 30 Trench Drain
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 21 13 Retrievable, Self-Cleaning, Cylindrical Fish Screens
35 21 15 Diffuser Wall, Floor Panels and Adjustable Weir Blades
35 21 16 False Weir, Fish Transfer Flumes, and Fish Loading Pipes
35 21 17 Anesthesia Tank and Work Tables
35 21 18 Fish Lock False Floor, False Wall and Overflow Drain
35 21 21 Fish Ladder Bulkhead Gate
35 21 22 Stop-Planks and Seat Angles
35 21 23 V-Gate
35 21 24 Horizontal Crowder
35 21 84 Outlet Works Deflector Plate
35 21 94 Intakes Pipes and Discharge Pipes
35 22 10 Slide Gates
35 22 11 In-Line Drain Check Valve
DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT
41 22 10 Hoist for Fish Lock False Floor
41 22 14 JIB Crane
DIVISION 51 - INFORMATION AVAILABLE TO OFFERORS
51 00 00 Information Available to Offerors
51 10 20 Hydrographs, Exceedance Curves, and Reservoir Time History
51 10 50 Underwater Inspection Reports
DIVISION 52 - DRAWINGS
52 00 00 Drawings
DIVISION 53 - GEOLOGIC INVESTIGATIONS AND RECORDS
53 10 00 Geotechnical Baseline Conditions
53 20 00 Geologic Investigations
53 30 00 Records of Geologic and Subsurface Investigations
SECTION D PACKAGING AND MARKING .................................................................. D-1
SECTION E INPSECTION AND ACCEPTANCE ............................................................ E-1
E.1. 52.246-12 Inspection of Construction (Aug 1996) .................................................... E-1
SECTION F Section F Deliveries and Performance ........................................................... F-1 vii
F.1. 52.211-10 Commencement, Prosecution, and Completion of Work (Apr 1984) ...... F-1
F.2. 52.211-12 Liquidated Damages — Construction (Sep 2000) ................................... F-1
F.3. 52.211-18 Variation in Estimated Quantity (Apr 1984) ............................................ F-1
F.4. 52.242-14 Suspension of Work (Apr 1984) .............................................................. F-1
SECTION G CONTRACT ADMINISTRATION .............................................................. G-1
G.1. Government Point of Contact ................................................................................... G-1
G.2. 1452.201-70 Authorities and Delegations (Sep 2011) ............................................. G-1
G.3. DOI-AAAP-0028 Electronic Invoicing and Payment Requirements – Invoice
Processing Platform (IPP) (Feb 2021) ................................................................................. G-2
G.4. WBR 1452.201-80 Contracting Officer’s Representative’s Authorities and
Limitations – Bureau of Reclamation (May 2018) .............................................................. G-3
SECTION H SPECIAL CONTRACT REQUIREMENTS................................................. H-1
H.1. DOI-AAAP-0050 Contractor Performance Assessment Reporting System (Dec 2015)
H-1
PART II CONTRACT CLAUSES .......................................................................................... H-1
SECTION I CONTRACT CLAUSES ................................................................................. I-1
I.1. 52.252-2 Clauses Incorporated by Reference (Feb 1998) .......................................... I-1
I.2. 52.202-1 Definitions (Jun 2020) ................................................................................. I-1
I.3. 52.203-3 Gratuities (Apr 1984) .................................................................................. I-1
I.4. 52.203-5 Covenant Against Contingent Fees (May 2014) ......................................... I-1
I.5. 52.203-6 Restrictions on Subcontractor Sales to the Government (Jun 2020) ........... I-1
I.6. 52.203-7 Anti-Kickback Procedures (Jun 2020) ........................................................ I-1
I.7. 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper
Activity (May 2014) .............................................................................................................. I-1
I.8. 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (May 2014) ..... I-1
I.9. 52.203-12 Limitations on Payments to Influence Certain Federal Actions (Jun 2020)I-
I.10. 52.203-13 Contractor Code of Business Ethics and Conduct (Nov 2021) ............. I-1
I.11. 52.203-14 Display of Hotline Poster(s) (Nov 2021) ............................................... I-1
I.12. 52.203-17 Contractor Employee Whistleblower Rights (Nov 2023) ..................... I-1
I.13. 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or
Statements (Jan 2017) ............................................................................................................ I-1 viii
I.14. 1452.203-70 Restrictions on Endorsements – Department of the Interior (Jul 1996)
I-1
I.15. DOI-AAAP-0081 Security Requirements: Facility Access Information Technology
(Aug 2016) ............................................................................................................................. I-1
I.16. 52.204-9 Personal Identity Verification of Contractor Personnel (Jan 2011) ........ I-6
I.17. 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards
(Jun 2020) .............................................................................................................................. I-6
I.18. 52.204-13 System for Award Management (Oct 2018).......................................... I-6
I.19. Service Contract Reporting Requirements (Oct 2016) ........................................... I-6
I.20. 52.204-18 Commercial and Government Entity Code Maintenance (Aug 2020) .. I-6
I.21. 52.204-19 Incorporation by Reference of Representations and Certifications (Dec
2014) I-6
I.22. 52.204-21 Basic Safeguarding of Covered Contractor Information Systems (Nov
2021) I-6
I.23. 52.204-23 Prohibition on Contracting for Hardware, Software, and Services
Developed or Provided by Kaspersky Lab Covered Entities (Dec 2023) ............................. I-9
I.24. 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video
Surveillance Services or Equipment (Nov 2021) .................................................................. I-9
I.25. 52.204-27 Prohibition on a ByteDance Covered Application (Jun 2023) .............. I-9
I.26. 1452.204-70 Release of Claims – Department of the Interior (Jul 1996) ............... I-9
I.27. 52.209-6 Protecting the Government’s Interest When Subcontracting with
Contractors Debarred, Suspended, or Proposed for Debarment (Nov 2021) ........................ I-9
I.28. 52.209-9 Updates of Publicly Available Information Regarding Responsibility
Matters (Oct 2018)................................................................................................................. I-9
I.29. 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Nov
2015) I-9
I.30. 52.210-1 Market Research (Nov 2021) .................................................................. I-9
I.31. 52.215-2 Audit and Records – Negotiation (Jun 2020) .......................................... I-9
I.32. 52.215-8 Order of Precedence – Uniform Contract Format (Oct 1997) ................. I-9
I.33. 52.215-10 Price Reduction for Defective Certified Cost or Pricing Data (Aug 2011)
I-9
I.34. 52.215-12 Subcontractor Certified Cost or Pricing Data (Jun 2020) ...................... I-9
I.35. 52.215-15 Pension Adjustments and Asset Reversions (Oct 2010) ....................... I-9
I.36. 52.215-17 Waiver of Facilities Capital Cost of Money (Oct 1997) ....................... I-9 ix
I.37. 1452.215-70 Examination of Records by the Department of the Interior (Apr 1984)
I-9
I.38. 52.215-21 Requirements for Cost or Pricing Data and Data Other Than Certified
Cost or Pricing Data – Modifications (Jun 2021) ................................................................ I-10
I.39. 52.215-23 Limitations on Pass-Through Charges ................................................ I-10
I.40. WBR 1452.215-87 Incorporation of Technical Proposal (MAR 2021) ............... I-10
I.41. Contractor’s Technical Proposal Incorporated Into Contract – Bureau of
Reclamation – PN Region (Mar 2001) ................................................................................ I-11
I.42. 52.219-6 Notice of Total Small Business Set-Aside (Nov 2020) ......................... I-11
I.43. 52.219-8 Utilization of Small Business Concerns (Feb 2024) ............................. I-11
I.44. 52.219-14 Limitations on Subcontracting (Oct 2022) .......................................... I-11
I.45. 52.219-28 Post Award Small Business Program Rerepresentation (Feb 2024) ... I-11
I.46. 52.222-3 Convict Labor (Jun 2003) ...................................................................... I-11
I.47. 52.222-4 Contract Work Hours and Safety Standards – Overtime Compensation
(May 2018) .......................................................................................................................... I-11
I.48. 52.222-6 Construction Wage Rate Requirements (Aug 2018) ............................. I-11
I.49. 52.222-7 Withholding of Funds (May 2014) ........................................................ I-11
I.50. 52.222-8 Payrolls and Basic Records (Jul 2021) .................................................. I-11
I.51. 52.222-9 Apprentices and Trainees (Jul 2005) ..................................................... I-11
I.52. 52.222-10 Compliance with Copeland Act Requirements (Feb 1988) ................. I-11
I.53. 52.222-11 Subcontracts (Labor Standards) (May 2014) ....................................... I-11
I.54. 52.222-12 Contract Termination – Debarment (May 2014) ................................. I-11
I.55. 52.222-13 Compliance with Construction Wage Rate Requirements and Related
Regulations (May 2014) ...................................................................................................... I-11
I.56. 52.222-14 Disputes Concerning Labor Standards (Feb 1988) .............................. I-11
I.57. 52.222-15 Certification of Eligibility (May 2014) ............................................... I-11
I.58. 52.222-21 Prohibition of Segregated Facilities (Apr 2015).................................. I-11
I.59. 52.222-26 Equal Opportunity (Sep 2016) ............................................................. I-11
I.60. 52.222-27 Affirmative Action Compliance Requirements for Construction (Apr
2015) I-11
I.61. 52.222-35 Equal Opportunity for Veterans (Jun 2020) ........................................ I-11
I.62. 52.222-36 Equal Opportunity for Workers with Disabilities (Jun 2020) ............. I-11
I.63. 52.222-37 Employment Reports on Veterans (Jun 2020) ..................................... I-12 x
I.64. 52.222-40 Notification of Employee Rights Under the National Labor Relations
Act (Dec 2010) .................................................................................................................... I-12
I.65. 52.222-50 Combating Trafficking of Persons (Nov 2021) ................................... I-12
I.66. 52.222-54 Employment Eligibility Verification (May 2022) ............................... I-12
I.67. 52.222-55 Minimum Wages for Contractor Workers Under Executive Order 14026
(Jan 2022) ............................................................................................................................ I-12
I.68. 52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2022) ................ I-12
I.69. 52.223-3 Hazardous Material Identification and Material Safety Data (Feb 2021), Alternate I (Jul 1995) ........................................................................................................... I-12
I.70. 52.223-5 Pollution Prevention and Right-to-Know Information (May 2024) ...... I-12
I.71. 52.223-23 Sustainable Products and Services (May 2024) .................................. I-12
I.72. WBR 1452.223-80 Asbestos Free Warranty – Bureau of Reclamation (Aug 2021) I-
I.73. WBR 1452.223-81 Safety and Health – Bureau of Reclamation (Oct 2022) ....... I-12
I.74. WBR 1452.223-82 Ensuring Adequate Covid-19 Safety Protocols in Federal
Buildings and Federally Controlled Facilities – Bureau of Reclamation (Nov 2022) ........ I-13
I.75. 52.225-11 Buy American – Construction Materials Under Trade Agreements (Nov
2023) I-13
I.76. 52.225-13 Restrictions on Certain Foreign Purchases (Feb 2021) ....................... I-13
I.77. 52.226-1 Utilization of Indian Owned Economic Enterprises (Jun 2000) ............ I-13
I.78. 52.226-7 Drug-Free Workplace (May 2024) ........................................................ I-13
I.79. 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving
(May 2024) .......................................................................................................................... I-13
I.80. 52.227-1 Authorization and Consent (Jun 2020) .................................................. I-14
I.81. 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (Jun
2020) I-14
I.82. 52.227-4 Patent Indemnity – Construction Contracts (Dec 2007) ........................ I-14
I.83. 52.227-17 Rights in Data – Special Works (Dec 2007) ........................................ I-14
I.84. 52.228-2 Additional Bond Security (Oct 1997) .................................................... I-14
I.85. 52.228-5 Insurance – Work on a Government Installation (Jan 1997) ................. I-14
I.86. 52.228-11 Individual Surety—Pledge of Assets (Feb 2021) ................................ I-14
I.87. 52.228-12 Prospective Subcontract Requests for Bonds (Dec 2022) ................... I-14
I.88. 52.228-14 Irrevocable Letter of Credit (Nov 2014) .............................................. I-14
I.89. 52.228-15 Performance and Payment Bonds – Construction (Jun 2020) ............. I-14 xi
I.90. 1452.228-70 Liability Insurance – Department of the Interior (Jul 1996) ........... I-14
I.91. 52.229-3 Federal, State, and Local Taxes (Feb 2013) .......................................... I-15
I.92. 52.229-11 Tax on Certain Foreign Procurements-Notice and Representation (Jun
2020) I-15
I.93. 52.229-12 Tax on Certain Foreign Procurements (Feb 2021) .............................. I-15
I.94. WBR 1452.229-90 Notice of Washington State Sales and Use Tax – Bureau of
Reclamation – C-PN Region (Feb 1995) ............................................................................. I-15
I.95. 52.232-5 Payment under Fixed-Price Construction Contracts (May 2014) ......... I-15
I.96. 52.232-17 Interest (May 2014) ............................................................................. I-15
I.97. 52.232-23 Assignment of Claims (May 2014) ..................................................... I-15
I.98. 52.232-27 Prompt Payment for Construction Contracts (Jan 2017) ..................... I-15
I.99. 52.232-33 Payment by Electronic Funds Transfer – System for Award
Management (Oct 2018) ...................................................................................................... I-15
I.100. 52.232-39 Unenforceability of Unauthorized Obligations (Jun 2013) ................. I-15
I.101. 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Mar
2023) I-15
I.102. WBR 1452.232-80 Limitation of Funds – Bureau of Reclamation (Mar 2022) ... I-15
I.103. WBR 1452.232-81 Payment for Mobilization and Preparatory Work – Bureau of
Reclamation (Mar 2022), Alternate I (Mar 2022) ............................................................... I-17
I.104. 52.233-1 Disputes (May 2014), Alternate I (Dec 1991) ....................................... I-20
I.105. 52.233-3 Protest After Award (Aug 1996) ........................................................... I-20
I.106. 52.233-4 Applicable Law for Breach of Contract Claim (Oct 2004) ................... I-20
I.107. 52.236-1 Performance of Work by the Contractor (Apr 1984) ............................ I-20
I.108. 52.236-2 Differing Site Conditions (Apr 1984) .................................................... I-20
I.109. 52.236-3 Site Investigation and Conditions Affecting Work (Apr 1984) ............ I-20
I.110. 52.236-4 Physical Data (Apr 1984) ...................................................................... I-20
I.111. 52.236-5 Material and Workmanship (Apr 1984) ................................................ I-21
I.112. 52.236-6 Superintendence by the Contractor (Apr 1984) ..................................... I-21
I.113. 52.236-7 Permits and Responsibilities (Nov 1991) .............................................. I-21
I.114. 52.236-8 Other Contracts (Apr 1984) ................................................................... I-21
I.115. 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and
Improvements (Apr 1984) ................................................................................................... I-21
I.116. 52.236-10 Operation and Storage Areas (Apr 1984) ............................................ I-21 xii
I.117. 52.236-11 Use and Possession Prior to Completion (Apr 1984) .......................... I-21
I.118. 52.236-12 Cleaning Up (Apr 1984) ...................................................................... I-21
I.119. 52.236-13 Accident Prevention (Nov 1991), Alternate I (Nov 1991) .................. I-21
I.120. 52.236-14 Availability and Use of Utility Services (Apr 1984) ........................... I-21
I.121. 52.236-16 Quantity Surveys (Apr 1984), Alternate I (Apr 1984) ........................ I-21
I.122. 52.236-17 Layout of Work (Apr 1984) ................................................................. I-21
I.123. 52.236-21 Specifications and Drawings for Construction (Feb 1997), Alternate II
(Apr 1984) ........................................................................................................................... I-21
I.124. 52.236-26 Preconstruction Conference (Feb 1995) .............................................. I-21
I.125. WBR 1452.236-84 Preservation of Cultural Resources – Bureau of Reclamation
(Mar 2022) ........................................................................................................................... I-21
I.126. WBR 1452.237-80 Security Requirements – Bureau of Reclamation (Mar 2022) .. I-
I.127. WBR 1452.237-90 Implementation of Security Requirements – Construction
Contract – Bureau of Reclamation – C-PN Region (Aug 2010) ......................................... I-28
I.128. 52.242-13 Bankruptcy (Jul 1995) ......................................................................... I-29
I.129. 52.243-4 Changes (Jun 2007) ............................................................................... I-29
I.130. 52.243-6 Change Order Accounting (Apr 1984) .................................................. I-29
I.131. WBR 1452.243-80, Modification Proposals – Bureau of Reclamation (Mar 2022) –
Alternate II (Mar 2022) ....................................................................................................... I-29
I.132. 52.244-2 Subcontracts (Jun 2020) ........................................................................ I-31
I.133. 52.244-5 Competition in Subcontracting (Dec 1996) ........................................... I-31
I.134. 52.244-6 Subcontracts for Commercial Products and Commercial Services (Feb
2024) I-31
I.135. 52.245-1 Government Property (Sep 2021) .......................................................... I-31
I.136. 52.245-9 Use and Charges (Apr 2012) ................................................................. I-31
I.137. 52.246-21 Warranty of Construction Alternate I (Apr 1984) ............................... I-31
I.138. 52.248-3 Value Engineering – Construction (Oct 2020) ...................................... I-31
I.139. 52.249-2 Termination for Convenience of the Government (Fixed Price) (Apr
2012), Alternate I (Sep 1996) .............................................................................................. I-31
I.140. 52.249-10 Default (Fixed-Price Construction) (Apr 1984) .................................. I-31
I.141. 52.252-6 Authorized Deviation in Clauses (Nov 2020) ....................................... I-31
I.142. 52.253-1 Computer Generated Forms (Jan 1991) ................................................. I-31 xiii
I.143. WBR 1452.227-90 Contract Document Management System (CDMS)-CPN
Region (Apr 2021) ............................................................................................................... I-31
I.144. 1452.280-3 Indian Economic Enterprise Subcontracting Limitations (Feb 2021) ... I-
PART III LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS ............ I-1
SECTION J LIST OF ATTACHMENTS ........................................................................... J-1
J.1. Wage Determination (7 pages) .................................................................................. J-1
J.2. 140R1024R0015 Drawings (146 pages) .................................................................... J-1
J.3. Permits (625 pages) ................................................................................................... J-1
J.4. Geology Drawings (26 pages) ................................................................................... J-1
J.5. Bid Bond, Standard Form 24, OMB Control Number 9000-0045, Exp Date 8/31/2025
(2 pages) https://www.gsa.gov/forms-library/bid-bond ....................................................... J-1
J.6. Past Performance Questionnaire (6 pages) ................................................................ J-1
PART IV REPRESENTATIONS AND INSTRUCTIONS ................................................... J-1
SECTION K REPRESENTATIONS, CERTIFICATIONS, AND OTHER STATEMENTS
OF OFFERORS OR RESPONDENTS ................................................................................... K-1
K.1. Acquisition 360: Voluntary Survey (Sep 2023) ....................................................... K-1
K.2. 52.204-8 Annual Representations and Certifications (Feb 2024) ............................ K-1
K.3. 52.204-24 Representation Regarding Certain Telecommunications and Video
Surveillance Services or Equipment (Nov 2021) ................................................................ K-6
K.4. 52.204-29 Federal Acquisition Supply Chain Security Act Orders-Representation and
Disclosures (Dec 2023) ..................................................................................................... K-10
K.5. 52.209-7 Information Regarding Responsibility Matters (Oct 2018) .................... K-11
K.6. 52.209-13 Violation of Arms Control Treaties or Agreements-Certification (Nov
2021) K-13
K.7. 1452.280-4 Indian Economic Enterprise Representation (Feb 2021) .................... K-15
SECTION L INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR
RESPONDENTS ...................................................................................................................... L-1
L.1. 52.252-1 Solicitation Provisions Incorporated by Reference (Feb 1998) ................. L-1
L.2. 52.203-18 Prohibition on Contracting with Entities that Require Certain Internal
Confidentiality Agreements or Statements-Representation (Jan 2017) ............................... L-1
L.3. 52.204-7 System for Award Management (Oct 2018) .............................................. L-1
L.4. 52.204-16 Commercial and Government Entity Code Reporting (Aug 2020) .......... L-1
L.5. 52.204-22 Alternative Line Item Proposal (Jan 2017) .............................................. L-1 xiv
L.6. 52.211-1 Availability of Specifications Listed in the GSA Index of Federal
Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29 (Sep 2023)
L-1
L.7. 52.211-3 Availability of Specifications Not Listed in the GSA Index of Federal
Specifications, Standards and Commercial Item (Jun 1988) ................................................ L-1
L.8. 52.211-4 Availability for Examination of Specifications Not Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions (Jun 1988) ......... L-1
L.9. 52.211-6 Brand Name or Equal (Aug 1999) ............................................................. L-2
L.10. 52.215-1 Instructions to Offerors – Competitive Acquisitions (Nov 2021) .......... L-2
L.11. 52.215-16 Facilities Capital Cost of Money (Jun 2003) ........................................ L-2
L.12. 52.215-20 Requirement for Cost or Pricing Data Information Other than Cost or
Pricing Data (Nov 2021)....................................................................................................... L-2
L.13. 1452.215-71 Use and Disclosure of Proposal Information – Department of Interior
(Apr 1984) ............................................................................................................................ L-2
L.14. WBR 1452.215-80 Source Evaluation and Selection Procedures – Bureau of
Reclamation (Mar 2021) ....................................................................................................... L-2
L.15. WBR 1452.215-81 General Proposal Instructions – Bureau of Reclamation (Mar
2021) L-3
L.16. WBR 1452.215-86 Intent to Incorporate Technical Proposal – Bureau of
Reclamation (Mar 2021) ..................................................................................................... L-10
L.17. WBR 1452.215-91 Email Acknowledgement of Amendments, Modifications to
Offers, and Withdrawals of Offers (Apr 2022) .................................................................. L-10
L.18. 52.216-1 Type of Contract (Apr 1984) ................................................................ L-11
L.19. 52.222-5 Construction Wage Requirements – Secondary Site of Work (May 2014)
L-11
L.20. 52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal
Employment Opportunity for Construction (Feb 1999) ..................................................... L-11
L.21. WBR 1452.222-90 Non-Discrimination Notice to U.S. DOI Contractors, Subcontractors, and Lessors – Bureau of Reclamation - C-PN Region (Jan 2000) ........... L-13
L.22. 52.225-12 Notice of Buy American Requirement – Construction Materials Under
Trade Agreements (May 2014) ........................................................................................... L-13
L.23. 52.228-1 Bid Guarantee (Sep 1996) .................................................................... L-13
L.24. 52.232-13 Notice of Progress Payments (Apr 1984) ........................................... L-13
L.25. 1452.233-2 Service of Protest – Department of the Interior (Deviation) (Jul 1996)
L-13 xv
L.26. 52.236-27 Site Visit (Construction) (Feb 1995), Alternate I (Feb 1995) ............ L-13
L.27. 52.236-28 Preparation of Proposals – Construction (Oct 1997) .......................... L-14
L.28. WBR 1452.236-85 Instruction for Mobilization and Preparatory Work Schedule
Line Item – Bureau of Reclamation (Mar 2022) ................................................................ L-14
L.29. WBR 1452.236-92 Site Visit Attendance Restriction – Bureau of Reclamation – C-
PN Northwest Region (May 2004) ..................................................................................... L-15
L.30. 52.252-3 Alterations in Solicitation (Apr 1984) .................................................. L-15
L.31. 52.252-5 Authorized Deviation in Provisions (Nov 2020) .................................. L-15
SECTION M EVALUATION FACTORS FOR AWARD .............................................. M-15
M.1. WBR 1452.215-82 Evaluation Factors for Award – Quality Predominance –
Bureau of Reclamation (Mar 2021) .................................................................................. M-15
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION CALL
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
Bureau of Reclamation
Pacific Northwest Region
Regional Office Acquisition Management Division
R10
1150 N. Curtis Road, Ste. 100
Boise ID 83706-1234
Drew McGuire 2083785080
1x
140R1024R0015
INVITATION FOR BID
REQUEST FOR PROPOSAL
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
Project Title: Clear Creek Dam Fish Passage Facility
This solicitation is being solicited as a total small business set-aside.
The construction cost magnitude for this work is between $15,000,000.00 and
$20,000,000.00.
The contractor shall complete the work in accordance with F.1 52.211-10.
Commencement, Prosecution, and Completion of Work (Apr 1984)
Establish contractor Question and Answer (Q&A) cut-off date. The final date for contractor Q&A is 1400 Mountain Standard Time, on September 6th, 2024. No contractor questions will be accepted after this date and time. Please direct all questions to the Contracting Officer Lance Fleming at LFleming@usbr.gov and the Contract Specialist Drew McGuire at DMcGuire@usbr.gov.
A site visit has been scheduled for August 28th, 2024 at 1:00 PM PST. Participants need to register with Drew McGuire at DMcGuire@usbr.gov and Matt Maling MMaling@usbr.gov. Participants will meet at Clear Creek Dam Spillway, Naches, Yakima Continued ...
11. The Contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 1042 calendar days and complete it within ________________ ________________ calendar days after receiving
52.211-10
09/30/2024
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 12/2022)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
Lance Fleming
28. NEGOTIATED AGREEMENT 29. AWARD
and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations,certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
10 U.S.C. 3204(a) 41 U.S.C. 3304(a)
STANDARD FORM 1442 (REV. 12/2022) BACK
Continued...
and return
(Contractor is not required to sign this document.) Your offer on this
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
140R1024R0015
County, Washington 98937
To attend the site visit interested offers must adhere the provision requirements located in L.26 52.236-27 Site Visit (Construction) (Feb 1995), Alternate I (Feb 1995). Preregistration will close August 26th at 1200 MT.
1. Attendees should monitor weather conditions for the day of the site visit. Please plan and dress accordingly. Attendees should plan on walking 1-2 miles to tour the site
2. Attendees are required to bring Personal Protective Equipment (PPE). Appropriate PPE shall be worn throughout the duration of the site visit
(i.e. hard hats, safety shoes, safety vests, and safety glasses).
Please ensure Company UEI number is reflected on the proposal cover sheet.
Due to PRISM Limitation, the Period of
Performance in block 10. may be inaccurate. For accurate Period of Performance offerors are advised to review block 11. of this SF-1442 or the clause at F.1. 52.211-10. Commencement, Prosecution, and Completion of Work (Apr 1984)".
Delivery: 10/31/2027
Delivery Location Code: 0009906765
Bureau of Reclamation-PN-CCAO
Columbia Cascades Area Office
1917 Marsh Road
Yakima WA 98901-2058 US
Period of Performance: 12/23/2024 to 10/31/2027
00010 Clear Creek Dam Fish Passage Facility
(Price Schedule A CLINS 1 through 49)
Product/Service Code: Y1PZ
Product/Service Description: CONSTRUCTION OF
OTHER NON-BUILDING FACILITIES
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Clear Creek Dam Fish Passage Facility Yakima Project, Washington Solicitation No. 140R1024R0015
Price Schedule B - 1
CONTINUATION OF
SECTION B – SUPPLIES OR SERVICES AND PRICES
CLEAR CREEK DAM
FISH PASSAGE FACILITY
YAKIMA PROJECT, WASHINGTON
B.1 PRICE SCHEDULE
(a) Offers will be considered for award on the following Price Schedule, but no offer will be considered for award on only a part of the Price Schedule.
(b) Offers are subject to the terms and conditions of this solicitation.
(c) Quantities in the Price Schedule are estimated quantities for comparison of offers only.
Except as provided in the contract clause at FAR 52.211-18, Variation in Estimated Quantity, no claim shall be made against the Government for overruns or underruns. The contract clause at FAR 52.211-18, Variation in Estimated Quantity does not apply to lump sum items.
(d) See the contract clause at WBR 1452.232-81, Payment for Mobilization and Preparatory Work, for CLIN 1.
(e) Definitions:
(1) CLIN – Contract Line Item Number
PRICE SCHEDULE
CLIN Section Supplies or Services Quantity and Unit
Unit Price
Amount
1 WBR
1452.232 -81
Mobilization and Preparatory Work
For the lump sum of $
2 01 14 15 National Forest Roads For the lump sum of $
3 01 31 30 Contract Document Management System
For the lump sum of $
4 01 33 26 Electrical Drawings and Data For the lump sum of $
Price Schedule
B - 2
PRICE SCHEDULE
CLIN Section Supplies or Services Quantity and Unit
Unit Price
Amount
5 01 91 13 Commissioning For the lump sum of $
6 02 41 10 Selective Site Demolition For the lump sum of $
7 03 15 12 6-inch PVC Waterstop 2,600 lin ft $ $
8 03 30 30 Reinforced Cast-In-Concrete 1,160 yd3 $ $
9 03 30 30 Underwater Reinforced Concrete
For the lump sum of $
10 05 50 00 Miscellaneous Metalwork For the lump sum of $
11 13 34 40 Engine-Generator Building For the lump sum of $
12 25 00 01 System Control and Monitoring
For the lump sum of $
13 26 05 10 Conductors and Cables For the lump sum of $
14 26 05 26 Grounding and Bonding For the lump sum of $
15 26 05 33 Raceways and Boxes For the lump sum of $
16 26 24 16 Distribution Panelboards For the lump sum of $
17 26 24 30 Auxiliary Power and Control Equipment
For the lump sum of $
18 26 27 40 Wiring Devices For the lump sum of $
19 26 30 10 Automatic Transfer Switch For the lump sum of $
20 26 32 10 Standby Engine Generator Set For the lump sum of $
21 26 42 13 Submerged Galvanic Anode Cathodic Protection and Corrosion Monitoring Systems
For the lump sum of $
22 26 56 60 Luminaires For the lump sum of $
23 27 20 01 Communication System For the lump sum of $
24 28 10 01 Security and Surveillance System
B - 3
PRICE SCHEDULE
CLIN Section Supplies or Services Quantity and Unit
Unit Price
Amount
25 31 02 10 Water for Dust Abatement For the lump sum of
26 31 03 10 Diversion of Stream During Construction
For the lump sum of $
27 31 11 00 Clearing and Grubbing For the lump sum of $
28 31 23 11 Common Excavation 3,450 yd3 $ $
29 31 23 11 Rock Excavation 1,300 yd3 $
30 31 23 11 Compacted Backfill about Structures
1,230 yd3 $ $
31 31 23 39 Disposal of Excavated Material
For the lump sum of $
32 31 23 50 Earthwork for Roads For the lump sum of $
33 31 23 70 Controlled Low Strength Material (CLSM)
25 yd3 $ $
34 31 32 32 Geotextile 2,300 yd2 $ $
35 32 15 10 Gravel Surfacing 420 tons $ $
36 32 31 10 Chain Link Fence 550 lin ft $ $
37 32 31 10 Chain Link Fence Cover For the lump sum of $
38 32 92 20 Seeding and Restoration For the lump sum of $
39 33 09 12 Water Level Measuring Devices For the lump sum of $
40 33 12 71 Vertical Turbine Pumping Units
For the lump sum of $
41 35 10 10 Fish Screen For the lump sum of $
42 35 21 13 Cylindrical Screen For the lump sum of $
43 35 21 16 False Weir and Steep Pass For the lump sum of $
44 35 21 21 Coated Bulkhead Gate and Guides
For the lump sum of $
45 35 21 23 Bar Rack, Barrier Curtain Frame, and Guides
46 35 21 95 Steel Piping For the lump sum of $
B - 4
PRICE SCHEDULE
CLIN Section Supplies or Services Quantity and Unit
Unit Price
Amount
47 35 22 10 Slide Gates and Actuators For the lump sum of $
48 35 22 14 Valves and Equipment For the lump sum of $
49 35 79 30 Debris Boom Modifications For the lump sum of $
50 41 22 14 Jib Crane For the lump sum of $
TOTAL FOR PRICE SCHEDULE $_________________
END OF SUPPLIES OR SERVICES AND PRICES
TECHNICAL SERVICE CENTER
WRITTEN SPECIFICATIONS SIGNATURE SHEET
Specifications Title: Clear Creek Dam Fish Passage Facility
Project Title: Yakima Project, Washington
Region: CPN
Prepared:
Technical Approval:
Certified:
AMD/MOD
No.
Technical Approval Signature:
Prepared By Signature:
Revised Sections:
GERALD HORTON HORTON
Date: 2023.08.07 11:02:16 -06'00' P.E.
2023.08.07 11:42:38 -06'00' P.E.
NANCY ARTHUR ARTHUR
P.E.
DIVISION 01 - GENERAL REQUIREMENTS
Summary of Work
01 11 00 - 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.01 LOCATION
A. Work is located approximately 45 miles west of Yakima, Washington in Yakima County.
1.02 PRINCIPAL COMPONENTS OF WORK
A. Intake structure.
B. Piping and pump.
C. Fish ladder.
D. Dam gate automation with remote operation tie-in.
E. Site lighting and electrical system upgrade.
F. Electrical upgrades.
G. Construct access road.
1.03 SPECIFICATIONS REQUIREMENTS
A. Requirements in Division 1, General Requirements, apply to Divisions 2 through 53.
B. Imperative statements in these specifications are Contractor requirements, unless otherwise stated.
C. Where specifications are written in streamlined form, words “shall be” are included by inference where a colon (:) is used within sentence or phrase.
1.04 DEFINITIONS
A. When specifications use a word or term defined in Federal Acquisition Regulations (FAR), definition of the word or term shall be in accordance with FAR sections in effect at the time solicitation was issued.
1.05 ACRONYMS
A. The following acronyms apply to specifications Divisions 1 through 53:
1. CO: Contracting Officer.
2. COR: Contracting Officer’s Representative.
Summary of Work
01 11 00 - 2
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION
Use of Site 01 14 10 - 1
SECTION 01 14 10
USE OF SITE
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedule for other items of work.
1.02 REFERENCE STANDARDS
A. Bureau of Reclamation (Reclamation)
1. Cleaning Manual-2012 Inspection and Cleaning Manual for
Equipment and Vehicles to Prevent the Spread of Invasive Species (Technical memorandum No. 86-68220-07-05) 2012 Edition Available online at:
http://www.usbr.gov/mussels/prevention
1.03 SUBMITTALS
A. Submit in accordance with Section 01 33 00 - Submittals.
B. RSN 01 14 10-1, Land Use and Landscape Rehabilitation Plan:
1. For each Contractor use site on Government land.
a. Show use location and extent of impact. Uses include but are not limited to the following:
1) Buildings and service areas including offices, shops, warehouses, storage areas, fuel and oil storage areas, and fabrication yards.
2) Parking areas, temporary roads, and haul routes.
3) Utilities including air, power, and water lines; fire hydrants; and compressor station.
4) First-aid and medical facilities.
5) Aggregate processing. Show sizes, rated capacities, and general features of aggregate processing plant including transporting, storing, screening, and washing facilities; and concrete conveying, placing, and cooling plants.
6) Areas for processing, storing, and disposing of waste materials from construction operations.
http://www.usbr.gov/mussels/prevention
01 14 10 - 2
7) Temporary fences.
b. Describe methods to preserve, protect, and repair, vegetation (such as trees, shrubs, and grass) and other landscape features on or adjacent to jobsite and contractor use areas, which are not to be removed and which do not interfere with work required under this contract.
This is the start of the file's text. The full file is on GovTribe.