B08_Attachment_1-_A04_SOW_Hazard_Tree-Removal_2026_Rev_1_0001.docx
DOCX document 49 KB Posted
- Attached to
- GRSM CALL OUT TREE SERVICES
- Solicitation number
- 140P5326Q0031
About this file
This is a Statement of Work (SOW) for call-as-needed hazard tree removal services at Great Smoky Mountains National Park (GSMNP) across Tennessee (Blount, Sevier, and Cocke Counties) and North Carolina (Swain and Haywood Counties). The contract covers hazard tree removal along park roadways and developed areas, as well as strainer hazard tree removal within a 1.5-mile section of Deep Creek near Bryson City, NC. A hazard tree is defined as any tree greater than 6 inches diameter at breast height (DBH) with major defects—including dead snags, significant dead stems, unnatural lean toward targets, rot affecting over 30% of the defect site, internal hollows exceeding 66% basal area, trunk cracking, root lifting, or significant canopy dieback over 50%—likely to impact targets such as roadways, campsites, buildings, or parking areas. Work locations include roads, trails, campsites, picnic areas, parking areas, overlooks, pulloffs, and administrative areas, with removal tasks categorized by complexity levels based on diameter, access conditions, target conditions, and tree condition (live or dead).
The contractor must furnish all labor, supervision, equipment, tools, transportation, materials, and incidentals necessary for tree removal and woody material handling. The performance period runs approximately June 2026 through March 2027, with no work permitted on weekends, Federal holidays, October, or weeks surrounding major holidays unless authorized. Response time requirements are five business days for standard hazard calls and 72 hours for Deep Creek strainer calls. An International Society of Arboriculture (ISA) Certified Arborist must be physically present on site during all tree work. Work must comply with ANSI Z133 and ANSI A300 Part 1 standards, OSHA requirements, and the Manual on Uniform Traffic Control Devices (MUTCD), with traffic control required except during the seasonal restriction period (June 15–August 15) when no lane closures are permitted. Environmental protections include restrictions on cutting trees during Indiana Bat roosting periods (April 1–November 14) and conservation measures for Northern Flying Squirrels at elevations above 4,500 feet. Woody material handling requirements vary by location: 70–90% hauloff at roadsides (with chipping of remainder permitted), 100% hauloff in developed areas, logs 12 inches or greater bucked into 2-foot sections for campground firewood stacks, and 8-foot log lengths in streams. Pre-work submittals required include OSHA-compliant safety and traffic control plans, certificates of insurance, ISA credentials, CPR/First Aid certifications for sawyers, and a project schedule. Payment is contingent on funding, with final payment requiring submission of a Release of Claims.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Rev 1
1. Purpose & Background This Statement of Work (SOW) establishes requirements for call‑as‑needed hazard tree removal services across Great Smoky Mountains National Park (GSMNP), covering Tennessee (Blount, Sevier, and Cocke Counties) and North Carolina (Swain and Haywood Counties). Work includes: (1) hazard trees along park roadways and developed areas, and (2) strainer hazard trees within the Deep Creek waterway. Services are issued via individual task orders.
2. Scope of Services The Contractor shall furnish all labor, supervision, equipment, tools, transportation, materials, and incidentals necessary to remove park‑identified hazard trees and handle woody materials in accordance with this SOW, applicable standards, and environmental/resource protections. Work locations include roads, trails, campsites, picnic areas, parking areas, overlooks, pull‑offs, and administrative areas; Deep Creek work is limited to the 1.5‑mile section described herein.
2.1 Hazard Tree Removal (Roadside/Developed Areas) (Associated with CLINs 0050–0070)
· Remove park‑identified hazard trees adjacent to roadways and in developed areas (administrative sites, buildings, campgrounds, picnic areas, parking areas).
· Hazard tree definition: any tree >6″ DBH (Diameter at Breast Height) with a major defect likely to impact a target upon failure (e.g., roadway, campsite, building, parking area). Major defects include: dead snags; significant dead stems/leaders/scaffolds; heavy, unnatural lean toward/parallel to target; open hollows/cankers/rot affecting >30% at site of defect; internal hollows >66% basal area; horizontal/vertical trunk cracking; root lifting; damage/exposed >30% anchoring roots; significant canopy dieback >50%.
· For contract and ordering purposes, hazard tree removal tasks may be categorized by complexity levels based on diameter, access conditions (equipment vs. foot), target conditions, and whether the tree is live or dead. These complexity categories are defined in the contract price schedule and used for task order assignment.
2.2 Strainer Hazard Tree Removal (Deep Creek Waterway) (Associated with CLINs 0080–0100)
· Remove strainer trees (fallen or threatening to fall) within the identified Deep Creek 1.5‑mile section (approx. 3 miles north of Bryson City, NC). Equipment is restricted to roadway surfaces; crews may need foot access up to ~300 ft to reach trees in the creek. Cutting may be in or near swift water.
2.3 Professional Arborist Requirement (Associated with CLIN 0140) An International Society of Arboriculture (ISA)‑Certified Arborist shall be physically present on site during all tree work. Provide an alternate certified arborist when the primary is off site.
3. Performance Period & Response Times (Response times correspond to CLINs 0010–0040)
· Period of Performance: approximately June 2026 through March 2027; option periods subject to funding. No work permitted on weekends, Federal holidays, month of October, or the weeks surrounding Thanksgiving, Christmas, New Year’s, and Easter, unless the Park authorizes work in closed areas. Weekends: noon Friday to 8:00 a.m. Monday.
· Standard hazard calls: Contractor must respond and begin removal within 5 business days of Park notification.
· Deep Creek strainer calls: Contractor must respond and begin removal within 72 hours of Park notification.
4. Worksite Access & Traffic Control (Associated with CLINs 0120–0130)
· Keep roads open to the public at all times except where one‑lane closures are permitted and properly controlled. No lane closures are allowed June 15 – August 15. Debris must be cleared before lanes are reopened.
· Traffic control shall comply with the Manual on Uniform Traffic Control Devices (MUTCD). Arrow board is required for any work on the Gatlinburg Spur. Use appropriate signage, cones, flaggers, and maintain measures at all times during operations. Coordinate with the Facilities Management Office. Traffic control in areas closed to the public is still required for Park staff/contractor traffic.
Table 1 — Traffic Control Requirements
| Condition |
| Requirement |
| Notes |
| General operations |
| MUTCD‑compliant traffic control |
| Flaggers/signage/cones; clear debris before reopening lanes |
| Seasonal restriction |
| No lane closures (Jun 15 – Aug 15) |
| Exceptions only if Park authorizes work in closed areas |
| Gatlinburg Spur |
| Arrow board required |
| Use per MUTCD; coordinate with Park Facilities Management |
5. Protection of Park Infrastructure & Natural Resources
· Prevent damage to asphalt, guardrails, signage, headwalls, specimen trees, boulders, curbing, and other Park amenities; small patches are not allowed on roadway sections paved/overlaid within 3 years. Mill and overlay full lane width (per Federal Highway Administration (FHWA) requirements) is required where contractor operations damage newly paved sections.
· Prevent off‑road equipment use: no vehicular equipment beyond forest edge (including skid steers, tracked chippers). Avoid piling material against non‑hazard trees; protect cultural resources—stop work and notify COR immediately if encountered.
· Pruning/Felling Standards: comply with ANSI Z133 and ANSI A300 Part 1; pruning from bucket/aerial lift or trained climber using proper rope techniques; no spiking/gaffing on non‑removal trees.
6. Environmental & Wildlife Protections
6.1 Indiana Bats (Federally Listed)
· Normal cutting window: Nov 15 – Mar 31 for potential roost trees. Outside this period, Park will confirm no roosting before cutting trees >6″ DBH that exhibit structural roost characteristics (exfoliating bark, cavities, crevices, typically on dead/hollow/dying/damaged/very large trees). Certain trees may be cut outside the window (e.g., root‑sprung roadside hazards; live trees with tight bark/no cavities; Spruce/Fir forests).
6.2 Northern Flying Squirrels (Federally Listed)
· Applies at elevations >4,500 ft. Do not cut trees or limbs with holes/crevices/cavities; survey and show any non‑removed trees to COR for concurrence. Yellow birch/northern hardwoods require conservative cutting practices.
7. Woody Material Handling & Disposal (Associated with CLIN 0110)
· Roadside areas: 70–90% of felled logs/woody material shall be hauled off as directed by CO/COR; remaining material may be chipped and evenly spread if approved, ensuring aesthetics are not compromised.
· Developed areas: 100% of woody material must be hauled off Park property unless campground exception applies.
· Campgrounds (exception): logs ≤12″ diameter shall be bucked into 2‑ft sections and stacked at the woodline for firewood; tops/small material shall be hauled off.
· Stumps at roadsides: cut to ≤2″ height or remove and restore area to original contour.
· Streams: logs dropped in streams shall be cut to ≤8 ft lengths; keep chips/debris out of drainage structures; chip piles ≤3″ high, evenly spread, and not in open grass areas.
Table 2 — Woody Material Handling (by location)
| Location |
| Requirement |
| Contractor Action |
| Roadside |
| 70–90% haul‑off |
| Remove majority; chip balance as approved; maintain park aesthetics |
| Developed areas |
| 100% haul‑off |
| Legally dispose off Park property |
| Campgrounds |
| Logs ≤12″ → 2‑ft sections |
| Stack at woodline; haul off tops/small material |
| Streams |
| Logs ≤8 ft |
| Maintain flow; no debris in drainage structures |
| Roadside stumps |
| ≤2″ or remove |
| Restore original contour if removed |
Note:
· Along roadways, woody material (tree tops, branches, logs, etc.) shall be hauled out of the Park or be disposed of in adjacent wooded areas (chipped only) as long as, in the opinion of the government, the aesthetic quality of the park is not compromised.
· Logs left on site in Government-approved areas shall be laid flat to be in full contact with the ground
8. Health, Safety & Fire Prevention
· Comply with OSHA; furnish PPE (hard hats, goggles, chaps, gloves, hearing protection, high‑top leather boots with lugged soles). Keep first‑aid kit, bee‑sting kit, radio/cell communications, and a vehicle available for emergency transport. Sawyers must be trained and currently certified in First Aid and CPR.
· Fire prevention: Position exhausts away from combustibles; provide ≥1 fire extinguisher per vehicle/equipment; notify COR immediately of any fire starts, regardless of size.
· Contractor conduct: Comply with National Park Service rules while on or traveling within Park boundaries.
9. Reporting & Documentation
· Daily logs: Date, weather, personnel, equipment on site, and work accomplished; contractor’s own form acceptable.
· Tree removal reports: Daily count of hazard trees removed per call‑out.
· Accident reporting: Immediately report to area Ranger and COR (or Project Inspector).
10. Submittals (Pre‑Work / Before NTP) Provide the following prior to Notice to Proceed (NTP):
| Submittal |
| Description |
| Safety Plan |
| OSHA‑compliant safety & emergency plan (hazards, accident/spill response) |
| Traffic Control Plan |
| MUTCD‑compliant measures; staffing; devices; arrow board use on Gatlinburg Spur |
| Certificate of Insurance |
| Evidence of required coverage |
| ISA Credentials |
| Certification/licensure for arborists; provide alternates when primary off site |
| CPR/First Aid Certifications (Sawyers) |
| Current training as per OSHA |
| TN Herbicide/Pesticide Licensure |
| As applicable; include data and MSDS |
| SF‑1413 (Statement/Acknowledgement) |
| For all subcontractors |
| Project Schedule |
| Mobilization and activity plan; pre‑construction meeting and NTP milestones |
11. Quality Standards & Assurance
· Perform work per ANSI Z133/ANSI A300, base contract, and commercial practices. QA/QC is the Contractor’s responsibility; COR and Park inspectors will evaluate performance against this SOW. At completion, ensure safe access to roads, trails, pull‑offs, overlooks, and parking areas is re‑established; remove/chip/spread brush in the disturbance area; remove incidental trash/equipment daily; repair direct/indirect damage to Government property.
12. Schedule & Mobilization
· Work may start after award, submittal approvals, pre‑construction conference, issuance of NTP, and coordination of a work schedule with the CO (Contracting Officer). Standard hazard calls: 5 business days; Deep Creek strainer calls: 72 hours.
13. Funding Limitations
· Work is contingent on funding; Government liability is limited to amounts authorized via written contracts. Government may award base and any combination of options; all work under a single contract.
14. Fee & Payment
· Final payment requires submission of a Release of Claims; list any exceptions and monetary amounts with references.