This document is a pre-bid in-person meeting presentation for the National Park Service (NPS) Bandelier National Monument Replace Underground Utilities project, held on May 12, 2026 (PMIS: 266697). The project involves replacing aging utility infrastructure across the monument's Mesa Top and Canyon areas to support current and projected future visitor populations (200,000-250,000 annually, with projections of 18 million visitors over 100 years).
The base contract includes six primary contract line items (CLINs): CLIN 0001—Main Park Water System (new 10-inch, 8-inch, and 6-inch PVC water mains from Blue Tank through Abert's Squirrel Loop and Campground/Entrance Roads to Canyon Area, plus a 24,000-gallon concrete water storage tank and Canyon Mechanical Building); CLIN 0002—Mesa Housing and Field Operations Center (FOC) Water Mains and Service Lines (6-inch PVC mains with meter and fire hydrant replacements); CLIN 0003—Primary Electrical Distribution (new primary service from Los Alamos National Laboratory [LANL] to Mesa Top, plus fiber-optic conduits); CLIN 0004—Cellular Network (remote monitoring systems); CLIN 0005—Rock Excavation (during trenching operations); and CLIN 0006—Roadway (asphalt pavement removal, replacement, and restoration at Entrance Road and Visitor Center area). The contract includes multiple optional CLINs (Options A through O) covering electrical inter-connections, Frijoles Canyon water and gas systems, wastewater replacement, fiber-optic cables, utility demolition, Juniper Campground water systems, culvert and erosion repairs, and specialized electrical work at various locations.
Key construction challenges include sequencing utility outages to minimize service disruptions, managing public visitor safety on active roads and in visitor areas, coordinating with utility providers (Los Alamos County and LANL), navigating narrow and utility-dense corridors, working with medium-accuracy existing utility location data, and addressing archaeological and historical preservation requirements that may result in work stoppages if artifacts are discovered. The project requires careful management of hazardous materials (DDT-contaminated soil) and protection of historic features including flagstone walkways, retaining walls, and stone drainage systems throughout both the Mesa Top and Canyon areas.
View the file
Other files
Show all 41
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NATIONAL PARK SERVICE – BANDELIER NATIONAL MONUMENT
REPLACE UNDERGROUND UTILITIES
N P S – B a n d e l i e r N a t i o n a l M o n u m e n t
R e p l a c e U n d e r g r o u n d U t i l i t i e s
Pre-Bid In-Person Meeting May 12, 2026
PMIS: 266697
Welcome from the Jacobs and NPS Teams!
©Jacobs 2026
Agenda
Project Location Overview
Contract Line Items (CLINs)
Construction Challenges - Summarized
Site Walkthrough
Project Location Overview
Historical cornucopia: 1150 CE – 1550 CE
Ancestral lands for at least 23 tribal nations
Rich in archaeological artifacts:
− Cavates
− Pottery shards
− Tools
− Paleoindian points
− Burial grounds
Where are we?
Cochiti Pueblo guided Adolf Bandelier to the cliffs in 1880.
Established as monument in 1916 by Woodrow Wilson
Civil Conservation Corp (CCC) – constructed infrastructure (1930s)
Historic Mission 66 Corridor
NPS starting counting visitors in 1932 with 4,200. Peaked in 1994 with 430,000 visitors with a current steady annual visitation of 200,000 – 250,000.
Projected to have 18 Million visitors in 100 years.
Why Bandelier?
©Jacobs 20267
Location Overview
Mesa Top
Canyon Area
Contract Line Items (CLINs) (Dwg. 00G003)
CLIN 0001 - Main Park Water System
Partial scope:
− New 10-inch, 8-inch and 6-inch PVC water mains from existing Blue Tank (Mesa Top) through Abert’s Squirrel Loop, along Campground Road and Entrance Road, ending in Canyon Area maintenance yard.
− Replace meters, service lines and fire hydrants
− New 24,000-gallon cast-in-place concrete water storage tank
− New prefabricated Canyon Mechanical Building
Challenges:
− LANL coordination
− Public visitors safety on Entrance Road
− Narrow Entrance Road utility corridor (existing electric/fiber and force main)
CLIN 0002 - Mesa Housing and Field Operations Center (FOC) Water Mains and Service Lines
Partial Scope:
− New 6-inch PVC water mains from Campground Road to FOC and Mesa Housing (Saltbrush Ct. and Paintbrush Ct.)
− Replace service lines, water meters and fire hydrants
Challenges:
− Residential area
CLIN 0003 - Primary Electrical Distribution
Partial scope:
− New primary service from LANL to the Mesa Top System.
− New primary distribution system in the Mesa Top areas: Entrance Station, Juniper Campground, Mesa Top Housing, and FOC.
− New Fiber-Optic conduits and handholes
Challenges:
− Continued LANL coordination for service
− Los Alamos County maintains voltage system (need to meet County requirements)
− Built in parallel to prevent massive outages (sequence construction)
− Long lead items: pad-mount switch gears, pad-mount residential transformers and standby gas-generator
CLIN 0004 - Cellular Network
Scope:
− Remote Monitoring Systems for Main Blue Tank, PRV Vault and Main Lift Station
Challenges:
− Ensuring signal within Canyon
CLIN 0005 - Rock Excavation
Scope:
− Rock Excavation (during trenching)
Challenges:
− Slows trenching operations
− May require special equipment
CLIN 0006 - Roadway
Partial scope:
− Remove, dispose, and replace asphalt pavement on roads and parking to match existing curbs at Entrance Road and Frijoles Canyon Visitor Center area. Protect historic curbs, stone drainage, and retaining walls.
Challenges:
− Construction in public Entrance Road and parking areas – visitor safety
− Projection of historic features
CLIN Option A - Primary Electrical Inter-Connection Between Frijoles Canyon and Mesa Top Systems
Partial scope:
− Provide new electrical duct banks and access vaults to facilitate future interconnection tie between the Mesa Top and the Frijoles Canyon distribution systems.
− Install duct banks in the shared utility corridor parallel to the water and gas lines between Campground Road and the Fire Tower Lane.
− Construction in shared utility corridor with water and gas
CLIN Option B - Frijoles Canyon Water and Natural Gas Main Loop
Partial scope:
− Replace all existing 6-inch distribution waterlines, service lines to meters, fire hydrants, and water meters from Canyon Maintenance Yard inter-tie and loop around admin. buildings, casitas, and Visitor Center
− Replacement of all existing natural gas distribution lines (mains) and service lines for Frijoles Canyon areas (Visitor Center and Buildings).
Challenges:
− Construction in shared, narrow utility corridor with electric and communication
− Existing utilities’ location is not exact
− Historic flagstone walkways
− Hand dig/small excavating equipment within casita courtyard
Dwg 02C200
CLIN Option C - Frijoles Canyon Wastewater System
Partial scope:
− Replace vitrified clay sewers and manholes and sagging ductile and PVC pipes (from existing CCTV results) and install new 4-inch through 8-inch C900 PVC pipes.
− Dispose (only if needed) of DDT contaminated soil
− Remove and dispose sewer laterals and associated receiving manholes and install new Schedule C900 PVC laterals to cleanout.
Challenges:
− Traffic control needed; visitor safety
− Historic flagstone walkways
− Hand dig/small excavating equipment within casita courtyard
− Includes contact with DDT soil – excess soil to be disposed of per Hazardous Waste regulations. Use it as backfill!
CLIN Option D - Frijoles Canyon Natural Gas Laterals
Partial Scope:
− Replace service lines for each building within the Frijoles Canyon Loop up to the regulator for buildings where the regulator and meter are adjacent to the building.
Challenges:
− Construction in shared, narrow utility corridor with electric, communication and water.
− Hand dig/small excavating equipment within casita courtyard
− Existing utilities’ location is not exact
− Historic flagstone walkways
CLIN Option E - Fiber-Optic Cable from Existing Fiber Handhole Near the Entrance road (Pajarito) Microwave Tower to FOC and Entrance Station
Scope:
− Provide 12-strand fiber-optic cables from Frijoles Canyon IT room in Building #15 to FOC, and from FOC to Entrance Station. Existing duct bank conduits and innerduct will be utilized from the Canyon IT room to an existing communications handhole near Fire Tower Lane. New underground dedicated fiber-optic duct bank conduits from the existing handhole to the FOC and Entrance Station are included under CLINs 0003 and Option A.
Challenges:
− None expected
CLIN Option F - Frijoles Canyon Visitor Center Fiber Pathway Scope:
− Provide underground conduit pathway between the Building 15 IT room and the Visitor Center Server Room.
− Provide building penetrations for new conduits.
− None expected
CLIN Option G – Demolition of Utility Features
Scope:
− After new utility systems are active and functional, remove above ground features and underground valves of abandoned utility systems under CLINs 0001 to Option D.
CLIN Option H – Demolition of Existing Canyon Underground Concrete Water Tank and Exposed Suspended Utilities
Challenges:
− Foot traffic only
− Removal of water and gas pipes and rock façade on cliff
− Vault to be demolished in place and filled with native, local material
− Exposed equipment and pipe to be manually removed and disposed
Dwg 02C003
CLIN Option I – Juniper Campground Water Mains and Service Lines
Partial Scope:
− Install new 4-inch PVC water lines in the three Juniper Campground loops (Abert’s Squirrel, Black Bear, and Coyote) and install HDPE water service lines to the comfort stations, and existing and new Camp Host sites.
− Remove and replace existing fire and yard hydrants.
− Remove above ground features and underground valves of abandoned utility systems. Asphalt pavement patching of paved roadways and parking areas impacted.
Challenges:
− Sequencing construction within campground loops (only one loop closure at a time)
− Visitor safety
Dwg 02C207 Dwg 02C208A Dwg 02C2011A
CLIN Option J – Mesa Top Wastewater System
Partial Scope:
− Mesa Housing and FOC:
Replace vitrified clay sewers and manholes and sagging ductile and PVC pipes (from existing CCTV results) and install new 4-inch through 8-inch C900 PVC pipes.
Open cut and replace asbestos cement pipes and install new 4-inch to 8-inch Schedule C900 PVC pipes.
Remove and replace sewer laterals and associated receiving manholes.
Pulverize pavement in place and provide full depth asphalt pavement reclamation.
− Juniper Campground:
Remove and replace identified sewer laterals. Remove and replace identified sewer manholes.
Point repairs on segments of sewer pipes identified by CCTV.
Challenges:
− Residential area safety
− Public visitor (campers) safety
Dwg 02C014A
CLIN Option K – Agoyo Lane Electrical System
Partial Scope:
− Provide new single-phase buried electrical duct banks. Intercept the single-phase circuit near Building 25 transformer and extend to new sectionalizing cabinet. Provide single-phase primary circuit for Agoyo Lane.
− Provide a new transformer near the existing storage building and refeed secondary service to existing pole-mounted panelboard near RV Site #1.
− Provide new transformer near the existing Bunkhouse and refeed secondary service to the existing pole-mounted panelboard near the Bunkhouse.
− Demolish and dispose of the existing electrical equipment and wood poles.
− Asphalt pavement patching of areas impacted by this Option.
CLIN Option L – Fire Tower Lane Water and Natural Gas Line Replacement
Partial Scope:
− Install new 2-inch HDPE water service and 1-inch gas lateral from Entrance Road along Fire Tower Lane to the Fire Tower building.
− Asphalt pavement patching areas impacted by this Option
Challenges:
Dwg 02C023
CLIN Option M – Cottonwood Comfort Station (Building #1) Utility Connections
Partial Scope:
− Install new 4-inch Schedule C900 PVC sewer lateral from the comfort station to the manhole at the Canyon Visitor Center, electric to reactivate existing Building 1 Comfort Station. Install utilities under the pedestrian bridge across the Frijoles Creek.
− Install new NEMA 4X enclosed control panel, 208V, single-phase.
− Provide a new secondary electrical feed from the Visitor Center to serve the comfort station.
− Asphalt pavement patching of areas impacted.
− Visitor Safety
CLIN Option N – Natural Gas System
Partial Scope:
− Replacement of all existing natural gas distribution lines and service lines for Mesa Top (Mesa housing and FOC) and Frijoles Canyon areas (Stone House Road).
Challenges
− Construction around residential area
− Construct parallel with new 6” waterline
− Minimize utility outage
Dwg 02C015
CLIN Option O – Culvert and Erosion Repairs
Partial Scope:
− Grading, culvert repair, riprap installation, etc.
Challenges
− Deeply eroded arroyo
− Protect large tree in-place
− Construction adjacent to public Entrance Road
Dwg 04C104
Dwg 04C105
Construction Challenges
- Summarized
Construction Challenges - Summarized
Sequencing of utility outages
Public visitors (safety and curiosity)
Utility provider coordination (electric, gas and water) – Los Alamos County and LANL
Some existing/proposed utility corridor are narrow and utility-dense
Location of existing utilities is medium accuracy
Archaeological/historical preservation
Potential work stoppage if artifact is discovered
Others…
Site Walkthrough
Canyon Area