B08_Attachment_1_BAND_266697_Underground_Utilities_Rehab_100Percent_15APR2025_0001_unlocked_5_27_26_0004.pdf

PDF 6 MB Posted

Attached to
Update Utilities
Solicitation number
140P2026R0063
Issued by

About this file

Summary

This is a final construction specification document for the BAND 266697 Underground Utilities Rehabilitation Project at Bandelier National Monument in Los Alamos, New Mexico. The project involves comprehensive replacement of underground utility systems across multiple developed areas including Mesa Top, Entrance Road, and Frijoles Canyon, as well as Los Alamos National Laboratory right-of-way. The work addresses deferred maintenance on 60+ year-old systems and includes replacement of potable water distribution mains and laterals, primary electrical distribution (transitioning from single-phase to three-phase service), fiber-optic network extension, natural gas distribution lines, sanitary sewer pipes and components, and remote monitoring systems. Key infrastructure deliverables include a new 24,000-gallon below-grade water storage tank at Entrance Road with an adjacent Canyon mechanical building, hydropneumatic pressure booster tanks at three comfort stations, new three-phase primary electrical service from Los Alamos National Lab, cellular modem and antenna systems for cloud-based remote monitoring, and complete roadway rehabilitation with asphalt pavement replacement and markings.

The contract is structured as a single prime contract with base contract line items (CLINs 0001-0006) covering the main park water system, Mesa housing and FOC water mains, primary electrical distribution, cellular network systems, rock excavation on a unit cost basis, and roadway work. Thirteen optional CLINs (A through M) address secondary systems including inter-connection infrastructure, Frijoles Canyon water and gas systems, wastewater systems, fiber-optic pathways, campground water lines, utility demolition, and natural gas system upgrades. The project requires extensive coordination with National Park Service operations, compliance with historic preservation standards (CCC Historic District and Mission 66 Historic District), archeological protection measures, environmental considerations including Migratory Bird Act compliance, and public access management during construction. Typical work hours are 7:00 a.m. to dusk Monday through Friday, with extended hours and limited night work permitted with coordination, subject to restrictions on noise, lighting, and seasonal construction activities. Payment is structured on lump sum pricing for each CLIN with measurement based on percent completion, except for rock excavation which uses unit pricing per cubic yard.

View the file

Other files

File Type Posted
B09_QR_Tracker_BAND_266697_7_9_26_0007.pdf PDF
B09_BAND-266697_ContractPriceSchedule_Addendum1_20260701_0007.xlsx XLSX spreadsheet
Sol_140P2026R0063_Amd_0007.pdf PDF
B09_Solit_Clauses_Construction_7_9_26_0007.pdf PDF
Sol_140P2026R0063_Amd_0006.pdf PDF
Sol_140P2026R0063_Amd_0005.pdf PDF
B08_Solit_Clauses_Construction_6_23_26_0005.pdf PDF
B09_QR_Tracker_BAND_266697_6_23_26_0005.pdf PDF
B08_Attachment_9_Solit_PSP_Vol_I_PastPerf_REQD_5_27_26_0004.pdf PDF
B08_Solit_Clauses_Construction_5_27_26_0004.pdf PDF
B08_Attachment_1_000_ALL_SPECIFICATIONS_AddendumNo1_02APR2026_unlocked_5_27_26_0004.pdf PDF
Sol_140P2026R0063_Amd_0004.pdf PDF
B09_QR_Tracker_BAND_266697_5_27_26_0004.pdf PDF
B03_Wage_Determination_Heavy_5_27_26_0004.pdf PDF
B09_PowerPoint_Presentation_5_27_26_0004.pdf PDF
Sol_140P2026R0063_Amd_0003.pdf PDF
Sol_140P2026R0063_Amd_0002.pdf PDF
B09_BAND-266697_DD_InPersonMeeting_Presentation_0002.pdf PDF
B09_BAND_266697_-_Pre-Proposal_Sign_In_Roster_-_2026_5_12_0002.pdf PDF
B08_Attachment_2_BAND_266697_Construction_Drawings_Full_Size_Combined_Part3_0001.pdf PDF
Sol_140P2026R0063_Amd_0001.pdf PDF
B08_Attachment_2_BAND_266697_Construction_Drawings_Full_Size_Combined_Part2_0001.pdf PDF
B08_Attachment_1_BAND_266697_Underground_Utilities_Rehab_100Percent_15APR2025_0001.pdf PDF
B08_Attachment_2_BAND_266697_Construction_Drawings_Full_Size_Combined_Part1_0001.pdf PDF
B08_Attachment_2_BAND_266697_Construction_Drawings_Full_Size_Combined_Part4_0001.pdf PDF
B08_Clauses_and_Provisions_Construction_Amd_001_0001.pdf PDF
B08_Attachment_2_BAND-266697_Final_GeotechnicalReport_Sept2024_0001.pdf PDF
B08_Attachment_9_Solit_PSP_Vol_I_PastPerf_REQD.pdf PDF
B08_Attachment_7_Construction_Contract_Administration.pdf PDF
Sol_140P2026R0063.pdf PDF
B08_Attachment_12_Solit_PSP_Vol_II_SubKPlan.pdf PDF
B08_Attachment_1_000_ALL_SPECIFICATIONS_AddendumNo1_02APR2026.pdf PDF
B08_Attachment_11_Solit_PSP_Vol_II_GenRefs.pdf PDF
B08_Attachment_8_Solit_PSP_Vol_I_Exp_REQD.pdf PDF
B08_Attachment_6_Wage_Determination.pdf PDF
B08_Attachment_5_FINAL_-_BAND_MOD7_Addendum_Memo_02APR2026.pdf PDF
B08_Attachment_10_Solit_PSP_Vol_II_BidBond.pdf PDF
B08_Attachment_2_BAND_266697_DRAWINGS_ADDENDUM_01_07APR2026_Stamped.pdf PDF
B08_Attachment_4_BAND_MOD7_Exceptions_Report_Signed.pdf PDF
B08_Attachment_3_01_33_23I_Sup01_ADD1_SubmittalList-ReviewEstimate_Template_1-27-21_v508.xlsx XLSX spreadsheet
B08_Attachment_13_BAND-266697_ContractPriceSchedule_Final_CD_20250407.xlsx XLSX spreadsheet
Show all 41

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BANDELIER NATIONAL MONUMENT

LOS ALAMOS, NEW MEXICO

BAND 266697

UNDERGROUND UTILITIES REHABILITATION

PROJECT SPECIFICATIONS

NATIONAL PARK SERVICE (NPS)

DENVER SERVICE CENTER (DSC)

NATIONAL PARK SERVICE

BANDELIER NATIONAL MONUMENT, NEW MEXICO

BANDELIER NATIONAL MONUMENT

CONTRACT DOCUMENTS

for the construction of the

BAND 266697

UNDERGROUND UTILITIES REHABILITATION

D3167658

FINAL CONSTRUCTION DOCUMENTS

JACOBS

Los Alamos

April 2025

PW\JA FED-500\NPS\D3167658\30\SP SEALS PAGE

APRIL 2025 00 01 07 - 1

BAND 266697

SECTION 00 01 07

SPECIFICATIONS SEALS PAGE

FOR

BAND 266697

UNDERGROUND UTILITIES REHABILITATION

See Table of Contents for author of each specification section, identified by author’s initials as follows:

AUTHOR’S NAME = INITIALS

MICAH E. JOHNSON = MEJ JAMES MILLS = ML

THOMAS E. PAIGE =TEP ROBERT W. MARTIN = RWM

GREGORY SCOTT HINTE = GSH BRYOR WAYNE PRICE = BWP

JONATHAN B. JAMES = JBJ

Micah E. Johnson

SEALS PAGE PW\JA FED-500\NPS\D3167658\30\SP

00 01 07 - 2 APRIL 2025

BAND 266697

Thomas E. Paige

APRIL 2025 00 01 07 - 3

Gregory Scott Hinte

00 01 07 - 4 APRIL 2025

Jonathan B. James

APRIL 2025 00 01 07 - 5

James Mills

00 01 07 - 6 APRIL 2025

Robert W. Martin

APRIL 2025 00 01 07 - 7

BAND 266697

Bryor Wayne Price

END OF SECTION

PW\JA FED-500\NPS\D3167658\30\SP TABLE OF CONTENTS

APRIL 2025 00 01 10 - 1

BAND 266697

TABLE OF CONTENTS

Person Section Responsible Title Pages

SPECIFICATIONS

DIVISION 01—GENERAL REQUIREMENTS

01 11 00 MEJ Summary of Work.................................................................... 1- 10 01 26 01 MEJ Contract Modification Procedures ........................................... 1- 7 01 27 00 MEJ Definition of Contract Line Items ............................................ 1- 16 01 31 00 MEJ Project Management and Coordination ................................... 1- 13 01 32 16 MEJ Construction Schedule ............................................................. 1- 12 01 32 33 MEJ Photo Documentation............................................................... 1- 3 01 33 23 MEJ Submittal Procedures ............................................................... 1- 10

Supplement:

MEJ Submittal List ........................................................................... 1- 27

01 35 13.22 MEJ Archeological Protection ......................................................... 1- 3 01 35 23 MEJ Safety Requirements ................................................................ 1- 6 01 35 91 MEJ Historic Preservation Treatment Procedures ........................... 1- 10 01 40 00 MEJ Quality Requirements .............................................................. 1- 9

Supplement:

MEJ Statement of Structural Tests and Special Inspections ............ 1- 22

01 42 00 MEJ Reference Standards................................................................. 1- 15 01 45 33 TEP Special Inspection, Observation, and Testing .......................... 1- 6

Supplement:

TEP Contractor’s Statement of Responsibility ................................ 1- 2

01 50 00 MEJ Temporary Facilities and Controls........................................... 1- 13 01 57 19.12 MEJ Noise and Acoustics Management ........................................... 1- 3 01 57 23 MEJ Temporary Storm Water Pollution Prevention ........................ 1- 7 01 57 28 MEJ Temporary Flow Control ......................................................... 1- 7 01 67 00 MEJ Product Requirements .............................................................. 1- 7

Supplements:

MEJ Affirmative Procurement Reporting Form............................... 1- 2 MEJ Manufacturer’s Certificate of Proper Installation .................... 1- 1 MEJ Manufacturer’s Certificate of Compliance .............................. 1- 1

01 73 29 MEJ Cutting and Patching ................................................................ 1- 4 01 73 40 MEJ Execution ................................................................................. 1- 9 01 74 19 MEJ Construction Waste Management and Disposal ...................... 1- 11

Supplement:

MEJ Project Waste Management Plan Worksheet Sample .............. 1- 1

Person Section Responsible Title Pages

TABLE OF CONTENTS PW\JA FED-500\NPS\D3167658\30\SP

00 01 10 - 2 APRIL 2025

BAND 266697

01 77 00 MEJ Closeout Procedures................................................................. 1- 6 Supplement:

MEJ Closeout and Operation & Maintenance (O&M) Requirements Template & Sample ....................................... 1- 2

01 78 23 MEJ Operation and Maintenance Data............................................. 1- 10 Supplement:

MEJ Equipment Data Sheet.............................................................. 1- 1 01 79 00 MEJ Demonstration and Training .................................................... 1- 4 01 81 13 MEJ Sustainable Design Requirements for Non-LEED™

Projects .................................................................................. 1- 3 01 88 15 TEP Anchorage and Bracing............................................................ 1- 6 01 91 14 MEJ Total System Commissioning .................................................. 1- 14

DIVISION 02—EXISTING CONDITIONS

02 41 00 MEJ Demolition ............................................................................... 1- 9 02 61 00 MEJ Removal and Disposal of Contaminated Soil .......................... 1- 8 02 82 00 MEJ Asbestos Remediation .............................................................. 1- 21

DIVISION 03—CONCRETE

03 01 32 TEP Repair of Vertical and Overhead Concrete Surfaces ............... 1- 12 03 01 33 TEP Repair of Horizontal Concrete Surfaces .................................. 1- 12 03 10 00 TEP Concrete Forming and Accessories ......................................... 1- 6 03 15 00 TEP Concrete Joints and Accessories .............................................. 1- 11 03 21 00 TEP Steel Reinforcement ................................................................. 1- 5 03 30 00 TEP Cast-in-Place Concrete............................................................. 1- 27

Supplements:

TEP Concrete Mix Design, Class 4500F2S1W1C1......................... 1- 2 TEP Concrete Mix Design, Class 3500F1S1W1C1......................... 1- 2

03 39 00 TEP Concrete Curing ....................................................................... 1- 5 03 40 00 TEP Precast Concrete Structures ..................................................... 1- 4 03 62 00 TEP Grouting ................................................................................... 1- 10

Supplement:

TEP 24-hour Evaluation of Nonshrink Grout Test Form and

Grout Testing Procedures ..................................................... 1- 3 03 63 00 TEP Concrete Doweling .................................................................. 1- 4 03 64 23 TEP Epoxy Resin Injection Grouting .............................................. 1- 11 03 64 24 TEP Polyurethane Injection Grouting .............................................. 1- 9

PW\JA FED-500\NPS\D3167658\30\SP TABLE OF CONTENTS

APRIL 2025 00 01 10 - 3

BAND 266697

DIVISION 04—MASONRY

04 03 43 TEP Historic Stone Masonry Repointing......................................... 1- 9

DIVISION 05—METALS

05 05 19 TEP Post-Installed Anchors ............................................................. 1- 9 05 50 00 TEP Metal Fabrications ................................................................... 1- 17

DIVISION 06 (NOT USED)

DIVISION 07—THERMAL AND MOISTURE PROTECTION

07 21 01 TEP Thermal Insulation ................................................................... 1- 3

DIVISION 08—OPENINGS

08 16 13 TEP Fiberglass Doors ...................................................................... 1- 4 08 71 00 TEP Door Hardware......................................................................... 1- 8

DIVISION 09—FINIGSHES

09 90 00 TEP Painting and Coating ................................................................ 1- 29 Supplements:

TEP Paint System Data Sheet (PSDS) ............................................. 1- 1 TEP Paint Product Data Sheet (PPDS) ............................................ 1- 1

DIVISION 10—SPECIALTIES

10 14 00 TEP Signage ..................................................................................... 1- 6 10 44 00 TEP Fire Protection Specialties and Safety Equipment ................... 1- 3

DIVISION 11 AND DIVISION 12 (NOT USED)

DIVISION 13—SPECIAL CONSTRUCTION

13 34 20 TEP Precast Concrete Building........................................................ 1- 6

DIVISION 14 THROUGH DIVISION 21 (NOT USED)

TABLE OF CONTENTS PW\JA FED-500\NPS\D3167658\30\SP

00 01 10 - 4 APRIL 2025

BAND 266697

DIVISION 22—PLUMBING

22 07 00 GSH Plumbing Piping Insulation...................................................... 1- 4 22 10 01 MEJ Plumbing Piping and Accessories ............................................ 1- 22

Supplements:

MEJ Plumbing Piping Schedule ....................................................... 1- 2

22 10 01.12 MEJ Polyethylene (PE) Pipe and Fittings—Natural Gas Service Data Sheet ................................................................ 1- 2

22 10 01.15 MEJ Carbon Steel Pipe and Fittings—Gas Service Data Sheet ............................................................................. 1- 4

22 30 00 MEJ Plumbing Equipment ............................................................... 1- 5 Supplement:

MEJ Backflow Preventers Data Sheet .............................................. 1- 1 22 40 00 GSH Plumbing Fixtures .................................................................... 1- 3

DIVISION 23—HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)

23 05 48 GSH Vibration Isolation for HVAC Piping and Equipment ............ 1- 5 Supplement:

GSH Vibration Isolation Schedule for HVAC Piping and Equipment ............................................................................. 1- 1

23 81 00 GSH Unitary Air-Conditioning Equipment ...................................... 1- 11 Supplements:

GSH Ductless Split System DX Indoor Units Data Sheet ................ 1- 1 GSH Split System DX Outdoor Units Data Sheet ............................ 1- 1

23 82 00 GSH Terminal Heating and Cooling Units ....................................... 1- 5 Supplement:

GSH Unit Heaters Schedule.............................................................. 1- 2

DIVISION 24 AND DIVISION 25 (NOT USED)

DIVISION 26—ELECTRICAL

26 05 02 JBJ Basic Electrical Requirements ................................................. 1- 7 26 05 04 JBJ Basic Electrical Materials and Methods .................................. 1- 10 26 05 05 JBJ Conductors ............................................................................... 1- 18 26 05 26 JBJ Grounding and Bonding for Electrical Systems ...................... 1- 6 26 05 33 JBJ Raceway and Boxes for Electrical Systems ............................. 1- 23 26 05 70 JBJ Electrical Systems Analysis ..................................................... 1- 9

Supplements:

JBJ Figure 1: Example Arc Flash Label – Warning ....................... 1- 1 JBJ Figure 2: Example Arc Flash Label – Danger ......................... 1- 1

26 08 00 JBJ Commissioning of Electrical Systems ..................................... 1- 23

PW\JA FED-500\NPS\D3167658\30\SP TABLE OF CONTENTS

APRIL 2025 00 01 10 - 5

BAND 266697

26 12 02 JBJ Oil-Filled Pad Mounted Transformers ..................................... 1- 7 26 13.16.02 JBJ Pad-Mounted Switchgear ......................................................... 1- 12 26 20 00 JBJ Low-Voltage AC Induction Motors ......................................... 1- 6 26 22 00 JBJ Low-Voltage Transformers ...................................................... 1- 3 26 24 16 JBJ Panelboards .............................................................................. 1- 7 26 27 26 JBJ Wiring Devices ........................................................................ 1- 8 26 32 13.16 JBJ Natural Gas Engine Generator Set ........................................... 1- 13 26 43 00 JBJ Surge Protective Devices ......................................................... 1- 5 26 50 00 JBJ Lighting .................................................................................... 1- 9

DIVISION 27 THROUGH DIVISION 30 (NOT USED)

DIVISION 31—EARTHWORK

31 10 00 MEJ Site Clearing............................................................................. 1- 4 31 23 13 JM Subgrade Preparation ............................................................... 1- 3 31 23 16 MEJ Excavation................................................................................ 1- 5 31 23 19.01 MEJ Dewatering ............................................................................... 1- 3 31 23 23 MEJ Fill and Backfill ....................................................................... 1- 9 31 23 23.15 MEJ Trench Backfill ........................................................................ 1- 10 31 32 19.16 MEJ Geotextile ................................................................................. 1- 7 31 37 00 RWM Riprap ....................................................................................... 1- 3 31 40 00 RWM Tunneled Crossings .................................................................. 1- 7 31 41 00 RWM Shoring ..................................................................................... 1- 3 31 42 00 RWM Horizontal Auger Boring ......................................................... 1- 11 31 43 00 RWM Steel Casing Pipe ..................................................................... 1- 3 31 44 00 RWM Settlement Monitoring ............................................................. 1- 6 31 45 00 RWM Installation of Carrier Pipe in Steel Casing.............................. 1- 5 31 46 00 RWM Backfill Grouting ..................................................................... 1- 11

DIVISION 32—EXTERIOR IMPROVEMENTS

32 11 23 JM Aggregate Base Course(s) ........................................................ 1- 7 32 12 16 JM Asphalt Paving ......................................................................... 1- 15 32 13 13 JM Concrete Paving ....................................................................... 1- 16 32 16 00 JM Curbs and Gutters .................................................................... 1- 4 32 17 23 JM Pavement Markings ................................................................. 1- 5 32 31 13 MEJ Chain Link Fences and Gates .................................................. 1- 8 32 91 13 MEJ Soil Preparation ........................................................................ 1- 3 32 93 00 MEJ Plants ........................................................................................ 1- 5

TABLE OF CONTENTS PW\JA FED-500\NPS\D3167658\30\SP

00 01 10 - 6 APRIL 2025

BAND 266697

DIVISION 33—UTILITIES

33 05 01 MEJ Conveyance Piping—General .................................................. 1- 11 33 05 01.02 MEJ Ductile Iron Pipe and Fittings .................................................. 1- 12 33 05 01.09 MEJ Polyvinyl Chloride (PVC) Pressure Pipe and Fittings ............. 1- 6 33 05 01.12 MEJ Gravity Sewer Pipe and Fittings .............................................. 1- 17 33 05 13 MEJ Manholes .................................................................................. 1- 15 33 05 23.13 MEJ Utility Horizontal Directional Drilling .................................... 1- 6 33 12 13 MEJ Water Service Connections ...................................................... 1- 9 33 12 16 MEJ Water Utility Distribution Valves ............................................ 1- 4 33 12 16.29 MEJ Air and Vacuum Release Valve Assemblies ........................... 1- 6 33 12 19 MEJ Water Utility Distribution Fire Hydrants ................................. 1- 5 33 13 00 BWP Disinfection of Water Utility Distribution Facilities ............... 1- 6

DIVISION 34 THROUGH DIVISION 39 (NOT USED)

DIVISION 40—PROCESS INTERCONNECTIONS

40 05 15 BWP Piping Support Systems ........................................................... 1- 9 Supplement:

BWP Table 1: Nonchemical Areas .................................................... 1- 1 40 27 00 BWP Process Piping—General ......................................................... 1- 20 40 27 00.01 BWP Fusion Bonded-Epoxy-Lined Ductile Iron Pipe and Fittings

Data Sheet ............................................................................. 1- 5 40 27 00.03 BWP Carbon Steel Pipe and Fittings—Water Service Data Sheet ... 1- 7 40 27 00.10 BWP Polyvinyl Chloride (PVC) Pipe and Fittings Data Sheet ......... 1- 4 40 27 00.13 BWP Copper and Copper Alloy Pipe, Tubing, and Fittings

Data Sheet ............................................................................. 1- 2 40 27 02 BWP Process Valves and Operators .................................................. 1- 17 40 80 01 BWP Process Piping Leakage Testing .............................................. 1- 5 40 90 00 JBJ Instrumentation and Control for Process Systems ................... 1- 38

Supplements:

JBJ Process Control Narratives – Loop Specific ............................ 1- 3 JBJ Control Panel Schedule ............................................................ 1- 1 JBJ Instrument List ......................................................................... 1- 1 JBJ PLC Input/Output List ............................................................. 1- 1 JBJ Preparation for Testing and Functional Test Forms ................ 1- 3 JBJ Performance Test Sheet - Example .......................................... 1- 1

40 91 00 JBJ Instrumentation and Control Components ............................... 1- 33 40 95 60 JBJ Telemetry System .................................................................... 1- 6

PW\JA FED-500\NPS\D3167658\30\SP TABLE OF CONTENTS

APRIL 2025 00 01 10 - 7

BAND 266697

40 95 80 JBJ Fiber Optic Communication System ........................................ 1- 18 Supplements:

JBJ On-Reel Fiber Optic Cable Test Summary Form .................... 1- 1 JBJ Fiber Optic Attenuation Performance Test Form .................... 1- 1 JBJ Post-Installation Fiber Optic Cable Test Summary Form........ 1- 2

DIVISION 41 THROUGH DIVISION 49 (NOT USED)

DRAWINGS

SPECIFICATIONS

PW\JA FED-500\NPS\D3167658\30\SP SUMMARY OF WORK

APRIL 2025 01 11 00 - 1

BAND 266697

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 SUMMARY

A. Section includes the following:

1. Work Covered by Contract Documents.

2. Work Phases.

3. Construction Contractor Use of Site.

4. Public Use of Site.

5. Occupancy Requirements for Buildings.

6. Conduct of Operations.

7. Work Restrictions.

8. Special Construction Requirements.

9. Soils Investigation Report.

10. Additional Reports.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: Bandelier National Monument, Los Alamos, New Mexico. The Project will be located at the following developed areas within NPS park-owned land:

Mesa Top, Entrance Road, and Frijoles Canyon; and Los Alamos National Lab (LANL) right-of-way across Highway-4 from Bandelier. The Mesa Top area consists of Entrance Station, Juniper Campground, Mesa Housing (Residential Area), and Field Operations Center (FOC). Entrance Road consists of Entrance Road and Fire Tower Lane. The Canyon Area consists of Agoyo Lane, Stone House Road, Visitor Center, and Other Buildings.

B. The Work consists of:

1. The Work required in the scope as described in Section 01 27 00, Definition of Contract Line Items, includes the following at Bandelier National Monument developed areas, as described herein but not limited to:

a. General Conditions. Include General Requirements, Mobilization/ Demobilization, Erosion and Sediment Control, Traffic Control, Non-vegetative Surface Restoration, and Protection and Preservation of historic buildings and features as required to complete the Work per Contract Specifications and Drawings.

b. The Work is to be completed within two National Register of Historic Places districts, the Civilian Conservation Corps (CCC) Historic District in the Canyon Area, and Mission 66 Historic District in the Mesa Top Area.

SUMMARY OF WORK PW\JA FED-500\NPS\D3167658\30\SP

01 11 00 - 2 APRIL 2025

BAND 266697

c. Replace utility systems at the major distribution and collection systems to address deferred maintenance and code deficiencies on 60 plus year old systems utilizing existing utility corridors and road shoulders and/or under roads to maintain code required separation horizontally and vertically while mitigating impact to sensitive natural and cultural resource areas. Utilities include underground potable water, primary electrical, fiber-optic, natural gas, and sanitary sewer.

d. The main park water system consists of replacing primary distribution mains and laterals, connecting to a new 24,000-gallon belowgrade water storage tank at Entrance Road (referred as Entrance Road Water Tank) and adjacent new Canyon mechanical building, abandoning the existing Canyon 20,000-gallon belowgrade water storage tank (referred as Existing Canyon Underground Concrete Water Tank), removing water main hanging from the Canyon cliff, and providing hydropneumatic tanks with pumps as water pressure boosters at Juniper Campground comfort stations.

e. The primary electrical distribution system consists of replacing Mesa Top single-phase feed with a new three-phase primary electrical service, facilitate future interconnection tie between the Mesa Top and the Frijoles Canyon distribution systems, and replacing aging electrical feeders, equipment, and conductors for the three main areas at Mesa Top, Entrance Road, and Frijoles Canyon.

f. The fiber-optic network consists of extending existing fiber-optic from the Frijoles Canyon to Mesa Top areas including FOC and Entrance Station.

g. The remote monitoring system consists of a cellular modem and antenna for a cloud based monitoring. A remote monitoring system will be installed at the Main Blue Water Tank, Abert’s Squirrel Loop, PRV vaults, and Main Lift Station. The existing 35,000-gallon above-grade Existing Main Blue Water Tank level sensor will be wired to Mesa Top Abert’s Squirrel Loop.

h. The natural gas system consists of replacing existing natural gas distribution lines and service lines for Mesa Top (Mesa housing, FOC, and Fire Tower Lane) and Frijoles Canyon areas (Visitor Center and other buildings).

i. The wastewater system consists of replacing existing sewer pipes, manholes, and laterals at Mesa Top, Juniper Campground, and Frijoles Canyon developed areas. It also consists of providing new gravity sewer from the Frijoles Canyon Comfort Station Building #1 (also known as Cottonwood Comfort Station) to a manhole near the Visitor Center and installing new electric utility under the pedestrian bridge to re-activate the existing comfort station.

C. Project will be constructed under a single prime contract.

APRIL 2025 01 11 00 - 3

BAND 266697

1.3 WORK PHASES

A. Refer to Section 01 32 16, Construction Schedule, for additional sequencing requirements.

1.4 CONSTRUCTION CONTRACTOR USE OF SITE

A. General: Construction Contractor shall have limited use of site for construction operations. Limit use of premises to work in areas indicated on the Drawings. Do not disturb portions of Project Site beyond areas in which the Work is indicated.

Bandelier National Monument will remain open during construction project. See Article Public Use of Site, for additional requirements.

1. Limits: Confine construction and disturbance operations to the Limits of Disturbance (LOD) boundary shown on the Drawings. Coordinate with the requirements of Section 31 10 00, Site Clearing.

B. Storage of Materials: Confine storage of materials to staging areas indicated on the Drawings, or allowable work area next to utility trenches. Use of temporary barriers and signage is not exclusive to locations shown on the Drawings. It is the responsibility of the Construction Contractor to provide protection to any trees, historic buildings and features that may be harmed by equipment during construction.

C. Staging areas shall be located within areas that are already compacted, graded, gravel or paved surface as indicated on Drawing No. 00G004.

D. Parking: Confine parking to areas as shown on Drawing No. 00G004. During busy visitor seasons, preference is for parking at the Bone Yard and carpooling to the active worksites. Contractor is prohibited from parking on the main visitor parking loop by the Visitors Center.

E. Stockpiling: Unless otherwise approved by Contracting Officer, all excess excavated material must be disposed offsite. Temporary stockpiles within approved work areas may be allowed by Contracting Officer in consultation with Bandelier operations, and with appropriate protection of visitors. Contractor may be allowed to reuse material from the existing stockpiles at the Bone Yard for certain project activities, such as filling in the demolished water tank in Contract Line Item Option B. When suitable material is available at the Bone Yard, preference is to use those onsite materials instead of offsite materials.

F. Protection of Cultural Resources: Bandelier National Monument is listed as a National Historic Landmark on the Register of Historic Places. The Contractor must undertake operations with sensitivity to preserve the historic integrity of the Park.

1. Unless approved by Bandelier staff, construction vehicles and equipment must stay on pavement or gravel surfaces. Equipment will avoid known

01 11 00 - 4 APRIL 2025

BAND 266697

archeological resources. Coordinate offroad work in advance in accordance with Section 01 32 16, Construction Schedule.

2. Items identified as significant resources, intrinsic features and elements of the property that are not specifically named, as well as archeological remains and artifacts are valued and important.

3. Construction activity must demonstrate treatment approaches that protect Park cultural resources. Construction means and methods must comply with the Secretary of the Interior (SOI) Standards for Rehabilitation and SOI Guidelines for Treatment of Cultural Landscapes and Archeological Protection.

4. Excavation requires archeological monitoring provided by NPS staff.

5. Construction methods that are considered radical, unproven, or have the potential to adversely alter or cause irreversible loss of the fabric, character defining qualities or appearance, must not be attempted.

6. Construction deviating from approved Contract Documents require review and approval by the Contracting Officer in advance of commencing work.

7. Historic Preservation Treatment Plan (HPTP) must be submitted in advance of mobilization, highlighting means and methods for accomplishing critical tasks when and where an elevated risk of damage to resources exists.

8. If previously unknown archeological resources are discovered during construction, all work in the immediate vicinity of the discovery shall be halted until the resources are identified and documented and an appropriate mitigation strategy developed, if necessary, in accordance with pertinent laws and regulations. Contracting Officer shall be called immediately.

G. Preservation of Natural Features:

1. Unless approved by Bandelier staff, construction vehicles and equipment must stay on pavement or gravel surfaces. Coordinate offroad work in advance in accordance with Section 01 32 16, Construction Schedule.

2. Prevent damage to natural surroundings. Limit disturbance to boundaries shown on Drawings. Replace removed and damaged trees at no additional expense to the Government at the location determined by the Bandelier National Monument Integrated Resources Program Manager in accordance with Section 32 93 00, Plants.

3. Provide temporary barriers in accordance with Section 01 50 00, Temporary Facilities and Controls, to protect existing trees and plants and root zones.

4. Do not remove, injure, or destroy trees or other plants without prior approval from the Bandelier National Monument Integrated Resources Program Manager .

5. Do not fasten ropes, cables, or guys to existing trees.

6. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

7. Prior to vehicles entering Bandelier National Monument, power wash all vehicles and equipment that will travel off paved surfaces into the construction corridor. Washing shall be sufficient to remove all visible plant material and soil from prior locations where vehicles and equipment have been used. NPS

APRIL 2025 01 11 00 - 5

BAND 266697

shall inspect vehicles and equipment for adequacy of cleaning before they are used within the Park. Any equipment leaving the Park must be recleaned before re-entry to the Park and Project Site.

8. Subsequent to project completion, Park staff will monitor the Park for the presence of invasive species. The Contractor will be responsible for the removal of any invasive species observed.

9. All introduced fill material coming from outside the Park shall be certified sterile, weed-free soil.

10. Do not paint rocks for subsurface utility marking, temporary benchmarks, or any other reason.

11. Care will be taken not to disturb any wildlife species (reptiles, migratory birds, raptors, or bats) found nesting, hibernating, estivating, or otherwise living in, or immediately nearby, worksites. Follow time of year restrictions for tree removal. Coordinate construction dates with Section 01 32 16, Construction Schedule.

12. All machinery containing fuels and oils shall have a spill kit available immediately in the event of a spill. In the event of a fuel or oil leak/spill, the work shall cease immediately, spill containment deployed, Contracting Officer and other jurisdictional authorities shall be called immediately, as designated.

H. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government employees, residents, and emergency vehicles at all times.

Do not use these areas for parking or storage of materials.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

I. Construction Camp: Establishment of a camp within the Park will not be permitted.

J. Hauling Restrictions: Comply with legal load restrictions in hauling of materials.

Load restrictions on park roads are identical to state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Construction Contractor of liability for damage which may result from moving of equipment.

K. Bridge Restrictions: Identify jurisdictions, load restrictions, permit requirements, time and calendar restrictions as outlined.

1.5 PUBLIC USE OF SITE

A. Construction Contractor shall conduct operations to ensure the least inconvenience to the public.

01 11 00 - 6 APRIL 2025

BAND 266697

B. Coordinate with Section 01 32 16, Construction Schedule. Pause construction and ensure park is fully accessible during the first 2 weeks of October, and second week of March. Coordinate with park staff on other special events.

C. Single lane closures are permitted during visitor hours. See Paragraph Extended Hours with Coordination, for additional requirements. Building and Road closures may be permitted, when required, upon specific approval of Contracting Officer. The maximum allowable full road closure in Entrance Road is 15 minutes during visitor hours.

1. The Construction Contractor will be responsible for traffic control during road closures and shall provide routing around the work being performed, unless a full road closure is specifically approved. All traffic control methods are to be performed in accordance with all federal, state, and local codes.

D. Construction Contractor to maintain the same number of Architectural Barriers Act (ABA) existing or temporary spaces during construction.

E. Provide continuity for visitor seasonal (May – October) shuttle operations, including pickup and dropoff points, and access past active construction zones.

F. Phase work to keep at least one road loop of the campground available at all times.

Coordinate timing of campground work per Section 01 32 16, Construction Schedule, in advance with the Contracting Officer to allow Bandelier staff to have predictability with their online camping space reservation system.

G. Coordinate in advance with Bandelier staff for any trail detours necessitated by construction activities. Reference Section 01 50 00, Temporary Facilities and Controls.

1.6 OCCUPANCY REQUIREMENTS FOR BUILIDINGS

A. Existing Buildings:

1. Partial Government Occupancy: Government will occupy premises during entire construction period, with exception of areas under construction.

Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform Work so as not to interfere with Government’s operations. Maintain existing exits, unless otherwise indicated.

a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Contracting Officer.

b. The Construction Contractor is responsible for maintaining and providing power, water, gas, and sewer to existing buildings at all times.

APRIL 2025 01 11 00 - 7

BAND 266697

B. New Buildings:

1. Government Occupancy of Completed Areas of Construction: Government reserves right to occupy and to place and install equipment in completed areas of building, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and partial occupancy shall not constitute acceptance of the entire Project.

a. Contracting Officer will prepare a Beneficial Occupancy letter for each specific portion of the Work to be occupied before Government occupancy.

b. Obtain a Certificate of Occupancy from National Park Service (NPS) before Government occupancy.

c. Before partial Government occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed. On occupancy, Government will operate and maintain mechanical and electrical systems serving occupied portions of building.

d. On occupancy, Government will assume responsibility for maintenance and custodial service for occupied portions of building.

1.7 CONDUCT OF OPERATIONS

A. Construction Contractor shall conduct operations in conformance with rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by Park Superintendent. The Contractor shall contact the Contracting Officer to obtain the current Park rules and regulations.

B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed unless stated in the Work Restrictions below or without prior consent from the Contracting Officer. Submit requests 3 business days in advance of the work to the Contracting Officer for approval.

C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

1.8 WORK RESTRICTIONS

A. Typical On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:00 a.m. to dusk, Monday through Friday, except when otherwise indicated.

1. Weekend Hours and Federal Holidays: No work shall be performed without the approval of the Contracting Officer.

2. Early Morning Hours: No work shall be performed without the approval of the Contracting Officer.

01 11 00 - 8 APRIL 2025

BAND 266697

3. Quiet Hours: Juniper Campground and staff housing area quiet hours are from 10:00 p.m. to 6:00 a.m.

4. Coordinate with the requirements of Section 01 57 19.12, Noise and Acoustics Management.

B. Extended Hours with Coordination:

1. Extended work hours until 10:00 p.m. may be approved for Entrance Road utility and pavement rehabilitation and canyon utility work, with full coordination with Bandelier operations.

2. Night work may be approved for Entrance Road utility installation and pavement rehabilitation between the Campground Road and Agoyo Lane with full coordination of Bandelier operations.

a. Emergency access must remain available past work areas at all times, or be able to be re-established during the interval first responders are traveling to the site.

b. Excavation requires archaeological monitoring and is allowable only between 8:00 a.m. and 10:00 p.m.

c. Full road closure outside of normal park visitor hours is acceptable in January and February. 90 day advance notification is a prerequisite for a full road closure request.

3. Temporary lights must be full cutoff luminaires with an International Dark Sky Association / Illuminating Engineering Society BUG rating uplight value of U0 to protect bats and birds. Use of temporary lights is not allowed between April and August.

4. Project shall comply with NPS and park lighting guidelines to reduce impacts to the night sky and wildlife. This will include, but is not limited to, low-level lighting, minimized glare, downward focused light fixtures, and energy efficient light sources such as low-pressure sodium lamps. If night work is permitted, lights need to be shielded from the sky to minimize impact to migratory birds and bats.

C. Existing Utilities:

1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.

2. Construction Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.

3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the Contract.

APRIL 2025 01 11 00 - 9

BAND 266697

D. Existing Utility Interruptions:

1. Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

a. Notify Contracting Officer not less than seven business days in advance of proposed utility interruptions.

b. Do not proceed with utility interruptions without Contracting Officer’s written permission.

c. Hours and Length of Utility Shutdowns: Maximum of 4 hours.

1) Gas system outages are allowed only between 5:00 p.m. and 10:00 p.m.

E. Nonsmoking Building/Tobacco Use/Vaping: Smoking is not permitted within buildings or within 25 feet of entrances, operable windows, or outdoor air intakes, or at locations where smoking would be a nuisance to Park visitors as determined by the Contracting Officer.

1.9 SPECIAL CONSTRUCTION REQUIREMENTS

A. Project Management and Communication Software: Software administered by NPS shall be used to manage communication and document sharing during construction.

1. See Section 01 31 00, Project Management and Coordination, for requirements on using NPS project management and communication software.

B. Coordinate with the requirements in Section 01 50 00, Temporary Facilities and Controls.

C. Equipment is prohibited within the channel of Rito de los Frijoles. Cross-reference to CLIN Option M Cottonwood Comfort Station (Building #1) Utilities Connections.

D. Backfill within the demolished water tank of CLIN Option H Demolition of Existing Canyon Underground Concrete Water Tank and Exposed Suspended Utilities must be delivered by helicopter.

E. When the park closes for snow removal, the Park is also closed to Contractor. Use of steel plates for trenches in roadways is prohibited when there is a risk of snow.

F. Comply with the Migratory Bird Act of 1918.

1. Ensure that the nest of migratory birds are not damaged by timing the construction activities outside of nesting period and/or visual inspection of vegetation before it is treated or removed. Complete all tree/brush removal outside of nesting season (April-July). No construction may occur from

01 11 00 - 10 APRIL 2025

BAND 266697

STA 115+25 to STA 123+00 (Drawing 02C029) between April-July due to an active Peregrine Falcon nest in that area.

2. The regulatory risk to LANL is from the destruction of active bird nests, which are defined as nests with eggs or nestlings. Prioritize tree and shrub removal outside of the peak bird breeding season, May 15 to July 31. If tree or shrub removal must be conducted during breeding season, you must contact and schedule LANL EPC-ES biologists (Brent Thompson or Milu Velardi) to survey smaller trees and shrubs immediately prior to removal. Large trees often cannot be adequately cleared and may not be approved for removal during breeding season. Active nests built within structures or equipment are also protected and must not be disturbed. If active nests are discovered any time of year, then work must be paused and the Contracting Officer and LANL EPC-ES biologists must be notified.

1.10 SOILS INVESTIGATION REPORT

A. The report Preliminary Geotechnical Report NPS Bandelier National Monument Utility Rehabilitation, February 2022, prepared by Shannon & Wilson is available to all plan holders with this package.

B. The report Geotechnical Report NPS Bandelier National Monument Utility Rehabilitation, September 26, 2024, prepared by Shannon & Wilson is available to all plan holders with this package.

C. In case of conflict between report and the Drawings or Specifications, the Drawings and Specifications govern.

1.11 ADDITIONAL REPORTS

A. The report Limited Discrete Soil Sampling Results from the Entrance Road near the Frijoles Canyon Visitor Center Maintenance Area, February 23, 2022, prepared by Jacobs is available to all plan holders with this package.

B. In case of conflict between report and the Drawings or Specifications, the Drawings and Specifications govern.

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION (NOT USED)

PW\JA FED-500\NPS\D3167658\30\SP CONTRACT MODIFICATION PROCEDURES

APRIL 2025 01 26 01 - 1

BAND 266697

SECTION 01 26 01

CONTRACT MODIFICATION PROCEDURES

PART 1 GENERAL

1.1 SUMMARY

A. Section consists of administrative and procedural requirements for contract modifications.

1.2 DEFINITIONS AND ALLOWANCES

A. Home Office Overhead:

1. Costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):

a. Rent.

b. Utilities.

c. Furnishings.

d. Office equipment.

e. Executive and management staff not exclusively assigned to the Project.

f. Support, accounting, and administrative staff.

g. Preparation of cost proposals, estimating, and schedule analyses connected with Modifications.

h. Estimating and preconstruction services.

i. Mortgage costs.

j. Real estate and corporate taxes.

k. Automobile maintenance and travel costs for home office personnel.

l. Home office insurances i.e., structure, automotive, umbrella, flood, etc.

m. Depreciation of equipment and other assets.

n. Home office supplies (paper, staples, etc.).

o. Legal services.

p. Accounting and data processing.

q. Professional fees/registration.

CONTRACT MODIFICATION PROCEDURES PW\JA FED-500\NPS\D3167658\30\SP

01 26 01 - 2 APRIL 2025

BAND 266697

B. General Conditions (Field Office Overhead):

1. Management and administrative costs incurred on site for the designated project. Costs associated with preparation of modifications will not be allowed.

Costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:

a. Project Manager (PM), Assistant Project Manager.

b. Superintendent, Assistant Superintendent.

c. Quality Control, Safety Officer, Environmental Manager, etc.

d. Engineers.

e. Travel, lodging, and per diem (as established by Federal Travel

Regulations).

f. Scheduling.

g. Field Office Trailers and associated temporary utilities.

h. Field office supplies.

1) Mailing and couriers.

2) Reproduction costs.

3) Storage.

4) Phones.

5) Computers.

6) Copiers.

i. Personnel vehicles i.e., Superintendent Pickup trucks.

C. General Requirements:

1. Costs directly associated with the Project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:

a. Hosiery heating and power.

APRIL 2025 01 26 01 - 3

BAND 266697

D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on project site.

Modification costs for salaried workers are only allowed within the structure of a 40-hour week and no overtime or holiday pay will be allowed.

1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:

a. Base Rate: The hourly rate paid directly to the worker.

b. Labor Burden:

1) Employer payments of all applicable burdens; includes insurance and taxes the business must pay on behalf of the worker to government entities and educational forums, such as:

a) Social Security.

b) Medicare.

c) Workers Compensation: Policy and company calculation to be made available.

d) Federal Unemployment Tax Act (FUTA): Cap Rate and percentage to be proportionally allocated over 1 year.

e) State Unemployment Tax Act (SUTA): Cap Rate and percentage to be proportionally allocated over 1 year.

f) Union Agreement Costs: Other costs required under an enforceable collective bargaining agreement.

c. Fringe Benefits:

1) Various non-wage compensations provided to employees such as:

a) Health Care Insurance Premiums.

b) Cell Phone.

c) Clothing.

d) 401K and Pensions.

e) Vehicle allowances.

f) Gas allowance.

g) Life insurance premiums.

h) Disability insurance.

i) Other Fringe Benefits required under an enforceable collective bargaining agreement.

E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.

01 26 01 - 4 APRIL 2025

BAND 266697

F. General Liability Insurance: An insurance policy that protects Contractor from claims resulting from bodily injury or property damage to a third party. Include as a separate line item within all modification proposals and provide a current insurance quote upon request.

G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees the Contractor will pay the labor and material costs incurred. Banks and Insurance companies charge a premium for individual project based on a sliding scale related to the size of the Project. Include as a separate line item in modification proposals and provide current company bonding rates upon request.

H. Builder’s Risk Insurance: Covers the contractor’s loss due to fire, high winds, or other natural forces. Not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.

1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS

A. General:

1. Proposal be received in the format and within the time frame specified in the Request for Proposal (RFP) letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.

2. Proposal shall be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Government’s form.

3. Requests for extensions of contract time as a result of change must be justified with a Time Impact Analysis (TIA). Refer to Section 01 32 16, Construction Schedule, for time impact analysis requirements. TIA and associated costs shall be received with the proposal by the date shown within the Request for Proposal letter. Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving right for additional time and no time extension will be allowed.

4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer (CO) upon request.

5. Contractor shall review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.

APRIL 2025 01 26 01 - 5

BAND 266697

6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.

B. Labor:

1. Contractor shall estimate cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing hours required for each craft directly engaged in modification work. Any work proposed requiring overtime work or premium pay shall be itemized separately. Rates shall be in accordance with the Davis- Bacon Act as incorporated herein.