This is a Contract Price Schedule template for a Lump-Sum and Unit-Price contract related to underground utilities rehabilitation at Bandelier National Monument in New Mexico. The solicitation number is PARK-PMIS: BAND-266697, issued by the National Park Service Denver Service Center. The project encompasses rehabilitation of utilities in three developed areas: Mesa Top, Entrance Road, and Frijoles Canyon.
The contract includes six base line items (CLINs 0001-0006) covering Main Park Water System, Mesa Housing and Field Operations Center Water Mains and Service Lines, Primary Electrical Distribution, Cellular Network, Rock Excavation, and Roadway work, each priced as lump-sum (LS) items except Rock Excavation which is unit-priced per cubic yard. Additionally, fifteen option line items (Options A through O) are available for pricing, including primary electrical interconnections, water and natural gas main loops, wastewater systems, fiber-optic cable installation, demolition of utility features, and various lateral connections and system replacements throughout the monument. Offerors must submit pricing for all base line items and all option line items as a minimum requirement for proposal acceptability. Unit prices govern in case of calculation errors, and corrected amount totals govern in case of summation errors. All extended prices and totals must be rounded to whole dollars, with detailed measurement and payment information contained in Division 01 Specifications Section 01 27 00.
View the file
Other files
Show all 41
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BAND 266697 CLIN List
| Contract Price Schedule Template | |||||
| National Park Service (NPS) - Denver Service Center (DSC) | 3-13-18 | |||||
| Solicitation Number: | |||||
| PARK - PMIS: | BAND - 266697 | ||||
| (Project Management Information System) | |||||
| Developed Area: | Mesa Top, Entrance Road, and Frijoles Canyon Developed Areas | ||||
| Project Title: | Underground Utilities Rehabilitation, Bandelier National Monument | ||||
| Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all | |||||
| option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced | |||||
| line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related | |||||
| item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts | |||||
| govern. Round totals and extended prices to whole dollars. | |||||
| Contract Line Item Number (CLIN) | Contract Line Item (CLI) Title | Quantity | Unit of Measure | Unit Price | Total Price |
| 0001 | Main Park Water System | 1 | LS | ||
| 0002 | Mesa Housing and Field Operations Center (FOC) Water Mains and Service Lines | 1 | LS | ||
| 0003 | Primary Electrical Distribution | 1 | LS | ||
| 0004 | Cellular Network | 1 | LS | ||
| 0005 | Rock Excavation | 1 | CY | ||
| 0006 | Roadway | 1 | LS | ||
| TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Number 0001 through 0006) ----------------------------------------------------------- | |||||
| Option A | Primary Electrical Inter-Connection between Frijoles Canyon and Mesa Top systems | 1 | LS | ||
| Option B | Frijoles Canyon Water and Natural Gas Main Loop | 1 | LS | ||
| Option C | Frijoles Canyon Wastewater System | 1 | LS | ||
| Option D | Frijoles Canyon Natural Gas Laterals | 1 | LS | ||
| Option E | Fiber-Optic Cable from Existing Fiber Handhole near the Entrance Road Microwave Tower to FOC and Entrance Station | 1 | LS | ||
| Option F | Frijoles Canyon Visitor Center Fiber Pathway | 1 | LS | ||
| Option G | Demolition of Utility Features | 1 | LS | ||
| Option H | Demolition of Existing Canyon Underground Concrete Water Tank and Exposed Suspended Utilities | 1 | LS | ||
| Option I | Juniper Campground Water Mains and Service Lines | 1 | LS | ||
| Option J | Mesa Top Wastewater System | 1 | LS | ||
| Option K | Agoyo Lane Electrical System | 1 | LS | ||
| Option L | Fire Tower Lane Water and Natural Gas Line Replacement | 1 | LS | ||
| Option M | Cottonwood Comfort Station (Building #1) Utility Connections | 1 | LS | ||
| Option N | Natural Gas System | 1 | LS | ||
| Option O | Culvert and Erosion Repairs | 1 | LS | ||
| TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Number Option A through O) ----------------------------------------------------------- | |||||
| TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Number 0001 through 0006 and Option A through O) ------------------------------------------------------------------------------------------------------------------------------------------- | |||||
| All measurement and payment information is included in Division 01 Specifications Section 01 27 00 Definition of Contract Line Items. |