A4-2-1_-_ENLARGED_ELEVATIONS_-_HANGAR_4_DOORS_06_11_26_0002.pdf

PDF 2 MB Posted

Attached to
Hangars 3&4 Construction NY Floyd BennetField Gat
Solicitation number
140P2026R0060
Issued by

About this file

This is an architectural drawing for hangar door and glazing repair work at Floyd Bennett Field, a National Park Service facility within Gateway National Recreation Area.

The drawing specifies enlarged elevations and repair details for Hangar 4's north and south friezes, identifying multiple restoration tasks including: removal and reinstallation of existing aluminum panels with shop priming and painting to match Hangars 1 and 2; careful removal and cleaning of existing wireglass with replacement of damaged glazing using replica etched chickenwire single-pane glazing; removal of existing gasketing; dismantle and restoration of existing wheel hardware to operational condition with salvaged wheel replacement as needed; abatement of lead paint on existing metal trim; in-kind replacement of historic aluminum doors and hardware; and replication of two sliding hangar doors utilizing salvaged wheel hardware and replica glazing. Additional work includes priming and painting corrugated copper sheeting and painting text and symbols to match existing hangar specifications. Light fixture installation at original junction box locations is also specified with reference to electrical drawings. All contractors are required to verify existing field dimensions, remove hangar doors completely from tracks for restoration, refer to structural drawings for member replacement, and ensure all doors are reinstalled to full operability. The work emphasizes historic preservation and matching existing conditions across all hangar friezes.

View the file

Other files

File Type Posted
Sol_140P2026R0060_Amd_0004.pdf PDF
28_20_00_Video_Surveillance_-_06_23_26_0003.pdf PDF
A3-0_-_BUILDING_SECTIONS_06_23_26_0003.pdf PDF
Sol_140P2026R0060_Amd_0003.pdf PDF
Sign-in_Sheet_for_06_16_26_Site_Visit_0003.pdf PDF
A5-0-2_-_ROOF___HANGAR_DOOR_DETAILS_06_23_26_0003.pdf PDF
FINAL_BID_QUESTIONS_AND_ANSWERS__UPDATED_06_23_26_0003.pdf PDF
GATE_308504_-_140P2026R0060_Bid_Questions_and_Answers_-_06_11_26_0002.docx DOCX document
B08_Solicitation_P2026R0060_Revisions_to_Section_L_06_11_26_0002.docx DOCX document
S2-6_-_WPA_INFILL_ROOF_FRAMING_PLAN_06_11_26_0002.pdf PDF
012700_DefinitionOfContractLineItems_Revised_06_11_26_0002.pdf PDF
G0_-_COVER_SHEET_06_11_26_0002.pdf PDF
Sol_140P2026R0060_Amd_0002.pdf PDF
B08_Fillable_Past_Performance_Questionnaire_0002.docx DOCX document
A0-4_-_EXTERIOR_ELEVATIONS_-_DEMOLITION_06_11_26_0002.pdf PDF
Solicitation_P2026R0060_GATE_308504_Contract_Price_Schedule_Revised_06_11_26_0002.xlsx XLSX spreadsheet
A0-6_-_EXISTING_CONDITIONS_PHOTOS_-_EXTERIOR_06_11_26_0002.pdf PDF
B08_Fillable_Project_Experience_Questionnaire_0002.docx DOCX document
S6-3_-_MASONRY_REPAIR_AND_LINTEL_REPLACEMENT_DETAILS_06_11_26_0002.pdf PDF
S6-5_-_TYPICAL_CONCRETE_REPAIR_DETAILS_06_11_26_0002.pdf PDF
S6-2_-_STEEL_BEAM_REPAIR_DETAILS_06_11_26_0002.pdf PDF
WD_NY20260003_05_26_26_-_Issued_06_11_26_0002.pdf PDF
P4_-_PLUMBING_SCHEDULES_06_11_26_0002.pdf PDF
Sol_140P2026R0060_Amd_0001.pdf PDF
Amendment_0001_P2026R0060_0001.pdf PDF
Sol_140P2026R0060.pdf PDF
1__25-1219_GATE_308504_Final_CD_Project_Specifications.pdf PDF
3_25-1219_GATE_308504_Final_CD_Structural_Design_Calculations.pdf PDF
B08_GATE_308504_Hangars_3_and_4_Solicitation_140P2026R0060.pdf PDF
2_Final_CD_Drawings_-_Condensed.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

4 4 N A T I O N A L P A R K S E R V I C E

F L O Y D B E N N E T T F I E L D

05-06

09-03

09-03 09-0409-04 09-0409-04 05-13

08-01.GL

08-02.GL

08-01 08-03

08-02.DR

TYP

TYP

TYP TYP08-01.RW TYP

A4.3.3

Sim

A5.0.2

A5.1

Sim

A5.1

Sim

A5.0.2

Sim

A5.0.2

Sim

26-08

26-08

26-0826-08

7' - 11" ±10' - 3 1/2" ±

18' - 2 1/2" ± 08-09

4 4 N A T I O N A L P A R K S E R V I C E

F L O Y D B E N N E T T F I E L D 09-03

09-0409-04

2 3

08-01.GL

08-02.GL

08-0108-03

08-02.DR 08-02.DR

TYP

TYP

TYP

TYP08-01.RW

TYP

A4.3.3

Sim1

A5.0.2

A5.1

Sim

A5.1

Sim

A5.0.2

Sim

A5.0.2

Sim

26-08

26-0826-08

26-08

GLAZING ROLLING DOOR HARDWARE

08-01.GL

08-02.GL

ALUMINUM PANEL

08-01.AL

08-02.AL

08-02.DR

08-01.RW

08-02.RW

GLAZING AND HANGAR DOOR REPAIR LEGEND

1. CONTRACTOR TO VERIFY ALL EXISTING DIMENSIONS IN

FIELD.

2. ALL HANGAR DOORS SHOULD BE REMOVED COMPLETELY

FROM THEIR TRACKS FOR RESTORATION.

3. REFER TO STRUCTURAL DRAWINGS FOR

REPLACEMENT/REPAIR OF HANGAR DOOR STRUCTURAL

MEMBERS.

4. HANGAR DOORS ARE TO BE REINSTALLED TO BE FULLY

OPERABLE.

5. FOR HANGAR DOOR STRUTURAL MEMBER REPAIRS, SEE

DETAILS ON STRUCTURAL DRAWINGS.

SHEET NOTES

LEAN-TO 4 HANGAR 4 WPA INFILL HANGAR 3

BOILER

ROOM

LEAN-TO 3

KEY PLAN

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OF

190066

GATE 308504

GATEWAY NATIONAL RECREATION AREA

CT

SW

AK

10/17/2025

/9

/2

:5

:5

P

M A u to d e s k D o c s /G

A T

E F lo y d B e n n e tt F ie ld

/G A

T E

F lo y d B e n n e tt F ie ld

R

.r v t

A4.2.1

ENLARGED ELEVATIONS -

HANGAR 4 DOORS

SCALE OF FEET

2'4' 0 8'4'

SCALE A

SCALE AA4.2.1

1 ELEVATION - HANGAR 4 NORTH FRIEZE

SCALE AA4.2.1

2 ELEVATION - HANGAR 4 SOUTH FRIEZE

KEYNOTES

KEY

VALUE TEXT

05-06 IN-KIND REPLACEMENT SHEET METAL TRIM

PANEL. PRIME AND PAINT. COLOR TO MATCH

HANGARS 1&2 TRIM.

05-13 ABATE LEAD PAINT ON EXISTING METAL

TRIM. CLEAN, PRIME AND PAINT TO MATCH

HANGARS 1&2.

08-01 REMOVE EXISTING ALUMINUM PANEL. STRIP

EXISTING PAINT. SHOP PRIME AND PAINT.

REINSTALL WITH ALUMINUM RIVETS TO

MATCH EXISTING HISTORIC FASTENERS.

PRIME AND PAINT RIVETS TO MATCH.

08-01.GL CAREFULLY REMOVE EXISTING WIREGLASS

FROM STEEL FRAME. CLEAN AND

REINSTALL. IF GLAZING APPEARS TO BE

DAMAGED ONCE CONTRACTOR HAS

REMOVED IT, THE EXISTING GLAZING

SHOULD BE REPLACED WITH REPLICA

GLAZING.

08-01.RW DISMANTLE EXISTING WHEEL. BLAST TO

BARE METAL. SHOP PRIME AND PAINT.

REINSTALL TO BE OPERATIONAL. REPLACE

WITH ON SITE SALVAGED WHEEL

AS-NEEDED.

08-02.DR REPLACE EXISTING DOOR WITH IN-KIND

REPLACEMENT HISTORIC ALUMINUM DOOR

AND HARDWARE.

08-02.GL REMOVE EXISTING GLAZING. REPLACE WITH

REPLICA ETCHED CHICKENWIRE SINGLE

PANE GLAZING.

08-03 CAREFULLY REMOVE EXISTING GASKETING.

08-09 REPLICATE TWO (2) SLIDING HANGAR

DOORS TO MATCH EXISTING ALUMINUM

FRAME AND SHEET METAL DOORS. UTILIZE

SALVAGED WHEEL HARDWARE. GLAZING

SHALL BE REPLICA GLAZING, GL-1.

09-03 PRIME AND PAINT CORRUGATED COPPER

SHEETING. COLOR TO MATCH HANGARS 1&2.

09-04 PAINT TEXT AND SYMBOLS TO MATCH

HANGARS 1&2 IN SIZE AND TEXT TYPE.

26-08 INSTALL LIGHT FIXTURE AT EXISTING

ORIGINAL JBOX LOCATIONS. SEE

ELECTRICAL.

HANGAR 3&4 FRIEZES MATCH EXISTING HANGAR 1&2 FRIEZES.

Sheets
A4.2.1 - ENLARGED ELEVATIONS - HANGAR 4 DOORS

File details come from the government source that posted it. Updated .