This is Amendment 0013 which defines the Contract Line Items (CLINs) for a Visitor Center rehabilitation project at Martin Luther King Jr. National Historical Park in Atlanta, GA. The document outlines 15 distinct line items, with CLINs 4-7 not being used.

The base scope includes three main components: CLIN 1 covers interior building rehabilitation (excluding generator infrastructure), CLIN 2 covers exterior rehabilitation including roof replacement, sealant work, and generator infrastructure (excluding the generator itself), and CLIN 3 covers site improvements including drainage and re-striping. The remaining CLINs (8-15) are bid options that include exhibit space rehabilitation (ceiling, floor, and wall finishes), fountain removal, site signage improvements, 2nd floor casework replacement, temporary visitor restrooms (4-stall and 8-stall options), and a 35kW natural gas generator installation. All items are to be paid as lump sum based on monthly percentage completion. The work includes detailed specifications for electrical infrastructure, with generator service specifically designated for Curatorial Storage air conditioning units.

View the file

Other files

File Type Posted
B09_SF30_Amendment_0013_Solicitation_140P2024R0056_MALU293291_0013.pdf PDF
B09_MALU_293291_Amendment0013_Vol_II_Solit_Attach_6_Price_Schedule_0013.xlsx XLSX spreadsheet
Sol_140P2024R0056_Amd_0013.pdf PDF
B09_MALU_293291_Amendment_0013_Drawings_0013.pdf PDF
B09_140P2024R0056_MALU293291_Amendment0013_Solicitation_Clauses_Pg9_0013.pdf PDF
B09_Amendment_0013_WageDecision_DBA_GA20240307_Updated_Attachment_3_0013.pdf PDF
B09_MALU_293291_Amendment_0013_Specs_0013.pdf PDF
B09_Amendment_0013_Summary_of_Changes_to_Specifications_and_Drawings_0013.pdf PDF
B09_Amendment_0013_RFI_s_MALU_293291_140P2024R0056_0013.pdf PDF
Sol_140P2024R0056_Amd_0012.pdf PDF
B09_Amendment_P0011_140P2024R0056_MALU293291_0011.pdf PDF
B09_Amendment_11_Sign_in_Sheet_0011.pdf PDF
Sol_140P2024R0056_Amd_0011.pdf PDF
B09_MALU_293291_Questions_Responses_Spreadsheet_-_Amend_10_0010.xlsx XLSX spreadsheet
B09_Amendment_P0010_140P2024R0056_MALU293291_0010.pdf PDF
Sol_140P2024R0056_Amd_0010.pdf PDF
B09_MALU_293291_DefinitionOfContractLineItems_Amend_10_0010.pdf PDF
B09_Amendment_10_140P2024R0056_MALU293291_Page_66_0010.pdf PDF
B09_MALU_293291_ContractPriceSchedule_Amend_10_0010.xlsx XLSX spreadsheet
B09_Amendment_P0009_140P2024R0056_MALU293291_0009.pdf PDF
Sol_140P2024R0056_Amd_0009.pdf PDF
B09_SF30_Amendment_P0008_MALU293291_140P2024R0056_0008.pdf PDF
Sol_140P2024R0056_Amd_0008.pdf PDF
B09_SF30_Amendment_P0007_MALU293291_140P2024R0056_0007.pdf PDF
Sol_140P2024R0056_Amd_0007.pdf PDF
B09_SF30_Amendment_P0006_MALU293291_140P2024R0056_0006.pdf PDF
Sol_140P2024R0056_Amd_0006.pdf PDF
B09_MALU_293291_Questions_Responses_Spreadsheet_-_Amend_06_0006.xlsx XLSX spreadsheet
Sol_140P2024R0056_Amd_0005.pdf PDF
B09_SF30_Amendment_P0005_MALU293291_140P2024R0056_0005.pdf PDF
B09_MALU_293291_Questions_Responses_Spreadsheet_-_Amend_05_0005.xlsx XLSX spreadsheet
B09_SF30_Amendment_P0004_MALU293291_140P2024R0056_0004.pdf PDF
B09_Amendment_4_Sign_In_Sheet_0004.pdf PDF
Sol_140P2024R0056_Amd_0004.pdf PDF
B09_Amendment_4_PreProposal_Conf_Slides_MALU_293291_0004.pptx PPTX presentation
B09_Amendment_3_MALU_293291_Combined_Div_01___Technical_specs_8_12_24__0003.pdf PDF
Sol_140P2024R0056_Amd_0003.pdf PDF
B09_Amendment_03_140P2024R0056_MALU293291_Page_48_0003.pdf PDF
B09_Amendment_3__MALU_293291_Geotechnical_Engineering_Report_MLK_Visitor_Center_FINAL_Attchment_9_0003.pdf PDF
B09_Amendment_3_MALU_293291_MLK_Mold_and_RBM_Survey_Report_Attachment_12_0003.pdf PDF
B09_Amendment_3_MALU_293291_Canopy_Roof_and_Window_Sealants_Evaluation_Attachment_10_0003.pdf PDF
B09_SF30_Amendment_P0003_MALU293291_140P2024R0056_0003.pdf PDF
B09_Amendment_3_MALU_293291_Final_Drawings_20240531_20240715_0003.pdf PDF
B09_Amendment_3_MALU_293291_Video_Pipe_Inspection_Attachment_11_0003.pdf PDF
B09_Amendment_3_MALU_293291_Hydrant_Test_Results_Attachment_13_0003.pdf PDF
B09_SF30_Amendment_P0002_MALU293291_140P2024R0056_0002.pdf PDF
Sol_140P2024R0056_Amd_0002.pdf PDF
B09_Amendment_02_140P2024R0056_MALU293291_Page_66_0002.pdf PDF
B09_Amendment_01_140P2024R0056_MALU293291_Page_66_0001.pdf PDF
Sol_140P2024R0056_Amd_0001.pdf PDF
Show 40 more

Latest 50 of 62 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT 0013

MALU 293291 01 27 00 - 1

012721 DEFINITION OF CONTRACT LINE ITEMS

SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS

PART 1 - GENERAL

1.1 SUMMARY

A. Section explains in general, what is and is not included in a contract line item, and limits or cut-off points where one item ends and another begins.

B. If no contract line item exists for a portion of work, include costs in a related item.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 LIST OF CONTRACT LINE ITEMS

A. Contract Line Item Number 1: Building Rehabilitation- Interior

1. This item includes all base bid interior work at the Visitor Center, except for generator infrastructure work included in CLIN 2.

2. Measurement for payment will be the percentage of work completed in the previous month.

3. Payment will be made at the contract price per lump sum (LS).

B. Contract Line Item Number 2: Building Rehabilitation- Exterior (Roof and Entry Canopy, Generator Infrastructure)

1. This item consists of replacing membrane roof; replacing sealant at construction joints, coping, and column covers; installing lightning protection and housekeeping pads; and installing infrastructure to accommodate generator with new natural gas conduit from existing building natural gas service, 100A, 480/277V, 3-pole, NEMA 3R transfer switch located on exterior of building feeding into a new 100A, 480/277V, M.L.O., 30-space electrical panel located within Mechanical Room 207. Generator service will be used to provide standby power for the Curatorial Storage air conditioning units (AHU-3 and CU- 1). A Generator Annunciator panel will be provided within Curator Work Space 205 to indicate the status of generator.

2. Line item excludes generator and installation.

3. Measurement for payment will be the percentage of work completed in the previous month.

4. Payment will be made at the contract price per lump sum (LS).

C. Contract Line Item Number 3: Site Improvements (Drainage, Re-striping, Fountain Sidewalk)

1. This item consists of new and replacement inlets, drains, and site grading to improve stormwater drainage; filling and capping abandoned pump vault; replacing concrete paving, turfgrass, and irrigation; and limited pavement marking at parking lot.

2. Measurement for payment will be the percentage of work completed in the previous month.

3. Payment will be made at the contract price per lump sum (LS).

MALU 293291 01 27 00 - 2

012721 DEFINITION OF CONTRACT LINE ITEMS

D. Contract Line Items Numbers 4 through 7 – NOT USED

E. Contract Line Item Number 8: Bid Option- Exhibit Space Rehabilitation (Full Ceiling Scope)

1. This item consists of replacing all acoustic ceiling grid and tile, replacing all grilles, registers, diffusers, exit signs, and sprinkler heads.

2. Line item includes protecting floor mounted exhibits and suspended exhibit lighting in place, and removing and re-installing suspended sound structure. Work to be performed from ladders and scaffolding across the Exhibit space.

3. Line item excludes acoustic ceiling tile work listed in Contract Line Item Number 5.

4. Measurement for payment will be the percentage of work completed in the previous month.

5. Payment will be made at the contract price per lump sum (LS).

F. Contract Line Item Number 9: Bid Option- Exhibit Space Rehabilitation (Floor and Wall Finishes)

1. This item consists of removal and temporary storage of floor mounted exhibits, and replacing carpet, wood base, and painted wall finishes.

2. Work to be performed from ladders and scaffolding across the Exhibit space.

3. Measurement for payment will be the percentage of work completed in the previous month.

4. Payment will be made at the contract price per lump sum (LS).

G. Contract Line Item Number 10: Bid Option- Fountain Removal

1. This item consists of removing concrete and stone fountain, capping utilities, and filling exposed area with topsoil.

2. Measurement for payment will be the percentage of work completed in the previous month.

3. Payment will be made at the contract price per lump sum (LS).

H. Contract Line Item Number 11: Bid Option- Site Signage Improvements

1. This item consists of removing, reinstalling or rehabilitating existing interpretative and identity signage.

2. Measurement for payment will be the percentage of work completed in the previous month.

3. Payment will be made at the contract price per lump sum (LS).

I. Contract Line Item Number 12: Bid Option- 2nd Floor Casework Replacement

1. This item consists of replacing existing casework at Curator Work Space, Mail Room, Copy Room, and Reference Room with new plastic laminate casework. Work includes replacement sink at Curator Work Space.

J. Contract Line Item Number 13: Bid Option- Temporary 4-Stall Visitor Restroom

1. This item consists of supplying and maintaining ADA compliant toilet trailer with four stalls for project duration of 12 months. Line item includes twice weekly maintenance to empty holding tank and re-fill water tank.

MALU 293291 01 27 00 - 3

012721 DEFINITION OF CONTRACT LINE ITEMS

K. Contract Line Item Number 14: Bid Option- Temporary 8-Stall Visitor Restroom

1. This item consists of supplying and maintaining ADA compliant toilet trailer with eight stalls for project duration of 12 months. Line item includes twice weekly maintenance to empty holding tank and re-fill water tank.

2. Measurement for payment will be the percentage of work completed in the previous month.

3. Payment will be made at the contract price per lump sum (LS).

L. Contract Line Item Number 15: Bid Option- Generator

1. This item consists of supplying and installing new 35kW, 480/277V, 3-phase, 4-wire, natural gas generator with Level II sound attenuated enclosure.

END OF SECTION 01 27 00

PART 1 - GENERAL
1.1 SUMMARY
A. Section explains in general, what is and is not included in a contract line item, and limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of work, include costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item Number 1: Building Rehabilitation- Interior
1. This item includes all base bid interior work at the Visitor Center, except for generator infrastructure work included in CLIN 2.
2. Measurement for payment will be the percentage of work completed in the previous month.
3. Payment will be made at the contract price per lump sum (LS).
B. Contract Line Item Number 2: Building Rehabilitation- Exterior (Roof and Entry Canopy, Generator Infrastructure)
1. This item consists of replacing membrane roof; replacing sealant at construction joints, coping, and column covers; installing lightning protection and housekeeping pads; and installing infrastructure to accommodate generator with new natural gas c...
2. Line item excludes generator and installation.
3. Measurement for payment will be the percentage of work completed in the previous month. 4. Payment will be made at the contract price per lump sum (LS).
C. Contract Line Item Number 3: Site Improvements (Drainage, Re-striping, Fountain Sidewalk)
1. This item consists of new and replacement inlets, drains, and site grading to improve stormwater drainage; filling and capping abandoned pump vault; replacing concrete paving, turfgrass, and irrigation; and limited pavement marking at parking lot.
2. Measurement for payment will be the percentage of work completed in the previous month.
3. Payment will be made at the contract price per lump sum (LS).
D. Contract Line Items Numbers 4 through 7 – NOT USED
E. Contract Line Item Number 8: Bid Option- Exhibit Space Rehabilitation (Full Ceiling Scope)
1. This item consists of replacing all acoustic ceiling grid and tile, replacing all grilles, registers, diffusers, exit signs, and sprinkler heads.
2. Line item includes protecting floor mounted exhibits and suspended exhibit lighting in place, and removing and re-installing suspended sound structure. Work to be performed from ladders and scaffolding across the Exhibit space.
3. Line item excludes acoustic ceiling tile work listed in Contract Line Item Number 5.
4. Measurement for payment will be the percentage of work completed in the previous month.
5. Payment will be made at the contract price per lump sum (LS).
F. Contract Line Item Number 9: Bid Option- Exhibit Space Rehabilitation (Floor and Wall Finishes)
1. This item consists of removal and temporary storage of floor mounted exhibits, and replacing carpet, wood base, and painted wall finishes.
2. Work to be performed from ladders and scaffolding across the Exhibit space.
3. Measurement for payment will be the percentage of work completed in the previous month.
4. Payment will be made at the contract price per lump sum (LS).
G. Contract Line Item Number 10: Bid Option- Fountain Removal
1. This item consists of removing concrete and stone fountain, capping utilities, and filling exposed area with topsoil.
2. Measurement for payment will be the percentage of work completed in the previous month.
3. Payment will be made at the contract price per lump sum (LS).
H. Contract Line Item Number 11: Bid Option- Site Signage Improvements
1. This item consists of removing, reinstalling or rehabilitating existing interpretative and identity signage.
2. Measurement for payment will be the percentage of work completed in the previous month.
3. Payment will be made at the contract price per lump sum (LS).
I. Contract Line Item Number 12: Bid Option- 2nd Floor Casework Replacement
1. This item consists of replacing existing casework at Curator Work Space, Mail Room, Copy Room, and Reference Room with new plastic laminate casework. Work includes replacement sink at Curator Work Space.
2. Measurement for payment will be the percentage of work completed in the previous month.
3. Payment will be made at the contract price per lump sum (LS).
J. Contract Line Item Number 13: Bid Option- Temporary 4-Stall Visitor Restroom
1. This item consists of supplying and maintaining ADA compliant toilet trailer with four stalls for project duration of 12 months. Line item includes twice weekly maintenance to empty holding tank and re-fill water tank.
2. Measurement for payment will be the percentage of work completed in the previous month.
3. Payment will be made at the contract price per lump sum (LS).
K. Contract Line Item Number 14: Bid Option- Temporary 8-Stall Visitor Restroom
1. This item consists of supplying and maintaining ADA compliant toilet trailer with eight stalls for project duration of 12 months. Line item includes twice weekly maintenance to empty holding tank and re-fill water tank.
2. Measurement for payment will be the percentage of work completed in the previous month.
3. Payment will be made at the contract price per lump sum (LS).
L. Contract Line Item Number 15: Bid Option- Generator
1. This item consists of supplying and installing new 35kW, 480/277V, 3-phase, 4-wire, natural gas generator with Level II sound attenuated enclosure.
2. Measurement for payment will be the percentage of work completed in the previous month.
3. Payment will be made at the contract price per lump sum (LS).

END OF SECTION 01 27 00