Sol_140P2024R0048_Amd_0006.pdf
PDF 93 KB Posted
- Solicitation number
- 140P2024R0048
About this file
This document is an amendment (Amendment 06) to a solicitation for the SLBE 318729 Comprehensive Facility Rehabilitation project on the Manitou Islands, issued by the National Park Service. The amendment provides construction document clarifications, including the use of park utilities and facilities for contractors, the Trude Cottage addition and demolition plan, past performance requirements, government-furnished permits, small business contracting goals, and environmental and quality control manager requirements. It also provides references to geotechnical studies, updates to the wildlife biologist and tree trimming requirements, and clarifications to the piling, water supply well, and abutment details. The proposal due date is not extended. The solicitation number is 140P2024R0048.
View the file
Other files
Show all 37
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140P2024R0048 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
PDS
Denver CO 80225-0287 P.O. Box 25287 12795 W. Alameda Pkwy NPS, DSC Contracting Services Div
07/08/20240006
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
07/08/2024
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this Amendment 06 is to provide construction document clarifications listed below. This amendment also provides an answer to questions 36-63, additional questions are expected to be answered in subsequent amendments. This amendment also provides Geotechnical
References and additional information on the following attachments: Summary of Work, Submittal List, Steel Piling Marine, Water Supply Well and Abutment and Mooring Details.
Please see Amend 06 Attachments. Proposal due date is not extended.
Construction Document Clarifications:
General Clarifications
Use of park utilities and facilities for contractors.
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Edwin Berry
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140P2024R0048/0006
Trude Cottage addition.
Trude Cottage demo plan (reference Section 02 41
01).
Factor 6 ¿ Past Performance.
Government furnished permits.
Non-Large business contracting goals.
Small business revenue limits and certification requirements.
Requirements for an Environmental Manager presence on-site.
Requirements for a Quality Control Manager presence on-site.
Roles of the Wildlife Biologist (reference
Section 01 11 00).
Estimations of existing vertical and battered piling withing the existing North Manitou Island
Sheet Pile Dock structure were provided.
References ¿ Geotechnical
1984 Engineering Survey & Design Study - Manitou
Islands
1985 Sleeping Bear Prelim Design Rpt N Manitou
Dock
2011 South Manitou Island Geotechnical Report
Section 01 11 00
1.9 ¿ Wildlife Biologist is not needed if the trees are cut within allowable window, October 1 through April 15.
1.10 B.6.b - Removal or trimming of trees and
other woody vegetation dates have been updated.
1.10 15 ¿ Specification and associated project submittal list has been updated to note the restoration plan is to be provided by the
Contractor for review and approval.
Section 31 62 16
Added Section 1.2 D.3 ¿ Engineering Survey &
Design Study for Manitou Islands for the historical soil boring information.
1.5.E.1 ¿ Revised ¿preconstruction¿ to be
¿pre-installation¿. Revised meeting location to be at the jobsite or conducted virtually.
2.3 F ¿ Jetting is acceptable for the demo and
removal of existing piling.
3.3 - Clarification provided to depth of required borings, locations, SPT intervals, bedrock, and third-party involvement.
3.4 D.1.b ¿ Revisions made from excavating
driveline to probing driveline and performing
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
3 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140P2024R0048/0006 excavation if required.
3.4 H.1.b ¿ Piling cut-offs are to become the
property of the Contractor (instead of the
Contracting Officer).
3.5A - Clarification provided for obstructions reasonably anticipated to be encountered.
Section 33 11 13
1.2 A.1 - ¿Driven¿ replaced with ¿Drilled¿.
2.1 B ¿ Section removed.
2.3 A.1 ¿ Section been updated to specify
submersible pumps.
3.1 G ¿ Section removed.
3.1 H ¿ Reference to ¿provision supplement¿
removed.
3.1 M.4 ¿ Section removed.
3.2 A ¿ Reference specification updated from
221113 Facility Water Distribution Piping to
221118 Water Distribution System.
Sheet C0.0
Response provided to documentation required of existing conditions.
Sheet CT3.5
Clarification to Details 1/CT3.5 and 4/CT3.5 have been updated to more accurately depict the insitu sand placement extents around the concrete abutments.