This document is an amendment to a solicitation for the SLBE 318729 Comprehensive Facility Rehabilitation project on Manitou Islands, issued by the National Park Service. The amendment updates several attachments, including the project manual, drawings, and contract price schedule. It removes the requirement for three optional CLINs: CLIN 09 for a septic system replacement, CLIN 14 for temporary access during construction, and CLIN 19 for soil remediation. The proposal due date and time remain the same and are not extended. The agency is no longer requesting pricing for the removed CLINs, and any future related work will be accomplished through a contract modification.
View the file
Other files
Show all 37
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140P2024R0048 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
PDS
Denver CO 80225-0287 P.O. Box 25287 12795 W. Alameda Pkwy NPS, DSC Contracting Services Div
07/08/20240001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
07/08/2024
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this amendment is to attach updated Attachment 1 SLBE 318729 - Project
Manual Part 1 of 2, Attachment 3 SLBE 318729 - FINAL DWG CDs Part 1, Attachment 11 SLBE
318729 - Contract Price Schedule - BLANK.
NPS is not moving forward with the following optional CLINS- CLIN 09 SMI - Replace-In-Kind
Septic System, Option CLIN 14 NMI - Temporary Access During Construction, and Option CLIN
19 NMI - Remediation of Contaminated Soils. References and specifications for this work have been removed from the specs and drawings or noted that this work is no longer required. NPS is not requesting pricing for the option CLINS referenced here and therefore a new Contract Price Schedule is attached noting which CLINS will not be used.
If the same or similar work is considered after award it will be accomplished through a
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Edwin Berry
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 2
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140P2024R0048/0001 modification.
The following changes were made to Attachment 1
SLBE 318729 - Project Manual Part 1 of 2
Reduced spacing and removal of excess space have decreased the page count from 829 to 822
Page 5 of 822: Removed table of contents line for spec 35 01 50 Maintaining Island Access.
Page 24 of 822: CLIN 09 SMI-Replace-In-Kind
Septic System no longer used.
Page 26 of 822: CLIN 14 NMI-Temporary Access
During Construction no longer used.
Page 27 of 822: CLIN 19 NMI-Remediation of
Contaminated Soils no longer used.
Page 27 to 28 of 822: E. Tobin Cottage
(FMSS#51760) moved from CLIN 21 to CLINs 22 and
23.
Page 72 of 822: Removed submittal list spec 35 01
Page 788 to 796 of 822: Removed spec 35 01 50 description. Page is intentionally left blank.
Changes to Attachment 3 SLBE 318729 - FINAL DWG
CDs Part 1 includes a callout that CLINS 9, 14, and 19 are not used.
Proposal due date and time remains the same and is not extended.
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)