This price schedule solicits pricing for construction services required to develop the Marjory Stoneman Douglas Visitor Center at Everglades National Park in Everglades City, Florida. Offerors must submit pricing for 17 contract line items including the base requirements of building and site work for the visitor center and waterfront concessions, associated landscaping, dredging, bulkheads and floating docks, as well as optional items such as an upland seawall, kayak launch, and living shoreline establishment. Pricing is solicited in lump sums or unit prices as specified for each line item, with the total proposed price to be the sum of the base requirements and all optional line items. The National Park Service is the contracting agency managing this project through the Denver Service Center.
View the file
Other files
Show all 45
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Price Schedule
| Contract Price Schedule | |||||
| National Park Service (NPS) - Denver Service Center (DSC) |02/21/23 | |||||
| Solicitation Number: | 140P2023R0031 | ||||
| PARK - PMIS: | EVER 244476 | ||||
| (Project Management Information System) | |||||
| Developed Area: | Gulf Coast Visitor Center | ||||
| Project Title: | Construct Marjory Stoneman Douglas Visitors Center | ||||
| Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all | |||||
| option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced | |||||
| line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related | |||||
| item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts | |||||
| govern. Round totals and extended prices to whole dollars. | |||||
| Contract Line Item Number (CLIN) | Contract Line Item (CLI) Title | Quantity | Unit of Measure | Unit Price | Total Price |
| 1 | Zone 1 - Building - Visitor Center | 1 | LS | ||
| 2 | Zone 1 - Sitework - Visitor Center Plaza | 1 | LS | ||
| 3 | Zone 1 -3 - Sitework - Utilities | 1 | LS | ||
| 4 | Zone 1 - Landscaping - Visitor Center Plaza | 1 | LS | ||
| 5 | Zone 2 - Building - Waterfront Concessions | 1 | LS | ||
| 6 | Zone 2 - Sitework - Waterfront Area | 1 | LS | ||
| 7 | Zone 2 - Fuel System | 1 | LS | ||
| 8 | Zone 2 - Landscaping - Waterfront Area | 1 | LS | ||
| 10 | Marine - Dredging & Placement | 1 | LS | ||
| 12 | Zone 3 - Sitework - Remainder of Site | 1 | LS | ||
| 14 | Marine - Bulkhead | 1 | LS | ||
| TOTAL BASE PRICE (Contract Line Item Number 1 through 8, 10, 12, and 14) --------------------------------------------------------------------------------- | |||||
| 9 | Zone 1 - Upland Seawall | 1 | LS | ||
| 11 | Marine - Kayak Launch | 1 | LS | ||
| 13 | Zone 3 - Landscaping - Remainder of Site | 1 | LS | ||
| 15 | Marine - Floating Docks | 1 | LS | ||
| 16 | Marine - Demolish Seawall & Establish Living Shoreline | 1 | LS | ||
| 17 | Zone 2 - Building - Waterfront Concessions - Hardened Flood Load Design | 1 | LS | ||
| TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Number 9, 11, 13, and 15 through 17) ----------------------------------------------------------- | |||||
| TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Number 1 through 17) ------------------------------------ | |||||