This document contains responses to pre-bid questions on a federal solicitation for construction of the Marjory Stoneman Douglas Visitor Center at Everglades National Park. The solicitation seeks a turnkey construction project including site work, utilities, buildings, security systems, and landscaping. Questions covered topics such as dock designs, waterproofing systems, structural connections, landscaping requirements, and clarification of bid line items. The National Park Service intends to award all line items in the base bid and provided assurances that optional line items will only be exercised if overall funding is available. The response document aims to resolve construction issues upfront and mitigate risks to the contractor from ambiguous scope items.

View the file

Other files

File Type Posted
B08_RFP_140P2023R0031_Amendment_0010_4_4_23_0010.pdf PDF
B08_Sol_140P2023R0031_Amendment_10_Attachment_1_Responses_to_Pre-Bid_RFIs_3_28_23_0010.pdf PDF
Sol_140P2023R0031_Amd_0010.pdf PDF
B08_Sol_140P2023R0031_Amendment_9_Attachment_1_Additionl_Responses_Clarifications_Pre-Bid_RFIs_3_23_23_0009.pdf PDF
Sol_140P2023R0031_Amd_0009.pdf PDF
B08_RFP_140P2023R0031_Amendment_0009_3_23_23_0009.pdf PDF
Sol_140P2023R0031_Amd_0008.pdf PDF
B08_RFP_140P2023R0031_Amendment_0008_3_16_23_0008.pdf PDF
Sol_140P2023R0031_Amd_0007.pdf PDF
B08_RFP_140P2023R0031_Amendment_0007_3_8_23_0007.pdf PDF
B08_Sol_140P2023R0031_Amendment_6_Attachment_2_Contract_Price_Schedule_2_21_23_0006.xlsx XLSX spreadsheet
B08_RFP_140P2023R0031_Amendment_0006_2_22_23_0006.pdf PDF
Sol_140P2023R0031_Amd_0006.pdf PDF
B08_SO_1_0006.PDF PDF
B08_Sol_140P2023R0031_Amendment_5_Attachment_1_Additionl_Responses_Clarifications_Pre-Bid_RFIs_Round_2_0005.pdf PDF
B08_Sol_140P2023R0031_Amendment_5_Attachment_3__SF_1442_Conformed_Copy_0005.pdf PDF
B08_Sol_140P2023R0031_Amendment_5_Attachment_2_Pre-Bid_RFIs_Round_2_RFI_29_Word_Attachment_0005.pdf PDF
B08_RFP_140P2023R0031_Amendment_0005-2_16_23_0005.pdf PDF
Sol_140P2023R0031_Amd_0005.pdf PDF
Sol_140P2023R0031_Amd_0004.pdf PDF
B08_RFP_140P2023R0031_Amendment_0004-2_10_23_0004.pdf PDF
B08_Sol_140P2023R0031_Amendment_3_Attachment_4_Picture_2_of_the_Canopy-Picnic_Area_foundation_0003.JPG JPG image
B08_Sol_140P2023R0031_Amendment_3_Attachment_1__Pre-Bid_RFIs_Question_and_Responses_Round_1_0003.pdf PDF
B08_Sol_140P2023R0031_Amendment_3_Attachment_4_Picture_1_of_the_Canopy-Picnic_Area_foundation_0003.JPG JPG image
B08_Sol_140P2023R0031_Amendment_3_Attachment_3_Demolished_Maintenance_Building_Floor_Plan_0003.pdf PDF
B08_RFP_140P2023R0031_Amendment_0003-1_27_23_0003.pdf PDF
Sol_140P2023R0031_Amd_0003.pdf PDF
B08_Solicitation_140P2023R0031_Amendment_2_Conformed_Copy_0002.pdf PDF
B08_RFP_140P2023R0031_Amendment_0002-1_18_23_0002.pdf PDF
Sol_140P2023R0031_Amd_0002.pdf PDF
B08_Section_J_Attachment_5_General_Decision_Number_FL20230002_0002.pdf PDF
B09_Pre-Bid_Site_Visit_Sign-In_Sheet_EVER_244476_0002.pdf PDF
B08_Section_J_Attachment_4_General_Decision_Number_FL20230201_0002.pdf PDF
B08_Section_J_Attachment_1_Specifications_6_22_22-UPDATED_12_5_22_0001.pdf PDF
B08_Solicitation_140P2023R0031_Amendment_1_Conformed_Copy_0001.pdf PDF
B09_PreBid_Site_Visit_Powerpoint_Presentation-1_12_23_0001.pptx PPTX presentation
B08_RFP_140P2023R0031_Amendment_0001-1_4_23_0001.pdf PDF
Sol_140P2023R0031_Amd_0001.pdf PDF
B08_Section_J_Attachment_5_General_Decision_Number_FL20220096.pdf PDF
Sol_140P2023R0031.pdf PDF
B08_Section_J_Attachment_3_Contract_Price_Schedule_12_14_22.xlsx XLSX spreadsheet
B08_Section_J_Attachment_4_General_Decision_Number_FL20220022.pdf PDF
B08_Solicitation_140P2023R0031_EVER_244476.pdf PDF
B08_Section_J_Attachment_6_Proposal_Submission_Package_Forms_Portfolio.pdf PDF
B08_Section_J_Attachment_1_Specifications_6_22_22-UPDATED_9_8_22.pdf PDF
Show all 45

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q&A # (all Qs)

ROUND 2

Q&A #

Discipline Sheet Detail Spec Description / Question NPS Response Date

Recived 26 1 General Can you please explain more about the kingboard dock skirt on the floating docks for the Everglades National Park project?

The kingboard dock skirt is for NPS vessel safety operations to prevent potential pinching/entrapment hazards during docking operations.

1/24/2023

27 2 General Is the skirt to be on all sides of all docks, or just on the end of the fingers?

The kingboard dock skirt is for NPS vessel safety operations to prevent potential pinching/entrapment hazards during docking operations.

(This was an NPS request during SD phase to avoid fingers/hands getting pinched/injured while docking)

1/24/2023

28 3 General Please define where the skirting is to be located on the docks. Skirting is proposed on all sides of the docks where vessel operations occur.

1/24/2023

29 4 Specs See 3 RFIs in the attached Word Document. NPS Responses are found in the attached word document with each of the 3 RFIs.

1/25/2023

30 5 Contracting 01 11 00 Paragraph 1.3 Work Phases/Sequences, provides phased completion dates for various work items. As the due date for this proposal has been extended, please consider revising these dates to better align with potential NTP timeline and overall period of performance.

The solicitation and contract is based on the clause FAR 52.211‐10 which states the Period of Performance is 720 Calendar Days after issuance of the notice to proceed. Your schedule shall be in accordance with that clause and you may assume a NTP Issue Date of no later than June 30, 2023.

2/6/2023

31 6 Structural SM111 E1 Detail E1/SM111 calls for Hot Dipped Galvanized (HDG) T‐ Connection welded to H‐Pile which is to be coated with Coal Tar Epoxy (CTE). This connection cannot be made as welding after applying CTE and Welding after HDG is not practical or advisable. Recommend modifying this connection for one of two options. Option A. predrill H‐pile prior to CTE coating and HDG the T‐Connection after drilling. Modify connection to H‐ Pile for a 4‐bolt connection through the H‐pile Flanges (eliminate the welded connection). Bolt on T‐connection after H‐pile is installed. Option B. Weld attach T‐Connection to H‐ pile prior to coating. coat the H‐Pile and T‐Connection with CTE. Install H‐pile with T‐Connection already attached and coated in conjunction with the H‐pile. Please advise.

Option A is recommended over option B.

Option A: The bolted type connections is acceptable.

A design for this alternate connection will be prepared to establish number of bolts and plate thickness.

Option B is not recommended as tip elevation may vary upon installation. Contractor shall be responsible for damages during installation / driving operations which may affect the prefabricated connection.

2/6/2023

32 7 Landscape 31 22 13 Please confirm that the mangrove fertilization in spec 31 22 13 Paragraph 2.2.D.2 is completed during the nursery period and not after planting on the site

The fertilization is completed during the nursery period. No fertilization shall be completed after planting.

2/6/2023

Attachment 1: Pre-Bid RFIs and NPS Responses Round 2

Attachment 1: Page 1 of 4

33 8 Architectural A851 07 13 00 07 13 00 Sheet waterproofing indicates that the sheet waterproofing is to be installed underneath the elevator pit slab. Sheet A851 does not detail any waterproofing under the elevator pit slab, but does show a "Post Applied Waterproofing" on the pit walls to just below the top of the slab. Please confirm the detail should be followed and the specification should be revised.

Wall Section 1/A851 does illustrate a dashed line below the elevator pit slab/foundation. The specs should be followed.

2/6/2023

34 9 Architectural A851 Sheet A851 shows a "Comprehensive Waterproofing System" on one side of the elevator pit. Please provide detail on this system, showing layers and specs.

This note is describing the system that is specified in section 07 13 00. The comprehensive system includes the sheet waterproofing membrane, primers, sealants, drainage board, protection board, flashing and other specified accessories.

2/6/2023

35 10 Structural 05 12 00 Specification 05 12 00 ‐ Structural Steel Paragraph 2.7.A2 states, "Galvanize lintels, shelf angles, any framing exposed to earth or weather, and other framing as noted in Construction Drawings." The construction drawings do not note any of the structural steel to be galvanized. Please clarify what structural steel will need to be galvanized.

Any lintel as well as an outriggers or joist extensions exposed to the weather. Outriggers/joist extensions that are within architectural finished space do not need to be galvanized. The screenwall posts, if exposed to the elements shall be galvanized.

For marine elements, coating requirements are indicated on drawings (SM001) and specifications 31

62 16.16 and 09 97 13.26.

2/6/2023

36 11 Structural S101 Drawing S101, where the elevator is located there is a reference to section 1/S303. On drawing S301, detail 1 shows the cross section from sheet S101. Please revise S101 to show cross section detail on elevator is 1/S301.

The section cut on S101 calls out 6/S301. This detail should be 1/S301.

2/6/2023

37 12 Architectural 07 16 16 Specification 07 16 16 Crystalline Waterproofing Paragraph 2.2 calls for the crystalline waterproofing to be applied on negative (interior side) Pile Cap. To clarify, please confirm that the requirement is to apply the crystalline coating to the bottom and sides of the elevator pit as shown on detail 1/A851 to the height of Level 2.

Yes. The crystalline coating is to be installed on the bottom and sides of the elevator shaft walls and pit, up to the height of Level 2, as indicated on section

1/A851.

2/6/2023

38 13 Architectural 07 16 16 Specification 07 16 16 Crystalline Waterproofing Paragraph 2.2 calls for the crystalline waterproofing to be applied on negative (interior side) Pile Cap. Please confirm only the elevator pit piles have the crystalline waterproofing or if all pile have this applied.

All pile caps are to have the crystalline waterproofing applied, per the spec. Not the pile itself; just the pile cap.

2/6/2023

39 14 Architectural 12 48 13 Specification 12 48 13 Paragraph 3.2.A states, "Mats: Verify size of floor recess before fabricating mats." No recesses are shown on the drawings, please confirm that a surface mounted mat is required

The walk off mats are not intended to be recessed, but will be surface laid.

2/6/2023

40 15 Civil C105 SG6 Site Signage Keynote "SG6" is called out on the Civil layout plan on the three parking spaces to the east of the visitors center, but are not included in the keynote descriptions. Please provide description and specification for SG6.

SG6' signage is a parking sign that will say "Park Personnel Only", or something similar.

2/6/2023

Attachment 1: Page 2 of 4

41 16 Civil C105 S31 Site Layout Keynote "S31" is called out on the Layout plan in the bus parking area but not listed in the keynote descriptions.

Please provide description and specification for S31.

Keynote S31 is to be removed.

2/6/2023

42 17 Civil C105 The Keynote and proposed feature legend for the ADA parking are in conflict. The ADA parking spots are hashed in concrete, but called out with S1b (Asphalt Pavement ‐ Light Duty) keynotes. Please clarify if the ADA parking spots are asphalt or concrete.

The ADA parking spots are intended to be concrete, per S2 keynote. The keynot S1b should be pointed to the hatched area for the light duty asphalt. 2/6/2023

43 18 Civil Various Various The scope of this project requires significantly raising the grade of the site approximately 2 to 5 feet above the existing grade.

The causes concern with the current zoning and bid form structure as it related to certain option line items. The Civil drawings do not clearly depict how the proposed grading of the site is to be accomplished if CLIN 12 (Zone 3 ‐ Sitework) and/or CLIN 14 (Marine Bulkhead) are not awarded. The project requires significant fill to meet the proposed grades, however if the Zone 3 sitework (CLIN 12) and/or the marine bulkhead (CLIN 14) are not awarded, how are the proposed grades tying into existing grades at the Zone 3 boundary and the existing bulkhead? To mitigate this and other conflicts, we recommend including all sitework and all marine bulkhead in base bid CLINs.

The intent is to award all CLINs. If bids come in above overall available funds then a formal path forward will be issued by the NPS prior to execution.

2/6/2023

44 19 Civil Various Various There are storm drainage lines which drain to the dry retention ponds 1, 2 and 3, located within Zone 3. If CLIN 12, Zone 3 Sitework Option is not exercised, where should these storm drain lines be routed to? To mitigate this and other conflicts, we recommend including all sitework in base bid CLINs

The intent is to award all CLINs. If bids come in above overall available funds then a formal path forward will be issued by the NPS prior to execution.

2/6/2023

45 20 Civil Various Various CLIN 3 includes all utilities throughout the site. Various proposed utilities are routed through Zone 3, an area for which the grading is included in a bid option, CLIN 12. Certain utilities in this area, particularly Storm Line A‐A, is located above existing grades, so if CLIN 12 is not exercised, this line could not be installed. To mitigate this and other conflicts, we recommend including all sitework in base bid CLINs

The intent is to award all CLINs. If bids come in above overall available funds then a formal path forward will be issued by the NPS prior to execution.

2/6/2023

46 21 Civil Geotechni cal Report

Please confirm the preload program outlined in the geotechnical report is required at all fill areas and not limited to paved areas and path of new utilities only

The preload program is required at all fill areas, per the Geotechnical Report.

2/6/2023

47 22 Civil Please confirm if preload program for zone 3 should be priced in the base bid, or included with zone 3 options.

The preload program for Zone 3 should be included in Zone 3 CLIN #12. 2/6/2023

48 23 Security E503 2 Please confirm the scope of work for the Intrusion Detection System is to provide rough‐in only inclusive of conduit, backboxes, cover plates and pull strings

The Intrusion Detection System should be priced as a turn‐key system. Only infrastructure to be provided is for the card access system, all others are to be turnkey systems.

Attachment 1: Page 3 of 4

49 24 Security E503 2 Please confirm that the Intrusion Detection Panel, Door Contacts, Keypads, wiring, programming etc. will be furnished and installed by the owner or owners security contractor

The Intrusion Detection System should be priced as a turn‐key system. To be provided and installed by the

Contractor.

2/6/2023

50 25 Civil 31.62.13 Please confirm that the 14" precast concrete piles can be pre‐ augured to 8‐10' to erect pile prior to driving.

If necessary, the precast piles can be pre‐augured prior to pile driving (Refer to FDOT 455‐5.1 specification on pre‐drilling). Please note that methodology and pre‐drilled depth will factor in the final design of the piles.

2/6/2023

51 26 General G107 Please clearly delineate Zones on drawing G107 associated with CLIN descriptions. No revisions will be issued at this time. 2/6/2023

52 27 General Solicitatio n

Please clarify whether the NPS intends to award the bid options in ascending order Contractor to assume award of Bid Options based on the option period specified in Solicitation, pages 15‐ 16, Section __ SECTION H – SPECIAL CONTRACT

REQUIREMENTS

"SPECIAL REQUIREMENT 1: OPTION FOR ADDITIONAL

SERVICES—SEPARATELY PRICED LINE ITEM. The Government may require the delivery of the numbered line items identified in the Schedule as option items at the price stated in the Schedule. The Contracting Officer may unilaterally exercise the option by written notice to the Solicitation Contractor within 90 days after contract award. Performance of added line‐item tasks shall be at the price negotiated in the contract Schedule." No additional information is available at this time regarding exercise of options;

however, the Contractor may provide information and assumptions in the technical approach and schedule narratives in its proposal that inform the Government of the Contractor's approach to these bid options.

Attachment 1: Page 4 of 4