This document contains responses to contractor questions (RFIs) regarding a federal construction solicitation to build the Marjory Stoneman Douglas Visitor Center at Everglades National Park in Florida. The responses clarify that MSHP-1 should be labeled as MSCU-1 in the unit schedule. Galvanized sheet metal must be used for all supply and return ductwork within the building, with stainless steel required for outside air intake ducts and high-humidity intake areas like showers. Florida state license information and examples of two past projects of similar size and scope are required installer qualifications for all seismic-rated systems.
View the file
Other files
Show all 45
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI 29.1:
23 05 29 1.4 D
D. Installer's Qualifications: Include evidence of compliance with specified requirements for all seismic-rated systems, including Georgia State license information and examples of at least
(2) successful projects of similar size and scope.
NPS RESPONSE: The correct statement is “D. Installer's Qualifications: Include evidence of compliance with specified requirements for all seismic-rated systems, including Florida State license information and examples of at least”
RFI 29.2:
Please confirm that MSHP-1 is a mislabeling of MSCU-1.
NPS RESPONSE: CONFIRMED. PER UNIT SCHEDULE MSHP-1 IS ACTUALLY MSCU-1.
RFI 29.3:
Please confirm supply duct shown on the plans is galvanized sheetmetal. Below snaps are the source of confusion:
Per Spec 23 31 00
Attachment 2: Pre-Bid RFIs Round 2 Word Attachment for RFI # 29
Attachment 2 Page 1 of 2
NPS RESPONSE: GALVANIZED FOR ALL SUPPLY / RETURN DUCTWORK WITHIN BUILDING. STAINLESS
STEEL FOR ALL OUTSIDE AIR INTAKE DUCTWORK AND HIGH-HUMIDITY INTAKE (SHOWERS). REFER TO
ERV SCHEDULE ON M601, AND DETAIL 1/M502.
Attachment 2 Page 2 of 2