B08_Sol_140P2023R0031_Amendment_5_Attachment_1_Additionl_Responses_Clarifications_Pre-Bid_RFIs_Round_2_0005.pdf

PDF 1 MB Posted

Attached to
EVER 244476, Construct MSD Visitor Center
Solicitation number
140P2023R0031
Issued by

About this file

This document contains responses to questions from prospective offerors on a National Park Service solicitation to construct a Marjory Stoneman Douglas Visitor Center in Everglades City, Florida. The responses provide clarification on the scope of work, schedule, and evaluation approach. Key details include: the solicitation requires construction of a visitor center and associated site work amenities, with optional line items for additional features; responses aim to address offeror questions on phasing, contingencies in pricing given funding constraints, and substitution of specified equipment; and the period of performance is defined as 720 calendar days from a planned notice to proceed date of around June 30, 2023, with evaluation based on submission of a proposal according to requirements by the revised due date.

View the file

Other files

File Type Posted
B08_RFP_140P2023R0031_Amendment_0010_4_4_23_0010.pdf PDF
B08_Sol_140P2023R0031_Amendment_10_Attachment_1_Responses_to_Pre-Bid_RFIs_3_28_23_0010.pdf PDF
Sol_140P2023R0031_Amd_0010.pdf PDF
B08_Sol_140P2023R0031_Amendment_9_Attachment_1_Additionl_Responses_Clarifications_Pre-Bid_RFIs_3_23_23_0009.pdf PDF
Sol_140P2023R0031_Amd_0009.pdf PDF
B08_RFP_140P2023R0031_Amendment_0009_3_23_23_0009.pdf PDF
Sol_140P2023R0031_Amd_0008.pdf PDF
B08_RFP_140P2023R0031_Amendment_0008_3_16_23_0008.pdf PDF
Sol_140P2023R0031_Amd_0007.pdf PDF
B08_RFP_140P2023R0031_Amendment_0007_3_8_23_0007.pdf PDF
B08_Sol_140P2023R0031_Amendment_6_Attachment_2_Contract_Price_Schedule_2_21_23_0006.xlsx XLSX spreadsheet
B08_RFP_140P2023R0031_Amendment_0006_2_22_23_0006.pdf PDF
Sol_140P2023R0031_Amd_0006.pdf PDF
B08_SO_1_0006.PDF PDF
B08_Sol_140P2023R0031_Amendment_5_Attachment_3__SF_1442_Conformed_Copy_0005.pdf PDF
B08_Sol_140P2023R0031_Amendment_5_Attachment_2_Pre-Bid_RFIs_Round_2_RFI_29_Word_Attachment_0005.pdf PDF
B08_RFP_140P2023R0031_Amendment_0005-2_16_23_0005.pdf PDF
Sol_140P2023R0031_Amd_0005.pdf PDF
B08_Sol_140P2023R0031_Amendment_4_Attachment_1_Pre-Bid_RFI_and_NPS_Response_Round_2_0004.pdf PDF
Sol_140P2023R0031_Amd_0004.pdf PDF
B08_RFP_140P2023R0031_Amendment_0004-2_10_23_0004.pdf PDF
B08_Sol_140P2023R0031_Amendment_3_Attachment_4_Picture_2_of_the_Canopy-Picnic_Area_foundation_0003.JPG JPG image
B08_Sol_140P2023R0031_Amendment_3_Attachment_1__Pre-Bid_RFIs_Question_and_Responses_Round_1_0003.pdf PDF
B08_Sol_140P2023R0031_Amendment_3_Attachment_4_Picture_1_of_the_Canopy-Picnic_Area_foundation_0003.JPG JPG image
B08_Sol_140P2023R0031_Amendment_3_Attachment_3_Demolished_Maintenance_Building_Floor_Plan_0003.pdf PDF
B08_RFP_140P2023R0031_Amendment_0003-1_27_23_0003.pdf PDF
Sol_140P2023R0031_Amd_0003.pdf PDF
B08_Solicitation_140P2023R0031_Amendment_2_Conformed_Copy_0002.pdf PDF
B08_RFP_140P2023R0031_Amendment_0002-1_18_23_0002.pdf PDF
Sol_140P2023R0031_Amd_0002.pdf PDF
B08_Section_J_Attachment_5_General_Decision_Number_FL20230002_0002.pdf PDF
B09_Pre-Bid_Site_Visit_Sign-In_Sheet_EVER_244476_0002.pdf PDF
B08_Section_J_Attachment_4_General_Decision_Number_FL20230201_0002.pdf PDF
B08_Section_J_Attachment_1_Specifications_6_22_22-UPDATED_12_5_22_0001.pdf PDF
B08_Solicitation_140P2023R0031_Amendment_1_Conformed_Copy_0001.pdf PDF
B09_PreBid_Site_Visit_Powerpoint_Presentation-1_12_23_0001.pptx PPTX presentation
B08_RFP_140P2023R0031_Amendment_0001-1_4_23_0001.pdf PDF
Sol_140P2023R0031_Amd_0001.pdf PDF
B08_Section_J_Attachment_5_General_Decision_Number_FL20220096.pdf PDF
Sol_140P2023R0031.pdf PDF
B08_Section_J_Attachment_3_Contract_Price_Schedule_12_14_22.xlsx XLSX spreadsheet
B08_Section_J_Attachment_4_General_Decision_Number_FL20220022.pdf PDF
B08_Solicitation_140P2023R0031_EVER_244476.pdf PDF
B08_Section_J_Attachment_6_Proposal_Submission_Package_Forms_Portfolio.pdf PDF
B08_Section_J_Attachment_1_Specifications_6_22_22-UPDATED_9_8_22.pdf PDF
Show all 45

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q&A # (all Qs)

ROUND 2

Q&A #

Discipline Sheet Detail Spec Description / Question NPS Response Date

Recived 29 4 General Amendment

4 Q&A Response 29

Amendment 4, Q&A response #29 (Round 2 Q&A 4) states, "NPS Responses are found in the attached word document with each of the 3 RFIs." The Amendment did not include a word document. Please provide this document so that we can review the referenced questions and answers

The Word Attachment for Pre‐Bid RFIs Round 2 with NPS Responses has been converted to a PDF document and properly attached to Amendment 5.

2/15/2023

30 5 General Amendment 4 Q&A

Response 30

The question response does not provide clarity to the turnover Phasing defined in specification section 00 11 00 Paragraph 1.3

1. Kayak Launch: Work to be completed and ready for Government’s full use by November 1, 2023.

2. Dredging and Bulkhead: Work to be completed and ready for Government’s full use by November 1, 2023.

3. Remote Concessions building to be Substantially Complete by December 1, 2024.

4. Visitor Center building to be Substantially Complete by December 1, 2024."

With an potential NTP in late June, the current period of performance for each phasing item have been reduced. Please confirm the response to imply the phase turnover dates are no long applicable and the entire project now to be turnover at the same time (Day 720). If not please consider extended the phased turn over dates.

The Phase turn over dates are no longer applicable, the Solicitation and subsequent contract will be held to the clause FAR 52.211‐10 which states the Period of Performance is 720 Calendar Days after issuance of the notice to proceed. Your schedule shall be in accordance with that clause and you may assume a NTP

Issue Date around June 30, 2023.

ADDITIONAL INFORMATION TO SUPPLEMENT

ANSWER: It is expected that pending U.S. Army Corps of Engineers (USACE) wetland permits for this project will be approved in June 2023, which ties to the anticipated Construction NTP date on or about June 30, 2023. Construction NTP is dependent upon the permitting, but also approval of Bonds, acceptance of Division 1 submittals, and a variety of pre-construction requirements; therefore, the end of June 2023 is the target date for construction NTP. FAR 52.211-10 which states the Period of Performance is 720 Calendar Days after issuance of the notice to proceed (NTP), and is the relevant time period that should be used for scheduling.

2/15/2023

Attachment 1: Additional NPS Responses/Clarifications for the Second Round of Pre-Bid Questions received by 02/06/23

Attachment 1: Page 1 of 3

43‐45 18‐20 General Amendment 4 Q&A

Responses 43, 44, 45

Amendment 4, Q&A responses #43, 44, 45 (Round 2 Q&As 18, 19, 20) indicate that the NPS's intent is to award all CLINs, and that if bids come in above available funds then a formal path will be issued regarding tying in significant fill areas to existing grades at the marine bulkhead, other site areas and utilities. It is not possible for the bidding contractors to provide a firm fixed price for the base bid scope of work without knowing how the NPS may subsequently change the scope of the project if CLINs 12 and 14 are not able to be exercised. Due to the current format of the Bid Form, there are areas of 3‐5' of fill directly adjacent to the marine bulkhead and other site areas with hardscapes, utilities, etc. Without understanding how this scope may be unilaterally changed by the NPS, the only way to mitigate risk is to include significant contingency dollars which will exacerbate the potential issue of funding availability. In order to drastically reduce cost to the NPS, we recommend including CLINs 12 and 14 within the base bid if it is truly the intent to award these CLINs. Otherwise, we will need an alternate design to understand how the proposed grades and hardscapes should tie back into the existing grades.

The proposal should be based on issuance of a Contract for i) all Base CLINs 1 - 8 at award and ii) all Options 9 - 17 at award or within the 90-day option period as stated in the Solicitation, as one complete project. Bid in accordance with the requirements. Assumptions will not be accepted

2/15/2023

53 28 Contracting 01 11 00 Paragraph

1.3

Work Phases/Sequences, provides phased completion dates for various work items. As the due date for this proposal has been extended, please consider revising these dates to better align with potential NTP timeline and overall period of performance.

The solicitation and contract is based on the clause FAR 52.211‐10 which states the Period of Performance is 720 Calendar Days after issuance of the notice to proceed. Your schedule shall be in accordance with that clause and you may assume a NTP Issue Date around June 30, 2023.

ADDITIONAL INFORMATION TO SUPPLEMENT

ANSWER: It is expected that pending U.S. Army Corps of Engineers (USACE) wetland permits for this project will be approved in June 2023, which ties to the anticipated Construction NTP date on or about June 30, 2023. Construction NTP is dependent upon the permitting, but also approval of Bonds, acceptance of Division 1 submittals, and a variety of pre-construction requirements; therefore, the end of June 2023 is the target date for construction NTP. FAR 52.211-10 which states the Period of Performance is 720 Calendar Days after issuance of the notice to proceed (NTP), and is the relevant time period that should be used for scheduling.

1/31/2023

54 29 General As an interested supplier for the project, could you please forward to us the prebid meeting attendee's sign‐in sheet?

The Pre‐Bid Site Visit sign‐in sheet was posted with Amendment 02 to the Solicitation and may be accessed through SAM.gov under Notice ID

1402023R0031.

1/31/2023

Attachment 1: Page 2 of 3

55 30 Specification s Section 01 67 00 – 6

After reviewing the plans for the Marjory Stoneman Visitors Center in Everglades City, I noticed it was spec’d for a video surveillance system on the basis of design of Avigilon. Would a substitute system, like March Networks, suit the requirement?

If the intention is to substitute a product at the bid/proposal phase, that substitution must be clearly documented in the Technical proposal, so that the product substitution may be evaluated and determied if it is acceptable. Otherwise, bids/proposals should be based on the requirements in the Specifications. For substitutions post‐award, please review Specifications Section 01 67 00 – 6 (page 179) for Product Selection Procedures, and 01 33 23 (page 104) for Submittal

Procedures.

2/1/2023

56 31 General Please provide the specific graphic (see to be perforated into the metal fins. Is that something that Government can send us?

Per the rendering it appears to have an MSD perforated into it

– per the plans it is some other circular pattern. The type of pattern it will be (is necessary to understand) as cost can be significantly impacted.

The graphic and specifications provided in the Solicitation documents should be used for pricing the proposal.

1/31/2023

Attachment 1: Page 3 of 3

File details come from the government source that posted it. Updated .