This document outlines a federal presolicitation notice for construction services to repair historic structures at Kennecott Mines National Historic Landmark in Alaska. The National Park Service seeks proposals for a firm-fixed price contract to stabilize the landmark's 14-story timber frame Mill Building through selective replacement of deteriorated wood components, scaffold installation, siding reinstallation, new frame and roof construction, and partial demolition and reconstruction of an exterior ore chute. Known hazardous materials are present. The small business set-aside contract is estimated between $1-5 million with a 730-day performance period. A pre-proposal site visit is scheduled for September 10, 2019, with proposals due in August according to the anticipated solicitation.

Mill North Slope Scaffolding and Deck work plan

View the file

Other files for this federal contract opportunity

Other files attached to Repair Historic Kennecott Mine Structures, newest first.
File Type Posted
SF30_140P2019R0021_Amd_006.pdf PDF
Clarification_on_Spec_06_10_00_2.2B_.pdf PDF
SF30_140P2019R0021_Amd_0005.pdf PDF
WRST_159092C_Contract_Questions_NPS_Responses_10.15.19_Amendment_5.pdf PDF
WRST_159092C_Contract_Questions_NPS_Responses_10.4.19_Amendment_4.pdf PDF
Kennecott_Mill_North_Slope_Scaffold_and_Deck_Stabilization_Pads_Report.pdf PDF
SF30_140P2019R0021_Amd_0004.pdf PDF
Kennecott_ORE_CHUTE_9-2019_Revised_Volume_2.pdf PDF
Kennecott_Mines_NHL_Photographs_2.pdf PDF
WRST_159092C_Contract_Questions_NPS_Responses_10.1.19_Final.pdf PDF
SF30_140P2019R0021_Amd_0003.pdf PDF
Revised_Specs_and_Drawings_Portfolio_9-18-19.pdf PDF
NPS-ProjectSustainabilityChecklist-LEED2009_5-28-10.xls XLS spreadsheet
SF30_140P2019R0021_Amd_002.pdf PDF
WRST_159092C_Site_Visit_Meeting_Minutes_9-10-19.pdf PDF
B08_RFP_Submission_Package.pdf PDF
Sol_140P2019R0021_Amd_0001.pdf PDF
E15_LmtOnSubconRpt_REQD.xlsx XLSX spreadsheet
B08_Attch_4_Rec_Hall_Parking_map_Rev1.docx DOCX document
SF24-Bid_Bond.pdf PDF
B08_140P2019R0021.pdf PDF
B03_WDOL_Builing_and_Heavy_Construction.pdf PDF
B08_140P2019R0021.pdf PDF
B08_Attch_4_Rec_Hall_Parking_map.docx DOCX document
B08_WRST_159092C_drawings_.pdf PDF
B08_WRST_159092C_Specs_8-22-19.pdf PDF
Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Mill North Slope Scaffolding and Deck Stabilization work plan:

Staff: Dates: Sept. 30-Oct. 4, 2019 Matt Smith (Project Lead), Tim George (Blasting Officer), Paul Hanis, and Marie Thorn.

Incident Response Lead: Greg Runyan

Goals:

1. Ensure the health and safety of all members of the team.

2. Protect all workers from heavy metals exposure.

3. Identify potential explosives before any disturbance takes place.

4. Be prepared in the case of an explosive event or other injuries.

5. Mitigate any explosives discovered.

6. Install 8 scaffold pads (4x12x24 nom) along north wall of Mill.

7. Install 4-5 pads (4x12x24 nom) for deck stabilization.

Process and Timeline:

1. Discuss the plan with the team. Allow comments and concerns to be addressed and ensure that all members are comfortable moving forward with the plan.

2. Complete a GAR/SPE/ORMA model and review applicable JHAs (winch, explosives).

3. Tim will be the overall safety office and will keep the “big picture” view unless a potential explosive is discovered. In this case Matty will transition to this role while Tim assesses the hazard.

4. Establish an anchor approximately 100 feet from the building that will be used to attach an electric winch to. This creates a safe working distance from possible explosion.

5. Use appropriate rigging to move any heavy woody debris that is within the work area. Smaller debris will be moved by hand. Only move as far as necessary.

6. Establish pads for scaffold tower to be erected by Phase III contractor in 2020. Eight pads will be installed using 4” x 12” x 24” pressure treated wood.

7. Layout of pads will be 16” from wall plumb line, 7 feet between frames that are 5 feet wide.

There will be 4 sets of frames used so the total run will be 21 feet x 5 feet wide. Slope angle is approximately 43°.

8. Establish 4-5 pads for deck stabilization.

9. Soil will be dug only as deep as necessary to fully support each 4 x 12 pad.

10. Utmost care will be taken when excavating the soil in order to not disturb any buried blasting caps. No compression of soil will be allowed. Water will be used to help settle and compact the pad areas.

11. Layout of pads will be confirmed and each pad will be checked for level in two directions.

12. After Action Review will be conducted to identify if our plan was sufficient to meet all of our goals and identify if any changes need to be made next time this type of activity is done.

PPE and Engineering Controls:

• A temporary waterline will be established by tying in to the main waterline near the water treatment house and run up past the top of the Mill Building and down the northern slope.

• A decontamination facility will be located near the top of Mill.

o Canopy for weather, if needed.

o Garbage cans and liners o Wet wipes o Duct tape o Water buckets and Hudson sprayer for decontamination.

• Half-face Respirators with combo Mercury vapor/particulate cartridges.

• Tyvek suits with hoods

• Helmets while winching

• Eye protection, face shields

• Heavy duty clothing such as insulated Carhartt-type bibs and coats.

• Leather gloves for winch/cable work

• Rubber gloves for digging

• Rubber boots with safety toes.

Rescue gear for potential steep angle rescue will be staged near top of Mill prepared for quick deployment. Greg Runyan in charge of rescue Ops.

Schedule:

Sept. 30:

• Tim drives to Kennecott.

• Run waterline to site. Hose down soil/set up sprinkler.

• Stage materials for deck pads, shoring and scaffold pads at top of Mill.

• Stage winch, generator, rigging materials at top of Mill.

• Photo document site before and artifact or ground disturbance.

• Tim leads explosives awareness training for project crew (1 hour?)

October 1:

• Explosives ID briefing led by Tim.

• Last minute staging and prep.

• Review plan and get everyone’s approval.

• Commence work, plan Lunch and other breaks.

• Stop all work by 4:30 to allow time to decon and shower.

• Re-asses plan for following day’s activities.

October 2:

• Review previous day’s activity and address additional concerns.

• Complete project or plan third day??