AMEND006 Specifications 20200729.pdf

PDF 365 KB Posted

Attached to
USFS Colorado Springs Air Tanker Base
Solicitation number
1282BH20R0003
Issued by

About this file

This document outlines specifications for a construction project to build a new USDA Forest Service air tanker base in Colorado Springs, Colorado. The project involves constructing new buildings including an operations building and retardant storage building, concrete pavement, asphalt, utilities, site drainage, and landscaping. The specifications cover requirements for various construction materials and methods including concrete, masonry, metals, wood, thermal and moisture protection, doors and windows, finishes, equipment, furnishings and more. The document also includes sections on earthwork, paving, utilities, and miscellaneous site elements. It establishes measurement and payment terms for 42 separate line items. The scheduled completion date is not specified.

View the file

Other files

File Type Posted
AMEND006 Drawings 20200729.pdf PDF
AMEND006 Bidder Questions FINAL PART2.pdf PDF
1282BH20R0003 Amendment6 SF30.pdf PDF
AMEND006 Bidder Questions FINAL PART1.pdf PDF
AMEND006 ScheduleOfItems COSATB 20200729.xlsx XLSX spreadsheet
AMEND006 QandA Amendment Instructions 20200729.docx DOCX document
Amendment5 SF30.pdf PDF
Am4 Attach06 DEICE - CCD 02_COMBINED_SIGNED.pdf PDF
Am4 Attach05 DEICE - CCD 01 COMPLETE_SIGNED.pdf PDF
Am4 Attach11 05.28.20 Sewer Addendum #1 and #2.pdf PDF
Am4 Attach03 Technical Requirements Briefing by Lacie.docx DOCX document
Am4 Attach10 01a. COSA USFS Wastewater Plans - Addendum#1.pdf PDF
Am4 Attach08 05.28.20 Water Addendum #2.pdf PDF
Am4 Attach09 COSA USFS Wastewater Plans COMPLETE.pdf PDF
Am4 Attach07 COSA USFS Water Plans COMPLETE.pdf PDF
Amendment04 SF30.pdf PDF
Am4 Attach02 presolicitation attendees.docx DOCX document
Am4 Attach04 20200212 COS DEICE IFC PLANS.pdf PDF
Am4 Attach01 Preproposal Conference Agenda.docx DOCX document
Amendment3 SF30.pdf PDF
Amendment3 Attach_02_COSATB_SPECIFICATIONS COMBINED_20191023_20200430 v2.pdf PDF
AMENDMENT2 1282BH20R0003.pdf PDF
AMENDMENT1 1282BH20R0003.pdf PDF
Solicitation v2.pdf PDF
Attach_04_ScheduleOfItems_COSATB.xlsx XLSX spreadsheet
SF1442 Solicitation.pdf PDF
Attach_02_COSATB_SPECIFICATIONS COMBINED_20191023_20200430.pdf PDF
Attach_03_COS ATB Special Inspection Reqts.pdf PDF
Attach_01_COSATB_Final DWG w Cover Sheet 10-23-19.pdf PDF
Attach_07_Technical_Proposal_Submission_Aid.pdf PDF
Attach_05_EM_385_1_1_2014.pdf PDF
ATTACH_06_Wage_Determination.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONSTRUCTION SAFETY AND PHASING PLAN 010001.1

SECTION 010001

CONSTRUCTION SAFETY AND PHASING PLAN

This document supplements the Plans and Specifications and other Contract Documents prepared for the USDA Forest Service - Colorado Springs Airtanker Base Project. This document aids in identifying all aspects of the construction project that pose a potential safety hazard to airport operations and outlines respective mitigation procedures for each hazard. It provides all information necessary for the Airport Operations department to conduct airfield inspections and expeditiously identify and correct unsafe conditions during construction. The requirements outlined in this Construction Safety and Phasing Plan (CSPP) are developed from Advisory Circular 150/5370-2G.

1. Coordination

Safety Plan Compliance Document (SPCD): Prior to the Pre-Construction meeting, the Contractor will be required to submit a SPCD, as required by the Contract Documents, to the airport operator, describing how they will comply with the requirements in the CSPP and supply any details that could not be determined before contract award. The SPCD outline is attached in Appendix A.

Notice: The Contractor shall provide a minimum of 48 hours’ notice to the Contracting Officer of his desire to perform construction within each area and shall begin operations within these areas only upon receipt of authorization from the Contracting Officer.

Closures: Once work is commenced, Contractor shall steadily and diligently work on the project to ensure completion within specified contract time, or Liquidated Damages will be applied as described in this document.

Prior to beginning construction operations in any areas, all barricades and "temporary" closed markings shall be installed as shown in the Plans or designated by the Contracting Officer.

Airport Operations During Construction: It is the intention of the Owner to complete construction of the improvements within a minimum time period. The Owner will notify the necessary agencies as to the closure of affected operations at the Airport. The Contractor shall notify the Contracting Officer 48 hours in advance of any requested closure, so that the required Notice to Airmen (NOTAM's) can be arranged.

a. Contractor Progress Meetings

The Contractor and all affected parties will be required to meet a minimum of once per week during each week the Contractor is working on site, prior to any closure phasing change, and as necessary to discuss safety operations and changes in phase elements.

These meetings will help assure all construction personnel know of any applicable airport procedures and of any changes to those procedures that may affect their work.

b. Scope or Schedule Changes

Prior to any scope or schedule changes a safety meeting will be held, as necessary, with the Contractor and all affected parties to discuss any safety phase changes or other changes that may affect their work. Any scope or schedule changes that necessitate revisions to the CSPP will require review and approval by the airport operator and the FAA.

CONSTRUCTION SAFETY AND PHASING PLAN 010001.2

c. FAA ATO Coordination

FAA Air Traffic Organization (ATO) will be notified of all conditions that may adversely affect the operational safety of the airport via Notices to Airmen (NOTAM) and other methods, as appropriate. There are no anticipated improvements that will require a reimbursable agreement or flight inspection as part of this project.

2. Phasing

Plan: The construction phasing plan only includes one phase. The area of construction for this project has no adverse impacts to mitigate due to construction within aeronautical operational surfaces. Strict adherence to the provisions of the construction operations phasing plan by all personnel assigned to or visiting the construction site is mandatory for all construction projects.

In the event Contractor activities are not in conformance with the provisions of the construction operations plan, the Contractor shall immediately cease those operations violating provisions of the construction operations plan and conduct a safety meeting. The construction operations plan is open to input at safety meetings, but the Contracting Officer and ATO have the final determination of safe operations. The Contracting Officer may direct the Contractor, in writing, to immediately cease those operations involved in the violation of the provisions of this Construction Safety and Phasing Plan. The Contractor shall not resume construction operations until an appropriate action is taken as determined by the Resident Contracting Officer.

Although aircraft emergencies are quite rare, should one occur during the project, it is expected that lifesaving measures will take precedence over the convenience and expense of the Contractor.

On-going operations shall be kept neat and cleaning shall be continuous, so any required clean-up for use by an aircraft in distress will be minimal. Any costs for Contractor delays or inconvenience will be considered incidental costs of the project with no additional compensation by the Owner.

a. Phase Elements

Construction Activity

Impact on

AOA*

Planned Closure

Method of Marking

Detours

Commun-ications

Conditions for Closure

Phase I – Construct:

USFS Operations Building; Retardant Storage Building;

Concrete Retardant Containment Slab;

paved access and parking, utilities and other miscellaneous improvements

None

De-icing apron – east edge.

Fencing around the perimeter of the construction site – including the eastern most edge of the new de-icing apron.

None NOTAM Adjacent Construction in progress

*AOA = Airport Operations Areas NOTAM = Notice to Airmen

b. Construction Safety Drawings

The Construction Safety Drawings, titled “Construction Safety / Phasing Plan” and “Construction Access”, are included in the Construction Plans.

CONSTRUCTION SAFETY AND PHASING PLAN 010001.3

3. Areas and Operations Affected by the Construction Activity

Affected areas and proposed mitigation are listed in the Phase Elements Table above and the Construction Safety Drawings in the Construction Plans.

4. Protection of Navigational Aids (NAVAIDs)

All affected NAVAID’s will be shut down and locked out as part of the corresponding phase closure(s). Any FAA Owned NAVAID’s will be shut down by FAA personnel. Coordination of these closures has been / will be with the NAS Planning & Integration Team and Technical Operations Front Range SSC.

There are no anticipated impacts to the NAVAID’s as part of this project. Construction activities, materials/equipment storage, and vehicle parking will not be permitted near any functioning

NAVAID.

The construction limits do not contain existing FAA owned, operated, and maintained facilities or buried cable runs.

5. Contractor Access

All Contractor access, stockpile locations, material and staging area, and vehicle parking will be as referenced in the Construction Plans. Stockpiled material and equipment storage will not be permitted within the Object Free Area (OFA) of an operational runway or taxiway.

a. Location of Stockpiled Construction Materials

As stated above, all stockpile construction materials will be located as specified in the safety drawings attached in Construction Plans. No stockpiled materials will be permitted within the OFA of any runway or taxiway (closed or operational).

b. Vehicle and Pedestrian Operations

Vehicle parking areas will only be permitted in the Contractor staging areas as detailed in the safety drawing included in Construction Plans. No unauthorized entry of persons or vehicles onto the AOA will be permitted. All construction vehicles will be parked and serviced in the designated staging area(s), with no inactive equipment being parked within the OFA of a closed taxiway or runway. If it is necessary to leave specialized equipment within the OFA of a closed taxiway or runway at night, this will be coordinated with the ATO/ATC and the equipment shall be well lighted. NO WORK WHATSOEVER IS ANTICIPATED WITHIN ANY OFAs FOR THIS PROJECT.

Pedestrian operations will be permitted in work zones as necessary to complete the required work but will not be permitted as cross-airport transit.

CONSTRUCTION SAFETY AND PHASING PLAN 010001.4

1) Access and Haul Routes

Haul Routes and Maintenance: Any haul routes and staging areas for any Contractor's equipment will be designated prior to any work being done. Only these routes and staging areas shall be used, and unauthorized travel by haul vehicles will be prohibited.

Contractor employees involved in driving any vehicles outside the temporary construction fence but within the airport fence during the project must receive training from the Colorado Springs Airport Operations Staff. All contractor employees entering the airport well be briefed on airport safety.

Runway Crossings. The Contractors will not be permitted to have his operations cross active runways or taxiways unless approved in writing by the Contracting Officer. Any work in a runway or taxiway OFA will begin only after it is closed – both by NOTAM and “X” closure markings at the runway ends or low-level barricades at the designated points.

2) Marking and Lighting of Vehicles

All vehicles shall be lighted and/or marked in accordance with AC 150/5210-5D. All construction and support vehicles shall have standard white and orange-checkered flags or amber strobes mounted on these vehicles to be readily visible during daylight operations.

Any night-time work will require vehicles to have amber strobe lights.

3) Two-Way Radio Communication Procedures

The airport operator (Contracting Officer) and at least one member of the construction crew will monitor the airport radio frequency, (Ground Control 121.7 MHz (preferred) or Tower

119.9 MHz) during construction activities and provide direction to crews and aircraft as necessary to avoid conflicts. The personnel will observe the proper procedures for communications on the UNICOM frequency, including read back requirements, and proper phraseology.

Contractor employees involved in radio communications during the project must receive radio communications training from the Colorado Springs Airport Operations Staff.

6. Wildlife Management

a. Trash

All trash, including food scraps, will be collected and deposited in an enclosed trash bin(s) to prevent wildlife attraction.

b. Standing Water

Large areas of standing water that may attract wildlife will not be permitted on the airport property, unless otherwise authorized by the Contracting Officer.

c. Tall Grass and Seeds

Reclamation, including seeding and fertilizing, of any significantly disturbed areas will

CONSTRUCTION SAFETY AND PHASING PLAN 010001.5

occur after construction is completed. All seed will comply with the guidance in AC 150/5370-10, Standards for Specifying Construction of Airport, Item T-901, Seeding.

Broadcast seeding will not be permitted, to aid in preventing an avian attractant.

d. Poorly Maintained Fencing and Gates

All fencing and gates will be maintained during construction unless otherwise authorized by the Contracting Officer and approved by the FAA. As necessary / required, temporary gates and fencing will be installed. All gates will be left closed and locked when not in use to help assure no unauthorized use occurs.

e. Disruption of Existing Wildlife Habitat

If any wildlife is observed by any Contractor’s personnel, they shall immediately contact the Contracting Officer and appropriate actions will be taken. Typical avian and rodent sighting may not be reported, but any sighting that are deemed to be abnormal or of increased numbers shall also be reported.

The Contractor shall take no action as part of their operations that attract or habituate wildlife to the airport property. Best practices shall be followed to remove food sources (trash, food scraps, loose seed, etc.), attractants (standing water, etc.), and/or breaks in perimeter fencing (maintain fences/gates, provide temporary fence/gates, vigilantly close gates, etc.).

7. Foreign Object Debris (FOD) Management

Waste and Loose Material: Waste and loose material capable of causing damage to aircraft landing gears or propellers shall not be placed on active aircraft movement areas. Material tracked on these areas shall be removed continuously during all phases of the project.

8. Hazardous Materials (HAZMAT) Management

Any hazardous materials spillage from construction vehicles (gasoline, diesel fuel, oil, etc.) will require immediate action in accordance with State and Federal regulations. The vehicle shall be immediately repaired or removed from the project.

9. Notification of Construction Activities

a. Maintenance of a List of Responsible Representatives / Points of Contact

A list of responsible representatives and points of contact is included in Appendix B. This list will be provided to the FAA, Contractor, Subcontractors, ATO, and affected parties.

Before award of the construction bid, the successful bidder will be required to complete this list of all responsible personnel for the Prime Contractor and all Subcontractors.

b. Notices to Airmen (NOTAM)

The Contractor shall contact the Contracting Officer with all closure requests a minimum of 48-hours in advance of their proposed action. The Contracting Officer will coordinate

CONSTRUCTION SAFETY AND PHASING PLAN 010001.6

the issuance, maintenance, and cancellations of all Notices to Airmen (NOTAM) with the Owner / airport operator.

c. Emergency Notification Procedures

The emergency notification contacts for medical, firefighting, and police response are included in the Appendix B emergency contact sheet.

d. Coordination of Aircraft Rescue and Fire Fighting (ARFF) Personnel

Colorado Springs Airport does provide ARFF services. Care should be taken not to hinder access or movement of the fire-fighting equipment. Notification of construction activities to ARFF personnel will occur through the Contracting Officer and Airport Administration personnel.

e. Notification to the FAA

The Contracting Officer will keep the FAA ADO up-to-date on construction activities through weekly progress reports if requested and other periodic contacts.

Coordination of FAA Owned NAVAID’s will be with the NAS Planning & Integration Team. Emergency contact shall be 1-866-432-2622 (FAA Air Traffic Organization - Operations Control Center). A minimum of 45-days’ notice will be provided for the necessary shut-down period of these facilities. Updates will be provided, as necessary, regarding the construction scheduling and actual closure dates.

No impacts to FAA Owned NAVAID’s are anticipated.

10. Inspection Requirements

a. Daily Inspections

The Contracting Officer and Contractor will conduct twice daily inspections, and more frequently as needed, to ensure construction personnel comply with the CSPP and SPCD and that there are no altered construction activities that could create potential safety hazards. The checklist included in Appendix C will be used, at a minimum, to aid in verifying conformance.

b. Final Inspections

A final inspection will be held prior to reopening of any air operations area (AOA). The FAA will be invited to attend all final inspections conducted, including the FAA Airport Certification Safety Inspector (ACSI).

11. Underground Utilities

In any location the Contractor breaks ground to a depth of 1’ or more as part of the project, they will be responsible for checking with the owners of underground utilities regarding the location of

CONSTRUCTION SAFETY AND PHASING PLAN 010001.7

their underground lines. The Contractor will be required to fully coordinate his work with the agencies and to keep them informed of his construction activities so that these vital installations are always fully protected. The Contractor shall be solely responsible for any damage done to these installations due to failure to locate or to properly protect them when their location is known.

12. Penalties

In the event contractor activities are not in conformance with the provisions of the CSPP, the Contractor shall immediately cease those operations involved in the violation of the provisions of the CSPP and conduct a safety meeting. The Contracting Officer or Owner may direct the Contractor, in writing, to immediately cease those operations involved in the violation of the provisions of the CSPP. The Contractor shall not resume construction operations until an appropriate action is taken as determined by the Contracting Officer. Penalties will be as determined by the Contracting Officer and may include such items as rescission of driving privileges, installation of additional closure marking / signing, and / or denial of access to the

AOA.

13. Special Conditions

Not applicable to this project.

14. Runway and Taxiway Visual Aids.

a. General

The construction area will be clearly and visibly separated from the areas where aircraft will be operating by closure markings, as shown on the Construction Phasing Plan drawings included in the Construction Plans.

b. Markings

All marking will be in compliance with the standards of AC 150/5340-1, Standards for Airport Markings. All “temporarily” closed taxiways and aprons will have barricades (candles, cones, and /or low-level barricades) placed at all access points (outside of the connecting taxiway / runway object free areas). See also the Construction Phasing Plan drawings in the Construction Plans.

c. Lighting and Visual NAVAID’s

Temporary taxiway closure barricades remaining in place for overnight will be lighted with red flashing lights. Runways or taxiways remaining closed during nighttime or any low-visibility conditions will have their lighting systems shutdown and locked out during all closure periods, including runway lights, and associated approach lighting.

d. Signs

At any time a sign does not serve its normal function; it will be covered to prevent misdirecting pilots. Information signs will not be covered, as they will still serve their intended purpose.

CONSTRUCTION SAFETY AND PHASING PLAN 010001.8

15. Marking and Signs for Access Routes

Since the staging area (outside the airport fence) is adjacent to the access point, no marking or signing is needed. If the contractor chooses to secure access to a water sources within the airport security fence, the contractor shall coordinate with the Airport regarding protocol, marking or signing of that activity.

16. Hazard Marking and Lighting

Hazard marking and lighting prevents pilots from entering areas closed to aircraft and prevents construction personnel from entering areas open to aircraft. The spacing of barricades must be such that a breach is physically prevented, barring a deliberate act. If temporary taxiway closure barricades remain in place overnight, they will be lighted with red flashing lights, spaced no more than 4-feet apart. Runways or taxiways remaining closed during nighttime or any low-visibility conditions will have their lighting systems shutdown and locked out during all closure periods.

Hazard marking and lighting will also be placed to aid in identifying any open manholes, small areas under repair, stockpiled material, waste areas, and areas subject to jet blast, where applicable.

The Contractor will be required to have a person on call 24-hours a day for emergency maintenance of airport hazard lighting and barricades. The Contractor must file the contact person’s information with the airport operator and Contracting Officer. Lighting will be checked for proper operation at least once per day.

17. Work Zone Lighting for Nighttime Construction

Not anticipated for this project. If the Contractor proposes any night time operations, coordination with the Airport Management and ATC will be required and the lighting / signage requirements established at that time. Additional lighting and signage agreed upon for the convenience of the Contract will be at the Contractor’s expense and cannot interfere with aircraft operations.

18. Protection

a. Runway Safety Area (RSA)

No construction will occur within a runway safety area while the runway is open for aircraft operations. Neither open trenches nor excavations will be permitted within the RSA while the runway is open. Any disturbances of the runway shoulders due to construction must be returned to standard conditions prior to returning the construction zone to airport

CONSTRUCTION SAFETY AND PHASING PLAN 010001.9

operations.

No operations are anticipated within any RSA’s for this project.

b. Runway Object Free Area (ROFA)

Minimum Parking Distance: When not in use, equipment and materials will be parked or located a minimum of 800 feet from all runway centerlines or in the areas designated in the Plans.

Minimum Evacuation Distance: The Contractor will evacuate all equipment and men from the vicinity of the applicable runway a minimum distance of 800 feet from the runway centerline during landing and takeoff of aircraft.

Open Excavation and Barricades: Open trenches or excavations exceeding 3 inches in depth and 3 inches in width or stockpiled materials will not be permitted within 250 feet of centerline of any active runway. Coverings for open trenches or excavations shall be of sufficient strength to support the weight of the heaviest aircraft operating on the runway or taxiway. Lightweight barricades and/or flagging shall be used to identify the limits of construction near open trenches or excavations. The Contractor shall also light any open trenches or excavations with red lights during hours of restricted visibility or darkness.

No operations are anticipated within any ROFA’s for this project.

c. Taxiway Safety Area (TSA)

No construction will occur within a taxiway safety area while the taxiway is open for aircraft operations. Neither open trenches nor excavations will be permitted within the TSA while the taxiway is open.

No operations are anticipated within any TSA’s for this project.

d. Taxiway Object Free Area (TOFA)

Because wingtips regularly penetrate the taxiway object free area during normal operations, no construction will occur within a taxiway object free area while the taxiway is open for aircraft operations. Neither open trenches nor excavations will be permitted within the TOFA while the taxiway is open.

Minimum Parking Distance: When not in use, equipment and materials will be parked or located a minimum of 200 feet from taxiway centerlines or in the areas designated in the Plans.

No operations are anticipated within any TOFA’s for this project.

e. Obstacle Free Zone (OFZ)

Personnel, material, and / or equipment will not be permitted to penetrate the OFZ while the runway is open for aircraft operations.

CONSTRUCTION SAFETY AND PHASING PLAN 010001.10

f. Runway Approach / Departure Surfaces

All personnel, materials, and / or equipment will be required to clear the applicable threshold siting surfaces, in accordance with the approved Airport Layout Plan (ALP).

Construction in the runway approach / departure areas will be completed only when the runway is closed.

No work is anticipated in the Approach or Departure Surface areas for Runway 35R.

19. Other Limitations on Construction

a. Prohibitions

1) No use of tall equipment (cranes, concrete pumps, etc.) will be permitted unless a

7460-1 determination letter is issued for such equipment.

2) No use of open flame welding or torches will be permitted unless fire safety precautions are provided.

3) No use of electrical blasting caps on or within 1,000-feet of the airport property will be permitted.

4) No use of flare pots within the AOA will be permitted.

b. Restrictions No one shall enter the airport property without having received proper “badging” from the Airport Authority unless the person is escorted by a Contractor’s “badged” supervisor who maintains continual visual contact. The Gate Guard may also allow entry.

The Contractor is responsible for completing the badging process and associated costs for “badging” of their supervisors and subcontractor supervisors when necessary.

20. Liquidated Damages

Subject to the provisions of the Contract Documents, the Contractor will be assessed liquidated damages, upon failure to complete the work in the time specified. The liquidated damages shall include compensation to the Owner for non-use and unscheduled employment of the Contracting Officer or their representatives.

A. If the Contractor fails to complete the work within the time specified in the contract, the

Contractor shall pay liquidated damages to the Government in the amount of $842 for each calendar day of delay until the work is completed or accepted.

B. If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause. (FAR 52.211-12).

No charge will be made during any time extensions granted.

CONSTRUCTION SAFETY AND PHASING PLAN 010001.11

Appendix A

Safety Plan Compliance Document (SPCD) Outline

CONSTRUCTION SAFETY AND PHASING PLAN 010001.12

SAFETY PLAN COMPLIANCE DOCUMENT (SPCD)

- PLANNING FOR SAFETY -

This document supplements the Plans and Specifications and other Contract Documents prepared for the USDA Forest Service - Colorado Springs Airtanker Base Project. The Contractor shall complete this SPCD describing how they will comply with the requirements of the CSPP and supplying any details that could not be determined prior to contract award. The Owner will issue a Notice to Proceed only after the Contractor has successfully completed this SPCD. The SPCD shall follow the outline below, as developed from Advisory Circular 150/5370-2G.

The SPCD is a subset of the CSPP, in the same way a shop drawing is a subset of the Technical Specifications. The SPCD should not restate nor propose differences to provisions already addressed in the CSPP. Any construction practice that does not conform to the CSPP and SPCD will require safety document revisions and re-coordination with the airport Owner and FAA in advance of the proposed action.

1) Coordination Discuss details of proposed safety meetings with the airport operator and Contractor employees and subcontractors.

2) Phasing Provide proposed construction schedule elements, including:

a. Duration and proposed start date of each phase – required a minimum of two-weeks in advance

b. Daily start and finish of construction, including scheduled over-night shut-downs

c. Duration of construction activities

1) Normal runway/taxiway operations

2) Closed runway/taxiway operations

3) Areas of Operations Affected by the Construction Activity No supplemental information required.

4) Protection of Navigational Aids (NAVAIDs) Provide details of Taxiway A temporary lighting installation(s), including schedule, durations, methods of covering or shutting off any lights or signs which are not serving their intended purpose.

5) Contractor Access Provide the following:

a. Details on how the Contractor will maintain the integrity of the airport security fence (temporary fence, etc.)

b. Details of driver training or escort vehicles that shall be utilized for all construction personnel and material deliveries.

c. Radio Capabilities (types of radios and backup capabilities, who will be monitoring radios, details on how the Contractor will escort material delivery vehicles, etc.)

CONSTRUCTION SAFETY AND PHASING PLAN 010001.13

6) Wildlife Management Discuss methods and procedures to prevent wildlife reporting, and wildlife reporting procedures.

7) Foreign Object Debris (FOD) Management No supplemental information required.

8) Hazardous Material (HAZMAT) Management No supplemental information required.

9) Notifications of Construction Activities Provide the following:

a. Contractor points of contact

b. Contractor emergency contact

c. All Subcontractors emergency contacts

d. All radio operators

e. Safety contact officer

f. Personnel in charge of 24-hour lighting / barricade maintenance.

g. Listing of tall (crane, concrete pump, etc.) or other requested equipment proposed for use on the airport and the timeframe for submitting 7460-1 forms not previously submitted by the airport operator.

10) Inspection Requirements

11) Underground Utilities Discuss proposed methods of identifying and protecting underground utilities.

12) Penalties No supplemental information required.

13) Special Conditions No supplemental information required.

14) Runway and Taxiway Visual Aids No supplemental information required.

15) Marking and Signs for Access Routes Discuss proposed methods of training vehicle drivers of the allowed access routes.

16) Hazard Marking and Lighting Discuss proposed equipment, scheduling, and methods for identifying excavation areas that remain open and unattended.

17) Work Zone Lighting Not applicable to this project. No supplemental information is required.

CONSTRUCTION SAFETY AND PHASING PLAN 010001.14

18) Protection of Runway and Taxiway Safety Areas

19) Other Limitations on Construction No supplemental information required.

20) Contractor CSPP Compliance Statement Additionally, the Contractor will be required to submit a written statement of compliance documenting that he / she has read and will abide by the CSPP. The Contractor statement shall include the name of the Contractor, the title of the project CSPP, the approval date of the CSPP, and a reference to any supplemental information.

CONSTRUCTION SAFETY AND PHASING PLAN 010001.15

Contractor CSPP Compliance Statement

<Date>

Robert Peccia & Associates Attn: , Construction Contractor Representative PO Box 5653 Helena, MT 59604

I, <name and title>, for <Contractor name>, have read the USDA Forest Service - Colorado Springs Airtanker Base Project, Construction Safety and Phasing Plan (CSPP), approved on <date of FAA approval to be supplied by Contracting Officer>, and will abide by it as written and with the following additions as noted above in the supplied Safety Plan Compliance Document (SPCD).

Sincerely, <Name and Title> <Company>

CONSTRUCTION SAFETY AND PHASING PLAN 010001.16

Appendix B

Emergency Contract Notification Procedures Information

CONSTRUCTION SAFETY AND PHASING PLAN 010001.17

EMERGENCY TELEPHONE NUMBERS

Project Name USDA Forest Service - Colorado Springs Airtanker Base Project Project #

Frequency to monitor: 121.7 GROUND CONTROL and 119.9 MHz TOWER

The following are the business, cellular, and home telephone numbers where project key personnel can be reached at all times. In addition, the emergency telephone numbers of other vital agencies are listed:

CONTRACTORS PROJECT MANAGER / SUPERINTENDENT

Prime Contractor Contacts Safety Officer – 24-hr contact Project Manager Superintendent Foreman Paving Foreman Subcontractor Contacts Project Manager Superintendent Foreman

AIRPORT

Deputy Director Ops. and Const.

Airfield Foreman Airport Manager Airport Security

AARF

Air Traffic Control

USFS

Contracting Officer Contracting Officer Representative

A&E PROJECT MANAGER and RESIDENT PROJECT REPRESENTATIVE Robert Peccia & Assoc. 406-447-5000(w) 406-447-5036(f) Rick Donaldson, PM 406-447-5004(w) 406-439-4905(m) Craig Jenneskens 406-447-5025 (w) 406-439-0668 (m) Lance Bowser 406-447-5059(w) 406- 439-0674(m)

FLIGHT SERVICE (for NOTAMs) 1-877-487-6867 928-772-4390(f)

FAA DENVER AIRPORTS DISTRICT OFFICE 449-5257

OTHER EMERGENCY TELEPHONE NUMBERS

OSHA REPRESENTATIVE 1-800-772-1213

FIRE / HOSPITAL / POLICE / SHERIFF 911

LINE LOCATE 811

OTHER

All key personnel should have a copy of this information, and a copy should be posed in each field office in a prominent location.

CONSTRUCTION SAFETY AND PHASING PLAN 010001.18

Appendix C

Construction Project Daily Safety Inspection Checklist

CONSTRUCTION SAFETY AND PHASING PLAN 010001.19

Construction Project Daily Safety Inspection Checklist

The situations identified below are potentially hazardous conditions that may occur during airport construction projects. Safety area encroachments, unauthorized and improper ground vehicle operations, and unmarked or uncovered holes and trenches near aircraft operating surfaces pose the most prevalent threats to airport operational safety during airport construction projects. The list below is one tool that the airport operator or Contractor may use to aid in identifying and correcting potentially hazardous conditions.

Potentially Hazardous Conditions Item Action Required Or None

Excavation adjacent to runways, taxiways, and aprons improperly backfilled. □ Mounds of earth, construction materials, temporary structures, and other obstacles near any open runway, taxiway, or taxi lane; in the related Object Free area and aircraft approach or departure areas/zones; or obstructing any sign or marking.

Runway resurfacing projects resulting in lips exceeding 3 in (7.6 cm) from pavement edges and ends.

Heavy equipment (stationary or mobile) operating or idle near AOA, in runway approaches and departures areas, or in OFZ.

Equipment or material near NAVAIDs that may degrade or impair radiated signals and/or the monitoring of navigation and visual aids.

Unauthorized or improper vehicle operations in localizer or glide slope critical areas, resulting in electronic interference and/or facility shutdown.

Tall and especially relatively low visibility units (that is, equipment with slim profiles) — cranes, drills, and similar objects — located in critical areas, such as OFZ and approach zones.

Improperly positioned or malfunctioning lights or unlighted airport hazards, such as holes or excavations, on any apron, open taxiway, or open taxi lane or in a related safety, approach, or departure area.

CONSTRUCTION SAFETY AND PHASING PLAN 010001.20

Obstacles, loose pavement, trash, and other debris on or near AOA. Construction debris (gravel, sand, mud, paving materials) on airport pavements may result in aircraft propeller, turbine engine, or tire damage. Also, loose materials may blow about, potentially causing personal injury or equipment damage.

Inappropriate or poorly maintained fencing during construction intended to deter human and animal intrusions into the AOA. Fencing and other markings that are inadequate to separate construction areas from open AOA create aviation hazards.

Improper or inadequate marking or lighting of runways (especially thresholds that have been displaced or runways that have been closed) and taxiways that could cause pilot confusion and provide a potential for a runway incursion.

Inadequate or improper methods of marking, barricading, and lighting of temporarily closed portions of AOA create aviation hazards.

Wildlife attractants — such as trash (food scraps not collected from construction personnel activity), grass seeds, tall grass, or standing water — on or near airports.

Obliterated or faded temporary markings on active operational areas. □ Misleading or malfunctioning obstruction lights.

Unlighted or unmarked obstructions in the approach to any open runway pose aviation hazards.

Failure to issue, update, or cancel NOTAMs about airport or runway closures or other construction related airport conditions.

Failure to mark and identify utilities or power cables.

Damage to utilities and power cables during construction activity can result in the loss of runway / taxiway lighting; loss of navigation, visual, or approach aids; disruption of weather reporting services; and/or loss of communications.

Restrictions on ARFF access from fire stations to the runway / taxiway system or airport buildings. □

CONSTRUCTION SAFETY AND PHASING PLAN 010001.21

Lack of radio communications with construction vehicles in airport movement areas. □ Objects, regardless of whether they are marked or flagged, or activities anywhere on or near an airport that could be distracting, confusing, or alarming to pilots during aircraft operations.

Water, snow, dirt, debris, or other contaminants that temporarily obscure or derogate the visibility of runway/taxiway marking, lighting, and pavement edges. Any condition or factor that obscures or diminishes the visibility of areas under construction.

Spillage from vehicles (gasoline, diesel fuel, oil) on active pavement areas, such as runways, taxiways, aprons, and airport roadways.

Failure to maintain drainage system integrity during construction (for example, no temporary drainage provided when working on a drainage system).

Failure to provide for proper electrical lockout and tagging procedures. At larger airports with multiple maintenance shifts/workers, construction contractors should make provisions for coordinating work on circuits.

Failure to control dust. Consider limiting the amount of area from which the contractor is allowed to strip turf.

Exposed wiring that creates an electrocution or fire ignition hazard. Identify and secure wiring, and place it in conduit or bury it.

Site burning, which can cause possible obscuration. □ Construction work taking place outside of designated work areas and out of phase. □

SECTION 010250

DEFINITION OF CONTRACT ITEMS AND MEASUREMENT & PAYMENT

COLORADO SPRINGS AIRTANKER BASE

PSICC NATIONAL FORESTS AND GRASSLANDS

010250 - 1

DEFINITION OF CONTRACT ITEMS

AND MEASUREMENT & PAYMENT

PART 1 - GENERAL

1.1 SUMMARY

A. The intent of this section is to explain, in general; what is and what is not included in a contract item; the limits or cut-off points where one item ends and another begins; and method of measurements and basis of payment for work items listed in the Schedule of Items.

B. Work: Furnishing all labor, materials, equipment, and other incidentals necessary to successfully complete the project or any portion of it and carrying out all duties and obligations imposed by the contract on the Contractor.

C. Payment: For each individual item listed here and in the Schedule of Items, payment shall be full compensation for all work related to the particular item in accordance with these specifications and as shown on the drawings.

D. Measurement and payment for contract work shall be made only for and under those pay items included in the Schedule of Items. All other work and materials shall be considered incidental or as included in the payment for items shown.

1.2 UNITS OF MEASUREMENT

A. Payment shall be by units defined and determined according to U.S. Standard measure and by the following:

B. Lump Sum: Do not measure directly. The bid amount is complete payment for all work described in the contract and necessary to complete the work for that item.

PART 2 - METHOD OF MEASUREMENT

2.1 GENERAL

A. One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:

COLORADO SPRINGS AIRTANKER BASE

PSICC NATIONAL FORESTS AND GRASSLANDS

010250 - 2

1. Lump Sum (LS): These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall be measured complete and in-place.

2. Cubic Yard (CY): These items are measured and paid by the cubic yard of material completed and in-place.

3. Square Feet (SF): These items are measured and paid by the square feet of material completed and in-place.

4. Lineal Foot (LF): These items are measured and paid by the lineal foot of material completed and in-place.

5. Square Face Feet (SFF): These items are measured and paid by the square feet of material installed on the face of a structural wall or similar, completed and in-place. For example, if stone veneer is placed on two sides of a site wall, the total quantity shown includes the total square footage for both sides of the wall, as well as the top and ends of the wall.

6. Each (EA): These items are measured and paid by each unit installed and in-place.

7. Ton (TON): These items are measured and paid by the ton (2,000 pounds) of material completed and in-place.

8. Acre (ACRE): These items are measured and paid by the acre of improvements completed and in-place.

PART 3 – DEFINITION OF CONTRACT ITEMS

3.1 SCHEDULE OF ITEMS

A. The project Schedule of Items organizes the contract items into Base Items and Optional Items. When a pay item is described as a Base Item, the description will be the same when that item or a similar item is included as an Optional Item. Provide item pricing for all items listed in the Schedule of Items. Contract award will be made for all Base Items. Those items listed as Optional Items will be awarded based on available project funding. The Optional Items are not listed in priority order and may be awarded in any combination of individual items.

COLORADO SPRINGS AIRTANKER BASE

PSICC NATIONAL FORESTS AND GRASSLANDS

010250 - 3

3.2 DEFINITION OF BASE ITEMS

A. Base Items:

1. Base Item #1: Mobilization, Bonding, Insurance, General Conditions

a. Measurement: This item is measured as a lump sum (LS) quantity.

b. Payment: Payment shall be made at the contract unit price bid for the lump sum bid item shown in the Schedule of Items and shall include all materials, equipment, labor and incidentals required to perform all operations necessary for the movement of personnel, equipment, supplies and incidentals to the project site, and for all other work and operations that must be performed or that cause costs to be incurred prior to beginning work on the various items on the project site, providing required bonding, insurance and construction submittals, quality control, testing, construction surveying & staking, as-built record drawings, etc.

2. Base Item # 2: Concrete – Building Footings

a. Measurement: This item is measured by the cubic yard (CY).

b. Payment: Payment shall be made at the contract unit price shown in the Schedule of Items per cubic yard of concrete placed. Work shall include all materials, equipment, labor and incidentals required as shown on the drawings and specifications. Item includes subgrade preparation; steel reinforcement; and cast-in-place concrete including forms and placement.

3. Base Item # 3: Concrete - Building Foundation Walls

a. Measurement: This item is measured by the square foot (SF).

b. Payment: Payment shall be made at the contract unit price shown in the Schedule of Items per square foot of concrete placed. Work shall include all materials, equipment, labor and incidentals required as shown on the drawings and specifications. Item includes steel reinforcement;

dampproofing; and cast-in-place concrete including forms and placement.

4. Base Item # 4: Concrete – Building Interior Slab on Grade

a. Measurement: This item is measured by the square foot (SF).

b. Payment: Payment shall be made at the contract unit price shown in the Schedule of Items per square foot of concrete slab placed and finished. It includes 4-inch and 6-inch slabs and 4” Slab on Deck. Work shall include all materials, equipment, labor and incidentals required as shown on the drawings and specifications. Item includes subgrade preparation; gravel base, vapor retarder; steel reinforcement; cast-in-place concrete including forms and placement; and texturing and surface finishing.

COLORADO SPRINGS AIRTANKER BASE

PSICC NATIONAL FORESTS AND GRASSLANDS

010250 - 4

5. Base Item # 5: Concrete – Shade Structure Footings and Piers

a. Measurement: This item is measured by the cubic yard (CY).

b. Payment: Payment shall be made at the contract unit price shown in the Schedule of Items per cubic yard of concrete placed. Work shall include all materials, equipment, labor and incidentals required as shown on the drawings and specifications. Item includes subgrade preparation; steel reinforcement; and cast-in-place concrete including forms and placement.

6. Base Item # 6: Concrete – Reserved.

a. Measurement: Reserved.

b. Payment: Reserved.

7. Base Item # 7: Concrete – Foundation Walls for Site Walls

a. Measurement: This item is measured by the cubic yard (CY).

b. Payment: Payment shall be made at the contract unit price shown in the Schedule of Items per cubic yard of concrete placed. Cutting and repair of adjacent apron shoulder is considered incidental to this work. Work shall include all materials, equipment, labor and incidentals required as shown on the drawings and specifications. Item includes subgrade preparation;

steel reinforcement; and cast-in-place concrete including forms and placement.

8. Base Item # 8: Metals – Architectural

a. Measurement: This item is measured as a lump sum (LS) quantity.

b. Payment: Payment shall be made at the contract unit price bid for the lump sum bid item shown in the Schedule of Items. Work shall include all materials, equipment, labor and incidentals required as shown on the drawings and specifications. Item includes assembly and construction of pan and grating stairs; pipe, tube and decorative railings; including all required fasteners, hardware and related appurtenances.

9. Base Item # 9: Metals – Structural

a. Measurement: This item is measured as a lump sum (LS) quantity.

b. Payment: Payment shall be made at the contract unit price bid for the lump sum bid item shown in the Schedule of Items. Work shall include all materials, equipment, labor and incidentals required as shown on the drawings and specifications. Item includes assembly and construction of the complete steel roof deck assembly, including all required fasteners, hardware and related appurtenances.

COLORADO SPRINGS AIRTANKER BASE

PSICC NATIONAL FORESTS AND GRASSLANDS

010250 - 5

10. Base Item # 10: Wood – Structural – Storage Building

a. Measurement: This item is measured as a lump sum (LS) quantity.

b. Payment: Payment shall be made at the contract unit price bid for the lump sum bid item shown in the Schedule of Items. Work shall include all materials, equipment, labor and incidentals required as shown on the drawings and specifications. Item includes assembly and construction of the complete mezzanine assembly, including all required fasteners, hardware and related appurtenances.

11. Base Item # 11: Thermal and Moisture Protection

a. Measurement: This item is measured as a lump sum (LS) quantity.

b. Payment: Payment shall be made at the contract unit price bid for the lump sum bid item shown in the Schedule of Items. Work shall include all materials, equipment, labor and incidentals required as shown on the drawings and specifications. Item includes air barrier materials;

waterproofing; insulation; metal roofing assembly; underlayment;

drainage mat; metal siding; metal fascia; rain channels and chains;

sealants, etc.

12. Base Item # 12: Doors and Windows

a. Measurement: This item is measured as a lump sum (LS) quantity.

b. Payment: Payment shall be made at the contract unit price bid for the lump sum bid item shown in the Schedule of Items. Work shall include all materials, equipment, labor and incidentals required as shown on the drawings and specifications. Item includes all doors and windows on the new Visitor Center Building; frames; glazing; exterior doors; interior doors; overhead door; storefront assemblies; door and window hardware;

and steel breezeway gate assemblies.

13. Base Item # 13: Finishes and Miscellaneous Interior

a. Measurement: This item is measured as a lump sum (LS) quantity.

b. Payment: Payment shall be made at the contract unit price bid for the lump sum bid item shown in the Schedule of Items. Work shall include all materials, equipment, labor and incidentals required as shown on the drawings and specifications. Item includes interior building finishes; and other miscellaneous interior items not specifically included in other bid items.

14. Base Item # 14: Specialties

COLORADO SPRINGS AIRTANKER BASE

PSICC NATIONAL FORESTS AND GRASSLANDS

010250 - 6

b. Payment: Payment shall be made at the contract unit price bid for the lump sum bid item shown in the Schedule of Items. Work shall include all materials, equipment, labor and incidentals required as shown on the drawings and specifications. Item includes fire extinguishers and cabinets;

mechanical louvers; metal building systems; and building signage.

15. Base Item # 15: Equipment (Elevator)

a. Measurement: This item is measured as a lump sum (LS) quantity.

b. Payment: Payment shall be made at the contract unit price bid for the lump sum bid item shown in the Schedule of Items. Work shall include all materials, equipment, labor and incidentals required as shown on the drawings and specifications.

16. Base Item # 16: Furnishings (FF&E Not Included)

a. Measurement: This item is measured as a lump sum (LS) quantity.

b. Payment: Payment shall be made at the contract unit price bid for the lump sum bid item shown in the Schedule of Items. Work shall include all materials, equipment, labor and incidentals required as shown on the drawings and specifications.

17. Base Bid Item # 17: HVAC – Operations Building

a. Measurement: This item is measured as a lump sum (LS) quantity.

b. Payment: Payment shall be made at the contract unit price bid for the lump sum bid item shown in the Schedule of Items. Work shall include all materials, equipment, labor and incidentals required as shown on the drawings and specifications. Item includes installation of HVAC equipment, air outlets and inlets, ducts and accessories, refrigeration piping, fuel gas piping, mechanical insulation, hangers and supports, testing adjusting and balancing, and start-up testing and commissioning.

18. Base Bid Item # 18: HVAC – Retardant Storage Building

a. Measurement: This item is measured as a lump sum (LS) quantity.

b. Payment: Payment shall be made at the contract unit price bid for the lump sum bid item shown in the Schedule of Items. Work shall include all materials, equipment, labor and incidentals required as shown on the drawings and specifications. Item includes installation of HVAC equipment, air outlets and inlets, ducts and accessories, refrigeration piping, fuel gas piping, mechanical insulation, hangers and supports, testing adjusting and balancing, and start-up testing and commissioning.

COLORADO SPRINGS AIRTANKER BASE

PSICC NATIONAL FORESTS AND GRASSLANDS

010250 - 7

Item excludes items listed in HVAC – Retardant Store Building Heat Pumps & Electric Heaters.

19. Base Bid Item # 19: HVAC – Retardant Storage Building Heat Pumps & Electric Heaters

a. Measurement: This item is measured by each (EA) unit installed.

b. Payment: Payment shall be made at the contract unit price bid for each bid item shown in the Schedule of Items for each heat pump and electric heater installed.