Am4 Attach03 Technical Requirements Briefing by Lacie.docx

DOCX document 22 KB Posted

Attached to
USFS Colorado Springs Air Tanker Base
Solicitation number
1282BH20R0003
Issued by

About this file

This document contains notes from a technical requirements briefing for the construction of an operations building, retardant mixing plant, and retardant storage building at the USDA Forest Service Colorado Springs Airtanker Base.

Key details include specifications for construction safety and phasing plans, administrative requirements, quality control plans, and geotechnical investigation appendices. Questions asked at the briefing focused on permitting, fees, the notice to proceed date, safety officer duties, scheduling requirements, and availability of utilities. The federal contracting opportunity is for the USDA Forest Service Colorado Springs Airtanker Base project, set aside for small businesses. The solicitation number is 1282BH20R0003. Clarification on questions will be provided in an upcoming amendment with the goal of including all questions and answers at once.

View the file

Other files

File Type Posted
AMEND006 Drawings 20200729.pdf PDF
AMEND006 Bidder Questions FINAL PART2.pdf PDF
1282BH20R0003 Amendment6 SF30.pdf PDF
AMEND006 Bidder Questions FINAL PART1.pdf PDF
AMEND006 ScheduleOfItems COSATB 20200729.xlsx XLSX spreadsheet
AMEND006 QandA Amendment Instructions 20200729.docx DOCX document
AMEND006 Specifications 20200729.pdf PDF
Amendment5 SF30.pdf PDF
Am4 Attach06 DEICE - CCD 02_COMBINED_SIGNED.pdf PDF
Am4 Attach05 DEICE - CCD 01 COMPLETE_SIGNED.pdf PDF
Am4 Attach11 05.28.20 Sewer Addendum #1 and #2.pdf PDF
Am4 Attach10 01a. COSA USFS Wastewater Plans - Addendum#1.pdf PDF
Am4 Attach08 05.28.20 Water Addendum #2.pdf PDF
Am4 Attach09 COSA USFS Wastewater Plans COMPLETE.pdf PDF
Am4 Attach07 COSA USFS Water Plans COMPLETE.pdf PDF
Amendment04 SF30.pdf PDF
Am4 Attach02 presolicitation attendees.docx DOCX document
Am4 Attach04 20200212 COS DEICE IFC PLANS.pdf PDF
Am4 Attach01 Preproposal Conference Agenda.docx DOCX document
Amendment3 SF30.pdf PDF
Amendment3 Attach_02_COSATB_SPECIFICATIONS COMBINED_20191023_20200430 v2.pdf PDF
AMENDMENT2 1282BH20R0003.pdf PDF
AMENDMENT1 1282BH20R0003.pdf PDF
Solicitation v2.pdf PDF
Attach_04_ScheduleOfItems_COSATB.xlsx XLSX spreadsheet
SF1442 Solicitation.pdf PDF
Attach_02_COSATB_SPECIFICATIONS COMBINED_20191023_20200430.pdf PDF
Attach_03_COS ATB Special Inspection Reqts.pdf PDF
Attach_01_COSATB_Final DWG w Cover Sheet 10-23-19.pdf PDF
Attach_07_Technical_Proposal_Submission_Aid.pdf PDF
Attach_05_EM_385_1_1_2014.pdf PDF
ATTACH_06_Wage_Determination.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Technical Requirements Briefing by Lacie Drawings

· Constructing an Operations Building, a Retardant Mixing Plant, and a Retardant Storage Building and related site features.

· As noted on drawings, concrete apron and apron shoulder construction is by others and is anticipated to be completed prior to start of this project.

· Retardant plant mixing plant tanks and equipment will be installed by a separate contractor and a partner in this project.

Specifications

· Construction Safety and Phasing Plan & Safety Plan Compliance Document

· This section is intended to communicate expectations relative to working within the airport property.

· 010250 Definition of Contract Items and Measurement and Payment

· Aligns with Schedule of Items

· Defines the contract line items for the 41 base items and 3 optional items.

· Lump Sum Breakdowns are required before the first pay request.

· 01 30 00 Administrative, General, and Special Requirements

· Pay close attention to this section. Some areas of importance we want to highlight today are:

· Commencement, Prosecution, and Completion of Work Specifies the Period of Performance.

· Preconstruction Conference

· Preconstruction, Progress and Completion Pictures

· As-Built Drawings

· O&M Manuals

· Partnering

· Accommodations for Government Representatives

· Time Extension for Weather

· Permissible Hours of Work

· 01 32 01.00 10 – Project Schedule

· Cost loading

· Project Schedule Detailed Requirements

· Periodic Schedule Update Meetings

· Government may not have access to P6. Primary purpose is to facilitate review and resolve issues as a team. This will also be required for the initial project schedule submissions

· P6 Mandatory Requirements

· 3.11 will not be required for this project.

· 01 33 00 – Submittal Procedures

· This is the general submittal expectations

· Submittal Exchange will be used for submittal transfers. Gvm’t will procure and set up submittal exchange program. Contractor still has primary responsibility in submittal management.

· 01 35 26 – Government Safety Requirements

· Please be aware the USACE EM385-1-1 is used as well as other referenced safety documents. EM-385-1-1 may be more restrictive than OSHA.

· Site Safety and Health Officer

· Pay particular to Load Handling Equipment

· 01400 Quality Requirements & 01 45 00.00 10 Quality Control

· These two sections work together.

· Quality Control Plan

· Quality Control Manager & CQC Personnel

· Control – Preparatory Phase, Initial Phase, Follow Up Phase

· Weekly Meetings

· Appendix A – Geotechnical Investigation

· Appendix B – Pikes Peak Regional Asphalt Paving Specifications.

· Attachment – Special Inspection Requirements includes additional information on soils, concrete, and steel/ weld testing inspections and requirements.

Questions Notes from Lacie:

Q. Will this be permitted by Pikes Peak Regional Building Department? Will be addressed in Amendment Five.

Q. Who will pay fee? Will be addressed in Amendment Five.

Q. When do we anticipate NTP relative to bids due?

A. As promptly as possible after award. Award will be prior to this FY end.

Q. Does SSHO have to be on site at all times?

A. Ref 1.5.1.1: If the SSHO is off-site for a period longer than 24 hours, an equally-qualified alternate SSHO must be provided and must fulfill the same roles and responsibilities as the primary SSHO. When the SSHO is temporarily (up to 24 hours) off-site, a Designated Representative (DR), as identified in the AHA may be used in lieu of an Alternate SSHO, and must be on the project site at all times when work is being performed. Note that the DR is a collateral duty safety position, with safety duties in addition to their full-time occupation.

Q. Are PM, SSHO, and QCM separate duties?

A. Read the collateral duties requirement in the safety spec.

Red 1.5.1.1.1: The SSHO may also serve as the Quality Control Manager. The SSHO may also serve as the Superintendent. Assignments of collateral duties shall not affect the fulfillment of the individual role of SSHO, QCM, and Superintendent. If the fulfillment of roles is negatively affected by the collateral duties, then the allowance for collateral duties may be retraced by the CO and the Contractor shall acquire a separate individual for this role at no additional cost to the Government.

Q. Is the project scheduler required?

A. Requirements are in schedule spec, added by Amen 0003 Q. Are water and electric available at site? Are they free? Will be addressed in Amendment Five.

Q. Project is a full small business set aside, so if a large business submits, they would either need a JV or a teaming agreement in place. Does USDA requirement teaming agreement or JV be approved by SBA prior to submittal?

A. Yes.

Q. Will USACE inspectors be on site?

A. Inspector we are planning for is a USACE inspector. Also, I was a USACE COR.

Q. 013201 – 3.11 references QCS/RMS. Does that apply?

A. RMS and QCS will NOT be used for this project. Submittal exchange will be the program.

Government will pay for submittal exchange. Contractor does not have to pay those costs.

Q. Will we extend the questions and answers period?

A. We do not plan to at this time. If you do have additional questions, submit them in writing and we will consider them up until we issue the amendment. Questions asked during this meeting do not need to be resubmitted in writing.

Q. Where does RFP state that this is a small business set aside project?

A. Clauses in section I. FAR 52.219-6.

Q. On going site work, there is a pad built ands one sills completed. At what state will the grading be accomplished to? Drawings show original grades on site but that is not how they will receive the site. How will they receive the site.

A. We will provide the plans for that project. When we issue those, we will also include out expectations for use with those plans. Plans provided in Amendment Four.

Q. What is the expectation for this contractor to complete the engineered fills under the structures of this projects?

A. C-201, note 3. Clarifies this. Confirmation and Question will be included in Amendment Five.

Q. When do we expect amendment with answers to questions to be out?

A. Next week or week after. Goals is to provide all Q&A at once, along with airport plans.

Q. “Hygiene Questions” – SF vs CY in bid questions.

A. Christina said – point these out to us in writing.

Q. What taxing entities are relative?

A. We will get Colorado state tax exemption, so state tax and local tax exempt. No Federal Tax. So, tax exempt project. CORRECTION. The tax exemption on this project that the awardee may apply for includes only state taxes. This was confirmed after the meeting. Exemption forms will be provided to the awarded contractor at the time of award.

Q. What Tap fees will the contractor be responsible for (water, sewer, gas, electric)?

A. Will be addressed in Amendment Five.

Q. Will there be a sign in sheet distributed?

A. The attendee names shall be submitted to Christina Schofield at Christina.schofield@usda.gov and will be issued via amendment. All offeror attendees must email Business Name, Name of Attendees, Email, and Telephone #s to Christina