12445125R0002 004.pdf
PDF 577 KB Posted
- Attached to
- USDA-FS GWJ NF Call for Quals Design-Build Virginia Creeper Bridge(s) /Trail(s) Reconstruction
- Solicitation number
- 12445125R0002
- Issued by
-
Department of Agriculture Forest Service
About this file
This document is an Amendment (Amendment 004) to a federal solicitation for the USDA Forest Service's Virginia Creeper Trail (VCT) Phase II Design-Build Rehabilitation project. The amendment incorporates Questions and Answers from 08082025 and updates several key contract details, including:
Key project dates include a site visit from 11-14 August 2025, a proposal submittal deadline of 09 September 2025 at 1300 hours ET, and a virtual presentation on 16 September 2025. The last day for questions is 22 August 2025. The government will offer a temporary bridge for contractor use during the contract. A notable change involves correcting the general liability insurance clause from "500K*500K per occurrence" to "500K per occurrence". The project involves rehabilitating bridges and trail sections along the Virginia Creeper Trail, with specific requirements for design, materials, and construction approaches that prioritize durability, aesthetic considerations, and minimal environmental impact.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
12445125R0002 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
ATLANTA GA 30309-2449
STE 876S
1720 PEACHTREE ST NW
USDA-FS CSA EAST 11
05/22/20250004
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
05/22/2025
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of Amendment 004 is to incorporate Questions and Answers as of 08082025 due to the technical nature of the questions. In addition, the following clause updates are made:
- 22 Aug 2025: Last Day for Questions
- Section H.1 Insurance, Paragraph (b)(1) General Liability. Correct (2) from 500K*500K per occurrence to read 500K per occurrence
SCHEDULE Remains Unchanged:
-- 11-14 AUG 2025: SITE VISIT - Date: 11-14 Aug 2025 Preproposal Conference/Site Visit /Time: 0800- 1600 ET -- 09 SEP 2025: PROPOSAL SUBMITTAL DEADLINE 09 SEP 2025, 1300hrs ET; INCLUDE READ AHEAD FOR PRESENTATION -- 16 SEP 2025: PRESENTATION (VIRTUAL) - 16 SEP 2025; per calendar invitations sent
- Government Furnished Property (GFP) FAR 52.245-1 -- The USDA-FS offers the contractor use of a temporary bridge for use during this contract. See attached construction specifications for the bridge in possession of the government.
All other terms and conditions remain unchanged.
Attachment:
12445125R0002 Phase II Questions Asked 08082025
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
STEVEN J. ALVES
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
X 1 salves Highlight salves Highlight
COMMENTS MATRIX FOR USDA-FS ISSUANCES: 12445125R0002 GWJ VCT Phase II Design-Build Rehabilitation
(Please read instructions on back before completing form.)
# CLASS
COMPONENT AND
POC NAME, PHONE,
AND E-MAIL
PAGE PARA COMMENT
TYPE (C/S) COMMENTS, JUSTIFICATION, AND ORIGINATOR JUSTIFICATION FOR RESOLUTION
A/ R/ P
SD FORM 818, JAN 09 PREVIOUS EDITION IS OBSOLETE
Last day for Phase II RFP questions 22 Aug 2025
SITE VISIT SCHEDULE / LOCATION UPDATES
*ID Required: Day 1 Rally Point: Unchanged from Notice (11 Aug 25/ 0800 Caboose) *ID Required: Day 2 Rally Point: unchanged from Notice (12 Aug 25/ 0800 Caboose) Day 3: CHANGED 13 Aug 2025.
*ID Required: The Damascus Old Mill Inn located at 215 Imboden St, Damascus, VA 24236, will be the meeting location for the contractor Q&A session from 0800 – 1200 EST Wednesday August 13 after the 2 field days (Aug 11 and 12). There is no limit to Prime Contractor/sponsored subcontractor attendance on the conference day at the Damascus Inn on Wednesday August 13.
*ID- Prime Contractor or Sponsored Subcontractor Requested
07/31/2025
Bidder Comment: Is there a limit to how many people can attend?
Resolution: Each contractor will be limited to one vehicle during the tour on Aug 11 and Aug 12, due to the lack of safe turn-round spots and parking. All driving locations on the tour will be accessible using a standard passenger vehicle, although vans or other vehicles are totally appropriate.
2 Email
Bidder Comment: The agenda references walk/ride. Is there more details on the “ride.” Does the USFS plan some sort of transport, or should we be making provisions for some sort of transport beyond walking?
Resolution: Each contractor will be limited to one vehicle during the tour on Aug 11 and Aug 12, due to the lack of safe turn-round spots and parking. August 11th will be a day of driving, ensuring the locations where the trail and construction staging areas are accessible by car can be viewed.
The locations that can be accessed for the entirety of the trail will be visited. August 12th will be a day for hiking to more damaged locations, with less driving. At the conclusion of Monday and start of Tuesday hike locations will be determined based on group interest in certain locations from the Monday canvassing. All driving locations on the tour will be accessible using a standard passenger vehicle, although vans or other vehicles are totally appropriate.
3 07/31/2025
Bidder Comment: Like the above, is the USFS planning on transporting people to the various access points on the trail or do we need to prepare to provide transportation for our personnel between access points Resolution: Each contractor will be limited to one vehicle during the tour on Aug 11 and Aug 12, due to the lack of safe turn-round spots and parking. All driving locations on the tour will be accessible using a standard passenger vehicle, although vans or other vehicles are totally appropriate. USFS will not provide transport. Contractors limited to one vehicle will follow the USFS https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.bing.com%2Fck%2Fa%3F!%26%26p%3Daedd752f20f977de23db9a78c23adeb338fbe06e860571c9a3ab3e1c58a310e6JmltdHM9MTc1MzkyMDAwMA%26ptn%3D3%26ver%3D2%26hsh%3D4%26fclid%3D1fbc628d-2d3d-6aac-0c20-74ba2c8b6b52%26u%3Da1L21hcHM_Jm1lcGk9MTA5fn5Ub3BPZlBhZ2V-QWRkcmVzc19MaW5rJnR5PTE4JnE9RGFtYXNjdXMlMjBPbGQlMjBNaWxsJTIwSW5uJnNzPXlwaWQuWU44NzN4MTE0ODMxNTIzJnBwb2lzPTM2LjYzNjM2MDE2ODQ1NzAzXy04MS43ODk4NjM1ODY0MjU3OF9EYW1hc2N1cyUyME9sZCUyME1pbGwlMjBJbm5fWU44NzN4MTE0ODMxNTIzfiZjcD0zNi42MzYzNn4tODEuNzg5ODY0JnY9MiZzVj0xJkZPUk09TVBTUlBM%26ntb%3D1&data=05%7C02%7Csteven.alves%40usda.gov%7Ccdd6d84025dd446e58fd08ddd057c966%7Ced5b36e701ee4ebc867ee03cfa0d4697%7C1%7C0%7C638895797644654633%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=6x%2B2owZEPjKvDkAv8pKP%2FK1saqhH%2F8ic7JRJWYWKsag%3D&reserved=0
# CLASS
COMPONENT AND
POC NAME, PHONE,
AND E-MAIL
PAGE PARA COMMENT
TYPE (C/S) COMMENTS, JUSTIFICATION, AND ORIGINATOR JUSTIFICATION FOR RESOLUTION
A/ vehicle during the tour. Self-guide is permitted with a visitor list so the USFS can notify Law Enforcement. This list will need to be provided by noon on Wednesday.
4 Email
Bidder Comment: Will all teams be traveling together in a large group or is the plan to split up into smaller groups for the site visit?
Resolution: All teams will be traveling in tandem on August 11th and 12th. Self-guide is permitted with a visitor list so the USFS can notify Law Enforcement. This list will need to be provided by noon on Wednesday, August 13th prior to departing. Each contractor will need to provide an attendance list for August 11th and 12th by COB Friday August 8th to the jessie.howard@usda and cc:
steven.alves@usda.gov
5 07/31/2025
Bidder Comment: The provided information references sturdy boots being required for the site visit. With many structures missing, and fording of streams required for full access to see the trail, does the USFS have any requirements or plans related to stream crossings as part of the site visit or do teams need to make provisions for this on their own?
Resolution: August 11th will largely be driving to accessible stop locations and included construction staging locations. Additionally, a temporary bridge at Straight Branch may be installed by Tuesday August 12th to provide better access to cross the creek. August 12th will be a day for more hiking to access and see more damaged trail locations.
if they want to go to see very many bridge locations, waders recommended.
Bidder Comment: If I understand the draft agenda the plan is to do the site visit the first two days with the pre-proposal conference on the third day. Is it acceptable to have more attendees at the conference that do not attend the site visit? Also, previous information indicated that virtual attendees may be allowed, is that still the case or will it only be in person for the pre-proposal conference?
Resolution: There is no limit to attendance on the conference day, Wednesday August 13 from 8 am to 12 pm. There will be a virtual option to attend this prime contractor/subcontractor only meeting. See calendar invite sent to prime contractors.
Bidder Comment: We understand that any Drone use must be coordinated through the Forest Supervisor, and that we need to provide a list of all team members attending this site visit. Are there any requirements for self-guided site visits outside of the week of Aug 11th?
Resolution: Onsite access is provided the week of August 11th exclusively to ensure safety of contractors and onsite contractors actively removing debris from the project site.
All teams will be traveling in tandem on August 11th and 12th. Self-guide is permitted with a visitor list so the USFS can notify Law Enforcement. This list will need to be provided by noon on Wednesday, August 13th prior to departing. Each contractor will need to provide an attendance list for August 11th and 12th by COB Friday August 8th to the jessie.howard@usda and cc:
steven.alves@usda.gov
8 Email 8/1/2025 Bidder Comment:
mailto:jessie.howard@usda
# CLASS
COMPONENT AND
POC NAME, PHONE,
AND E-MAIL
PAGE PARA COMMENT
TYPE (C/S) COMMENTS, JUSTIFICATION, AND ORIGINATOR JUSTIFICATION FOR RESOLUTION
A/
• Is it permissible to drill a water well directly on the Virginia Creeper Trail?
• If so, what permissions, permits, or environmental reviews are required prior to proceeding
• If drilling on the trail is not permitted, would it be acceptable to source water from a nearby private property, provided we obtain written permission from the landowner?
Resolution:
Drilling a well on the VCT trail for water to utilize during construction could be allowed. The Forest Service will require application for a Special Use Permit. The Forest may have specific restrictions on where such a well might go. The Forest may require that the well be properly abandoned once the project is complete if they do not have a use for it. In Virginia groundwater withdrawal is regulated by the Virginia Department of Environmental Quality (DEQ) under the Groundwater Management Act. Approval may depend on the amount of water being extracted and the length of time the extraction is required. If the well impacts surface water, a Virginia Water Protection Permit may also be required. Other potential permits could be (and not limited to) a Virginia Well Construction Permit, a Clean Water Act Section 404 Permit or other applicable local state or Federal permits.
Drilling a well on USFS property will likely trigger a NEPA review. Additionally, depending on where the well is placed a National Historic Preservation Act and an Endangered Species Act review might be warranted.
Alternatively, if the contractor makes an independent deal with a nearby private property to either drill a well or tap into an existing well then, USFS has no objections as long as all local, state and federal regulations are followed.
9 Email 8/1/2025
Bidder Comment: Per Attachment 08, Section M, Phase II General Submission Requirements for Phase II Request for Proposal states that “During Phase II, the most highly qualified firms will be issued a Request for Proposal (RFP), which will outline the remainder of the selection process requirements. The RFP will contain the requirements necessary for the most highly qualified Offerors to submit both a Technical Proposal and a Price Proposal during Phase II.”
Question: Does the USDA-FS intend to issue the updated Phase II RFP, or is the Contractor/Design Builder to assume Amendment 0003 serves as the Phase II RFP?
Resolution: As stated in Amendment 003, 12445125R0002 with all amendments is the RFP. Terms and conditions from Amendment 0002 remain unchanged. Deadlines for submittals and presentations remain unchanged from Amendment 002. You are now in Phase II.
10 Email 8/1/2025
Bidder Comment: Per Attachment 08, Section M, Phase II General Submission Requirements for Phase II Request for Proposal states “Those Offerors will be required to provide the necessary information to the USDA-FS within approximately 60 calendar days after receiving the RFP.”
Question: Phase I selection notifications were sent out on 7/29/2025 with the Phase II Proposal Submittal Deadline of 9/9/2025. Forty-two calendar days is a very limited amount of time for the
# CLASS
COMPONENT AND
POC NAME, PHONE,
AND E-MAIL
PAGE PARA COMMENT
TYPE (C/S) COMMENTS, JUSTIFICATION, AND ORIGINATOR JUSTIFICATION FOR RESOLUTION
A/
Design Build Contractors to provide a proposal along with fixed firm pricing for what is a significant Design Build Project. We request the Phase II Proposal Submittal Deadline be extended to 10/9/2025.
Resolution: The deadline remains unchanged.
11 Email 8/1/2025
Bidder Comment: Regarding the steel truss designed bridges, industry standards and best practices include details for rails that are integrally welded to structural steel members of the truss in the longest sections practicable. These industry standards meet FSH 7709.56b Ch. 80. Experience with steel rails attached in this way has shown them to be adequately durable with rare need for repair.
Removable 10’ sections will require additional fabrication and design time that may challenge the delivery goals of the project while returning little practical benefit. Please confirm the need for removable rail sections.
Resolution: The intent of making the railing easily replaceable is because one of the main areas on Forest Service trail bridges that are normally damaged is the railing. Typically, this comes from falling debris such as trees and tree limbs or from debris and flood water. If the railing is protected by the superstructure, such as would be the case with a truss, the falling debris should not be as much of an issue and the welded rail sections will be acceptable.
8/1/25
Bidder Comment: XXXX is interested in bidding on the USDA-FS GWJ Virginia Creeper Bridge and Trail Reconstruction Design-Build project as a subcontractor. Are we allowed to register for the Preproposal Conference/Site Visit scheduled for 11-14 Aug 2025?
Resolution: NO and YES. Subcontractors may attend the site visit BUT ONLY AS PART OF A PRIME CONTRACTOR TEAM. Your firm must clearly identify the prime contractor team you are part of (sponsoring prime contractor). This is to maintain the prime/subcontractor relationship and to comply with FAR 52.219-9. https://www.sba.gov/federal-contracting/contracting-guide/prime-subcontracting#:~:text=Large%20business%20contractors%20must%20ensure,Subcontract%20rep orting
8/3/2025
Bidder Comment: There is approx. 10 miles of trail each day scheduled to view on Monday and Tuesday - will this be a group tour with all teams and attendees travelling the corridor as a team? If not in a group format will our team be permitted to roam these trail sections freely?
Resolution: Each contractor will be limited to one vehicle during the tour on Aug 11 and Aug 12, due to the lack of safe turn-round spots and parking. August 11th will be a day of driving, ensuring the locations where the trail and construction staging areas are accessible by car can be viewed.
The locations that can be accessed for the entirety of the trail will be visited. August 12th will be a day for hiking to more damaged locations, with less driving. At the conclusion of Monday and start of Tuesday hike locations will be determined based on group interest in certain locations from the Monday canvassing. All driving locations on the tour will be accessible using a standard passenger vehicle, although vans or other vehicles are totally appropriate. There is no limit to attendance to https://www.sba.gov/federal-contracting/contracting-guide/prime-subcontracting#:%7E:text=Large%20business%20contractors%20must%20ensure,Subcontract%20reporting https://www.sba.gov/federal-contracting/contracting-guide/prime-subcontracting#:%7E:text=Large%20business%20contractors%20must%20ensure,Subcontract%20reporting https://www.sba.gov/federal-contracting/contracting-guide/prime-subcontracting#:%7E:text=Large%20business%20contractors%20must%20ensure,Subcontract%20reporting
# CLASS
COMPONENT AND
POC NAME, PHONE,
AND E-MAIL
PAGE PARA COMMENT
TYPE (C/S) COMMENTS, JUSTIFICATION, AND ORIGINATOR JUSTIFICATION FOR RESOLUTION
A/ the conference day at the Damascus Inn on Wednesday August 13. Contractors are then free to access the Trail for the afternoon of August 13, 14, and 15. No USFS transport will be provided.
Self-guide is permitted with a visitor list so the USFS can notify Law Enforcement. All teams will be traveling in tandem on August 11th and 12th. Self-guide is permitted with a visitor list so the USFS can notify Law Enforcement. This list will need to be provided by noon on Wednesday, August 13th prior to departing. Each contractor will need to provide an attendance list for August 11th and 12th by COB Friday August 8th to the jessie.howard@usda and cc: steven.alves@usda.gov
Bidder Comment: The attached site document outlines riding the trail will be permitted:
• Will the USFS be providing a means of riding the trail, or will this be up to our team to procure?
• Will ATV travel be permitted or possible on sections of the trail?
Resolution: The USFS will not provide transportation. One vehicle per contractor will be permitted on the tour August 11th and 12th. After 12 pm on August 13th through August 15th will be a self-guide opportunity for the contractor.
ATV use will not be permitted.
8/3/2025
Bidder Comment: August 13-15th Self-Guided Investigations
• When does this list need to be submitted?
• Will teams be allowed to travel the corridor if additional information is required outside of the week of 8/11/25?
Resolution: Self-guide is permitted with a visitor list so the USFS can notify Law Enforcement. All teams will be traveling in tandem on August 11th and 12th. Self-guide is permitted with a visitor list so the USFS can notify Law Enforcement. This list will need to be provided by noon on Wednesday, August 13th prior to departing. Each contractor will need to provide an attendance list for August 11th and 12th by COB Friday August 8th to the jessie.howard@usda and cc: steven.alves@usda.gov Onsite access is provided during the week of August 11th exclusively to ensure the safety of contractors and onsite contractors actively removing debris from the project site.
Bidder Comment: Drone Usage
• We would like to bring a drone to capture photos and videos of certain areas of the trail, who is the best POC to receive authorization to do this?
Resolution: Please coordinate with Jessie Howard, 540 492 1728. Jessie.howard@usda.gov
8/2/2025
Bidder Comment: I would like to be invited as a non-participating observer to the site visits to be conducted August 11-14 in Damascus, Virginia, for the three finalists in the reconstruction of the Virginia Creeper Trail.
https://sam.gov/workspace/contract/opp/067d60684ff049ae9bb436bc41a8e2c4/view You have graciously listed a website I do as well as a video I helped organize as resources for applicants:
mailto:Jessie.howard@usda.gov
# CLASS
COMPONENT AND
POC NAME, PHONE,
AND E-MAIL
PAGE PARA COMMENT
TYPE (C/S) COMMENTS, JUSTIFICATION, AND ORIGINATOR JUSTIFICATION FOR RESOLUTION
A/
Link Updated Date The Creeper Trail, Damascus VA: Documenting Hurricane Helene's Destruction Jun 8, 2025 The Destruction of the Virginia Creeper Trail Jun 8, 2025 We are also doing a "recovery" site both for local residents and those who wish to know what is going on with the rebuilding of the Creeper Trail. Rumors abound as you might imagine and it is our purpose to accurately portray what is happening. We do this through our website, https://www.vacreepertrail.us/recovery/, and through other media.
I would be a quiet observer at your site visits. I would, however, privately let the finalists know that if they need local information or volunteer assistance in getting set up for the rebuilding, we can provide a wealth of information on where to stay, restaurants, cleaning and other services in the area.
Resolution: This question has multiple parts:
1. Site Visit: The site visit on 11-14 Aug is only for the prime contractors and their subcontractors only. This is due to limited transportation to the actual VCT work locations and overall public safety in a declared disaster area. Site Visit Notes will be available on sam.gov following the meeting.
2. Interface with Prime Contractors: The release of the names of the three most highly qualified firms participating in Phase II was posted to SAM.GOV. You are encouraged to contact them directly.
3. Press Day: As you have pointed out, “Rumors abound”! PENDING
8/4/2025
Bidder Comment: Will there be a deadline for questions?
Resolution: Amendment 004 - 22 Aug 2025 will be the deadline.
8/4/2025
Bidder Comment: Can you confirm if all Q&A will be publicly shared as was in Phase I?
Resolution: Yes, the Q&As, Site Visit Notes and Attendance Roster will all be posted.
*Proprietary technical questions will be excluded as necessary
8/5/2025
Attachmen t 02
Section C
SOO
Version
06302025
Bidder Comment:
The SOO states, “Design of new and rehabilitated structures to have a service life of 75 years.”
Defining and achieving a target service life is based on design decisions, construction quality and regular inspection and maintenance. During design, our expectations would be to develop a project specific definition for service life and duration of the service life for replaceable and non-replaceable components. Routine maintenance would include the replacement of renewable elements. Non-replaceable elements will meet the 75-year service life requirement. Does this
# CLASS
COMPONENT AND
POC NAME, PHONE,
AND E-MAIL
PAGE PARA COMMENT
TYPE (C/S) COMMENTS, JUSTIFICATION, AND ORIGINATOR JUSTIFICATION FOR RESOLUTION
A/ approach align with your intent for new and rehabilitated structures meeting a 75-year service life?
Examples of renewable items are joints, coatings, and timber decking. Examples of non-replaceable elements would be primary structural elements beams, trusses, arches, abutments, bents and foundations.
Resolution: Definitions of terms not explicitly defined in handbooks, manuals, and regulations can be defined using engineering or construction industry definitions or standards. When using such definitions, please include the references used to make these determinations.
Section C
SOO
Version
06302025
31 of 43 Bidder Comment:
"The SOW Structure Design Parameters states, “Design of new and rehabilitated structures to have a service life of 75 years.” In Section C SOW Elements and Section 102 of the SOW (Site Specific Description of Work) certain structures are listed for rehabilitation: 16 (main span), 17 (main span if feasible), 21, 35 (if feasible), 36, 38 (if feasible), 39(if feasible), 42 and 43. In the time period required and with the lack of as built information, the Design Builder may not be able to certify the structure for the 75-year service life and will have to assume replacement of the structure is needed. In order to preserve the historic structures, reduce cost, improve schedules, and reduce environmental impacts, would the government consider a lower service life requirement for structures to be rehabilitated and remain?
Resolution: It is the preference of the USFS to reuse the superstructures that are listed in the scope of work where possible. To aid the teams to do this a 50-year design life for the reused portions of those structures will be acceptable.
t 8 page 13 of 18 Bidder Comment:
The Engineering Geologist or Geotechnical Engineer requirements only allow for a Professional Geologist licensed in the state of VA. There is not an option for a licensed Geotechnical Engineer.
The majority of the geotechnical design work (i.e., bridge foundation design, retaining wall design, slope stability analyses) on this project is best suited for an engineer, not a geologist. We request a geotechnical engineer registered in the state in VA also be an option to fill this role.
Resolution: A geotechnical engineer (or civil engineer with geotechnical experience) licensed in the Commonwealth of Virginia is acceptable.
Section C
SOO
Version 06302025
Bidder Comment:
The SOO references AASHTO requirements. Please confirm if the AASHTO GBF-5 Guide for Development of Bicycle Facilities is included in with project requirements. If so, please confirm the sections.
# CLASS
COMPONENT AND
POC NAME, PHONE,
AND E-MAIL
PAGE PARA COMMENT
TYPE (C/S) COMMENTS, JUSTIFICATION, AND ORIGINATOR JUSTIFICATION FOR RESOLUTION
A/
Resolution: Use applicable AASHTO requirements.
Section C
SOO
Version
05052025
Bidder Comment:
Regarding Q&A #88 - The final design exploration requirements conflict between USFS, VDOT and AASHTO design guides. The USFS Handbook 7709.56b "Transportation Structures Handbook Chapter 30 Site Surveys", Section 31 Foundation Investigations states "Investigations may range from visual observation of site conditions and mapping of geological conditions to test pits or extensive soil borings....", and "Where rock outcrops are present and drilling is not necessary to determine the extent of rock or its quality, ....". VDOT "Materials Manual of Instruction", Chapter III Geotechnical Engineering, Section 303, Table 3-1 requires a minimum of 2 borings per substructure for shallow foundations and 1 boring per substructure for deep foundations. AASHTO "LRFD Bridge Design Specifications", 10th Ed, 2024, Table 10.4.2-1 requires 1 boring per substructure for shallow and deep foundations. Please confirm that the USFS Handbook referenced above should be used to develop the final design geotechnical exploration program.
Resolution: The Forest Service Handbook does not give adequate guidance for these investigations.
VDOT Guidance is preferred. The Teams are ultimately responsible for conducting a professional investigation, but attached is a list, based on field observation, of what is generally minimally anticipated/acceptable for the bridge foundations. Issues during construction due to inadequate information due to lack of investigation will be the responsibility of the contractor. Additional boring will be required as outlined in the Scope of Work or as directed by the Team’s geotechnical engineers.
16 – No borings required for the reused concrete foundations. Assume they are on bedrock.
Minimum of 1 boring per new substructure unit.
17 – At least one boring per new substructure unit. At least 2 core holes at the existing concrete pier at the truss that has had prior issues. No borings required at the abutment near the pool unless the geotechnical engineer or the geologist note issues with long term stability of that foundation and the exposed rock face.
18 - At least 2 borings per new substructure. Alternative methods may be allowed for existing foundation.
19 - Visual/alternate methods of examinations of the pier footings will be allowed. At least 2 brings per new substructure.
20 – Exposed but dipping bedrock here. At least 2 core holes per substructure.
# CLASS
COMPONENT AND
POC NAME, PHONE,
AND E-MAIL
PAGE PARA COMMENT
TYPE (C/S) COMMENTS, JUSTIFICATION, AND ORIGINATOR JUSTIFICATION FOR RESOLUTION
A/
21 – Visual/alternate evaluations will be acceptable here for the existing concrete foundations. The rock line is erratic at this location. Certification and reuse of the existing concrete foundations will be allowed if the wooden components surrounding the bridge can be replaced without compromising the foundations. New foundations will require at least 2 borings per substructure.
Additional borings may be needed to replace the wooden components.
22– At least 2 borings per substructure.
23 - At least 2 borings per substructure
24 – Highly fractured and dipping bedrock here. 2 core holes per substructure unless you can do a dewaterd test pit with percussion holes to verify the bedrock.
25 - Large boulder field here. At least 1 core hole per substructure.
26 – Bedrock appears to be exposed here. Test pits/alternate methods may be acceptable here if proposed by the Geotech/geologist. Otherwise a minimum of 1 boring per substructure.
27 - At least 2 borings per substructure
28 – At least one core hole per side.
29 – Where bedrock is exposed and a geologist/Geotech accepts its competrence, no borings required. Otherwise at least one boring per substructure.
30-35 - At least 2 borings per substructure
36 – No borings required unless needed for abutment repair.
37 - At least 2 borings per substructure
38 – Visual/Alternative methods for evaluating the existing concrete foundations are acceptable.
At least 2 borings per new substructure.
39 - Visual/Alternative methods for evaluating the existing concrete foundations are acceptable. At least 2 borings per new substructure.
40 - At least 2 borings per substructure
# CLASS
COMPONENT AND
POC NAME, PHONE,
AND E-MAIL
PAGE PARA COMMENT
TYPE (C/S) COMMENTS, JUSTIFICATION, AND ORIGINATOR JUSTIFICATION FOR RESOLUTION
A/
41 – At least one core per substructure
42 – 43 – No borings required if the existing foundations are certified for reuse. Borings may be required for replacement of wood components/walls.
44 - Visual/Alternative methods for evaluating the foundations or 1 boring per side are acceptable.
45 – 48 - At least 2 borings per substructure
Section C
SOO
Version
06302025
Bidder Comment:
Structures are to be designed to be extremely resilient against future storm events. Please provide clarification on the definition/expectation for 'extremely'.
Resolution: the structures are required to be designed and built to withstand the effects of low frequency (e.g., probability less than 1% in any given year) weather events including hurricanes, snow storms, and ice storms. Definitions of terms not explicitly defined in handbooks, manuals, and regulations can be defined using engineering or construction industry definitions or standards.
When using such definitions, please include the references used to make these determinations.
Section C
SOO
Version
06302025
Bidder Comment:
All slopes at bridge ends are to be 2:1 slopes or flatter. Many of the existing slopes do not satisfy this requirement. Is this intended for locations where the existing substructure will remain?
Resolution: This requirement is intended for all bridge locations. Where this is infeasible due to existing topographic constraints, the constructed slope and the increased scour countermeasures shall be noted on the design.
Section C
SOO
Version
06302025
32 of 41 Bidder Comment:
Steel truss top of rail is allowed to be 48 inches. Is this to imply that all trusses must have a minimum of 48" above top of decking?
Resolution: The height of the trusses are not specified. The truss height will be determined for each structure based on load rating and span requirements. The height requirement applies to safety railings.
Section C
31 of 41 Bidder Comment:
FPL-GTR-260 allows an asphalt wearing surface with waterproofing membrane. Is this approach allowable in lieu of wood preservatives for deck surfaces?
Resolution: No.
# CLASS
COMPONENT AND
POC NAME, PHONE,
AND E-MAIL
PAGE PARA COMMENT
TYPE (C/S) COMMENTS, JUSTIFICATION, AND ORIGINATOR JUSTIFICATION FOR RESOLUTION
A/
SOO
Version
06302025
Section C
SOO
Version
06302025
Bidder Comment:
Railing is to comply with FSH 7709.56b Ch, 80. This spec makes no mention of railing. Please provide guidance on railing expectations outside of listed elsewhere in the SOO.
Resolution: the railing specifications are located in FSH 7709.56b Ch, 80, section 82.4 - Trail Bridge User Barriers, pages 7-9.
Section C
SOO
Version
06302025
Bidder Comment:
What finish is required on concrete decking? Broom finish or other?
Resolution: Select a finish that is aseptically pleasing and meets the requirements of AASHTO for bridge decks. Ensure that there is acceptable skid resistance, durability and drainage. Broom finish is acceptable.
Section C
SOO
Version
06302025
Bidder Comment:
Please provide the specific locations of previously disturbed areas related to repairing US 58 and debris removal in the VCNRT corridor, including staging areas and access routes, so that the Design- Build contractor can include these in the project existing conditions and collocate disturbance areas for trail reconstruction. Please also provide the results of archaeological and biological monitoring completed during these activities.
Resolution: The separate debris removal contract is currently active. The Forest can provide a map of existing staging areas and access routes. No archeological or biological monitoring reports have been completed by the current debris removal contractor. When these reports are completed, they will be made available.
Section C
SOO
Version
06302025
Bidder Comment:
Does form liner requirement for all exposed concrete surfaces also apply to concrete deck surfaces?
# CLASS
COMPONENT AND
POC NAME, PHONE,
AND E-MAIL
PAGE PARA COMMENT
TYPE (C/S) COMMENTS, JUSTIFICATION, AND ORIGINATOR JUSTIFICATION FOR RESOLUTION
A/
12445125R
0002 Phase
II
Administrat ive
Informatio n Site Visit
Details
Pg 1
Bidder Comment:
The pre-proposal site visit agenda does not have any time scheduled for the shortlisted firms to have one-on-one discussions with client. Requesting time slots for Wednesday afternoon for each firm to meet with client. One-hour sessions preferred.
Resolution: No individual sessions will be provided. During the solicitation, all discussion between the government and prospective bidders will be open to all bidders.
Section C
SOO
Are new concrete decks required to be sloped for water shedding?
Resolution: Yes. Ensure that the deck will facilitate positive drainage to prevent water pooling.
Section C
SOO
Version
06302025
Bidder Comment:
The multi-girder steel option requires a minimum of (3) girders. Does this also apply to wood structures?
Resolution: Not necessarily. The minimum number of girders would depend on factors detailed in FPL-GTR-260 Standard Plans for Glued Laminated Timber Bridge Superstructures. This document can be found at: https://www.fpl.fs.usda.gov/documnts/fplgtr/fpl_gtr260.pdf
Section C
SOO
Version
06302025
31 of 41 Bidder Comment:
The multi-girder steel option requires a minimum of (3) girders. We assume that should the (2) existing large plate girders be found to be structurally acceptable (bridges 38 & 39), that a third girder would not be required?
Resolution: That is correct. The third girder will not be required in those instances.
Section C
SOO
31 of 41 Bidder Comment:
Can representative (acceptable) photos of stone patterns be provided in an effort to streamline the form liner selection and colors?
# CLASS
COMPONENT AND
POC NAME, PHONE,
AND E-MAIL
PAGE PARA COMMENT
TYPE (C/S) COMMENTS, JUSTIFICATION, AND ORIGINATOR JUSTIFICATION FOR RESOLUTION
A/
Resolution: This is not readily available at this time. We will need to research this further.
Section C
SOO
Are there restrictions on concrete deck reinforcement materials? Are steel fibers or synthetic macro-fibers acceptable?
0002 0003 Pg 1
Bidder Comment:
What is the deadline for questions for Phase II of the procurement?
Resolution: Amendment Pending - 22 Aug 2025 will be the deadline.
Section C
SOO
Version
06302025
31 of 41 Bidder Comment:
May precast, interlocking panels be considered for concrete decking surfaces (with maximum controlled widths)?
Resolution: Cast in place decks are preferred, but if the team can show that the precast panels will be aesthetically pleasing and will give similar long term durability for typical use as well as for potential floodwater inundation, pre-cast decks may be acceptable.
Section C
SOO
Version
06302025
31 of 41 Bidder Comment:
Please provide clarity on the vehicular rated curbs to be provided in addition to the railing on all bridges rated for vehicular traffic. Is traffic rated curb to be standalone separate from truss? What is the level of vehicular rating? Is the curb to be integral with the railing?
Resolution: The railing on the bridge will not be required to be designed for vehicles. An equivalent TL-1 curb will be acceptable. The curb is not to be integral with the railing. Curbs on truss bridges shall be attached to the concrete decking. The Contractor is responsible for design of curb and rail systems and the attachment to structural system.
Section C
SOO
31 of 41 Bidder Comment:
Is a minimum thickness required for wood deck?
Resolution: Design of wood decking is the responsibility of the contractor and shall meet applicable design specifications for load conditions.
# CLASS
COMPONENT AND
POC NAME, PHONE,
AND E-MAIL
PAGE PARA COMMENT
TYPE (C/S) COMMENTS, JUSTIFICATION, AND ORIGINATOR JUSTIFICATION FOR RESOLUTION
A/
06302025
Section C
SOO
06302027
May sections of trail be lowered if otherwise in compliance with the SOO?
Resolution: Yes, provided that there is no abrupt or substantial change in grade that would adversely affect the bicycle riding experience. Variation of trail grade and elevation, as required by design, are subject to government approval.
Section C
SOO
Version
06302025
32 of 41 Bidder Comment:
Local polls are required (if instructed) for color selection of truss coating. Due to schedule restrictions and lack of specific on type, scope, methods for polling, may color selection be made exclusively by the USFS?
Resolution: Yes.
Section C
SOO
06302028
May the trail be wider in some areas than 10 ft.?
Resolution: the trail construction width should be 10 feet. Where existing site conditions have a width greater than 10 feet, the newly constructed width should be 10 feet. Variation of trail width, as required by design, is subject to government approval.
Section C
SOO
As a follow-up to the RFI response #99, please confirm reconstruction, if any, within 100' from spurs/junctions is to be included in the scope.
Resolution: Confirmed.
t 001
Schedule B
Supplies or
Services and Prices
Pg 1
Bidder Comment:
Will the separate debris removal contracts currently underway along the VCNRT corridor affect the Debris/Cleanup/Demolition estimated quantities provided in Attachment 001 Schedule B?
Resolution: The currently active debris removal contract in the VCNRT corridor is primarily for removing woody debris and garbage; a small number of bridge debris was incidentally removed.
The quantities provided in Attachment 001 Schedule B for bridge structures is changed only for bridges (22 and 41), for which quantities are all reduced to zero.
# CLASS
COMPONENT AND
POC NAME, PHONE,
AND E-MAIL
PAGE PARA COMMENT
TYPE (C/S) COMMENTS, JUSTIFICATION, AND ORIGINATOR JUSTIFICATION FOR RESOLUTION
A/
03262025
Section C
SOO
Version
06302025
33 of 41 Bidder Comment:
Br. 16: Approaches: Replacement rail is to be in the same configuration as existing. Please confirm that the 4" or 4 3/8" sphere criteria listed in the Structure Design Parameters will not apply (as will none of the other parameters within that section).
Resolution: the site-specific description of work states “Replace wooden rail in the same dimensions and configuration as existing. Use wooden rail.” The Structure Design Parameters for railings apply “unless otherwise noted in the Scope of Work” (page 31), so do not apply.
Section C
SOO
Version
06302025
33 of 41 Bidder Comment:
Br. 16: Primary Structure/substructure: Confirm the existing concrete bridge supports need not be modified to bear upon rock if found not to do so.
Resolution: For the purpose of this project, assume the existing concrete foundations of bridge 16 do not need to be modified to extend to bedrock.
Section C
SOO
Version
06302025
33 of 41 Bidder Comment:
Br. 16: Primary Structure/substructure: No mention is made of a partial timber wingwall on the south side of the bridge span. Please confirm that this wingwall is to be replaced. If replaced with concrete, are form liners required - or is a smooth finish acceptable to match the adjacent support?
Resolution: Timber wingwall is part of the existing bridge substructure. The timber wingwall must be replaced. Matching the finish of the existing foundation is acceptable.
Section C
SOO
Version
06302025
33 of 41 Bidder Comment:
Br. 16: Primary Structure/deck: We assume that it is intent to remove the existing cross ties which supports the existing deck. Is the new deck to be supported from replacement ties or are other means acceptable (steel or glulam longitudinal elements)?
Resolution: Yes, the existing ties must be removed. Other means, such as steel or glulam longitudinal elements would be acceptable. Designer will determine type of supporting element(s) to support the deck.
Section C
SOO
33 of 41 Bidder Comment:
Br. 16: Primary Structure/deck: New rails are required that will meet AASHTO Pedestrian Guide.
This is in conflict with the approach directive (replace to match). Is new rail to be consistent throughout the length and what are the design specifications?
# CLASS
COMPONENT AND
POC NAME, PHONE,
AND E-MAIL
PAGE PARA COMMENT
TYPE (C/S) COMMENTS, JUSTIFICATION, AND ORIGINATOR JUSTIFICATION FOR RESOLUTION
A/
06302025
Resolution: The new rails should be consistent throughout the length of the bridge and match specifications for the approach railings.
Section C
SOO
Version
06302025
33 of 41 Bidder Comment:
Br. 17: Approach: May the bottom elevation of the new wood superstructure girders be lower than existing if demonstrated that the removal of the existing trestle substructure is an improvement in water clearance?
Resolution: Lowering the bottom elevation for the new wood superstructure below existing is a variation and would require supporting calculations to support and is subject to Government approval during design submission.
Section C
SOO
Version
06302025
33 of 41 Bidder Comment:
Br. 17: Primary Structure/superstructure: Any replacement main spans are to be 'similar' to the existing length. Is there a maximum length for any extension?
Resolution: No. The Designer is to determine span length based off analysis for each replacement bridge.
Schedule B
Supplies or
Services and Prices
03262025
Pg 1
Bidder Comment:
Please provide details on how the volumes for Trail and Bridge/Trestle demolition in Attachment 001 Schedule B are to be measured and what work is to be incidental to those items.
Resolution: As per Schedule B, the pay units are cubic yards. If direct measurement of cubic yards is infeasible, a surrogate measurement may be developed and converted (e.g., tare weight) based on officially measured load/scale tickets.
Section C
SOO
Version
06302025
Bidder Comment:
Br. 17: Approach: A 10 ft. clearance is required. However, item D indicates that the deck is to 'maintain existing deck width'. Which is the correct directive?
Resolution: The requirement is to “Maintain a 10 ft clear width and approximate grade”
Schedule B
Pg 1
Bidder Comment:
Please provide the conditions that must be met for the period of performance for demo/cleanup to be complete as shown on Attachment 001 Schedule B.
# CLASS
COMPONENT AND
POC NAME, PHONE,
AND E-MAIL
PAGE PARA COMMENT
TYPE (C/S) COMMENTS, JUSTIFICATION, AND ORIGINATOR JUSTIFICATION FOR RESOLUTION
A/
Supplies or
Services and Prices
03262025
Resolution: The demolition and cleanup quantities are shown on Attachment 001 Schedule B. The description of work at each bridge location is in Attachment 002, Section 102, pages 33-39. The performance conditions are, as stated, “remove and legally dispose of existing” debris and/or structures.
Section C
SOO
Version
06302025
Bidder Comment:
Br. 17: Approach/rail: we assume that the new wooden railing is to meet AASHTO Pedestrian Guide requirements. Please confirm.
Resolution: Yes. Use AASHTO Pedestrian Guide loading for rail design.
Section C
SOO
Version
06302025
Bidder Comment:
Br. 17: Approach: There is visual indication of some vehicle passage beneath the existing approach structure. Is this a requirement?
Resolution: Yes. The low chord cannot be lowered on this bridge.
Section C
SOO
Version
06302025
Bidder Comment:
Br. 20: Superstructure: Copper metal flashing is required. Are fasteners also required to be copper?
Resolution: Fasteners shall meet the installation standards supplied by the manufacturer of the copper metal flashing. Copper fasteners are required and to be provided by the contractor.
Schedule B
Supplies or
Services and Prices
03262025
Pg 1-4
Bidder Comment:
Please provide further detail on what is required to be included in the requested price breakdown excel supporting data as requested on Attachment 001 Schedule B pages 1-4.
Resolution: For each item, show relevant costs associated with each sub-item; including, but not limited to personnel, equipment, materials, supplies, expenses, and overhead.
SOO p. 03
Section (c)
"The RFQ does not specify a required design storm (e.g., 25-, 50-, 100-year) for bridge and drainage
# CLASS
COMPONENT AND
POC NAME, PHONE,
AND E-MAIL
PAGE PARA COMMENT
TYPE (C/S) COMMENTS, JUSTIFICATION, AND ORIGINATOR JUSTIFICATION FOR RESOLUTION
A/
Section C
SOO
Version
06302025
Drainage; SOO p.30 (c) hydraulic design parameters.
design.
What design storm event should be used for:
a. Bridge and major stream crossings
b. Trail drainage features (culverts, ditches, outfalls)
If no standard is set, would the Forest Service accept a 100-year event for bridges and a 25-year event for trail culverts, consistent with EM-7700-8 and AASHTO guidance?"
Resolution: Using a 100-year event for bridges and a 25-year event for trail culverts is required, as per Attachment 02, page 30 (of 41), section B (Trails) and section C (hydraulic design). The reference is FSH 7709.56b, Chapter 70, Section 74.
Section C
SOO
Version
06302025
Bidder Comment:
Section B Trail Design Parameters, 5h bullet. The first two sentences read "A geotechnical evaluation of the trail will be required. Evaluate the trail for geohazards and geotechnical concerns." Please confirm that geohazards and geotechnical concerns only refer to currently visible geohazards and geotechnical concerns, such as slope failures, trail erosion, and scour holes.
Geohazards and geotechnical concerns do not apply to areas of the trail that are currently stable and undamaged.
Resolution: Correct.
SF1442
Complete without attachment s 05222025
Section H
Pg 1
Bidder Comment:
H.1 Insurance, (b) (2) states that “The Contractor shall have property damage liability insurance shall be required in the amount of 500K*500K per occurrence.” Please correct this apparent typo as follows: “The Contractor shall have property damage liability insurance which shall be required in the amount of $500,000 500K*500K per occurrence.”
Resolution: This typographical error will be corrected in the amendment to the solicitation.
Section C
SOO
Recommend engineered wood superstructures be exclusively wood decked. This would change the scope of bridge 38 and 39 to be wood deck and not concrete deck.
Resolution: Yes. The engineered wood bridges would have wood decks.
# CLASS
COMPONENT AND
POC NAME, PHONE,
AND E-MAIL
PAGE PARA COMMENT
TYPE (C/S) COMMENTS, JUSTIFICATION, AND ORIGINATOR JUSTIFICATION FOR RESOLUTION
A/
Section C
SOO
Version
06302025
Bidder Comment:
Rail coating is specified to be durable and maintenance free. May rails be fabricated from AASHTO M270 50W steel?
Resolution: Yes. Alternative methods that achieve the same results can be proposed for consideration but are subject to Government approval and acceptance.
Section C
SOO
May replacement bridge spans be placed flat with no longitudinal slope?
Resolution: Yes, as long as all other structural requirements are still met, the surface drains properly and grade requirements are met on the approaches, but variations are subject to Government approval and acceptance.
Section
102.20 C.
Br. 20: Section 102.20 C. makes reference to Minnesota DOT report MN 2020-16. Searches of the Minnesota DOT website yielded no results. Can a copy of this report be provided?
Resolution: We do not have this readily available. We will find the correct reference and provide it.
Section C
SOO
Version
06302025
33 of 41 Bidder Comment:
Br. 20: Due to the expected sizes of the glulam arches, may the approximate 12 ft. maximum outside dimension be waived for this bridge?
Resolution: Yes. As long as all other requirements are met…