This document contains questions and answers regarding Solicitation 12034318R0017 for construction of Phase III of the Interagency Natural Resource Center in Coeur d'Alene, Idaho. The solicitation is expected to be posted on June 5, 2018 with responses due 30 days after. It will be for construction of the main 29,000 square foot office portion to support 173 employees from the U.S. Fish and Wildlife Service, Bureau of Land Management, and U.S. Forest Service. The magnitude of the project is estimated between $5 million and $10 million. Subcontracting will be allowed if requirements are met. Experience and past performance examples do not need to be for the same projects. Independent third party testing will be required. Procore software must be used for contract administration. Manufacturers beyond those listed will be considered if equivalent.
Q&A June 29 2018
View the file
Other files
Show all 40
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers
Solicitation 12034318R0017
INRC Phase III
June 18, 2018
Q1. Will Prime/Sub Teaming be allowed? If yes, will the past performance of the Teaming Sub be allowed and evaluated? If yes, will a Teaming Agreement need to be submitted in the proposal?
A1. A teaming arrangement is allowed as long as the requirements of FAR 52.219-14 are met.
This is an excerpt:
“(3) General construction. The concern will perform at least 15 percent of the cost of the contract, not including the cost of materials, with its own employees.
(4) Construction by special trade contractors. The concern will perform at least 25 percent of the cost of the contract, not including the cost of materials, with its own employees.”
You are expected to submit whatever experience and past performance information you feel is necessary in order to convince the evaluators that you understand and can successfully complete the proposed work.
Q2. Is there a minimum or maximum amount of projects we can submit? Do you have a required form for the Experience & Capability section? We want to confirm that the projects listed in the Experience
& Capability Section have to be the same as the projects listed in the Past Performance Section?
A2. There is no prescribed format for the proposal. The Experience and Capability portion of the offer is limited to 15 pages. You are expected to read and comply with the requirements of Section L-5 of the solicitation. The projects used to demonstrate experience and capability do not have to be the same as the past performance examples, but it makes sense that they would be.
Q3. If we already have completed PPQ’s or CPARS can those be included in our proposal in lieu of the
PPQ provided?
A3. You may include whatever information you feel will demonstrate your ability to perform the contract requirements successfully.
Q4. In which RFP attachment can I find the Green Globe Level 2 certification information?
A4. The Green Globe information may be found in Specification Section 018113-Sustainable Design
Requirements for Construction.
June 29, 2018
Q5. Quality Control tests clarification.
A5. All tests and Quality Control tests shall be completed by the contractor using an independent, certified, third party testing agency. Forward all test results to the contracting officer upon contractor receipt of the test results.
Q6. Procore Construction Management software clarification.
A6. The contractor shall use Procore Construction Management software for contract administration functions; RFIs, Submittals, Testing, Correspondence, etc. Delete section 0133000-2.1-A.
Q7. Approved Equal clarification.
A7. Change all specification sections that refer to specific manufacturers to include language that confirms that acceptable manufacturers are not limited to the listed manufacturers. Equivalent products and manufacturers that meet all of the performance requirements in the specifications are acceptable.
Reference section I-2 clause FAR 52.236-5 Material and Workmanship. "The Contractor may, at its option, use any equipment, material, article, or process that, in the judgment of the Contracting Officer, is equal to that named in the specifications.
Q8. RFI Clarification
A8. Change 013100-1.6-A to "Procedure: Immediately on discover of the need for interpretation of the
Contract Documents, submit an RFI in the form specified.
Q9. Are the two inch irrigation conduits already installed for the 1 inch irrigation lines on Sheet L1.4?
A9. Sheet L1.4 - Two inch conduit sleeves were installed under the asphalt as part of the Phase 1 project to accommodate the Phase 3 irrigation lines.
Q10. What are the asphalt restoration requirements for the Phase 3 contractor?
A10. Add note to detail 13/C1.3: "The Phase 3 Contractor shall include the following: 1) At the end of
Phase 3 construction install a fog seal for all existing asphalt pavement east of the pavilion including:
roads, front office parking, east parking, etc. 2) Repaint all asphalt pavement markings shown on detail
13/C1.3 east of the warehouse, . The seal coat shall use .08 to .1 G/S.Y. for CSS-1 diluted 50/50; prior to seal coat application, the asphalt surface shall be thoroughly cleaned removing all dirt and debris by broom, air, and sweeping.
Q11. Detail 1/C1.3 Clarification
A11. Add Note "Remove the existing large Ponderosa Pine tree and roots next to the retaining wall and replace it with a 7'-10' Douglas Fir Tree. The retaining wall was constructed as part of Phase 1."
Q12. Regarding section 122124, Roller Window Shades, the spec calls for Mecho Shade in 0% open/blackout, 0700 series. Sheet A9.0 calls for Hunter Douglas, 1% Green Screen. Should the shade cloth be 0700 black out (aka SB9000 by Hunter) or 1% open Green Screen?
A12. Use Sheet A9.0 Hunter Douglas Green Screen Evolve HD 3501, Rain 1% Openness