This document contains questions and answers related to solicitation 12034318R0017 for construction of the Interagency Natural Resource Center - Phase III in Coeur d'Alene, Idaho. Prime and subcontractor teaming is allowed provided the requirements of FAR 52.219-14 are met. There is no prescribed format or page limit for experience and capability sections in proposals. Completed past performance questionnaires or CPARS reports may be included instead of the provided past performance questionnaire. Specification Section 018113-Sustainable Design Requirements for Construction contains information on Green Globe Level 2 certification requirements. The anticipated award value is between $5 million and $10 million for construction of a 29,000 square foot main office building to support 173 employees from the U.S. Fish and Wildlife Service, Bureau of Land Management, and U.S. Forest Service. Proposals are due 30 days after solicitation posting on or around June 5, 2018.

Q&A

View the file

Other files

File Type Posted
INRC_First_Floor.dwg DWG drawing
INRC_Second_Floor.dwg DWG drawing
7-12-18_Q&A.XLSX XLSX spreadsheet
Amendment_0002.pdf PDF
Revised_B-1.pdf PDF
Questions_and_Answers_062918.pdf PDF
125900_SF_-_SYSTEMS_FURNITURE.pdf PDF
S0.1_(rev1).pdf PDF
Amendment_0001.pdf PDF
CV_(rev1).pdf PDF
C1.3_(rev1).PDF PDF
L1.5_(rev1).pdf PDF
Prebid_Notes_6-19-18.pdf PDF
Prebid_Attendance.pdf PDF
Drawings_Part_14_2018_06-01.pdf PDF
Drawings_Part_3_2018_06-01.pdf PDF
Drawings_Part_11_2018_06-01.pdf PDF
Short_Set_Solicitation_12034318R0017_Final_06072018.pdf PDF
Part_5_Project_Manual_2018_06_01.pdf PDF
Part_6_Project_Manual_2018_06_01.pdf PDF
Drawings_Part_1_2018_06-01.pdf PDF
Drawings_Part_13_2018_06-01.pdf PDF
Part_2_Project_Manual_2018_06_01.pdf PDF
Drawings_Part_6_2018_06-01.pdf PDF
J-4_State_of_Idaho_Workers'_Insurance.pdf PDF
Part_3_Project_Manual_2018_06_01.pdf PDF
Drawings_Part_8_2018_06-01.pdf PDF
Drawings_Part_9_2018_06-01.pdf PDF
J-1_Wage_Rate_Decision_ID180031_Mod_3_Dated_05112018.pdf PDF
Drawings_Part_10_2018_06-01.pdf PDF
Drawings_Part_7_2018_06-01.pdf PDF
Part_1_Project_Manual_2018_06_01.pdf PDF
Part_7_Project_Manual_2018_06_01.pdf PDF
Solicitation_12034318R0017_Final_06072018.pdf PDF
J-5_Past_Performance_Questionnaire.pdf PDF
Drawings_Part_5_2018_06-01.pdf PDF
Part_4_Project_Manual_2018_06_01.pdf PDF
Drawings_Part_4_2018_06-01.pdf PDF
Drawings_Part_12_2018_06-01.pdf PDF
Drawings_Part_2_2018_06-01.pdf PDF
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers

Solicitation 12034318R0017

INRC Phase III

June 18, 2018

Q1. Will Prime/Sub Teaming be allowed? If yes, will the past performance of the Teaming Sub be allowed and evaluated? If yes, will a Teaming Agreement need to be submitted in the proposal?

A1. A teaming arrangement is allowed as long as the requirements of FAR 52.219-14 are met.

This is an excerpt:

“(3) General construction. The concern will perform at least 15 percent of the cost of the contract, not including the cost of materials, with its own employees.

(4) Construction by special trade contractors. The concern will perform at least 25 percent of the cost of the contract, not including the cost of materials, with its own employees.”

You are expected to submit whatever experience and past performance information you feel is necessary in order to convince the evaluators that you understand and can successfully complete the proposed work.

Q2. Is there a minimum or maximum amount of projects we can submit? Do you have a required form for the Experience & Capability section? We want to confirm that the projects listed in the Experience

& Capability Section have to be the same as the projects listed in the Past Performance Section?

A2. There is no prescribed format for the proposal. The Experience and Capability portion of the offer is limited to 15 pages. You are expected to read and comply with the requirements of Section L-5 of the solicitation. The projects used to demonstrate experience and capability do not have to be the same as the past performance examples, but it makes sense that they would be.

Q3. If we already have completed PPQ’s or CPARS can those be included in our proposal in lieu of the

PPQ provided?

A3. You may include whatever information you feel will demonstrate your ability to perform the contract requirements successfully.

Q4. In which RFP attachment can I find the Green Globe Level 2 certification information?

A4. The Green Globe information may be found in Specification Section 018113-Sustainable Design

Requirements for Construction.